Table 6.08
Table 6.08
Date:
Sample Demolition Gross 12,000 sf
Cost Summary Shee Project: Area - sf
Item Activity Description Units Quant Unit Basic
Cost Cost
Demolition
1 Permits ls 1 1500 $1,500
2 Mobilization/Demob ls 1 7500 $7,500
3 Engineering hrs 0 150 $0
4 Temp Fence lf 440 6 $2,640
5 Site Protection ls 1 1500 $1,500
6 Misc Supplies/Matl's ls 1 500 $500
7 Utility Disconnects ea 3 500 $1,500
8 Salvage Work ls 1 0 $0
9 Sever Structure ls 1 0 $0
10 Gut Interior sf 12000 0.5 $6,000
11 (Blank) $0
12 Demo Structure $0
Above Grade cy 703 25 $17,575
13 Demo Foundations cy 94 35 $3,290
14 Demo Slabs cy 74 9 $666
15 Demo AC & Misc $0
Conc/Masonry cy 0 $0
16 Load & Haul Wood $0
Debris ld 9 346 $3,114
17 Prepare Concrete for $0
Crushing ton 1594 5 $7,970
18 Crush Concrete & $0
Stockpile on Site- ton 1742 6 $10,452
19 Load Scrap ton 48 11 $528
(use buyers drop box)
20 (Blank) $0
21 (Blank) $0
22 (Blank) $0
Site Restoration
24 Excavation cy 0 $0
25 Compacted Backfill cy 1480 6.5 $9,620
26 Grading sf 5000 0.15 $750
27 Seeding sf 5000 0.25 $1,250
(small area) $0
28 (Blank) $0
29 (Blank) $0
30 (Blank) $0