Table 6.

08 - Sample Demolition Cost Estimate Summary

Date:
Sample Demolition Gross 12,000 sf
Cost Summary Shee Project: Area - sf
Item Activity Description Units Quant Unit Basic
Cost Cost
Demolition
1 Permits ls 1 1500 $1,500
2 Mobilization/Demob ls 1 7500 $7,500
3 Engineering hrs 0 150 $0
4 Temp Fence lf 440 6 $2,640
5 Site Protection ls 1 1500 $1,500
6 Misc Supplies/Matl's ls 1 500 $500
7 Utility Disconnects ea 3 500 $1,500
8 Salvage Work ls 1 0 $0
9 Sever Structure ls 1 0 $0
10 Gut Interior sf 12000 0.5 $6,000
11 (Blank) $0
12 Demo Structure $0
Above Grade cy 703 25 $17,575
13 Demo Foundations cy 94 35 $3,290
14 Demo Slabs cy 74 9 $666
15 Demo AC & Misc $0
Conc/Masonry cy 0 $0
16 Load & Haul Wood $0
Debris ld 9 346 $3,114
17 Prepare Concrete for $0
Crushing ton 1594 5 $7,970
18 Crush Concrete & $0
Stockpile on Site- ton 1742 6 $10,452
19 Load Scrap ton 48 11 $528
(use buyers drop box)
20 (Blank) $0
21 (Blank) $0
22 (Blank) $0

23 Sub Total Demolition $64,735

Site Restoration
24 Excavation cy 0 $0
25 Compacted Backfill cy 1480 6.5 $9,620
26 Grading sf 5000 0.15 $750
27 Seeding sf 5000 0.25 $1,250
(small area) $0
28 (Blank) $0
29 (Blank) $0
30 (Blank) $0

Sub Total Site $11,620


Restoration

Item Activity Description Units Quant Unit Basic


Cost Cost
Project Support
31 Supervision Allowance days 8 600 $4,800
32 Per Diem man day 24 85 $2,040
33 Travel ea 5 250 $1,250
34 Job Office & Utilities days 8 200 $1,600
35 Sub Total Project
Support $9,690

Total Demolition Cost $86,045

36 Disposal of Debris ton 126 50 $6,300

Total Disposal Cost $6,300

EXAMPLE ONLY Environmental Cost


37 Allowance from Other $10,000
Worksheets
38 Total Environmental
Cost $10,000

39 Total Base Cost $102,345


40 Add for Overhead Cost 15% $15,352
41 Add for Profit 10% $10,235
42 Sub Total $127,931
43 Less Credit for Salvage ton 48 -150 -$7,200
(scrap steel)
44 Total Bid Price $120,731