Estimate Vertical Gate

Uploaded by

Irfan Ansari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 45

GOVERNMENT OF MADHYA PRADESH

WATER RESOURCES DEPARTMENT

WATER RESOURCES DEPARTMENT

BODHI

ROSHNABAD BARRAGE

ESTIMATION REPORT

1
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
UNIT-I
C-WORKS
ABSTRACT ESTIMATE FOR THE CONSTRUCTION OF SPILLWAY

SL. RATE
DESCRIPTION OF ITEMS UNIT QUANTITY AMOUNT Rs. Ref USR
NO. Rs. Ps.
1 2 3 4 5 6
1 Medium shrub jungle(25% to 50% area
covered by shrubs) clearance involving
removal of grass, shrubs, bushes and
twigs including rooting out & disposal etc. per sqm 4052.84 1.60 6,484.54 9.02
Complete.

Preparing foundation bed for masonry or


concrete by removing all loose material by
wedging / chiselling upto 150 mm and
disposing off the same as directed and
2 cleaning the surface with air and water jet per sqm 7810.00 52.00 406,120.00 3.01
including cost of all materials, machinery,
labour etc. Complete.

Excavation in all kind of


soft/loose/hard/dense soils, moorum &
moorum mixed with boulders and mud
including dressing, placing the excavated
soil neatly in specified dump area or
3 disposing off the same as directed per cum 74727.76 80 5,978,221.03 2.01 (a)
including cost of site clearance, all
materials, machinery, labour and dressing
etc. complete with lead up to 50 m and all
lifts.

Excavation in soft/ disintegrated/


weathered rock including wet excavation,
dressing, placing the excavated material
neatly in specified dump area or disposing
off the same as directed including cost of
4 per cum 49818.51 80 3,985,480.69 2.02 (b)
site clearance, all materials, machinery,
labour and dressing etc. complete with
lead up to 50 m and all lifts.

Excavation in hard rock of all toughness


requiring blasting, minimising damage to
rock beyond excavation line and placing
the excavated rock neatly in specified
dump area or disposing off the same as
directed including wet excavation, cost of
5 site clearance, all materials, machinery, per cum 124546.27 120 14,945,552.59 2.03 (a)
labour etc. complete with lead up to 50 m
and all lifts.
Providing and fixing 25 mm dia. 3 m long
cold twisted deformed steel dowel bars
with one end driven into 38 mm diameter
1.50 m deep hole drilled in bed rock and
other end provided with Lbend for
embedding in concrete / masonry of over
6 flow / non-over flow blocks and other Each 193.00 1171 226,003.00 3.11
appurtenant works including cost of all
materials, machinery, labour, drilling and
cleaning hole, filling hole with specified
cement mortar, driving anchor rod etc.
complete with all lead and lifts.

Wet percussion drilling 50 to 75 mm dia.


holes in drainage gallery, for grouting,
7 drainage holes or anchor etc., vertical or at
specified inclination, in masonry concrete
or rock up to 10 m depth
(i) 0° to 10° vertically downwards per Rmt 2443.50 1090.00 2,663,415.00 3.03.3.1
Consolidation grouting with neat cement grout
mix of suitable consistency under specified
grout pressure as directed in drilled holes by
stage grouting method including cost of all
materials, machinery, labour, re-drilling if
8 per tonne 61.00 9081 553,941.00 3.08
necessary, required admixtures etc. complete
with all lead and lifts.

Providing and laying M-15 grade Mass


Concrete design mix using graded aggregates ,
clean, hard, including cost of all materials,
machinery, labour, formwork, cantering,
scaffolding, cleaning, batching, mixing, placing
9 in position, levelling, vibrating, finishing, curing per cum 50087.1 3048 152,665,572.2 3.15.3
etc. complete with lead up to 50 m and all lifts.
Using aggregate of maximum size. (a) 40mm

Providing and laying M-20 grade Mass


Concrete design mix using graded
aggregates , clean, hard, including cost of
all materials, machinery, labour, formwork,
cantering, scaffolding, cleaning, batching,
mixing, placing in position, levelling,
10 per cum 17123.13 4223 72,310,969.54 3.16.3
vibrating, finishing, curing etc. complete
with lead up to 50 m and all lifts. Using
aggregate of maximum size. (a)
40 mm

Providing and laying M-20 grade RCC


design mix using graded aggregates,
clean, hard including cost of all materials,
machinery, labour, formwork, cantering,
scaffolding, cleaning, batching, mixing,
12 placing in position, levelling, vibrating, per cum 40176.50 4223 169,665,376.39 3.18.1
finishing, curing etc. complete with lead up
to 50m and all lifts using aggregate of
maximum size. (a) 40mm
Providing and laying M-25 grade RCC
design mix using graded aggregates ,
clean, hard including cost of all materials,
machinery, labour, formwork, cleaning,
batching, mixing, placing in position in
alternate panels as directed, levelling,
13 compacting, finishing, curing, packing per cum 7450.95 4893 36,457,498.35 3.19.1
joints of shuttering with asphalt mortar etc.
complete with lead up to 50m and all lifts
using aggregate of maximum size.
(a)40mm

Providing and laying Cement concrete


wearing coat M-30 grade
including reinforcement complete as per
drawing and Technical MP PWD
14 Specifications and as per relevant clauses per cum 625.46 10932 6,837,556.05 SOR 14.4
of sections 1500, 1700 and P-68
Clause 2702 of specifications..

Providing elastomeric bearings such as


restrained neoprene bearings or any
other type with mild steel plates or
shims, manufactured as per specifications
15 given in the approved cucm 907200 2 1,814,400.00 5.25
design of the bearings, includingpacking,
fixing with adhesives as specified in the
design etc. complete

Providing and forming expansion joint for


bridge consisting of 75 x 75 x 6 mm
angles 2 numbers provided with 250 mm
long 12 mm dia. anchors fixed to both
flanges at 150 mm c /c and 140 x 6 mm
plate welded on top of one of the
16 angle including cost of all materials, per m 126.00 1495 188,370.00 5.27
labour, machinery, providing and fixing
38 mm thick joint filler board
matching the thickness of wearing
coat, painting etc. complete

Providing and constructing PVC pipe


weep holes for concrete / masonry
walls including cost of all materials,
machinery, labour, providing 200 x
200 x 200 mm size porous concrete
block made of cement and 20 mm
17 down coarse aggregate in 1 : 4 per m 1332.80 243 323,870.40 5.26
proportion by volume with 100 mm
thick sand backing at the junction of
wall and soil back fill, etc.,
complete- 100 mm dia pipe

Providing, fencing and erecting 50 mm dia


(weighing 3.56 kg per mts.) painted steel
pipe railing in 3 rows on precast M20 grade
RCC vertical posts1.8 metres high (1.2 m
above GL) with 3 holes 50 mm dia for pipe, MP PWD
18 fixed 2 metres centre to, complete as per per m 390.00 1308 510,120.00 SOR 8.23
approved drawing. P-47
Providing, fabricating and placing in
position steel reinforcement bars for
Reinforced cement concrete / Plain
Cement Concrete structures including cost
of all materials, machinery, labour,
cleaning, straightening, cutting, bending,
19 hooking, lapping / welding joints wherever Tonne 1632.98 66936 109,305,155.97 3.13
required, tying with 1.25 mm diameter soft
annealed steel wire etc. complete with lead
up to 50 m and all lifts.

Providing and fixing in position 1mm thick


and 355 mm wide annealed copper sealing
strips In contraction joints, including
bending to specified shape and providing
butt joints with overlap of 50 mm and 10
mm dia. M. S. anchor rods of 600 mm
20 per m 188.00 2893 543,884.00 3.3
length at 900 mm centre to centre
alternately on both sides, Including welding
and brazing of anchor bars and joints, etc.
complete in all
respect

Dewatering and pumping the working area


including all connecting operation required
etc. complete. for
21 HOURS 28800.00 293 8,438,400.00 3.55.3
cleanliness of working area by 10 hp to 20
hp diesel pump

22 All types of Gate & Allied works As per Attached Detail 4,324,018.49 8.02
23 Coffer Dam As per Attached Detail -
24 Elevator As per Market rate 0
25 Room at elevator As per Market rate 0
26 Air vent pipe and Drain pipes As per Market rate 0
24 Electrification Work As per Market rate -
27 Generator Room ( 2 no.) As per Market rate 1000000
28 Instrumentation in Dam As per Market rate 0
29 Deduct for Govt Excavated rock 124546.27 -105.00 -13,077,358.51
TOTAL = 580,073,050.8
Instrumentation charge @ 0.5% 2,900,365.25
-
GRAND TOTAL 582973416.03.
Say ₹ 5829.7 Lakh
ROSHNABAD BARRAGE
UNIT - 1 HEAD WORK
ABSTRACT OF COST FOR - 'C' WORKS

S. No Description Amount
(in Rs. Lakhs)
1 Abstract of Cost for Masonry works for:

a Concrete 5829.73
b Earthen 39816.03
Total Rs 45645.76 Lakh

6
NAME OF PROJECT :- ROSHNABAD BARRAGE
Vertical Gate quantity
1 Width/Length of gate = 4.40 M

2 Height of gate = 3.00 M

3 Water head above sill = 3.00 M

4 Spill way length = 1.00 M

5 Span of hoist bridge = 2.00 M

6 Gantry Capacity = 10.00 T


7 No. of Vertical gate = 1.00 NO
8 Stoplog = 1.00
9 FSL = 422.00 M
10 SILL = 419.00 M
11 MWL = 422.00 M
12 TBL = 423.70 M
13 Pier thick = 1.00 M

Weight of 1 vertical lift gate including Vertical Gate


embedded parts in tonnes
V
E
R = 0.0690 x (L^2xHxh)^0.716
T
I (L) is length = clear vent width
C = 4.4 + 1 = 5.4 M
inm+1.0m.
A
L
(H) is height of gate in m = clear vent = 3.00 + 0.2 = 3.20 M
G height in m+0.20m.
A
T (h) is head of water above sill of gate in = 422.00 - 419.00 = 3.00 M
E m = FSL – Sill level

= 0.0690 x (L^2xHxh)^0.716 = 3.899 3.899 MT

1 Weight of vertical gate = 3.899 x 1.000 = 3.899 MT

Weight of Embedded Parts to be taken = 3.899 x 0.320 = 1.248 MT

Weight of Stoplog elements including 1 Set of stoplog gate


embedded parts in tonnes

S
T = 0.0578 x (L^2xHxh)^0.716
O
P
L (L) is length = clear distance between
O = 4.4 + 0.65 = 5.05 M
piers in m+0.65 m.
G
(H) is total height of stoplog gate in m = = 3.00 + 0.2 = 3.2 M
FRL – Sill level +0.20m.
(h) is head of water above sill of gate in = 422.00 - 419.00 = 3 M
m = FRL – Sill level
Weight of one gate = 2.967 MT
Number of gate = 1 x 2.967 = 2.967 MT
Embedded Parts = 1.00 x 0.534 = 0.534 MT
Weight of Embedded Parts = 1.25 + 0.534 = 1.782 MT
No. of Pieces = 1 One Piece 1
Weight of Automatic Lifting beam in
tones = 0.02212 x (L^2xHxh)^0.716/n
(L) is length = clear distance between = 4.4 + 0.65 = 5.05 M
piers in m+0.65 m.

(H) is total height of stoplog gate in m = = 3.00 + 0.2 = 3.2 M


FRL – Sill level +0.20m.

(h) is head of water above sill of gate in = 422.00 - 419.00 = 3.00 M


m = FRL – Sill level

(n) is number of gate elements in 1 set = = 1 NOS


= = 1.136 MT
Say 1.1 MT

Gantry Crane (No. of stoplog gate+No. of pieces*2.5) 5 MT

Columns with
bracings/Anchors/Stiffeners : 400kg per 1.6 MT
meter height

Beams with cross beams/stiffeners : 6.48 MT


400kg per meter span
Railing/ Chequered plate/Ladder etc. : 0.808 MT
10% of wt. of columns/beams

Weight of trunnion bridge : 300kg per 0 MT


meter length of catwalk

Structural Steel = 8.888 MT

ROSHNABAD BARRAGE
Item No Item = Quantity Total Q Unit Rate Amount
801 Embedded parts of vertical stop log gate 1.782 MT 1.782 T 123776.000 220,537.59
802 Radial gate T
803 Vertical gate wheel type 3.899 MT 3.899 T 130139.000 507,400.19
804 Vertical lift sliding type gate Stoplog gate 2.967 MT 2.967 T 135875.000 403,168.74
805 Vertical lift sliding type Shutter gates MT T
806 electrically operated rope drum hois 9.750 MT 0.000 T 40556.000 -
806 manually operated rope drum hoist MT T
808 screw type hoist T
809 Moving Gantry Crane ( round off ) 0.000 MT 0.000 T 190592.000 -
810 Automatic lifting beam 1.136 MT 1.136 T 160575.000 182,340.23
811 Structural steel hoist bridge/ 8.888 MT 8.888 T 101797.000 904,771.74
812 mono-rail hoist 40.000 MT 40.000 T 52645.000 2,105,800.00
813 EOT crane MT T 139425.000
814 Hydraulic Hoist MT T 85820.000
815 Sluice gate MT T
816 Rail track using 45 kg M T 6550.000
Total Weight 68 TOTAL 4,324,018.49
0.43
CRORE
ROSHNABAD BARRAGE

TEHSIL :-SIDHI DISTRICT :SINGRAULI


UNIT-I
C-WORKS
DETAILED ESTIMATE FOR THE CONSTRUCTION OF SPILLWAY

S.No. Item NOS L B H QTY. Unit

1 JUNGLE CLEARENCE AREA

Left NOF cum key wall 1 6.5 25.50 165.750 sqm

Right NOF cum key wall 1 6.5 25.50 165.750 sqm

OF 1 54.30 21.45 1164.735 sqm


Apron 1 54.3 32 1737.60 sqm
Key wall 1 5.00 6 30.000 sqm
Key wall 1 5.00 6 30.000 sqm
Training Wall-Section D/s 2 17 14.5 493.000 sqm
Training Wall-Section U/s 2 7.6 17.5 266.000 sqm

JUNGLE CLEARENCE
Total 4052.84 sqm
1
Medium shrub jungle(25% to 50% area
covered by shrubs) clearance involving
removal of grass, shrubs, bushes and twigs 100% of Total Area 4052.835
including rooting out & disposal etc.
Complete.

Preparing foundation bed for masonry or


concrete by removing all loose material by
wedging / chiselling upto 150 mm and
disposing off the same as directed and 1 156.20 50 7810.000
cleaning the surface with air and water jet
including cost of all materials, machinery,
labour etc. Complete.
3 Excavation in all kind of
soft/loose/hard/dense soils, moorum &
moorum mixed with boulders and mud
including dressing, placing the excavated
soil neatly in specified dump area or
disposing off the same as directed including
cost of site clearance, all materials,
machinery, labour and dressing etc.
complete with lead up to 50 m and all lifts. (As per Statement 1) 74727.763

4 Excavation in soft/ disintegrated/


weathered rock including wet excavation,
dressing, placing the excavated material
neatly in specified dump area or disposing
off the same as directed including cost of
site clearance, all materials, machinery,
labour and dressing etc. complete with lead (As per Statement 1) 49818.509
up to 50 m and all lifts.

5 Excavation in hard rock of all toughness


requiring blasting, minimising damage to
rock beyond excavation line and placing the
excavated rock neatly in specified dump
area or disposing off the same as directed
including wet excavation, cost of site (As per Statement 1) 124546.272
clearance, all materials, machinery, labour
etc. complete with lead up to 50 m and all
lifts.

6
Providing and fixing 25 mm dia. 3 m long
cold twisted deformed steel dowel bars
with one end driven into 38 mm diameter
1.50 m deep hole drilled in bed rock and
other end provided with Lbend for
embedding in concrete / masonry of over
32 54.3 193.000 Nos
flow / non-over flow blocks and other
appurtenant works including cost of all
materials, machinery, labour, drilling and
cleaning hole, filling hole with specified
cement mortar, driving anchor rod etc.
complete with all lead and lifts.

7
Wet percussion drilling 50 to 75 mm dia.
holes in drainage gallery, for grouting,
drainage holes or anchor etc., vertical or at
specified inclination, in masonry concrete
or rock up to 10 m depth

@ 3 m c/c 54.300
Depth 3
Total Qty of Drilling Drilling per Rmt 2443.5 Rmt
8 Consolidation grouting with neat cement
grout mix of suitable consistency under
specified grout pressure as directed in
drilled holes by stage grouting method
including cost of all materials, machinery,
labour, re-drilling if necessary, required `@ 25 kg per Rmt 61.09
admixtures etc. complete with all lead and
lifts.

Total Qty of Grouting say 61.00 Tonne


9 Providing and laying M-15 grade Mass
Concrete design mix using graded
aggregates , clean, hard, including cost of all
materials, machinery, labour, formwork,
cantering, scaffolding, cleaning, batching,
mixing, placing in position, levelling,
vibrating, finishing, curing etc. complete
with lead up to 50 m and all lifts. Using
aggregate of maximum size. (a) 40mm

40mm
Total Qty of C-1 50087.130 Cum
10 Providing and laying M-20 grade Mass
Concrete design mix using graded
aggregates , clean, hard, including cost of all
materials, machinery, labour, formwork,
cantering, scaffolding, cleaning, batching,
mixing, placing in position, levelling,
vibrating, finishing, curing etc. complete
with lead up to 50 m and all lifts. Using
aggregate of maximum size. (a) 40
mm

40 mm
Total Qty of C-2 17123.13 Cum
11 Providing and laying M-20 grade RCC design
mix using graded aggregates, clean, hard
including cost of all materials, machinery,
labour, formwork, cantering, scaffolding,
cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing,
curing etc. complete with lead up to 50m
and all lifts using aggregate of maximum
size. (a) 40mm

Total Qty of C-4 19919.25 Cum


12 Providing and laying M-25 grade RCC design
mix using graded aggregates , clean, hard
including cost of all materials, machinery,
labour, formwork, cleaning, batching,
mixing, placing in position in alternate
panels as directed, levelling, compacting,
finishing, curing, packing joints of shuttering
with asphalt mortar etc. complete with lead
up to 50m and all lifts using aggregate of
maximum size. (a)40mm

Total Qty of C-5 7450.95 Cum


13 Providing and laying Cement concrete Wearing
wearing coat M-30 grade Coat
including reinforcement complete as per (Road)
drawing and Technical
Specifications and as per relevant clauses of
sections 1500, 1700 and
Clause 2702 of specifications..

Total Qty of C-7 625.46 Cum


14 Providing elastomeric bearings such as
restrained neoprene bearings or any
other type with mild steel plates or
shims, manufactured as per specifications
given in the approved
12.00 6 12600 907200.00 CUCM
design of the bearings, includingpacking,
fixing with adhesives as specified in the
design etc. complete

15 Providing and forming expansion joint for


bridge consisting of 75 x 75 x 6 mm
angles 2 numbers provided with 250 mm
long 12 mm dia. anchors fixed to both
flanges at 150 mm c /c and 140 x 6 mm
plate welded on top of one of the
angle including cost of all materials,
labour, machinery, providing and fixing
38 mm thick joint filler board
matching the thickness of wearing
coat, painting etc. complete

12.00 10.50 126.00 Lm.


16 Providing and constructing PVC pipe
weep holes for concrete / masonry
walls including cost of all materials,
machinery, labour, providing 200 x
200 x 200 mm size porous concrete
block made of cement and 20 mm
down coarse aggregate in 1 : 4
proportion by volume with 100 mm
thick sand backing at the junction of
wall and soil back fill, etc.,
complete- 100 mm dia pipe

Weep hole in training walls


Total Expose area Lx H
Us 38.70 21.00 361.20 1.50 541.80
Ds 56.50 21.00 527.33 1.50 791.00
Total :- 1332.80
17 Providing, fencing and erecting 50 mm dia
(weighing 3.56 kg per mts.) painted steel
pipe railing in 3 rows on precast M20 grade
RCC vertical posts1.8 metres high (1.2 m
above GL) with 3 holes 50 mm dia for pipe, 2 195.00 390.00
fixed 2 metres centre to, complete as per
approved drawing.

18 Providing, fabricating and placing in


position steel reinforcement bars for
Reinforced cement concrete / Plain Cement
Concrete structures including cost of all
materials, machinery, labour, cleaning,
straightening, cutting, bending, hooking,
lapping / welding joints wherever required,
tying with 1.25 mm diameter soft annealed
steel wire etc. complete with lead up to 50
m and all lifts.

Surface Area
IN MCC work 6 kg per sq/m L H
NOF @ 6 kg/m² 2 6 10.00 29.50 3540 Kg
OF @ 6 kg/m² 11 6 18.05 32.00 38122 Kg
Stilling Basin @ 15 kg/m² 11 15 18.05 49.2 146530 Kg
Training wall for stilling basin @ 6 kg/m² 2 6 3.80 20 912 Kg
Training wall u/s @ 6 kg/m² 2 6 8.50 23.9 2438 Kg
Pier @ 100 kg/m3 12 100 3.80 298.34 1360430 Kg
Bridge @ 120 kg/m3 11 120 18.05 3.4 81008 Kg
Total RCC
Total 1632980.10 Kg
19 Providing and fixing in position 1mm thick
and 355 mm wide annealed copper sealing
strips In contraction joints, including
bending to specified shape and providing
butt joints with overlap of 50 mm and 10
mm dia. M. S. anchor rods of 600 mm
length at 900 mm centre to centre
alternately on both sides, Including welding
and brazing of anchor bars and joints, etc.
complete in all
respect

a In NOF Portion block joints 4.00 23.00 92.00 RM


b In O.F. Portion block joints 24 4.00 96.00 RM
Total Qty of PVC water joints 188.00 RM
20 Dewatering and pumping the working area
including all connecting operation required
etc. complete. for
cleanliness of working area by 10 hp to 20
hp diesel pump

a 5 PUMPS 16 HOURS 180 DAY FOR 2 28800.00 HOURS


YEARS
CONCRETE QUANTITY ESTIMATION OF ROSHNABAD BARRAGE
AREA QUANTITY
SECTION FROM TO LENGTH C1 C2 C3 C4 C5 C6 C1 C2 C3 C4 C5 C6
Key Wall 1510.0 1515.0 5 102 0 510
NON OVERFLOW 1515.0 1525.0 10 373.77 90.94 3737.7 909.4
OVERFLOW 1525.0 1720.0 195 137.15 56.2 33.65 5.56 26744.25 10959 6561.75 1084.2
Us Apron 1525.0 1720.0 195 15.3 0 2983.5
NON OVERFLOW/Power 47
House 1720.0 1767.0 0 0
Key Wall 1767.0 1772.0 5 102 510
PIER 12 3.8 300.34 13695.5
LEFT U/S TRAINING WALL 0 38.7 38.7 224.25 24.4 5207.085 566.568
RIGHT U/S TRAINING WALL 0 21.5 21.5 224.25 24.4 2892.825 314.76
LEFT D/S TRAINING WALL 0 56.5 56.5 154.65 20.5 5242.635 694.95
RIGHT D/S TRAINING WALL 0 56.5 56.5 154.65 20.5 5242.635 694.95
STILLING BASIN BOTTOM
STRLING BASIN TOP 0
0 195
684 195 102.15 32.65 19919.25 6366.75
684
D/S APRON 0 195 195 0 0
CUT OFF WALL DS APRON 0 195 195 0
BRIDGE DECK SLAB & 0 195 195
LONGITUDINAL GIRDER 1.8 351
Cross Girder 3 195 195 0 0.62 120.9
Wearing Coat 195 195 0 0.7875 153.5625
TOTAL:- 50087.13 17123.13 20257.25 19919.25 7450.95 625.4625
M-15 M-20 M-20 M-20 M-25 M-30
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
UNIT-I
C-WORKS
QUANTITY CALCULATION FOR EXCAVATION OF SPILLWAY (Statement 1)

Foundation
Chainage Length Avg. GL Width Depth of Cut slope T.W Area Mean Area Quantity Remark
Level
1510.0 0.000 377.62 360.000 24.920 17.620 0.50:1 42.540 594.323 297.161 0.000 Overflow
1530.0 20.000 370.34 360.000 24.920 10.340 0.50:1 35.260 311.131 452.727 9054.532 Overflow
1560.0 30.000 366.72 360.000 24.920 6.720 0.50:1 31.640 190.042 250.586 7517.583 Overflow
1590.0 30.000 366.62 360.000 24.920 6.620 0.50:1 31.540 186.883 188.462 5653.863 Overflow
1620.0 30.000 366.86 360.000 24.920 6.860 0.50:1 31.780 194.481 190.682 5720.454 Overflow
1650.0 30.000 366.81 360.000 24.920 6.810 0.50:1 31.730 192.893 193.687 5810.614 Overflow
1680.0 30.000 366.58 360.000 24.920 6.580 0.50:1 31.500 185.622 189.258 5677.726 Overflow
1710.0 30.000 367.3 360.000 24.920 7.300 0.50:1 32.220 208.561 197.091 5912.742 Overflow
1740.0 30.000 367.9 360.000 24.920 7.900 0.50:1 32.820 228.073 218.317 6549.510 Overflow
1770.0 30.000 372.94 360.000 24.920 12.940 0.50:1 37.860 406.187 307.374 9221.214 Overflow
1785.0 15.000 373.72 360.000 24.920 13.720 0.50:1 38.640 436.022 332.047 4980.710 Overflow

0 0 369.401 360.000 195.000 9.401 1.00:1 213.802 1921.554 960.777 0.000 Stilling Basin
49 49 369.401 360.000 195.000 9.401 1.00:1 213.802 1921.554 1921.554 94156.164 Stilling Basin

0 0 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 0.000 D/s L Training Wall
56.5 57 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 28979.878 D/s L Training Wall

0 0 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 0.000 D/s R Training Wall
56.5 56.5 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 28979.878 D/s R Training Wall

0 0 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 256.459 0.000 U/s L Training Wall
39 39 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 19849.934 U/s L Training Wall

0 0 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 0.000 U/s R Training Wall
21.5 21.5 377.620 360.000 20.300 17.620 0.50:1 37.920 512.918 512.918 11027.741 U/s R Training Wall

Total = 249092.543
D/s Spill portion Excavation:- 200 300 0 0
Total Qty of Excavation of Spill Channel = 249092.54 cum

i) HR (50%) = = 124546.27 cum


ii) D.I.R/S.R (20%) = = 49818.51 cum
ii) Soil (30%) = = 74727.76 cum
ROSHNABAD BARRAGE
UNIT I HEADWORKS
'L' EARTHWORK- ABSTRACT OF COST OF EARTHEN DAM

S.N Rate Amount


Item of Work Unit Qty. Ref. CSR
o. (in Rs) (in Rs)
1 2 3 4 5 6 7
Ordinary shrub jungle (area below 25% covered by shrubs)
1 clearance involving removal of grass, shrubs, bushes and twigs sqm 32120.00 0.70 22,484 9.01
including rooting out & disposal etc. complete.
Medium shrub jungle(25% to 50% area covered by shrubs)
2 clearance involving removal of grass, shrubs, bushes and twigs sqm 32120 1.60 51,392 9.02
including rooting out & disposal etc.complete.
Thick shrub jungle (area above 50% covered by shrubs)
3 clearance involving removal of grass, shrubs, bushes and twigs sqm 16060 2.90 46,574 9.03
including rooting out & disposal etc. complete
Removing stumps, tree roots etc., including excavation,
4 stacking materials neatly and levelling surface etc. complete.
Girth up to 0.60 m 1000 44.00 44,000 9.04.1
Girth over 0.6 m up to 1.2m 560 88.00 49,280 9.04.2
Stripping the seat of embankment of all foreign materials,
vegetation and other growth like grass roots etc. and removing
5 the rubbish up to a suitable distance including dressing and cum 10959.00 63.00 690,417 3.48
jungle clearance etc. complete.

EXCAVATION
Excavation in all kind of soft/loose/hard/dense soils, moorum
& moorum mixed with boulders and mud including dressing,
placing the excavated soil neatly in specified dump area or
disposing off the same as directed, including cost of site
6 clearance, all materials, machinery, labour and dressing etc. Cum 2.01
Complete.

(A) CUT-OFF TRENCH 970319.29 57 55,308,200


(B) FILTER 10459.50 57 596,192
(C) DRAIN 1120.24 57 63,854
Excavation in soft/disintegrated/weathered rock including wet
excavation, dressing, placing the excavated material neatly in
specified dump area or disposing off the same as directed,
7
including cost of site clearance, all materials, machinery, labour Cum 2.02
and dressing etc. Complete.

(A) CUT-OFF TRENCH 970319.29 125 121,289,912 2.02


(B) FILTER 10459.50 125 1,307,438
(C) DRAIN 980.21 125 122,526
Excavation in hard rock of all toughness requiring blasting,
minimising damage to rock beyond excavation line and placing
the excavated rock neatly in specified dump area or disposing
8 off the same as directed, including wet excavation, cost of site Cum 2.03
clearance, all materials, machinery, labour etc. Complete

(A) CUT-OFF TRENCH 1293759.06 387 500,684,756 2.03


(B) FILTER 0.00 387 -
(C) DRAIN 700.15 387 270,958

17
Earthwork for embankment (hearting/ casing) using selected
soil from approved borrow areas in layers of 250 to 300 mm
(before compaction) including cost of all materials, machinery,
labour and dressing, all other operations such as
collection of soil, spreading soil in layer of specified
9 thickness, sorting out, breaking clods, levelling, sectioning cum 21541148.45 99.00 2,132,573,697 2.07
edges / sides, (excluding watering and compacting).

Earthwork for cut off trench filling using selected impervious


soil from approved borrow areas in layers of 250 to 300
mm (before compaction) including cost of site clearance, all
materials, machinery, labour, dressing, all other operations
such as collection of soil, spreading soil in layer of specified
thickness, sorting out, breaking clods, levelling, watering,
10 compacting to achieve maximum dry density using cum 3685.00 109.00 401,665 2.08
sheep foot roller/vibratory compactors etc. Complete.

Compaction of earthwork at optimum moisture content to


11 achieve maximum dry density by mechanical sheep foot cum 24376393.90 20.00 487,527,878 2.09
roller/vibratory compactors etc. (excluding watering)
Watering earthwork for compaction at optimum moisture
12 content. cum 24376393.90 10.00 243,763,939 2.10

Construction of rock toe in earthen embankments Including


13 laying and hand packing, dressing, wedging and finishing over 3.37
surface etc. complete.
Other than black trap, basalt or granite cum 20720.00 949.00 19,663,280 3.37.2.1
Providing filter blanket horizontally, Including laying, spreading,
packing etc. Complete in layers of required thickness but
excluding excavation of foundation. (Extended filter) 3.35
14

Metal 40 mm nominal size. cum 15597.80 1094 17,063,995 3.35.3


Sand passing through 4.75 mm screen cum 324610.64 1241 402,841,808 3.35.10
Providing and constructing longitudinal/cross drains trapezoidal
in shape with 1 m bottom width and depth of 0.9 m having side
slope of 1:1 with graded filter having 150 mm thick sand & metal
layer, and 300 mm thick rubble layer from approved source
satisfying specified filter criteria in layers of specified thickness
15 including cost of all materials, machinery, labour, laying to 3.34
required slopes, compaction etc. complete as per specification
and approved drawings.

(b) Sand cum 1419.80 1247.0 1,770,492 3.34.1


(c) Aggregate 40mm nominal size cum 232.46 1090.0 253,386 3.34.2
(d) Rubble cum 149.62 566.0 84,685 3.34.3
Providing and constructing Dry rubble wall (toe wall) with stone
16 of minimum size 0.021 cum at the base of stone pitching or rip- cum 266.40 847.00 225,641 3.45
rap excluding excavation etc. complete.

18
Providing and constructing hand packed riprap as
per IS- 8237 over 300 mm thickgraded filter media
backing consisting of sand, clean; hard, and 40mm
graded (MetaUshingle) aggregates laid in layers of 150 mm
17 cum 29064.43 1280.00 37,202,468 3.46.2
thick each including cost of all materials, labour, hand packing/
wedging stone chips finishing etc. Complete. 450 MM THK

Providing stone chips under stone pitching complete.


18 cum 8719.33 838.00 7,306,797 3.42

Preparing surface for turfing, including laying 15 cm of good soil


19 on top in 7.5 cm layers, surface watering and light ramming etc. sqm 23764.00 42.00 998,088 3.5
Completes
20 Turfing on prepared surface including seed or sods. sqm 23764.00 27.00 641,628 3.51
Dewatering and pumping the working area including all
connecting operation required etc. complete. for cleanliness of 3.55
21 working area by

5hp to 10 hp diesel pump Hrs 1226.61 214.00 262,495 3.55.2


22 Drilling 50 to 75 mm dia. holes vertical or inclined upto 10
degrees to vertical in rock / masonry / concrete by
percussion drilling method using waggon drill or any
other suitable equipment including cost of all materials,
machinery, labour, re-drilling through partially set grout
wherever required etc. complete

Beyond 0 m to 06 m from surface : m 1554.00 1176 1,827,504 3.03.1.1


Beyond 6 m depth from surface add extra for every 6 m. 2,010,876
additional depth : m 1554.00 1294 3.03.1.2

23 Consolidation grouting with neat cement grout mix of suitable


consistency under specified grout pressure as directed in
drilled holes by stage grouting method including cost of all per
materials, machinery, labour, re-drilling if necessary, required tonne 5619.51 12033 67,619,534 3.09

24 DEDUCT FOR GOVT. EXCAVATED ROCK CUM 1171287.32 105.0 - 122985168.96


TOTAL 3,981,602,669
GRAND TOTAL 3,981,602,669
Say ₹ 39816.0 Lakh

19
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
UTILIZATION STATEMENT FOR THE CONSTRUCTION OF EARTHEN DAM
UTILIZATION For H.S/H.M = 90.00% For D.I.R/S.R = 0.00% For H.R = 90.00%
TOTAL UTILIZABLE QUANTITY FROM
RECIEVED QTY FROM EXCAVATION
EXCAVATION
SNO. PARTICULARS Qty.of Qty.of H.S /H.M D.I.R/S.R. H.R.
Qty.of Sand Qty.of H.R.
H.S./H.M D.R./S.R 90% 90%
1 Stripping 3287.700 0.000 0.000 7671.300 0.00 0.00 6904.17
2 Cut off Trench 0.000 970319.295 970319.295 ### 873287.37 0.00 1164383.15
3 Filter 0.000 10459.500 0.000 0.000 9413.55 0.00 0.00
4 Drains 0.000 1120.240 980.210 0.000 1008.22 0.00 0.00
5 Spillway 74727.763 0.000 67254.99 0.00 0.00
TOTAL UTILIZATION 950964.12 0 1171287.32

UTILIZATION STATEMENT

Qty Required Qty Recieved Net Qty to be brought from


Sno Particulars
(cum) (cum) Quarry (cum)
1 Boulder 20720.000 1171287.32 0.00
Quantity Left After Boulder Use 1150567.32
2 Pitching stone 29064.428 1150567.32 0.00
Quantity Left After Pitching Use 1121502.90
3 Quarry Spall / Gravel 15830.265 1121502.90 0.00
Unutilized Quantity Left 1105672.63
4 Sand 326030.444 326030.44
5 Metal 0.00
6 Masonry Stone 0.00
7 Rubble 0.00
8 C.O.T. Soil 3234397.648 3234397.65
9 E/W Soil 21141996.250 950964.12 20191032.13
Unutilized Quantity Left 20191032.13

20
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
Quantity of Earthwork of Dam
TBL 597.00 Max ht of dam = 136.775
Width
at end
Height of Dam Slopes of slope
(withou
t berm)
U/S Area Top width of Dam = 6.00 mts
0.00 to 10.00 2.0:1 20.00 100 RL
10.00 to 20.00 2.5:1 25.00 325 5.00 5.00
U/S berm
20.00
30.00 to 30.00
0.00 3.0:1
4.0:1 0.00 600 5.00 5.00
5.00
-450 5.00
D/S D/s berm-1 5.00 5.00
0.00 to 10.00 2.00:1 20.00 D/s berm-2 5.00 5.00
10.00 to 20.00 2.50:1 25.00 5.00 5.00
20.00
30.00 to
to 30.00 3.00:1
0.00 4.00:1 0.00
0.00

U/S Area D/S Area

from from from from Berm R.L. Berm Berm Total from from from from Berm Berm Berm Total
Height 0.00 10.00 20.00 30.00 5.00 R.L.
5.00 R.L.
5.00 Central 0.00 10.00 20.00 30.00 R.L.
5.00 R.L.
5.00 R.L.
5.00 Total Mean Quantity
S.No. R.D. G.L. Distance
of dam Area Area Area (in cum)
to to to to width width width to to to to width width width
10.00 20.00 30.00 0.00 5.00 5.00 5.00 10.00 20.00 30.00 30.00 5.00 5.00 5.00
2 :1 2.5 :1 3 :1 4 :1 mts mts 2 :1 2.5 :1 3 :1 4 :1 mts mts
1 0.00 477.834 0.00 0.00 0.00 0.00
2 20.00 477.375 119.63 100.00 325.00 600.00 22787.17 548.13 498.13 448.13 25306.55 717.75 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26449.30 13224.65 20.00 264493.00
3 40.00 476.6018 120.40 100.00 325.00 600.00 23123.54 551.99 501.99 451.99 25654.51 722.39 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26801.90 26625.60 20.00 532512.01
4 60.00 476.1109 120.89 100.00 325.00 600.00 23338.35 554.45 504.45 454.45 25876.69 725.33 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27027.03 26914.46 20.00 538289.28
5 80.00 475.5128 121.49 100.00 325.00 600.00 23601.36 557.44 507.44 457.44 26148.66 728.92 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27302.59 27164.81 20.00 543296.13
6 100.00 474.8571 122.14 100.00 325.00 600.00 23891.33 560.71 510.71 460.71 26448.47 732.86 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27606.33 27454.46 20.00 549089.17
7 120.00 474.7221 122.28 100.00 325.00 600.00 23951.27 561.39 511.39 461.39 26510.44 733.67 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27669.11 27637.72 20.00 552754.40
8 140.00 474.765 122.24 100.00 325.00 600.00 23932.22 561.18 511.18 461.18 26490.74 733.41 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27649.15 27659.13 20.00 553182.60
9 160.00 474.6212 122.38 100.00 325.00 600.00 23996.09 561.89 511.89 461.89 26556.77 734.27 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27716.05 27682.60 20.00 553651.96
10 180.00 474.4731 122.53 100.00 325.00 600.00 24061.98 562.63 512.63 462.63 26624.89 735.16 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27785.05 27750.55 20.00 555010.92
11 200.00 474.2656 122.73 100.00 325.00 600.00 24154.42 563.67 513.67 463.67 26720.44 736.41 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 27881.84 27833.45 20.00 556668.91
12 220.00 470.3134 126.69 100.00 325.00 600.00 25948.11 583.43 533.43 483.43 28573.41 760.12 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29758.53 28820.19 20.00 576403.70
13 240.00 469.8658 127.13 100.00 325.00 600.00 26155.16 585.67 535.67 485.67 28787.18 762.81 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29974.98 29866.75 20.00 597335.07
14 260.00 469.4218 127.58 100.00 325.00 600.00 26361.36 587.89 537.89 487.89 29000.03 765.47 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30190.50 30082.74 20.00 601654.78
15 280.00 469.5247 127.48 100.00 325.00 600.00 26313.50 587.38 537.38 487.38 28950.63 764.85 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30140.48 30165.49 20.00 603309.76
16 300.00 468.8589 128.14 100.00 325.00 600.00 26623.95 590.71 540.71 490.71 29271.07 768.85 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30464.92 30302.70 20.00 606053.98
17 320.00 468.4211 128.58 100.00 325.00 600.00 26829.01 592.89 542.89 492.89 29482.70 771.47 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30679.17 30572.04 20.00 611440.89
18 340.00 468.1999 128.80 100.00 325.00 600.00 26932.92 594.00 544.00 494.00 29589.92 772.80 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30787.72 30733.44 20.00 614668.90
19 360.00 462.1421 134.86 100.00 325.00 600.00 29854.69 624.29 574.29 524.29 32602.56 809.15 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 33836.71 32312.21 20.00 646244.27
20 380.00 460.225 136.77 100.00 325.00 600.00 30809.93 633.87 583.87 533.87 33586.55 820.65 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 34832.20 34334.45 20.00 686689.09
21 400.00 460.225 136.77 100.00 325.00 600.00 30809.93 633.87 583.87 533.87 33586.55 820.65 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 34832.20 34832.20 20.00 696644.02
22 420.00 460.225 136.77 100.00 325.00 600.00 30809.93 633.87 583.87 533.87 33586.55 820.65 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 34832.20 34832.20 20.00 696644.02
23 440.00 464.8116 132.19 100.00 325.00 600.00 28549.08 610.94 560.94 510.94 31256.90 793.13 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 32475.03 33653.62 20.00 673072.34
24 460.00 467.0117 129.99 100.00 325.00 600.00 27494.46 599.94 549.94 499.94 30169.29 779.93 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 31374.22 31924.63 20.00 638492.50
25 480.00 468.482 128.52 100.00 325.00 600.00 26800.43 592.59 542.59 492.59 29453.20 771.11 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30649.31 31011.76 20.00 620235.26
26 500.00 471.3044 125.70 100.00 325.00 600.00 25492.46 578.48 528.48 478.48 28102.89 754.17 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29282.06 29965.69 20.00 599313.71
27 520.00 470.7935 126.21 100.00 325.00 600.00 25726.86 581.03 531.03 481.03 28344.95 757.24 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29527.19 29404.63 20.00 588092.56
28 540.00 467.6519 129.35 100.00 325.00 600.00 27191.18 596.74 546.74 496.74 29856.40 776.09 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 31057.49 30292.34 20.00 605846.83
29 560.00 468.158 128.84 100.00 325.00 600.00 26952.64 594.21 544.21 494.21 29610.27 773.05 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 30808.33 30932.91 20.00 618658.17

21
30 580.00 471.0029 126.00 100.00 325.00 600.00 25630.65 579.99 529.99 479.99 28245.60 755.98 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29426.59 30117.46 20.00 602349.12
31 600.00 470.7234 126.28 100.00 325.00 600.00 25759.13 581.38 531.38 481.38 28378.28 757.66 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 29560.94 29493.76 20.00 589875.21
32 620.00 472.3935 124.61 100.00 325.00 600.00 24996.28 573.03 523.03 473.03 27590.38 747.64 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 28763.02 29161.98 20.00 583239.52
33 640.00 473.7913 123.21 100.00 325.00 600.00 24366.38 566.04 516.04 466.04 26939.51 739.25 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 28103.76 28433.39 20.00 568667.80
34 660.00 473.5439 123.46 100.00 325.00 600.00 24477.31 567.28 517.28 467.28 27054.15 740.74 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 28219.89 28161.82 20.00 563236.49
35 680.00 476.3523 120.65 100.00 325.00 600.00 23232.60 553.24 503.24 453.24 25767.32 723.89 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26916.21 27568.05 20.00 551360.93
36 700.00 476.6887 120.31 100.00 325.00 600.00 23085.62 551.56 501.56 451.56 25615.29 721.87 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26762.16 26839.18 20.00 536783.67
37 720.00 476.8595 120.14 100.00 325.00 600.00 23011.16 550.70 500.70 450.70 25538.26 720.84 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26684.11 26723.13 20.00 534462.67
38 740.00 477.355 119.64 100.00 325.00 600.00 22795.83 548.22 498.22 448.22 25315.50 717.87 100.00 325.00 0.00 0.00 0.00 0.00 0.00 425.00 26458.37 26571.24 20.00 531424.80
Total ###
1) Total Emb Qty = 21,541,148.45 cum
Total Earthwork Qty = 21,541,148.45 cum

Deduct For
a) Rock Toe/Boulder Toe = 20720.00 cum
b) Inclined Filter = 305343.44 cum
c) Horizontal Filter = 34865.00 cum
d) Cross Drains = 440.00 cum
e) Pitching = 37783.76 cum
NET EMBANKMENT QTY = 21,141,996.25 cum
`
#REF!

0.00 0.00
0.00 0.00
0.00 0.00

22
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
BOULDER TOE QUANTITY
MWL :- 595.00

R.D. Length Stripping M.W.L H Boulder Height of Inner Area M.A Qty
(m) (m) Level (m) (m) (m) Toe level B.T. slope Outer slope (Sqm) (sqm) (cum)
(m) (m)
1 2 3 4 5 6 7 8 9 10 11 12
0 0 477.83 595.00 117.17 495.41 4.00 1 :1 2.5 :1 28.00
20 20 477.37 595.00 117.63 495.02 4.00 1 :1 2.5 :1 28.00 28.00 560.00
40 20 476.60 595.00 118.40 494.36 4.00 1 :1 2.5 :1 28.00 28.00 560.00
60 20 476.11 595.00 118.89 493.94 4.00 1 :1 2.5 :1 28.00 28.00 560.00
80 20 475.51 595.00 119.49 493.44 4.00 1 :1 2.5 :1 28.00 28.00 560.00
100 20 474.86 595.00 120.14 492.88 4.00 1 :1 2.5 :1 28.00 28.00 560.00
120 20 474.72 595.00 120.28 492.76 4.00 1 :1 2.5 :1 28.00 28.00 560.00
140 20 474.77 595.00 120.24 492.80 4.00 1 :1 2.5 :1 28.00 28.00 560.00
160 20 474.62 595.00 120.38 492.68 4.00 1 :1 2.5 :1 28.00 28.00 560.00
180 20 474.47 595.00 120.53 492.55 4.00 1 :1 2.5 :1 28.00 28.00 560.00
200 20 474.27 595.00 120.73 492.38 4.00 1 :1 2.5 :1 28.00 28.00 560.00
220 20 470.31 595.00 124.69 489.02 4.00 1 :1 2.5 :1 28.00 28.00 560.00
240 20 469.87 595.00 125.13 488.64 4.00 1 :1 2.5 :1 28.00 28.00 560.00
260 20 469.42 595.00 125.58 488.26 4.00 1 :1 2.5 :1 28.00 28.00 560.00
280 20 469.52 595.00 125.48 488.35 4.00 1 :1 2.5 :1 28.00 28.00 560.00
300 20 468.86 595.00 126.14 487.78 4.00 1 :1 2.5 :1 28.00 28.00 560.00
320 20 468.42 595.00 126.58 487.41 4.00 1 :1 2.5 :1 28.00 28.00 560.00
340 20 468.20 595.00 126.80 487.22 4.00 1 :1 2.5 :1 28.00 28.00 560.00
360 20 462.14 595.00 132.86 482.07 4.00 1 :1 2.5 :1 28.00 28.00 560.00
380 20 460.23 595.00 134.77 480.44 4.00 1 :1 2.5 :1 28.00 28.00 560.00
400 20 460.23 595.00 134.77 480.44 4.00 1 :1 2.5 :1 28.00 28.00 560.00
420 20 460.23 595.00 134.77 480.44 4.00 1 :1 2.5 :1 28.00 28.00 560.00
440 20 464.81 595.00 130.19 484.34 4.00 1 :1 2.5 :1 28.00 28.00 560.00
460 20 467.01 595.00 127.99 486.21 4.00 1 :1 2.5 :1 28.00 28.00 560.00
480 20 468.48 595.00 126.52 487.46 4.00 1 :1 2.5 :1 28.00 28.00 560.00
500 20 471.30 595.00 123.70 489.86 4.00 1 :1 2.5 :1 28.00 28.00 560.00
520 20 470.79 595.00 124.21 489.42 4.00 1 :1 2.5 :1 28.00 28.00 560.00
540 20 467.65 595.00 127.35 486.75 4.00 1 :1 2.5 :1 28.00 28.00 560.00
560 20 468.16 595.00 126.84 487.18 4.00 1 :1 2.5 :1 28.00 28.00 560.00
580 20 471.00 595.00 124.00 489.60 4.00 1 :1 2.5 :1 28.00 28.00 560.00
600 20 470.72 595.00 124.28 489.37 4.00 1 :1 2.5 :1 28.00 28.00 560.00
620 20 472.39 595.00 122.61 490.78 4.00 1 :1 2.5 :1 28.00 28.00 560.00
640 20 473.79 595.00 121.21 491.97 4.00 1 :1 2.5 :1 28.00 28.00 560.00
660 20 473.54 595.00 121.46 491.76 4.00 1 :1 2.5 :1 28.00 28.00 560.00
680 20 476.35 595.00 118.65 494.15 4.00 1 :1 2.5 :1 28.00 28.00 560.00
700 20 476.69 595.00 118.31 494.44 4.00 1 :1 2.5 :1 28.00 28.00 560.00
720 20 476.86 595.00 118.14 494.58 4.00 1 :1 2.5 :1 28.00 28.00 560.00
740 20 477.36 595.00 117.64 495.00 4.00 1 :1 2.5 :1 28.00 28.00 560.00
TOTAL 20720 cum

i) Total Qty of excavation of Boulder Toe = 20720.0 cum

23
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI

Quantity of Cut off


Bottom width of cutoff = 4 mts Slope 0.5 M.W.L.= 597.00 M
S.No. R.D. G.L. Depth of Bottom Top C/S Area Avg. C/S Distance Qty of cut Bottom
cutoff width width of Area off RL of
of cutoff cutoff
cutoff

1 2 3 4 5 7 8 9 10 11 12

1 0.00 477.83 59.583 35.75 95.33 3905.15 3905.15 418.25


2 20.00 477.37 59.813 35.89 95.70 3935.29 3920.22 20.00 78404.39 417.56
3 40.00 476.60 60.199 36.12 96.32 3986.33 3960.81 20.00 79216.17 416.40
4 60.00 476.11 60.445 36.27 96.71 4018.90 4002.61 20.00 80052.26 415.67
5 80.00 475.51 60.744 36.45 97.19 4058.76 4038.83 20.00 80776.64 414.77
6 100.00 474.86 61.071 36.64 97.71 4102.69 4080.73 20.00 81614.55 413.79
7 120.00 474.72 61.139 36.68 97.82 4111.77 4107.23 20.00 82144.62 413.58
8 140.00 474.77 61.118 36.67 97.79 4108.88 4110.33 20.00 82206.53 413.65
9 160.00 474.62 61.189 36.71 97.90 4118.56 4113.72 20.00 82274.40 413.43
10 180.00 474.47 61.263 36.76 98.02 4128.53 4123.54 20.00 82470.89 413.21
11 200.00 474.27 61.367 36.82 98.19 4142.53 4135.53 20.00 82710.60 412.90
12 220.00 470.31 63.343 38.01 101.35 4413.61 4278.07 20.00 85561.40 406.97
13 240.00 469.87 63.567 38.14 101.71 4444.85 4429.23 20.00 88584.66 406.30
14 260.00 469.42 63.789 38.27 102.06 4475.95 4460.40 20.00 89208.04 405.63
15 280.00 469.52 63.738 38.24 101.98 4468.73 4472.34 20.00 89446.85 405.79
16 300.00 468.86 64.071 38.44 102.51 4515.54 4492.14 20.00 89842.76 404.79
17 320.00 468.42 64.289 38.57 102.86 4546.45 4530.99 20.00 90619.88 404.13
18 340.00 468.20 64.400 38.64 103.04 4562.10 4554.27 20.00 91085.48 403.80
19 360.00 462.14 67.429 40.46 107.89 5001.33 4781.71 20.00 95634.30 394.71
20 380.00 460.23 68.387 41.03 109.42 5144.54 5072.93 20.00 101458.64 391.84
21 400.00 460.23 68.387 41.03 109.42 5144.54 5144.54 20.00 102890.70 391.84
22 420.00 460.23 68.387 41.03 109.42 5144.54 5144.54 20.00 102890.70 391.84
23 440.00 464.81 66.094 39.66 105.75 4805.29 4974.91 20.00 99498.24 398.72
24 460.00 467.01 64.994 39.00 103.99 4646.67 4725.98 20.00 94519.55 402.02
25 480.00 468.48 64.259 38.56 102.81 4542.14 4594.40 20.00 91888.06 404.22
26 500.00 471.30 62.848 37.71 100.56 4344.83 4443.48 20.00 88869.68 408.46
27 520.00 470.79 63.103 37.86 100.97 4380.22 4362.52 20.00 87250.49 407.69

24
28 540.00 467.65 64.674 38.80 103.48 4601.00 4490.61 20.00 89812.24 402.98
29 560.00 468.16 64.421 38.65 103.07 4565.07 4583.04 20.00 91660.77 403.74
30 580.00 471.00 62.999 37.80 100.80 4365.70 4465.38 20.00 89307.69 408.00
31 600.00 470.72 63.138 37.88 101.02 4385.09 4375.39 20.00 87507.87 407.59
32 620.00 472.39 62.303 37.38 99.69 4269.87 4327.48 20.00 86549.58 410.09
33 640.00 473.79 61.604 36.96 98.57 4174.61 4222.24 20.00 84444.73 412.19
34 660.00 473.54 61.728 37.04 98.76 4191.39 4183.00 20.00 83659.96 411.82
35 680.00 476.35 60.324 36.19 96.52 4002.87 4097.13 20.00 81942.56 416.03
36 700.00 476.69 60.156 36.09 96.25 3980.57 3991.72 20.00 79834.40 416.53
37 720.00 476.86 60.070 36.04 96.11 3969.28 3974.93 20.00 79498.53 416.79
38 740.00 477.36 59.822 35.89 95.72 3936.60 3952.94 20.00 79058.83 417.53
Total 3234397.65 Cum

Hard soil/Hard m 30.00% = 970319.29


D.I.R/Soft Rock 30.00% = 970319.29
Hard Rock 40.00% = 1293759.06
Total 3234397.65

25
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
TBL 597.00
TURFING QUANTITY
D/S
Stripping Height of Inclined
R.D. Length Level Bund Length Average L Area
(m) (m) (m) (m) upto Rock (m) (sqm)
Toe Level
(m)
1 2 3 4 5 6 7
0 0 477.83 119.17 0.00
20 20 477.37 119.63 14.80 7.40 148.00
40 20 476.60 120.40 15.80 15.30 306.00
60 20 476.11 120.89 16.80 16.30 326.00
80 20 475.51 121.49 17.80 17.30 346.00
100 20 474.86 122.14 18.80 18.30 366.00
120 20 474.72 122.28 19.80 19.30 386.00
140 20 474.77 122.24 20.80 20.30 406.00
160 20 474.62 122.38 21.80 21.30 426.00
180 20 474.47 122.53 22.80 22.30 446.00
200 20 474.27 122.73 23.80 23.30 466.00
220 20 470.31 126.69 24.80 24.30 486.00
240 20 469.87 127.13 25.80 25.30 506.00
260 20 469.42 127.58 26.80 26.30 526.00
280 20 469.52 127.48 27.80 27.30 546.00
300 20 468.86 128.14 28.80 28.30 566.00
320 20 468.42 128.58 29.80 29.30 586.00
340 20 468.20 128.80 30.80 30.30 606.00
360 20 462.14 134.86 31.80 31.30 626.00
380 20 460.23 136.77 32.80 32.30 646.00
400 20 460.23 136.77 33.80 33.30 666.00
420 20 460.23 136.77 34.80 34.30 686.00
440 20 464.81 132.19 35.80 35.30 706.00

26
460 20 467.01 129.99 36.80 36.30 726.00
480 20 468.48 128.52 37.80 37.30 746.00
500 20 471.30 125.70 38.80 38.30 766.00
520 20 470.79 126.21 39.80 39.30 786.00
540 20 467.65 129.35 40.80 40.30 806.00
560 20 468.16 128.84 41.80 41.30 826.00
580 20 471.00 126.00 42.80 42.30 846.00
600 20 470.72 126.28 43.80 43.30 866.00
620 20 472.39 124.61 44.80 44.30 886.00
640 20 473.79 123.21 45.80 45.30 906.00
660 20 473.54 123.46 46.80 46.30 926.00
680 20 476.35 120.65 47.80 47.30 946.00
700 20 476.69 120.31 48.80 48.30 966.00
720 20 476.86 120.14 49.80 49.30 986.00
740 20 477.36 119.64 50.80 50.30 1006.00
TOTAL TURFING AREA = 23764.00

27
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
Quantity of Benching/Stripping
Excavation in Sand upto 0.15 m from Natural ground
Bottom Width of Dam

Bottom Width Avrage


Original Modified Height of Depth of Quanti
S.No. R.D. Botttom Distance
G.L. G.L. Dam Cutting ty
Width
U/S D/S TOTAL
1 2 3 4 5 6
1 0 477.83 477.684 0.000 0.000 0.000 6.000 6.000 0.000 0.000 0.00
2 20 477.37 477.225 119.625 548.125 498.125 100.000 53.000 20.000 0.150 159.00
3 40 476.60 476.452 120.398 551.991 501.991 100.000 100.000 20.000 0.150 300.00
4 60 476.11 475.961 120.889 554.446 504.446 100.000 100.000 20.000 0.150 300.00
5 80 475.51 475.363 121.487 557.436 507.436 100.000 100.000 20.000 0.150 300.00
6 100 474.86 474.707 122.143 560.714 510.714 100.000 100.000 20.000 0.150 300.00
7 120 474.72 474.572 122.278 561.390 511.390 100.000 100.000 20.000 0.150 300.00
8 140 474.77 474.615 122.235 561.175 511.175 100.000 100.000 20.000 0.150 300.00
9 160 474.62 474.471 122.379 561.894 511.894 100.000 100.000 20.000 0.150 300.00
10 180 474.47 474.323 122.527 562.635 512.635 100.000 100.000 20.000 0.150 300.00
11 200 474.27 474.116 122.734 563.672 513.672 100.000 100.000 20.000 0.150 300.00
12 220 470.31 470.163 126.687 583.433 533.433 100.000 100.000 20.000 0.150 300.00
13 240 469.87 469.716 127.134 585.671 535.671 100.000 100.000 20.000 0.150 300.00
14 260 469.42 469.272 127.578 587.891 537.891 100.000 100.000 20.000 0.150 300.00
15 280 469.52 469.375 127.475 587.376 537.376 100.000 100.000 20.000 0.150 300.00
16 300 468.86 468.709 128.141 590.706 540.706 100.000 100.000 20.000 0.150 300.00
17 320 468.42 468.271 128.579 592.894 542.894 100.000 100.000 20.000 0.150 300.00
18 340 468.20 468.050 128.800 594.000 544.000 100.000 100.000 20.000 0.150 300.00
19 360 462.14 461.992 134.858 624.289 574.289 100.000 100.000 20.000 0.150 300.00
20 380 460.23 460.075 136.775 633.875 583.875 100.000 100.000 20.000 0.150 300.00
21 400 460.23 460.075 136.775 633.875 583.875 100.000 100.000 20.000 0.150 300.00
22 420 460.23 460.075 136.775 633.875 583.875 100.000 100.000 20.000 0.150 300.00
23 440 464.81 464.662 132.188 610.942 560.942 100.000 100.000 20.000 0.150 300.00
24 460 467.01 466.862 129.988 599.942 549.942 100.000 100.000 20.000 0.150 300.00
25 480 468.48 468.332 128.518 592.590 542.590 100.000 100.000 20.000 0.150 300.00
26 500 471.30 471.154 125.696 578.478 528.478 100.000 100.000 20.000 0.150 300.00
27 520 470.79 470.644 126.206 581.032 531.032 100.000 100.000 20.000 0.150 300.00
28 540 467.65 467.502 129.348 596.740 546.740 100.000 100.000 20.000 0.150 300.00
29 560 468.16 468.008 128.842 594.210 544.210 100.000 100.000 20.000 0.150 300.00
30 580 471.00 470.853 125.997 579.985 529.985 100.000 100.000 20.000 0.150 300.00
31 600 470.72 470.573 126.277 581.383 531.383 100.000 100.000 20.000 0.150 300.00
32 620 472.39 472.243 124.607 573.033 523.033 100.000 100.000 20.000 0.150 300.00
33 640 473.79 473.641 123.209 566.044 516.044 100.000 100.000 20.000 0.150 300.00
34 660 473.54 473.394 123.456 567.281 517.281 100.000 100.000 20.000 0.150 300.00
35 680 476.35 476.202 120.648 553.239 503.239 100.000 100.000 20.000 0.150 300.00
36 700 476.69 476.539 120.311 551.557 501.557 100.000 100.000 20.000 0.150 300.00
37 720 476.86 476.710 120.140 550.702 500.702 100.000 100.000 20.000 0.150 300.00
38 740 477.36 477.205 119.645 548.225 498.225 100.000 100.000 20.000 0.150 300.00
Quantity 10959.00

Sand 30.00% = 3,287.70 cum


H.S/H.M 7,671.30 cum
70.00% =

28
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
JUNGLE CLEARENCE AREA
Depth of JC- 0.15
Extra
R.D Length G.L. Depth S.L. Width Width (30 Total Area Mean Area
(m) (m) (m) (m) (m) (m) m on both Width (sqm) (sqm)
sides) (m)

1 2 3 4 5 6 7 8 9 10

0 0 477.83 0.15 477.68 6.00 10.00 16.00


20 20 477.37 0.15 477.22 100.00 10.00 110.00 2200.00 1100.00
40 20 476.60 0.15 476.45 100.00 10.00 110.00 2200.00 2200.00
60 20 476.11 0.15 475.96 100.00 10.00 110.00 2200.00 2200.00
80 20 475.51 0.15 475.36 100.00 10.00 110.00 2200.00 2200.00
100 20 474.86 0.15 474.71 100.00 10.00 110.00 2200.00 2200.00
120 20 474.72 0.15 474.57 100.00 10.00 110.00 2200.00 2200.00
140 20 474.77 0.15 474.62 100.00 10.00 110.00 2200.00 2200.00
160 20 474.62 0.15 474.47 100.00 10.00 110.00 2200.00 2200.00
180 20 474.47 0.15 474.32 100.00 10.00 110.00 2200.00 2200.00
200 20 474.27 0.15 474.12 100.00 10.00 110.00 2200.00 2200.00
220 20 470.31 0.15 470.16 100.00 10.00 110.00 2200.00 2200.00
240 20 469.87 0.15 469.72 100.00 10.00 110.00 2200.00 2200.00
260 20 469.42 0.15 469.27 100.00 10.00 110.00 2200.00 2200.00
280 20 469.52 0.15 469.37 100.00 10.00 110.00 2200.00 2200.00
300 20 468.86 0.15 468.71 100.00 10.00 110.00 2200.00 2200.00
320 20 468.42 0.15 468.27 100.00 10.00 110.00 2200.00 2200.00
340 20 468.20 0.15 468.05 100.00 10.00 110.00 2200.00 2200.00
360 20 462.14 0.15 461.99 100.00 10.00 110.00 2200.00 2200.00
380 20 460.23 0.15 460.08 100.00 10.00 110.00 2200.00 2200.00
400 20 460.23 0.15 460.08 100.00 10.00 110.00 2200.00 2200.00
420 20 460.23 0.15 460.08 100.00 10.00 110.00 2200.00 2200.00
440 20 464.81 0.15 464.66 100.00 10.00 110.00 2200.00 2200.00
460 20 467.01 0.15 466.86 100.00 10.00 110.00 2200.00 2200.00
480 20 468.48 0.15 468.33 100.00 10.00 110.00 2200.00 2200.00
500 20 471.30 0.15 471.15 100.00 10.00 110.00 2200.00 2200.00
520 20 470.79 0.15 470.64 100.00 10.00 110.00 2200.00 2200.00

29
540 20 467.65 0.15 467.50 100.00 10.00 110.00 2200.00 2200.00
560 20 468.16 0.15 468.01 100.00 10.00 110.00 2200.00 2200.00
580 20 471.00 0.15 470.85 100.00 10.00 110.00 2200.00 2200.00
600 20 470.72 0.15 470.57 100.00 10.00 110.00 2200.00 2200.00
620 20 472.39 0.15 472.24 100.00 10.00 110.00 2200.00 2200.00
640 20 473.79 0.15 473.64 100.00 10.00 110.00 2200.00 2200.00
660 20 473.54 0.15 473.39 100.00 10.00 110.00 2200.00 2200.00
680 20 476.35 0.15 476.20 100.00 10.00 110.00 2200.00 2200.00
700 20 476.69 0.15 476.54 100.00 10.00 110.00 2200.00 2200.00
720 20 476.86 0.15 476.71 100.00 10.00 110.00 2200.00 2200.00
740 20 477.36 0.15 477.21 100.00 10.00 110.00 2200.00 2200.00
Total 80300.00 m²
1) TOTAL AREA FOR JUNGLE CLEARENCE = 80300.00 m²

40.00% Ordinary Jungle Clearance = 32120.00 m²


40.00% Medium Jungle Clearance = 32120.00 m²
20.00% Thick jungle Clearance = 16060.00 m²

30
ROSHNABAD BARRAGE
#REF! #REF!
Qty of U/s and D/s pitching
#REF! 595.00 Slopes
TBL 597.00 Height of Dam U/S D/S
MWL 587.00 0 to 10 mts 2.0 :1 587.00 #REF! #REF!
FTL 577.00 10 to 20 mts 2.5 :1 577.00 #REF! #REF!
567.00 20 to 30 mts 3.0 :1 567.00 -
#REF! 4.0 :1 557.00 -
#REF! - #REF! #REF!
#REF! - #REF! #REF!

U/s slant HT HT of HT of U/s Average D/s slant D/s Average


Height U/s Area of D/s Area of
S.No. R.D. G.L. length of OF PITCHI Back length of length of length of Distance
of Dam pitching pitching
pitching BT NG Water pitching pitching pitching

1 2 3 4 5 8 9 10
7 0.00 477.83 0.00 2.69 4.00 113.17 117.17 2.69 5.00 5.00 0.00 0.00 0.00
8 20.00 477.37 119.63 1.51 4.00 113.63 117.63 2.10 2.69 3.85 20.00 42.02 76.93
9 40.00 476.60 120.40 2.51 4.00 114.40 118.40 2.01 3.69 3.19 20.00 40.19 63.85
10 60.00 476.11 120.89 3.51 4.00 114.89 118.89 3.01 4.69 4.19 20.00 60.19 83.85
11 80.00 475.51 121.49 4.51 4.00 115.49 119.49 4.01 5.69 5.19 20.00 80.19 103.85
12 100.00 474.86 122.14 5.51 4.00 116.14 120.14 5.01 6.69 6.19 20.00 100.19 123.85
13 120.00 474.72 122.28 6.51 4.00 116.28 120.28 6.01 7.69 7.19 20.00 120.19 143.85
14 140.00 474.77 122.24 7.51 4.00 116.24 120.24 7.01 8.69 8.19 20.00 140.19 163.85
15 160.00 474.62 122.38 8.51 4.00 116.38 120.38 8.01 9.69 9.19 20.00 160.19 183.85
16 180.00 474.47 122.53 9.51 4.00 116.53 120.53 9.01 10.69 10.19 20.00 180.19 203.85
17 200.00 474.27 122.73 10.51 4.00 116.73 120.73 10.01 11.69 11.19 20.00 200.19 223.85
39 220.00 470.31 126.69 11.51 4.00 120.69 124.69 11.01 12.69 12.19 20.00 220.19 243.85
40 240.00 469.87 127.13 12.51 4.00 121.13 125.13 12.01 13.69 13.19 20.00 240.19 263.85
8 260.00 469.42 127.58 13.51 4.00 121.58 125.58 13.01 14.69 14.19 20.00 260.19 283.85
8 280.00 469.52 127.48 14.51 4.00 121.48 125.48 14.01 15.69 15.19 20.00 280.19 303.85
9 300.00 468.86 128.14 15.51 4.00 122.14 126.14 15.01 16.69 16.19 20.00 300.19 323.85
10 320.00 468.42 128.58 16.51 4.00 122.58 126.58 16.01 17.69 17.19 20.00 320.19 343.85
11 340.00 468.20 128.80 17.51 4.00 122.80 126.80 17.01 18.69 18.19 20.00 340.19 363.85
12 360.00 462.14 134.86 18.51 4.00 128.86 132.86 18.01 19.69 19.19 20.00 360.19 383.85

31
13 380.00 460.23 136.77 19.51 4.00 130.77 134.77 19.01 20.69 20.19 20.00 380.19 403.85
14 400.00 460.23 136.77 20.51 4.00 130.77 134.77 20.01 21.69 21.19 20.00 400.19 423.85
15 420.00 460.23 136.77 21.51 4.00 130.77 134.77 21.01 22.69 22.19 20.00 420.19 443.85
16 440.00 464.81 132.19 22.51 4.00 126.19 130.19 22.01 23.69 23.19 20.00 440.19 463.85
17 460.00 467.01 129.99 23.51 4.00 123.99 127.99 23.01 24.69 24.19 20.00 460.19 483.85
39 480.00 468.48 128.52 24.51 4.00 122.52 126.52 24.01 25.69 25.19 20.00 480.19 503.85
40 500.00 471.30 125.70 25.51 4.00 119.70 123.70 25.01 26.69 26.19 20.00 500.19 523.85
8 520.00 470.79 126.21 26.51 4.00 120.21 124.21 26.01 27.69 27.19 20.00 520.19 543.85
540.00 467.65 129.35 27.51 4.00 123.35 127.35 27.01 28.69 28.19 20.00 540.19 563.85
560.00 468.16 128.84 28.51 4.00 122.84 126.84 28.01 29.69 29.19 20.00 560.19 583.85
580.00 471.00 126.00 29.51 4.00 120.00 124.00 29.01 30.69 30.19 20.00 580.19 603.85
600.00 470.72 126.28 30.51 4.00 120.28 124.28 30.01 31.69 31.19 20.00 600.19 623.85
620.00 472.39 124.61 31.51 4.00 118.61 122.61 31.01 32.69 32.19 20.00 620.19 643.85
640.00 473.79 123.21 32.51 4.00 117.21 121.21 32.01 33.69 33.19 20.00 640.19 663.85
660.00 473.54 123.46 33.51 4.00 117.46 121.46 33.01 34.69 34.19 20.00 660.19 683.85
680.00 476.35 120.65 34.51 4.00 114.65 118.65 34.01 35.69 35.19 20.00 680.19 703.85
700.00 476.69 120.31 35.51 4.00 114.31 118.31 35.01 36.69 36.19 20.00 700.19 723.85
720.00 476.86 120.14 36.51 4.00 114.14 118.14 36.01 37.69 37.19 20.00 720.19 743.85
740.00 477.36 119.64 37.51 4.00 113.64 117.64 37.01 38.69 38.19 20.00 740.19 763.85
Total :- 14088.84 14975.59
Qty of DRY STONE PITCHING:- 0.45 X 29064.43 29064.43 Cum
Qty of STONE CHIPS:- 0.30 X 29064.43 8719.33 Cum
4) Toe wall at the base of Pitching :-
Area = 0.36 sqm
=
Length = 740.00 m
Qty = 266 cum
TOTALTOE WALL QTY = 266 cum

32
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
INCLINED FILTER QUANTITY ABOVE BOULDER TOE
Thk of Sand Layer = 0.3
Thk of Grael Layer = 0.4

Height Length of
Inclined SAND LAYER GRAVEL LAYER
R.D Length of Rock Inner Slope Area (Sqm) M.A
Filter Thickness
(m) (m) Toe
above BT
(sqm) Qty (cum) Thickness Qty (cum)
(m) (m) (m)
(m)
1 2 3 4 5 6 7 8 9 10 11
0 0 4.00 1 :1 5.66 0.00 0.00 0.30 0.00 0.40 0.00
20 20 4.00 1 :1 5.66 113.14 56.57 0.30 16.97 0.40 22.63
40 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
60 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
80 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
100 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
120 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
140 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
160 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
180 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
200 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
220 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
240 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
260 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
280 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
300 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
320 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
340 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
360 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
380 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
400 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
420 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
440 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
460 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
480 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
500 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
520 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25

33
540 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
560 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
580 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
600 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
620 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
640 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
660 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
680 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
700 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
720 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
740 20 4.00 1 :1 5.66 113.14 113.14 0.30 33.94 0.40 45.25
Total 1238.85 1651.80

1) Total Qty of Gravel in Inclined Filter = 1651.80 cum


2) Total Qty of Sand in Inclined Filter = 2477.70 cum

34
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
Thk of Sand Layer = 1 595.00
Thk of Grael Layer = 0
INCLINED FILTER QUANTITY ABOVE GL
Length of
Inclined SAND LAYER(two layer) GRAVEL LAYER
R.D Length Height of Inner M.A
(m) (m) Hearting Slope Filter above Area (Sqm) (sqm) Thickness Thickness
BT Qty (cum) Qty (cum)
(m) (m)
(m)
1 2 3 4 5 6 7 8 9 10 11
0 0 0.00 1 :1 0.00 0.00 0.00 0 0.00 0 0.00
20 20 173.00 1 :1 244.66 2446.59 1223.29 1.00 1223.29 0.00 0.00
40 20 292.63 1 :1 413.83 6584.93 4515.76 1.00 4515.76 0.00 0.00
60 20 293.40 1 :1 414.93 8287.62 7436.28 1.00 7436.28 0.00 0.00
80 20 293.89 1 :1 415.62 8305.50 8296.56 1.00 8296.56 0.00 0.00
100 20 294.49 1 :1 416.47 8320.90 8313.20 1.00 8313.20 0.00 0.00
120 20 295.14 1 :1 417.40 8338.63 8329.76 1.00 8329.76 0.00 0.00
140 20 295.28 1 :1 417.59 8349.81 8344.22 1.00 8344.22 0.00 0.00
160 20 295.24 1 :1 417.53 8351.11 8350.46 1.00 8350.46 0.00 0.00
180 20 295.38 1 :1 417.73 8352.54 8351.83 1.00 8351.83 0.00 0.00
200 20 295.53 1 :1 417.94 8356.67 8354.60 1.00 8354.60 0.00 0.00
220 20 295.73 1 :1 418.23 8361.70 8359.18 1.00 8359.18 0.00 0.00
240 20 299.69 1 :1 423.82 8420.53 8391.11 1.00 8391.11 0.00 0.00
260 20 300.13 1 :1 424.45 8482.75 8451.64 1.00 8451.64 0.00 0.00
280 20 300.58 1 :1 425.08 8495.36 8489.05 1.00 8489.05 0.00 0.00
300 20 300.48 1 :1 424.94 8500.18 8497.77 1.00 8497.77 0.00 0.00
320 20 301.14 1 :1 425.88 8508.14 8504.16 1.00 8504.16 0.00 0.00
340 20 301.58 1 :1 426.50 8523.75 8515.94 1.00 8515.94 0.00 0.00
360 20 301.80 1 :1 426.81 8533.07 8528.41 1.00 8528.41 0.00 0.00
380 20 307.86 1 :1 435.38 8621.87 8577.47 1.00 8577.47 0.00 0.00
400 20 309.78 1 :1 438.09 8734.65 8678.26 1.00 8678.26 0.00 0.00
420 20 309.78 1 :1 438.09 8761.76 8748.20 1.00 8748.20 0.00 0.00
440 20 309.78 1 :1 438.09 8761.76 8761.76 1.00 8761.76 0.00 0.00
460 20 305.19 1 :1 431.60 8696.90 8729.33 1.00 8729.33 0.00 0.00
480 20 302.99 1 :1 428.49 8600.92 8648.91 1.00 8648.91 0.00 0.00
500 20 301.52 1 :1 426.41 8549.01 8574.96 1.00 8574.96 0.00 0.00

35
520 20 298.70 1 :1 422.42 8488.30 8518.66 1.00 8518.66 0.00 0.00
540 20 299.21 1 :1 423.14 8455.61 8471.96 1.00 8471.96 0.00 0.00
560 20 302.35 1 :1 427.58 8507.27 8481.44 1.00 8481.44 0.00 0.00
580 20 301.84 1 :1 426.87 8544.54 8525.90 1.00 8525.90 0.00 0.00
600 20 299.00 1 :1 422.85 8497.15 8520.84 1.00 8520.84 0.00 0.00
620 20 299.28 1 :1 423.24 8460.87 8479.01 1.00 8479.01 0.00 0.00
640 20 297.61 1 :1 420.88 8441.20 8451.04 1.00 8451.04 0.00 0.00
660 20 296.21 1 :1 418.90 8397.82 8419.51 1.00 8419.51 0.00 0.00
680 20 296.46 1 :1 419.25 8381.55 8389.68 1.00 8389.68 0.00 0.00
700 20 293.65 1 :1 415.28 8345.33 8363.44 1.00 8363.44 0.00 0.00
720 20 293.31 1 :1 414.80 8300.85 8323.09 1.00 8323.09 0.00 0.00
740 20 293.14 1 :1 414.56 8293.68 8297.27 1.00 8297.27 0.00 0.00
Total 301213.94 0.00

1) Total Qty of Gravel in Inclined Filter = 0.00 cum


2) Total Qty of Sand in Inclined Filter = 301213.94 cum

36
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
Thk of Sand Layer = 0.3
Thk of Grael Layer = 0.4
EXTENDED FILTER QUANTITY
SAND LAYER GRAVEL LAYER
B.W. Of
R.D B.W. Of B.W. Of Boulder Width of Height of
Length (m) Dam Hearting Horizontal Area (Sqm) Thickness Qty of Sand Thickness Qty of Gravel
(m) Toe of Sand of Gravel Hearting
(m) (m) (m) Filter Layer (m3) Layer (m3)
Layer (m) Layer (m)
1 2 3 4 5 6 7 8 9 10 11
0 0 6.00 4.50 14.00 0.75 0.00 0.30 0.00 0.40 0.00 0.00
20 20 100.00 4.50 14.00 47.75 485.00 0.30 145.50 0.40 194.00 0.00
40 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 1.00
60 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 2.00
80 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 3.00
100 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 4.00
120 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 5.00
140 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 6.00
160 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 7.00
180 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 8.00
200 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 9.00
220 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 10.00
240 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 11.00
260 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 12.00
280 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 13.00
300 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 14.00
320 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 15.00
340 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 16.00
360 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 17.00
380 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 18.00
400 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 19.00
420 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 20.00
440 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 21.00
460 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 22.00
480 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 23.00
500 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 24.00
520 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 25.00
540 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 26.00
560 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 27.00
580 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 28.00
600 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 29.00
620 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 30.00
640 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 31.00
660 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 32.00
680 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 33.00
700 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 34.00
720 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 35.00
740 20 100.00 4.50 14.00 47.75 955.00 0.30 286.50 0.40 382.00 36.00
Total 10459.50 13946.00

1) Total Qty of Gravel in Inclined Filter = 13946.00 cum


2) Total Qty of Sand in Inclined Filter (in 2 layer) = 20919.00 cum

37
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
EXCAVATION QUANTITY FOR FILTER
Depth Below GL of Filter = 0.3

Depth of
Width of Filter Mean Qty of
R.D. Lengt Horizontal below Area Area Excavation
(m) h (m) Filter G.L (sqm) (sqm) (cum)
(m)

1 2 3 4 5 6 7
0 0 0.75 0.30 0.22 0.00 0.00
20 20 47.75 0.30 14.33 7.27 145.50
40 20 47.75 0.30 14.33 14.33 286.50
60 20 47.75 0.30 14.33 14.33 286.50
80 20 47.75 0.30 14.33 14.33 286.50
100 20 47.75 0.30 14.33 14.33 286.50
120 20 47.75 0.30 14.33 14.33 286.50
140 20 47.75 0.30 14.33 14.33 286.50
160 20 47.75 0.30 14.33 14.33 286.50
180 20 47.75 0.30 14.33 14.33 286.50
200 20 47.75 0.30 14.33 14.33 286.50
220 20 47.75 0.30 14.33 14.33 286.50
240 20 47.75 0.30 14.33 14.33 286.50
260 20 47.75 0.30 14.33 14.33 286.50
280 20 47.75 0.30 14.33 14.33 286.50
300 20 47.75 0.30 14.33 14.33 286.50
320 20 47.75 0.30 14.33 14.33 286.50
340 20 47.75 0.30 14.33 14.33 286.50
360 20 47.75 0.30 14.33 14.33 286.50
380 20 47.75 0.30 14.33 14.33 286.50
400 20 47.75 0.30 14.33 14.33 286.50
420 20 47.75 0.30 14.33 14.33 286.50
440 20 47.75 0.30 14.33 14.33 286.50
460 20 47.75 0.30 14.33 14.33 286.50
480 20 47.75 0.30 14.33 14.33 286.50
500 20 47.75 0.30 14.33 14.33 286.50
520 20 47.75 0.30 14.33 14.33 286.50
540 20 47.75 0.30 14.33 14.33 286.50
560 20 47.75 0.30 14.33 14.33 286.50

38
580 20 47.75 0.30 14.33 14.33 286.50
600 20 47.75 0.30 14.33 14.33 286.50
620 20 47.75 0.30 14.33 14.33 286.50
640 20 47.75 0.30 14.33 14.33 286.50
660 20 47.75 0.30 14.33 14.33 286.50
680 20 47.75 0.30 14.33 14.33 286.50
700 20 47.75 0.30 14.33 14.33 286.50
720 20 47.75 0.30 14.33 14.33 286.50
740 20 47.75 0.30 14.33 14.33 286.50
Total Qty of Excavation for Mat Filter = 10459.50

Total Qty of Excavation for Fi = 10,459.50 cum

2) H.S/H.M 100.0% = 10459.500 cum


3) D.I.R/S.R 0.0% = 0.000 cum
6) H.R 0.0% = 0.000 cum

39
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
Depth of Toe Drain 0.6 Top Width of Toe drain = 0.6
TOE DRAIN QUANTITY
BOULDER LAYER GRAVEL LAYER SAND LAYER
Slope of
Leng Toe Drain Dept Slant Slant Qty of Slant Slant Qty of Slant Slant
R.D th Dam D/s on the h of Thickn Length Length Boulder Thickn Length Length Boulder Thick Length Lengt Qty of
(m) (m) Slope other Drain ess T.W. B.W. on on ess T.W. B.W. on on ness T.W. B.W. on h on Boulder
Layer Layer
side (m) Dam Other (m) Dam Other (m) Dam Other Layer (m3)
Side Side (m3
) Side Side (m3
) Side Side

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1
0 0 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 0.00 0.20 0.71 0.82 2.64 1.44 0.00 0.30 0.82 0.98 3.50 2.00 0.00
20 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
40 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
60 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
80 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
100 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
120 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
140 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
160 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
180 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
200 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
220 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
240 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
260 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
280 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
300 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
320 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
340 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
360 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
380 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
400 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
420 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
440 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
460 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37

40
480 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
500 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
520 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
540 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
560 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
580 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
600 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
620 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
640 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
660 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
680 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
700 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
720 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
740 20 2.5 :1 1 :1 0.6 0.20 0.6 0.71 1.62 0.85 12.47 0.20 0.71 0.82 2.64 1.44 19.37 0.30 0.82 0.98 3.50 2.00 38.37
Total 149.62 232.46 1419.80

1) Total qty. of Boulder = 149.62 cum


2) Total qty. of Gravel = 232.46 cum
3) Total qty. of Sand = 1419.80 cum

41
ROSHNABAD BARRAGE
TEHSIL :-SIDHI DISTRICT :SINGRAULI
TOE DRAIN EXCAVATION QUANTITY

Total
R.D. Length Dam D/s Slope of Toe Depth of B.W. T.W. Area Mean Qty of
(m) (m) Slope Drain on the Drain (m) (m) (m) Area Excavation (cum)
other side (m) (sqm)

1 2 3 4 5 6 7 8 9 10
0 0 2.50 :1 1 :1 1.10 0.98 4.83 3.19 0.00 0.00
20 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
40 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
60 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
80 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
100 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
120 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
140 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
160 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
180 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
200 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
220 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
240 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
260 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
280 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
300 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
320 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
340 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
360 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
380 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
400 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
420 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
440 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
460 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
480 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
500 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
520 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
540 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80

42
560 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
580 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
600 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
620 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
640 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
660 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
680 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
700 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
720 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
740 20 2.50 :1 1 :1 1.10 0.98 4.83 3.19 3.19 63.80
2360.60

OUTFALL DRAIN EXCAVATION QUANTITY

Particulars No. Length Av.Width Height Qty


OutFall (Longitudanal) Drain 16 10 2 1 320
OutFall ( Parallel) Drain 1 60 2 1 120

TOTAL QTY OF EXCAVATION FOR DRAINS = 2800.60

1) H.S/H.M
40.0%
= 1120.2 cum
2) SR/DIR 35.0% = 980.2 cum
3) H.R 25.0% = 700.2 cum

43
ROSHNABAD BARRAGE

DRILLING AND GROUTING QUANTITY

Grouting
70% of Holes No.
Bottom R.L. Head of Water 2 Row & Quantity in
R.D. S.L. of Grouting Water Head for Length Length
6M. Apart
more than
10m

0.00 477.834 395.82 117.166 82.02 0.00 0 0.00


20.00 477.375 395.04 117.625041 82.34 20.00 7 576.36
40.00 476.602 393.72 118.398211 82.88 20.00 7 580.15
60.00 476.111 392.89 118.889134 83.22 20.00 7 582.56
80.00 475.513 391.87 119.487201 83.64 20.00 7 585.49
100.00 474.857 390.76 120.142864 84.10 20.00 7 588.70
120.00 474.722 390.53 120.277921 84.19 20.00 7 589.36
140.00 474.765 390.60 120.235 84.16 20.00 7 589.15
160.00 474.621 390.36 120.378789 84.27 20.00 7 589.86
180.00 474.473 390.10 120.526921 84.37 20.00 7 590.58
200.00 474.266 389.75 120.734408 84.51 20.00 7 591.60
220.00 470.313 383.03 124.686632 87.28 20.00 7 610.96
240.00 469.866 382.27 125.134184 87.59 20.00 7 613.16
260.00 469.422 381.52 125.578158 87.90 20.00 7 615.33
280.00 469.525 381.69 125.475263 87.83 20.00 7 614.83
300.00 468.859 380.56 126.141145 88.30 20.00 7 618.09
320.00 468.421 379.82 126.578895 88.61 20.00 7 620.24
340.00 468.200 379.44 126.800079 88.76 20.00 7 621.32
360.00 462.142 369.14 132.857883 93.00 20.00 7 651.00
380.00 460.225 365.88 134.775 94.34 20.00 7 660.40
400.00 460.225 365.88 134.775 94.34 20.00 7 660.40
420.00 460.225 365.88 134.775 94.34 20.00 7 660.40
440.00 464.812 373.68 130.188416 91.13 20.00 7 637.92
460.00 467.012 377.42 127.988342 89.59 20.00 7 627.14
480.00 468.482 379.92 126.517974 88.56 20.00 7 619.94
500.00 471.304 384.72 123.695579 86.59 20.00 7 606.11
520.00 470.794 383.85 124.206474 86.94 20.00 7 608.61

44
540.00 467.652 378.51 127.348066 89.14 20.00 7 624.01
560.00 468.158 379.37 126.842026 88.79 20.00 7 621.53
580.00 471.003 384.21 123.997053 86.80 20.00 7 607.59
600.00 470.723 383.73 124.276632 86.99 20.00 7 608.96
620.00 472.393 386.57 122.606526 85.82 20.00 7 600.77
640.00 473.791 388.95 121.208711 84.85 20.00 7 593.92
660.00 473.544 388.52 121.456132 85.02 20.00 7 595.14
680.00 476.352 393.30 118.647737 83.05 20.00 7 581.37
700.00 476.689 393.87 118.311329 82.82 20.00 7 579.73
720.00 476.860 394.16 118.1405 82.70 20.00 7 578.89
740.00 477.355 395.00 117.645 82.35 20.00 7 576.46
259.00 22478.03
Length of Hole Depth upto 6 m 259.00 x 6.000 = 1554 m
Length of Hole Depth more then 6 m 0.00 m

Grouting 0.25 Tonn per meter 5619.5075 MT


1123901.5 Bags
CEMENT 39024.36 Cu.M.

45