Daily Report TSEP 20241005
Daily Report TSEP 20241005
Daily Report
PROJECT : TANGGUH SECURITY ENHANCEMENT PROGRAM (TSEP) PROJECT NO. : ID-255
DATE : 05-Oct-24 DAY : Saturday
START TIME : 06:00 FINISH TIME : 18:00
A. WORKS TODAY
No Description of Work Location Total Qty Previous Qty Today Qty Unit Remarks
a Concrete Mixing
1. Concrete Production Groundwater Well 959 655 7.5 m3 Tie beam ( New patrol road, Hill Laydown, Stock pile ) Mesa Harya Nuradi
1. Installation - Fence Post & Rebar STA 1+000 to 5+000 2001 1939 0 Post
2. Pouring Concrete - Post & Rebar STA 1+000 to 5+000 2001 1872 0 Post
7. Installation - Frame & Welded Mesh Panel STA 0+000 to STA 2+000 2033 1139 13 Span (3m) STA 1+842 - 1+812, 1+100 - 1+094, 1+221 - 1+224 Cecep Anggi
8. Installation - Razor Wire STA 1+ 000 to STA 2+000 2033 257 0 Span (3m)
STA 1+221 - 1+254, 1+100 - 1+094, 1+055 - 1+052,
9. Tightening bolt STA 0+000 to 5+000 2033 157 19 Span (3m) Cecep Anggi
1+025 - 1+028
c Site Preparation
1. Site Clearing STA 1+000 to STA 2+000 5700 10090 0 m' Insulation Laydown Michael BJ Poli
3. Drilling - Fence Post STA 2+000 to STA 4+000 2001 2040 0 Post
STA 4+000 to STA 6+000 Additional total Qty of new patrol road as per drawing
4. New Patrol road (Subgrade) 5112 3300 0 m2
STA 13+900 to STA 14+202 number 0010 approval
STA 4+000 to STA 6+000 Additional total Qty of new patrol road as per drawing
5. New patrol road (Subbase) 5112 3300 0 m2
STA 13+900 to STA 14+202 number 0010 approval
STA 4+000 to STA 6+000 Additional total Qty of new patrol road as per drawing
6. New patrol road (Basecoarse) 5112 0 0 m2
STA 13+900 to STA 14+202 number 0010 approval
7. Site Clearing for New Log Pond New Patrol Road Area 2500 2500 0 m2
1. Main gate 5 0 0 ea
2. Gate personal 4 0 0 ea
1. Installation - Fence Post & Rebar STA 4 + 000 to STA 5+ 000 New Patrol Road 30 Pole Continue Junianto
2. Pouring Concrete - Post & Rebar STA 4 + 000 to STA 5+ 000 New Patrol Road and CWAA 30 Pole Continue Junianto
3. Excavation - Tie Beam STA 2 + 000 to STA 3 + 000 LCR24 , CWAA 30 Span (3m) Continue Mardi
Wawan
4. Pouring Concrete - Tie Beam STA 2 + 000 to STA 3 + 000 LCR24 , CWAA , Log Pond 30 Span (3m) Continue
Mardi
5. Installation - Frame & Welded Mesh Panel STA 4 + 000 to STA 5 + 000 Log pond 30 Span (3m) Continue Edwin
c Site Preparation
1. Site Clearing STA 3 + 000 to STA 4 + 000 Hill laydown & AR6 0 m2 -
STA 14 + 000 to STA 15 +
2. Grading & Levelling (25% of total length x 3m width) Hill laydown , AR6 200 m2 - -
000
3. Drilling - Fence Post STA 0 + 000 to STA 1 + 000 New Patrol Road 120 Post
5. New patrol road (Subbase) STA 4+000 to STA 6+000 STA 4+000 to STA 6+000 0 m2
6. New patrol road (Basecourse) STA 4+000 to STA 6+000 STA 4+000 to STA 6+000 0 m2
3. Duct Bank 2 ea
1. Main gate 0 ea
2. Gate personal 0 ea
Number
Role Name Remark Manpower Manhour
Day Shift
Construction Manager 2 Agustinus, Wahyu D P Previous Today Total Previous Today Cummulative
HSSE Manger 0
HR 2 Arnold
Civil Superintendent 1 Nanang Ali
Gerald, Saepudin,
Civil Supervisor 3
Hasmaul
Site Engineer 1 Fitrianto Supramono 10026 144 10170 111859 1584 111870
Environmental Engineer 1 Ade Firmawan
Commercial team 2 Aang, eib
Topan, Martahum,
Surveyor Crew 5
Frengky, Dede
Quallity Control Team 2 Nanang S & Ronald
Arief, Bagus, Marto,
HSSE & Medic 5 Equipment Time sheet
Adnan, Musa
Administrator Construction 1 Nanang C Nurdiana
Permit applicant 8 Mesa, Philip, mardi, Michael, Asep Previous Today Total Previous Today Cummulative
Scaffolder 4 Edwin, Tarlam, Ary, Aen
Electrician & Mechanic 4 Darius, Agung, Deni, Zulkifli
Operator & Driver 11
Lifting Crew 2 Rantau Galih, Sudarto
Welder 5
Flagman 5
Civil Crews 56
2474 12 2486 3758 127 3885
Foreman Warehouse 1 Enday Suhendar
Skeleton Team 23 Skeleton TEP
Proposional work (CVP03)
Total 144
F. CONSTRUCTION ISSUE
Advised /proceed
No Description Issued On Closed on Duration (day) Solution / Remarks
by
1. Access Blocked by Shelter CSTS at STA 3 + 350 to STA 3 + 400 11-Jul-24 14-Jul-24 3 Closed
2. STA 2 + 170 to Sta 2 + 500, fence to be re-route due to SPMT Road (Waiting ECC Early Work) 09-Aug-24 29-Aug-24 20 Closed
3. STA 2 + 850 to STA 2 +950, Fence to be re-route due to SPMT Road (Waiting ECC Early Work) 09-Aug-24 29-Aug-24 20 Closed
4. STA 3 + 500 to STA 3 + 600, Fence to be re-route due to SPMT Road (Waiting ECC Early Work) 09-Aug-24 29-Aug-24 20 Closed
5. Access Blocking by LUT Activity at STA 2 + 950 to STA 3 + 050 10-Jul-24 14-Jul-24 4 BP TSEP Closed
6. Access Blocked by Shelter CSTS at STA 1 + 600 to STA 1 + 700 18-Jun-24 25-Jul-24 37 LCI TSEP Closed
7. TMC troubled with its engine and radiator, unable to deliver materials, on going to repair 20-Aug-24 22-Aug-24 2 LCI TSEP Closed
G. HSE CONCERN
No Description Issued On Closed on Duration (day) Advised /proceed Solution / Remarks
1. N/A
2. N/A
1. 2.
Install Formwork Bracing at Insulation Laydown STA 1+812 - 1+824 Tre Cutting and Site Preparation Insulation Laydown
3. 4.
Install Fence Panel at Logpond 'STA 1+842 - 1+812, 1+100 - 1+094, 1+221 - 1+224 Manual Digging Tie Beam at Insulation Laydown 'STA 4+640 - 4+658
5. 6.
Tightening Bolt at Logpond 'STA 1+221 - 1+254, 1+100 - 1+094, 1+055 - 1+052, 1+025 - 1+028 Pouring Concrete Tie Beam at Insulation Laydown STA 2+789 - 2+834
COMMENTS (COMPANY) :
COMMENTS (CONTRACTOR) :
CONTRACTOR COMPANY
REVIEWED BY: APPROVED BY: ACKNOWLEDGED BY:
Fitrianto S. Digitally signed by Wahyu
Dwitya Pradipta
DN: OU=Leighton Contractors
10:17: leighton.co.id
Location:
(.............................................................)
Date: 2024.10.06
27+09'00' 17:34:04
+09'00'