Method Statement For Trees
Method Statement For Trees
TABLE OF CONTENT
1. PURPOSE
2. SCOPE OF WORK
3. GENERAL PREPARATION
4.1 Trees
4.2 Other materials
4.3 Safety of Plant
5. PLANTING OPERATION
6. QUALITY OF WORKS
8. SAFETY
9. MAINTENANCE OF TREES
10. APPENDIX
PLANTING DETAIL
METHOD STATEMENT OF TREES
MENAWAR RESOURCES SDN BHD Doc. No.: Rev. No: 001
Date Issued: 07/10/2019 Page 2 of 6
1.0 PURPOSE
The purpose of this procedure is to elaborate the process of planting works according to the specification.
The method statement is prepared as a guideline to the site personnel in implementing the above activities. It also
tells that the contractor has studied the requirement and capable to undertake scope of works.
1. Nursery visit
4. Practice the ISO 9000 Quality Management Method with notification to start works from and request for
inspection for every steps of operation.
2.1 REFERENCES
All works shall comply with the contract specification, construction drawing, approved environmental
management compliance plan and approved logistic plan for soft landscape works.
The affected area shall be ready for planting and cleared from the debris (i.e. Stone, concrete, timber etc.)
accordingly.
The affected planting area shall be indicated to locate the position and spacing of trees by using the numbered
pegging stick and confirmed by the Consultant.
The Sample materials such as top soil, coco peat, chicken dung etc. To be summated and confirmed by the
consultant.
All plant materials shall be supplied approved nursery as per specification and approved by Consultant.
Trees supplied shall be healthy, free of pest & disease and meets the Consultant requirement and approved by the
Consultant during nursery visit. Photo of trees shall be submitted to the Consultant one week after nursery visit for
confirmation and reference.
All trees shall be carefully protected during lifting, transportation, unloading and storage.
Consultant shall be notified of the intention to make a substitutions planting materials to be made immediately.
Note: Detail description of plants to be planted shall be notified to the Consultant at least 2 days prior of planting.
METHOD STATEMENT OF TREES
MENAWAR RESOURCES SDN BHD Doc. No.: Rev. No: 001
Date Issued: 07/10/2019 Page 3 of 6
• Topsoil and other related material of soil mixture shall be shown to the Consultant for approval.
• Samples of soil mixture materials shall be submitted to consultant prior to placement on site and
planting.
• Material shall be unloaded at site nursery or near the affected planting area.
1. Generally, all trees shall be carefully being taken care during lifting, transporting, unloading and
planting to avoid trunk injuries and damages. The cage machine is used to lift and unloading the
plants. The trunk should be wrapped with Hessian cloth or equivalent materials in order to keep
moist and prevent the trunk from damage. The canopy shall be wrapped or covered with netting to
protect from damaged while in transit.
2. The branches shall be trimmed/pruned (30% of the canopy density) in 2 or 3 weeks before deliver
without affected the requirement. Any trimming and pruning before and after planting, the
contractor shall apply the wound dressing process. This process will avoid:
- trees damages/injuries
- water loss
- shocked when planting
- easy for transportation
The main objective is to ensure minimal damage to planting materials during transportation. In order
to prevent damages, the trunk shall be properly wrapped and secured to the base of transporting
vehicle by guying rope to prevent movement. The lorry will be covered with netting to avoid severe
movement and injury during transportation.
a. Upon reaching to the planting location, the protection cover of plants shall be removed
and inspected for damages.
b. Inspection on the trunk shall be carried out to determine if there are any damages.
c. Slightly damaged planting materials would be treated with healing compound wound
treatment.
5. Watering: - to keep the root ball moist during transportation and storage.
7. Trees shall be transported to site and unloaded at site nursery or direct to planting areas (Transit
Nursery).
8. Transit Nursery: - Temporary area to receive plant materials before planting and inspect by the
Consultant. The setting up of the transit nursery to made with proper structure and materials.
METHOD STATEMENT OF TREES
MENAWAR RESOURCES SDN BHD Doc. No.: Rev. No: 001
Date Issued: 07/10/2019 Page 4 of 6
1. All planting procedure will follow as per specification. Consultant shall be informed at least 2 days prior to the
commencement work.
2. Setting out of planting will be based on approved shop drawing. The size timber peg must be 50 x 50 x 450
mm. To get the advice and inspection from the landscaping consultant in order to ensure the planting location
is according to the shop drawing.
1. Planting holes shall be excavated 1M min as per specification and to call consultant for inspection of
the planting hole’s size.
a) Big trees : 1m x 1m x 1m
2. Hole shall be dug wider not deeper than the existing root ball.
3. Excavation work shall be done by using backhoe and areas not accessible by machinery shall be done
manually. All excavated soil and debris shall be cart away before back filling with approved soil
mixture.
4. Ponding test need to be carried out before refill the approved soil mixture (50% topsoil, 30% organic
matter and 20% sand). The water must be dried out after 24 hours, if the water is not dried, the sub
soil drain needs to be installed and to be discharged to the nearest drain.
1. Pre-planting
• Compacted roots, branches and all dead leaves shall be pruned and applied wound dressing.
2. Planting of Trees
• The plant shall be set vertically in the center of the planting hole at a level that ensure that the
finished soil level is same level as surrounding area.
• The organic fertilizer (Chicken dung) and soil mix shall be stamped at the base and around root ball
and compacted firmly.
• The burlap from the top and side root ball shall be removed carefully. Any injured/broken roots shall
be cut and wound dressing shall be applied.
• Firm the soil and irrigate so that the soils settle around the root ball.
• All trees staked with clear rubber hose (8mm and above) with wire cable inside after planting. The
stake will be use only to avoid root from being shaking by the wind. Staking detail as per
Method drawing (specification).
METHOD STATEMENT OF TREES
MENAWAR RESOURCES SDN BHD Doc. No.: Rev. No: 001
Date Issued: 07/10/2019 Page 5 of 6
3. Planting on Slope
• The small crane (2 tones) or cage machine will be used for loading the plants. The Jut rope will be
used to hang the plants and to tie at the root ball and center of the trunk. The trunk shall be
wrapped with gunny sack to avoid damages. The trees shall be staked after planting in order to
avoid the trees from fall down as per consultant specification.
In order to ensure the trees are well planting the following shall be considered during the works process.
1. The root ball should neither be planted too high or too deep. If too high, the upper roots will be exposed
by soil erosion. If too deep, the bark may rot.
2. Staking and guying is done to prevent the stump from toppling over. A collar is tied around the trunk and
can be attached to a stave or several stakes, or secures with guy rope to pegs on the round.
3. Protect disturbed areas again runoff from above site by intercepting the area with diversion channels and
diverted runoff around the works.
4. Stabilize I backfill disturbed area quickly, once planting activities have finished. All adjustment of level is
depending on the site condition.
5. Get the advice and inspection from the landscaping consultant in order to ensure the works done
accordingly to the requirement.
We undertaking the following mitigation measures as when necessary to control and minimize soil erosion during
process of planting activities: -
1. Protect disturbed areas against runoff from above site by intercepting the area with diversion channels
and diverted runoff around the works.
2. Retain sediment on the site by providing sand beg if necessary.
3. Stabilize/backfill disturbed area quickly, once transplanting activities have finished.
4. Inspect control measures at regular interval particularly after heavy rainfall.
5. Plastic or tarpaulin will be used to cover slope/areas or excess earth as a temporary measure if necessary.
8.0 SAFETY
All the works shall be followed with the client’s Safety Regulation especially on the following Job Safety analysis:
6. Safety boots shall be worn all the times while at the site. Only boots with steel and embedded steel sole
shall be used.
7. Luminous vest shall be worn at all times while at work site.
8. No smoking or starting fires within the work site, whether during or after work hour.
9. Food to be taken at designated areas only
10. Goggles will used for spraying chemical.
Note: All workers shall be familiarized on the Safety Work Method Statement before proceeding with any work.
The scope of work of the soft landscape maintenance shall be generally including the implementation of
all agronomic and horticultural practices to ensure healthy plant growth.
The temporary maintenance schedule to be submitted before start planting. The maintenance of all plant
materials shall commence as soon as they are installed.
Maintenance Work
a) Watering
The most important in trees establishment after planting is consistent watering. New planted trees need
to be watered minimum twice a day especially during dry spell.
b) Pruning
Pruning shall be done when required. All the water shoot to be removed below than 2.5m and to be
applied wound dressing.
Manuring shall be started on the second month of planting at rate 200gm/plant to 500gm/plant once in
two months. Fertilizer (organic fertilizer – Super Green) shall be evenly spreader around the root area and
lightly cultivated.
e) Soil Scarify
f) Mulching
To remove / replace of mulching during the wet season (depend on the moisture).