FIS Method Statement For Installation of Access Control System
FIS Method Statement For Installation of Access Control System
1
Content
1- Purpose
2- Scope
3- References, Legislation & Code of Practice
4- Definitions
5- Responsibilities
6- Resources
6.1 Equipment & Tools
6.2 Human Resources
7- Work Procedure / Sequence of Work
7.1. Safety Requirements
7.2. Handling and Storage
7.3. Installation of ACS System
8- Appendices
• Appendix A Inspection Check List
• Appendix B ITP
• Appendix C Risk Assessment
2
1.0 PURPOSE
This Installation method statement covers the Guidance of Installation of the Access
Control System which will be installed in the project: Radiant Square at Reem Island.
The Access Control System Includes the following:
2.0 SCOPE
This document details the Security access control system Installation for
Implementation proposed to the project as follows:
2.1 Preparation of work
2.2 Delivery and inspection upon arrival of material at site.
2.3 Installation & Inspection of the system.
3.0 REFERENCE
- Specifications
- Samples approved
- Project Quality Plan
- Project HSE plan
- Approved Material submittal
3
4.0 DEFINITIONS:
Responsibilities for ensuring that the steps in this procedure shall be carried out are
specified at relevant steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Technician
- Project Manager is the overall responsible for the project in terms of work execution,
safety, planning & quality. The Project Manager will maintain the planning progress
and coordination of works with the main contractor.
- The work progress shall be carried out as per planned program and all the
equipment’s required to execute the works shall be available and in good condition
as per project planned.
4
- Specific attention is paid to all safety measures and quality control in coordination
with the Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
- The Construction Manager is responsible to supervise and control the work on site.
- Coordinating with QA/QC Engineer site Team and foremen for all activities on site.
- Control and sign all WIRs before issuing to Consultant approval.
- The monitoring of executions of works at the site should be as per the approved shop
drawings and project specifications.
- Ensure WIRs and MIRs are being raised for activities in a timely manner and
inspected by the Consultant.
- Check and ensure that all activities/work are done/completed prior to the offer for
consultant inspection.
- He will follow and carry out all the relevant tests per project specifications.
- Obtain the required clearance prior to the Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with the site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
5
5.5 Site Foreman
- The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for future planning with the
Site Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned
Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same
to the Site Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that
the whole workforce is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working
environment on the work activity.
- Inspection of all the site activities and training personnel in accident prevention and
its proper reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personnel shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high-risk elevated areas are provided are barricades, tape, safety nets, and
provided with ladders.
- Ensure service area/inspection area openings are provided with barricades, tape,
and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material
delivered to the site and keep it in a suitable area that will keep the material safe
from rusty and damage.
- One who will acknowledge the receiving of materials at the site in coordination with
QA/QC and the concerned Engineer.
6
5.8 Technician:
- The carrying-out of work and the proper distribution of all the available resources in
coordination with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for future planning with the
Site Engineer.
- Complying with the sub-contractors' basic design practices, particularly those
related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same
to the Site Engineer immediately.
6.0 RESOURCES
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Technician
7
7.0 PROCEDURE
8
7.3 Installation of the ACS system:
- The correct installation of the Host controller and Door Controller which is essential
to the success of the system.
- All Door Master Controllers will be networked through TCIP/ and slave controllers
will be connected via RS485
- The maximum length of TCIP (Master controller) must not exceed 90 meters.
- The Slave controllers to the master controller will be via RS485
- Readers are to be wired to the respective controller using OSDP
- The Readers, EM locks, push button, and door contacts are installed and terminated
properly using the specific cables approved in the drawings
- All Controllers will be installed in Enclosures and will have additional power
supplies as required for the system operation
- Controller cabinet doors shall open a minimum of 170 degrees to avoid blocking
personnel movement.
- Provisions shall be made for field wiring to enter the cabinet via standard knock-outs
at the top, bottom, and sides of controller cabinets.
- Each wire shall be identified at both ends with the labeled
- All exposed wiring within the cabinets, consoles, and terminals shall be formed
neatly with wires grouped in bundles using non-metallic, flame-resistant wiring
cleats or wire ties.
- All ferrous metalwork shall be painted, in accordance with the manufacturer’s
standards.
- All cables are to be numbered while laying the cable and wiring the system. Masking
tape or a proprietary numbering system can be used.
a. Cabling Works
- All The cables will be pulled for the field devices from the Door to the Respective
Door Controller Location.
- All the Cables used must be as per the approved types in the material submittal
- The Cables will be temporarily labeled at both ends after completing the cable-
pulling
- Cable testing will be carried out and consultant inspection will be raised and
approval availed if any comments are issued will be addressed and approval availed
9
3. Emergency Break glass as per the drawings
4. Push to Exit Button
5. Card Reader
The terminated cables will be labeled at both ends as per the labeling scheme
Installation Inspection will be carried out and consultant inspection will be raised
and approval availed if any comments are issued will be addressed and approval
availed.
8.0 APPENDICES
10
CHECK LIST FOR: Form No:
Access Control System Installation – Inspection of all cabling works Rev. No :
Page : 1 /2
SUBCONTRACTOR CONTRACTOR
1
Stage. Item Checked By: Date
S/C Contractor Consultant
1. Adequate lights are provided in
the Work Area prior to
installation.
2. All terminations cables have
been checked for any damage
or improper connections.
3. Ensure that barricade & warning
boards on the area are available
prior to installation.
4. Ensure all supports have been
properly installed & fixed prior
SAFETY PRECAUTIONS
2
CHECKLIST FOR: Form No:
Access Control System Installation – Door Perphials Installation Rev. No :
Page : 1 /2
SUBCONTRACTOR CONTRACTOR
3
CHECKLIST FOR: Form No:
Access Control System Installation – Enclosures & Door Controllers Rev. No :
Installation Page : 1 /2
SUBCONTRACTOR CONTRACTOR
Enclosure
2. Check the installation of the
Door Controller inside the
Enclosure.
3. Check the Installation Power
supply
4. Check the Termination of all
Perphials inside the
controllers
5. Check the termination of the
Network cable
6. Check the labeling of all the
cables
7. Check the Installation battery
back up inside the panels
8. Check the Termination power
supply unit
9. Check the installation of the
battery back up
10. Check all the panels are
labeled
4
CHECKLIST FOR: Form No:
Access Control System Installation – Control room equipment Rev. No :
Page : 1 /2
SUBCONTRACTOR CONTRACTOR
5
INSPECTION & TEST PLAN (ITP) For Installation of Access Control System
Main Contractor Maliah Investments & Projects Development Sp. System Integrator Future Integerated Systems LLC
Works Location (This ITP reflects status of testing/ inspection in the following area/ zone within the Project)
Responsibility1
Applicable
Frequency of Test / Contractor
SN Inspection / Test to be carried out Acceptance Criteria Specification / Control Data / Forms Inspection Method Completion Date
Inspection Third Party
Standard Subcontractor Consultant
Main Contractor (if any)
(if applicable)
A Preliminary Works
Specification
Delivered Material as Delivery Notes &
2 Material Inspection Every Delivery
per approval
UT Technology
MIR
Check qty , Type & Sizes P R A N/A
Ver11
Specification
All Materials and Accessories to be fixed were
2 approved Materials Every MIR Approval of MIR UT Technology Checklist Inspection P A H
Ver11
Specification
3 Installation of Access Control System Every WIR Approval of WIR UT Technology Checklist Inspection P S H
Ver11
MEP SERVICES related to the system were
4 completed and approved Every WIR Approval of WIR Checklist Inspection P S H
Specification
Location where the System to be installed were as
5 per approved drawings Every WIR Approval of Drawing UT Technology Checklist Inspection P S H
Ver11
Form. Ref.---------------------------------------------------
RISK ASSESSMENT
Radiant – Square
TITLE OF THE ACTIVITY: Installation of Access Control System Rv 0
ASSESSOR: Future Integrated Systems LLC ASSESSMENT DATE: 25/09/2023
Activity / Hazard Identified Persons/Assets/ Consequences Existing Control Measures Inherent Additional Control Responsible Residual
Task Environment/ (Risk / Impact) Risk Rating Measures Party Risk Rating
Exposed L S R L S R
followed
· Hard barricades should be
provided to isolate the working
areas.
· Prohibition of entry to working
areas by installation of safety
signages like danger and
• Collision with other Construction
warning signs. • All supervision to
equipment’s/machinery Manager, Project
Delivery of • Harm to · Any materials to be delivered monitor operation;
Materials
and vehicles All Involved 3 3 9 Engineer, 1 1 1
people/services should be planned with proper Regular topic in
• Damaging existing Supervisors,
coordination from the driver and TBT’s
services Forman
a banks man with a flag and
adequate supervision from the
supervisor
· Traffic Management Plan should
be followed as per as OSHAD
CoP 44.0
RISK ASSESSMENT
Radiant – Square
TITLE OF THE ACTIVITY: Installation of Access Control System Rv 0
ASSESSOR: Future Integrated Systems LLC ASSESSMENT DATE: 25/09/2023
Site Engineer/
Technician
• Work notification to be
applied and obtained prior to
start the night work from
contractor.
• Adequate illumination • Adequate lighting
While working • Poor illumination • Fatality shall be provided shall be provided
at night shift
Staff 2 2 4 while working at
Site Supervisor 1 1 1
Slip/trip/fall Cuts • light post to be secured
from fall night.
• Proper cable
management system to be
followed.
• Drink plenty of water
• Employees shall be
trained about heat stress
symptoms & first aid measures.
• Avoid highly physical • Provide
tasks during the hottest part of
• Dehydration sufficient rest breaks
Working in hot the day based on the humidity
Heat Stress All Involved • Sunburn 4 4 16 Technician 2 2 4
weather • Isotonic drinks to be & temperature
Skin Cancer
provided conditions.
• Heat stress management plan
RISK ASSESTMENT