Fundamentals of Organizational Structure
Fundamentals of Organizational Structure
Disadvantages :-
Temporary nature of organization
Loose bonding in groups (professional rivalry)
Difficult to meet time limit
Role of various personnel in Construction industry :-
For execution of work following persons are required at
site :-
• Site Engineer
• Supervisors
• Mistries
• Operators
• Labour
1. Site Engineer:-
He is the overall in charge of the execution of work at
site.
His decision is final in the execution of work.
He has to explain designs & other instructions at the
site.
He has to employ the required staff.
He has to see the purchase of materials, equipments &
machinery at the site & he also decides the use of
equipments & machinery.
He has to co-ordinates the various agencies required for
the work.
He is fully responsible for the satisfactory completion of
the work.
[Link] :-
Junior engineers, overseers, mistries are the persons
appointed for the supervision of the work.
Their job requirements are :-
(i) To supervise the work done by the skilled & unskilled
labourers & to guide them whenever necessary.
(ii) To prepare the schedule of work :- daily work
programmes under the direction of site engineer &
to arrange accordingly the men, material, equipment
for the execution of work.
2. Supervisor :-
Junior engineers, overseers, Mistries are the persons
appointed for the supervision of the work.
Their job requirements are :-
(1) To supervise the work carried out by the skilled &
unskilled labourers & to guide them whenever
necessary.
(2) To prepare the schedule of work :- Daily work
programmes under the direction of the site engineer
& to arrange accordingly the men, materials ,
equipment for the execution of work.
(iii) To check & see that, work is being done as per the
drawing & specifications.
(iv) To take the measurement of work done, record it, &
prepare the payment bill.
(v) To pass the instruction to lower level, which are
received from top.
(vi)To ensure safety & security at the work site.
Labour :-
There are following types of labour are generally
found in construction industry :-
Unskilled labour
Semi-skilled labour
Skilled labour
1. Unskilled labour :- These labours do
simple manual work such as cleaning,
sweeping, digging, concrete mixing,
ramming, curing, material handling etc.
2. Semi-skilled labour :- These labours do
works that do not require high skill &
training. They can operate simple
machinery.
Such labour is produced from an unskilled
labour who has been doing a particular
type of work over long period.
No formal training is given to such labour.
They have some skill by their own
experience of work.
3. Skilled labour :-
These labour do works which need special
skill.
Such labour needs to take specialized
training.
Such labour is produced after training
program in training institutes.
Some persons acquire the skill by family
traditions or by self-experience.
Ex:- Mason, painter, fitter, bar-bender, tiler,
plumber, welder, electrician, etc.
Agencies associated with construction work
:-
Owner
Promoter
Builder
Designer
Architects
Consulting Engineers
Owner :-
This is the person who decides to start the work or
any project.
Promoter :-
A person/firm, who starts civil engineering work is
called promoter.
Promoter may be a single individual, co-operative
society, private firms, public company, government or
semi-government agencies.
Promoter initiate the work, order the start of work &
get the work done through various agencies.
He hires the consulting engineer to help him
understand & handle the process of construction.
• Functions of Promoters :-
To give full details & requirements in the
beginning to the architect & consulting
engineer to complete the work in time & in
given budget.
To appoint suitable agencies for planning &
execution of work.
To arrange the required finance
To make payments to various agencies
To get the work done through various agencies
as per drawing details.
Builder :-
Contractors/builders are the persons who actually
do the construction work according to the plan,
design & specifications.
It do the work as per terms & conditions of the
contract.
They have to do the work as per the direction of
architect /consulting engineers.
• Functions of builder :-
To maintain a suitable organization required
for carrying out the work.
To arrange necessary tools, plants, equipments,
& machinery required for the work.
To arrange necessary labour required for work.
To take the full responsibility of the work till its
completion.
To arrange the schedule of the work in
consultation with the site engineer & carry out
work as per agreement.
Designer :-
These persons are specialist in designing components of a
project.
Ex- R.C.C. designers, waste disposal experts, water filter
designer etc.
• Functions :-
To provide complete design, drawings & specifications etc.
To check the work for proper implementation of design to make
sure the standard work.
To help & guide the site engineer for correct, speedy &
economical execution of works as per design.
To conduct tests after completion of the components to ensure
about implementation of the design.
Architects :-
• An Architect is a professional who turns building
design into reality.
• They develop concepts for structures and then
work with engineers to bring these designs into
reality.
• They deal with sketching, thinking, planning,
designing buildings or other structures.
Consulting Engineer :-
Consulting engineer is the mediator b/w the
promoter & the contractor.
He does advisory job in civil engineering project.
He prepares detailed drawings, estimate,
specifications & designs etc.
He supervises the work, guide the contractor &
his workers.
• Role of Consultant for various activities :-
Monitoring of progress & quality :-
Consultants play an important role in organizing
project activities from the start to the maintenance
stage.
They guide the contractor in preparing the project,
organizing and monitoring the project's progress.
They maintain a good coordination between teams in
executing the project using their vast experience.
They guide in estimating the project budget and
helps in smooth release of funds as per the schedule.
• They have the experience and resources to manage
the quality of the materials and structures during
construction
• They suggest steps and methods that ensure the
overall quality.
• They have methods to ensure the quality of various
works such as finishing, concreting, installation and
fabrication etc.
• They prepare structural elements according to
standard codes. Testing of materials in the laboratory
is done with the help of suitable processes.
• They develop strategies to eliminate defects, purchase
materials of suitable quality, and check the
dimensions of the structure after construction.
Settlement of disputes:-
Disputes are damaging, expensive, and time
consuming. They affect individuals, organizations,
government, and the economy.
Preventing disputes, and resolving disputes
earlier and more effectively, benefits everyone.
Consultants act as an arbitrator to settle the
disputes on the mutual agreement of both
parties, owner & contractor.
Consultants suggest ways & methods to settle the
dispute b/w parties.
Site Layout or Job Layout at building site :-
Site layout is the plan of the construction site.
It shows the area and the exact location for
placing the resources required in the work.
It also indicates the place for offices, godowns,
workshops, accommodation etc.
Besides this, it shows the existing relationship of
the site with its surrounding in respect of
communication, approaches and existing
facilities.
A systematic and scientifically prepared site
layout is necessary to :-
1. Get a continuous supply of materials in sufficient
amount.
2. Have an easy access to material
3. Easy to check material’s wastage
4. Decrease the number of plants and reduce the
movement of heavy equipment.
5. Avoid confusion and reduce accidents.
6. Have a clean outlook to facilitate the inspection of
the materials
The site layout depends on the following
factors:-
1. Location of the site.
2. Availability of space.
3. Access to the site.
4. Material bulk.
5. Type of equipment to be used.
6. Ground conditions.
Principles Of Job Layout:
• The following are the principles of job layout. They
promote economy, efficiency, tidiness and safety.
1. The site should have preferably two openings, one for
entry and the other for exist. It promotes flow of traffic.
If there is only one gate then it is preferable to provide a
cross-over near the gate.
2. The general office should be located near the main gate.
This avoids confusion at construction site.
3. The godown should be located just behind the general
office. So that it allows a closer supervision of the stores.
4. Temporary roads may be constructed around the
operation area. It promotes the flow of material and
movement of equipment.
5. The workshops for joiner, fitter, electrician etc should be
decided and located at suitable location for easy and
short routes.
6. Staff housing should be away from noise. It should be
concentrated in one area to promote communication
and reduce the cost of facilities and services.
7. The existing services should be used to the maximum
extent.
Preparation of Plan for job Layout
Before starting the construction work, a layout plan is prepared.
The plan gives proper location for machines, proper & safe storage for
materials & workers to facilitate the work as per schedule.
Materials are required to store near the work to reduce the cost of
transportation & easy handling of material.
Machines are placed in the most advantageous position.
For administrative control, office location should be at proper place.
Proper connectivity to vehicles coming at site for various reasons.
Sufficient place for movement should be available near the work for
easy movement of labour & machinery.
The layout should be planned in such a way that it gives maximum
efficiency in minimum movement, to save time & money.
Fencing & hording at site is required for safety & identification of
project.
❖ Project
➢It is defined as the combination of interrelated
activities. These activities must be executed in a
certain order before the entire task is completed.
❖ CPM (Critical Path Method)
➢ It uses activity oriented network which consists of
a no. of well defined tasks or activities.
➢Each activity is represented by an arrow & the
activities are joined together by events.
➢ CPM is generally used for simple, repetitive type of projects
for which activity times & costs are certainly & correctly
known.
➢It is a deterministic model.
➢E.g.- construction of bridge, road, building etc.
Disadvantages
Both contractor & owner has to hire a staff for taking
measurements
Exact cost of construction is not known at the start of
the project
Cost-based Construction Contracts
3. Percentage rate Construction Contract
• The contractor is paid based on the actual cost of the
project, including direct and indirect costs, plus a specific
fee. This fee could be a fixed fee or percentage of costs.
• All risks are associated with the owner, and he gets involved
with the contractor in the management of the project. The
contractor has no risk in case of increasing the cost of the
project; also, there isn't any incentive for an early finish.
• This type of contract is ideal when the project scope is
uncertain in the early stages of the project. The contractor
can start the execution of the project before finishing the
design. It is impossible to estimate the cost of the project
before the construction has been completed.
• This type of contract is classified as follows
:-
Cost plus percentage rate contract
Cost plus fixed fee contract
Cost plus variable percentage contract
Cost plus variable fee contract
1. Cost plus percentage rate contract
In this contract, owner agrees to pay to the
contractor the actual cost of the work plus an
agreed percentage of cost as his profit.
2. Cost plus fixed fee contract
In this contract, owner agrees to the contractor the
actual cost of work plus certain fixed amount as his
fees.
3. Cost plus variable percentage contract
In this contract, payment to the contractor is made on
varying percentage basis. i.e. contractor’s percentage is
linked with the cost of construction, % profit increases with
decreasing cost of construction & % profit decreases with
increasing cost & time of construction.
Contractor gets more profit if he bring down the estimated
cost of construction.
A variable scale of % profit, related to the cost of
construction is already prepared.
4 Cost Plus variable contract:-
This type of contract is similar to cost plus fixed fee
contract, but fee of contract varies with respect to the
cost of construction.
Fee to be paid to contractor is not fixed but it
increases or decreases with respect to actual cost of
construction.
Higher the actual cost of work, lower is the fee & vice
versa.
4. Target Cost Construction Contract
• Target cost contract has common features of the lump
sum and cost-plus contracts. The contractor is paid
based on the actual costs plus a certain fee either
fixed or percentage of total cost in case of the cost of
the project doesn't exceed certain target cost
mentioned by the owner.
• There is a risk carried by the contractor in case of an
increase in the cost of construction projects. The
contractor is also rewarded a percentage of any
savings between target and actual cost.
Labour Contract
• In this contract, owner & contractor enters into
agreement only for supply of labour.
• Material used in the project is supplied by owner &
labour ( & required machinery) is supplied by contractor.
• Quality of work in this contract is good because material
is supplied by the owner.
Advantages
Quality of work is superior
Extra work can be added
Disadvantages
Wastage of materials is common
Shortage of material may delay in construction
work
Fee Contract
In this contract, owner agrees to pay the
contractor an amount as fee for his technical
skills & knowledge.
Cost of materials, labour, & other expenses are
covered by owner separately.
Negotiated Contract
When the contract is given simply by the negotiation
between the parties without invitation of tender is called
as negotiated contract.
In this contract, there is no open competition & owner
negotiates with selected contractors.
Generally it is not used for public works or by
government dept./companies. Private companies often
uses this system of contract.
Contract Document
• A construction contract document is a valid document
that can be enforced by law.
• At the early stages of any construction project, the
owner with his engineer or consultant prepares
necessary documents for the tender process, which
will be included in the contract. These documents are
called contract documents.
• These are the reference documents that describe the
details of work to be performed.
• These are a legal part of the contract which describes
the work such as supplying labor, equipments,
technical expertise and materials for the construction.
Types of Documents in a Construction
Contract
The different types of documents in a
construction contract are as follows :-
• Contract Agreement
• Scope of work definition
• General conditions
• Special conditions
• Drawings and specifications
• B.O.Q (bill of quantity)
• Letter of acceptance
• Work Schedule
1. Contract Agreement
• A contract agreement defines the agreement
between the client. In this document parties are
specified and their responsibilities are defined in
the construction process.
• It is the important document to which other
contract documents attach or reference.
2. Scope of work definition
• Scope of work should describe the project, the
project deliverables, and details of work. It must
specify all tasks, duties, and limitations to get
desired results.
3. General Conditions of Contract
• General conditions define all general terms and items such as
utilities, vehicles, organizational structure, mobilization etc. But
these items are not directly related to the construction
activities. Obligations of both parties, general conditions,
overhead costs, bonuses, and some other conditions are
included in this portion.
• General conditions set the framework of the contract that
establishes all the rights and obligations of the parties involved.
• It generally includes:
• Definition of the project
• Contract components
• Rights and responsibilities for the owner and the contractor
• Project schedule
• Payment method
• Warranty and delay penalty
4. Special Conditions of Contract
• Special conditions describe specific requirements
and instructions for the work. Mostly these are
additional to the general conditions. Special
conditions include details and conditions
regarding the individual tasks or the whole
project.
5. Drawings & Specifications :-
• All contracts should involve drawings that contains
detail of the work to be done. Drawings have the
details like quantities, locations, dimensions, sizes,
shapes, and forms of the elements. These drawings
can be architectural, electrical, mechanical,
landscape & structural.
• Construction drawings include elevations, sections,
and profiles for the building to be constructed.
• Technical Specifications explain the materials,
workmanship, and equipments required for a work.
Client should describe the specifications clearly
before the tendering stage. Every little work should
be specified and deviation limits should be
determined in technical specifications.
6. Bill of quantity
• A bill of quantities is a document used
in tendering, which contain details of materials,
works, and labor (and their costs) etc. It also
details the terms and conditions of the
construction work. BOQ helps a contractor to
price the work for which he or she is bidding.
7. Letter of acceptance
• A letter of acceptance is a document sent and
signed by the employer, which says that the offer
submitted by the contractor has been fully
accepted and that the contractor may begin to
work.
8. Work Schedule
• Work schedule is very important for both parties.
Because a project cannot be performed without a
proper plan. A work schedule shows site delivery date,
start and finish milestones, project duration, and other
useful information.
• Different types of works are mentioned in the work
schedule, works of similar nature are grouped &
termed as civil, electrical, and mechanical works etc.
Contract Management
• Contract management or contract lifecycle
management (CLM) is the process of managing
contracts, from the initial stage to execution.
• It also manages termination or renewal of the contract.
• Key activities involved in contract management are
contract drafting and clause negotiation, performance
analysis to maximize operational and financial
performance and risk mitigation.
• Business relationships get damaged by defaulting on
contract terms.
• Contracts are the foundation of business relationships.
They describe every details of a business deal or
supplier relationship from start to finish.
• All contracts need to be managed for their entire
lifecycle, managing negotiated clauses, monitored for
compliance, and then reviewed again for renewal or
amendments.
• A single contract needs people from finance, legal and
procurement. These peoples should have great skill &
knowledge.
• This is a manual, time-consuming and costly process.
But it needs to be done for proper functioning of
business & have healthy relationship b/w parties
involved in the business.
• Without proper contract management, companies open
themselves to several risks, financial penalties etc.
• A small technical mistake or wording issue can cost
lakhs of rupees in the long run.
MODES OF SETTLEMENT OF DISPUTES
1. Capitulation- weaker party give in to retain
goodwill/ long term business relationship with
stronger party
2. Negotiation--Both parties sink differences and try to
reach amicable settlement
3. Arbitration- Disinterested/impartial third party
appointed to pass judgment
4. Litigation- Disputes taken to court resulting in
abnormal delay and heavy expenditure
5. Dispute Resolution Board- Board constituted on
award of contract to resolve disputes as and
when they arise
ARBITRATION
• It is the settlement of a dispute between parties to a contract by a
neutral third party without turn to court action.
• The neutral third party is called as the Arbitrator.
• Arbitration is usually voluntary but sometimes it is required by
law . If both sides agree to follow the arbitrator's decision,
'award' becomes a binding arbitration.
• Exact procedure to be followed is according to country's
arbitration laws or by arbitration rules prescribed by International
Chamber Of Commerce (ICC).
• Arbitration is the most popular method of disputes settlement in
building and construction disputes.
ARBITRATION-OBJECTIVES
• Make provision for arbitral procedure which is fair,
efficient, capable of meeting needs of specific
arbitration
• To minimize supervisory role of Courts
• Arbitral tribunal to give reasons for the award
• To ensure Arbitral tribunal remains within its
jurisdiction
• Permit Arbitral tribunal to use:- mediation,
conciliation or other procedures to settle disputes
• To make decisions of Tribunal enforceable as a decree
of court
DEFINITIONS
• Arbitrator- A person appointed to settle disputes
• Arbitration Agreement- A written agreement between client
and contractor to settle future disputes
• Order of reference- Order containing names of the arbitrator,
specific dispute, nature, time limit for award
• Presiding arbitrator-An umpire when each party's arbitrator or
both parties arbitrator choose one presiding arbitrator
• Award-Written decision of the arbitrator on completion of the
proceedings
• Arbitral tribunals :- It refer to panels of one or more arbitrators
responsible for passing judgment regarding disputes between
parties
PROCEDURE FOR ARBITRATION
• Specific clause to be introduced in contract for dispute
settlement by arbitration
• Unhappy party to approach the designated authority to
appoint arbitrator with list of disputes and amount
involved for dispute
• Arbitrator is then appointed & referred with the papers
submitted
• Few contracts provide for direct resolution of disputes
by parties- failure to do so can lead to appointment of
an Arbitrator
• Arbitration is conducted under the provisions of
Arbitration and Conciliation Act, 1996.
• Parties are to be treated equal and is given full
opportunity to present their case
• Parties are free to agree on the procedure for Arbitral Tribunal, place &
language for arbitration.
• Arbitration proceedings start from the date of receipt of request for
arbitration
• Claimant to state facts supporting the claim, issues involved and
remedy sought
• Respondent to give defence against these claims
• Tribunal to decide on oral/documentary evidence
• Experts appointed by Tribunal in case of specific technical issues
• Assistance of court may be sought for taking evidence
• Decision of the Tribunal is taken by majority. Award is given in writing
and signed by all members.
• Award amount, if not paid, to carry interest @18% per annum from
date of award to date of payment
• Award to be final and binding & Enforced as - decree of the Civil Court.
Safety in civil engineering
Safety is a term used for all the efforts given by the
management to prevent accidents.
Safety in construction is considered important for the
following reasons :-
(Importance of safety) :-
(i) Human life is considered invaluable
(ii) Direct cost of accidents :-
• Medical care & compensation to the injured
• Expenditure on insurance premium
• Cost of legal work
• Damage to the property
• Delay to the project
(iii) Indirect cost :-
• Investigation into cause of accidents
• Loss of skilled workers
• Loss of equipments.