CONCRETE
What is concrete?
Concrete is a mixture of sand, gravel, crushed rock, or
other aggregates held together in a rocklike mass with a
paste of cement and water. Sometimes one or more
admixtures are added to change certain characteristics of the
concrete such as workability, durability, and time of
hardening.
As with most rocklike substances, concrete has a high
compressive strength and a very low tensile strength.
Reinforced concrete is a combination of concrete and steel
wherein the steel reinforcement provides the tensile strength
lacking in the concrete. Steel reinforcing is also capable of
resisting compression forces and is used in columns as well
as in other situations.
Classes of Concrete Mixture
Class Propor tion Cement(bag) Sand( cu.f t.) Gravel( cu.f t ) Water
AA 1:2:3 1 2 3 5gal(19liter s)
A 1:2:4 1 2 4 6gal(23liter s)
B 1:2.5:5 1 2.5 5 7.5gal(29lit)
C 1:3:6 1 3 6 9gal(35liter s)
D 1:3.5:7 1 3.5 7 10.5gal(40lit)
Manpower Capability:
a. Concreting using lean concrete
– 2 men can pour 1.20 cu.m./day
b. Concreting of reinforced slab
– 2 men can pour 0.80 cu.m./day
c. Concreting of beam/column
– 2 men can pour 0.50 cu.m./day
Mixture= 1 : 2 : 3
Slab thickness = 100mm
Cement = PHP 250.00/bag
Sand = PHP 1,600.00/cu. m.
Gravel = PHP 1,600.00/cu. m
Water = PHP 175.00/cu. m
Mixer Operator = PHP 500.00/day
Carpenter = PHP 500.00/day
Mason = PHP 500.00/day
Laborer = PHP 404.00/day
1 Bagger Concrete Mixer = 1,000.00/day
Fuel = 50.00/Liter
Volume of concrete
= Vol. of footing + Vol. of WF + Vol. of
Slab + Vol. of Column + Vol. of Septic Tank
cover and floor + Vol. of Grease Trap
cover & floor + Vol. of Catch Basin + Vol. of
Beam + Vol. of Roof Beam + Vol. of Stairs +
Vol. Of Kitchen counter + Vol. of Baluster
toppings+ Vol. of Lintel beam
Volume of F1 (16 units) = L x W x T x (no. of units)
= (1.50m x 1.50m x 0.30m) (16 units)
= 10.80 cu. m.
Volume of F2 (4 units) = L x W x T x (no. of units)
= (1.80m x 1.80m x 0.35m) (4 units)
= 4.536 cu. m.
Volume of Footings = 15.336 cu. m.
Length of WF – 1 = 62m
Volume of WF – 1 = W x T x Length of WF-1
= 0.40m x 0.20m x 62m
= 4.96 cu. m.
Length of WF – 2 = 26m
Volume of WF – 2= Area of Trapezoid x Length of WF -2
0.45m:0.25m
= x 0.10m (26m)
2
= 0.91 cu. m.
Volume of WF = 5.87 cu. m.
Ht of column = 7.50m
Volume of Column (14 units) : From Ground floor to Roof Beam
= b x b x Ht of Col x no. of col.
= 0.20m x 0.20m x 7.50m (14 units)
= 4.2 cu. m.
Volume of Column at the Ground floor(6 units)
= b x b x ht. of column
= 0.20m x 0.20m x 4.5m x 6 units = 1.08 cu.m.
Length of Beam = 113.0m
Volume of Beam= b x h x Length of Beam
= 0.20m x 0.35m x 113.0m
= 7.91 cu. m.
Length of Roof Beam = 74.0m
Volume of Roof Beam=b x h x Length of Roof Beam
= 0.20m x 0.35m x 74.0m
= 5.18 cu. m.
Length of Lintel Beam = 112.50m
Volume of Lintel Beam=b x h x Length of Lintel Beam
= 0.10m x 0.25m x 112.50m
= 2.813 cu. m.
Volume of Floor Slab=Ground Floor Area x Thickness of Slab
= 121.0m 2 x 0.10m
= 12.10 cu. m.
Volume of Stairs
= Area of Trapezoid x Length x (no. of steps)
0.35m:0.15m
= x 0.18m (1.0m) x (15) +
2
(1.0m x 2.0m x 0.10m)
= 0.875 cu. m.
Vol. of Septic Tank cover & floor
= (L x W x T) (2)
= (3.15m x 1.20m x 0.10m) (2)
= 0.756 cu. m.
Volume of Catch basin floor
= L x W x T (no. of units)
= 0.80m x 0.80m x 0.05m x (6 units)
= 0.192 cu. m.
Volume of Grease Trap
= L x W x T (1 unit)
= 0.60m x 0.60m x 0.05m x (1 unit) (2)
= 0.036 cu. m.
TOTAL VOLUME OF CONCRETE = 65.043 cu. m.
*Using 1 : 2 : 3 Mixture:
c : w = 1 : 19 Liters
Volume of Cement
Cement Ratio (Density of Cement)
=
Specific Gravity of Cement (Density of Water)
1 ft 3 0.0283m 3 /ft 3 (1411 kg/m 3 )
=
3.14 (1000 kg/m 3 )
Volume of Cement = 0.0127 cu. m.
Sand Ratio (Density of Sand)
Volume of Sand =
Specific Gravity of Sand (Density of Water)
2 ft 3 0.0283m 3 /ft 3 (1684 kg/m 3 )
=
2.65 (1000 kg/m 3 )
Volume of Sand = 0.0359 cu. m.
MATERIALS:
No. of bags of cement
= (No .of Batches) x (Cement Ratio / batch)
= (545.205 batches) x 1bag / batch
= 545.205 bags ≈ say 546 bags
Req’d Volume of Sand
= (No .of Batches) x (Sand Ratio / batch)
= (545.205 batches)x(2ft 3 ) x (0.0283m 3 /ft 3 ) x 1.10
= 33.94 cu. m. ≈ say 34.0 cu. m.
Req’d Volume of Gravel
= (No .of Batches) x (Gravel Ratio / batch)
= (545.205 batches)x(3ft 3 ) x (0.0283m 3 /ft 3 ) x 1.10
= 50.92 cu. m. ≈ say 51.0 cu. m.
Req’d Volume of Water
= (No .of Batches) x (Water Ratio/batch)
= (545.205 batches) x (19L/batch) x (1m 3 /1000L)
= 10.36 cu. m. ≈ say 10.50 cu. m.
A. MATERIAL COST: