RMU and TF REPORT FORMAT

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views12 pages

RMU and TF REPORT FORMAT

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

SITE TEST REPORT

SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

value x 2) TIME (s)


R Y B R Y B
(A)
180
EARTH FAULT (Ie >)
APPLIED CURRENT Pick – Up (A) CALCULATED
Set value
(A) TIME (SEC) MEASURED TIME(SEC)
(A)
2×Is 1.0

5×Is 0.427
EARTH FAULT (Ie >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is x CALCULATED
value 2) TIME (ms) MEASURED TIME(ms)
(A)
4.0 0
SBEF RELAY TEST REPORT
EARTH FAULT (Ie >)
APPLIED CURRENT Pick – Up (A) CALCULATED
Set value
(A) TIME (SEC) MEASURED TIME(SEC)
(A)
2×Is 1.0

5×Is 0.427
EARTH FAULT (Ie >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is x CALCULATED
value 2) TIME (ms) MEASURED TIME(ms)
(A)
4.0 0
Fault Record:
Record No : Threshold :
Fault : Magnitude:
REMARKS:--
Trip test: Connected through (1) Primary Injection (2) Secondary Injection
3. Phase fault -- Passed Failed
4. Earth fault -- Passed Failed

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

CONTRACT No. : MANUFACTURER : LUCY

SUBSTATION No. : MODEL :

RMU TYPE : SERIAL No. :

DATE : TRANSFORMER :
RATING
RELAY : ASHIDA
1. FUNCTIONAL TEST
Sl.No. Description Result Remarks

1 Visual Inspection of RMU

2 Conformity checks with respect to drawings

3 Verification of labeling ferrules

4 Proper installation of MB and door

5 Painting

6 Mechanical operations of breaker

7 Protection relay trip test

8 Mechanical operation of disconnector

9 Mechanical interlocks (Breaker/Isolator)

10 Shunt trip test of Circuit Breaker

11 Electrical operation of Ring Switch 1 & 2

12 Mechanical operation of Earth Switch

13 Mechanical operation of Ring Switch 1 & 2

14 Relay Final setting checking

Remarks:

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

2. PROTECTION RELAY TEST


MANUFACTURER : ASHIDA MODEL No. :
SERIAL No. : VERSION :
RELAY SETTING :-
P/F CURVE : IEC SI
I> : tI > :
I >> : tI>> :
I >>> : tI >>> :
E/F CURVE : IEC SI
Ie > : tIe > :
Ie >> : tIe>> :
OVERCURRENT ( I >)
Pick – Up (A)
Set CALCULATED MEASURED TIME(SEC)
value APPLIED CURRENT (A)
R Y B TIME (SEC) R Y B
(A)
2×Is

5×Is
OVERCURRENT (I >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is CALCULATED MEASURED TIME(ms)
value x 2) TIME (ms)
(A) R Y B R Y B

0
OVERCURRENT (I >>>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is CALCULATED MEASURED TIME(s)
value x 2) TIME (s)
(A) R Y B R Y B

EARTH FAULT (Ie >)


APPLIED CURRENT Pick – Up (A) CALCULATED
Set value
(A) TIME (SEC) MEASURED TIME(SEC)
(A)
2×Is

5×Is
EARTH FAULT (Ie >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is x CALCULATED
value 2) TIME (ms) MEASURED TIME(ms)
(A)
4.0 0
Fault Record:
Record No : Threshold :
Fault : Magnitude:
REMARKS:--

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

SBEF RELAY TEST REPORT


EARTH FAULT (Ie >)
APPLIED CURRENT Pick – Up (A) CALCULATED
Set value
(A) TIME (SEC) MEASURED TIME(SEC)
(A)
2×Is

5×Is
EARTH FAULT (Ie >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is x CALCULATED
value 2) TIME (ms) MEASURED TIME(ms)
(A)
4.0 0
Fault Record:
Record No : Threshold :
Fault : Magnitude:

Trip test: Connected through (1) Primary Injection (2) Secondary Injection
1. Phase fault -- Passed Failed
2. Earth fault -- Passed Failed
3. PROTECTION RELAY TEST
MANUFACTURER : Alstom MODEL No. :
SERIAL No. : VERSION :
RELAY SETTING :-
P/F CURVE : IEC SI
I> : tI > :
I >> : tI>> :
I >>> : tI >>> :
E/F CURVE : IEC SI
Ie > : tIe > :
Ie >> : tIe>> :
OVERCURRENT ( I >)
Pick – Up (A)
Set CALCULATED MEASURED TIME(SEC)
value APPLIED CURRENT (A)
R Y B TIME (SEC) R Y B
(A)
2×Is 1.0

5×Is 0.427
OVERCURRENT (I >>)
Pick – Up (A)
Set APPLIED CURRENT (A) (Is CALCULATED MEASURED TIME(ms)
value x 2) TIME (ms)
(A) R Y B R Y B

0
OVERCURRENT (I >>>)
APPLIED CURRENT (A) (Is Pick – Up (A) CALCULATED
Set MEASURED TIME(s)

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

5. HIGH VOLTAGE TEST

INSULATION RESISTANCE TEST BEFORE HI-POT


Measured
Test Voltage dc (1Min.) (kV) Test connection REMARKS
Resistance (ohm)
5 KV R to Earth+Y+B

5 KV Y to Earth+ R+B

5 KV B to Earth+R+Y

DIELECTRIC TEST

Test Voltage ac (1min.) (kV) Test connection Leakage Current (mA) REMARKS

22.4 KV R to Earth+Y+B

22.4 KV Y to Earth+ R+B

22.4 KV B to Earth+R+Y

INSULATION RESISTANCE TEST AFTER HI-POT

Measured
Test Voltage dc (1Min.) (kV) Test connection REMARKS
Resistance(ohm)
5 KV R to Earth+Y+B

5 KV Y to Earth+ R+B

5 KV B to Earth+R+Y

REMARKS:-

TEST EQUIPMENTS USED:


INSTRUMENT NAME MEGGER HIGH VOLTAGE TESTER

SL. NO.

MAKE & MODEL MEGGER&MIT 510/2 HIGH VOLTAGE VLF HIPOT /PFT-5030MF

CALIB.DUE

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

5. CT RATIO TEST

Injected current (A) Measured Current (A)


RY/RN YB/YN BR/BN R Y B N
PROTECTION CT -- -- -- --
CT RATIO
-- -- -- --
FOR
-- -- -- --
-- -- -- --
E/F -- -- -- --
-- -- -- --
Injected current (A) Measured Current (A)
RY/RN YB/YN BR/BN R Y B N
PROTECTION CT -- -- -- --
CT RATIO
-- -- -- --
FOR
-- -- -- --
-- -- -- --
E/F -- -- -- --
-- -- -- --

POLARITY CHECKS:

Observations Of Polarity Checks For Protection CT


REMARKS
R PHASE Y PHASE B PHASE

Observations Of Polarity Checks For Protection CT


REMARKS
R PHASE Y PHASE B PHASE

6. METERING CT TEST:

Injected current (A) Measured Current (A)


METERING CT – Y PHASE CT RATIO
150 / 1A

NAME PLATE DETAILS MAKE: BURDEN CLASS:


METERING CT RATIO: SERIAL NO:
Injected current (A) Measured Current (A)
METERING CT – Y PHASE CT RATIO
150 / 1A

NAME PLATE DETAILS MAKE: BURDEN CLASS:


METERING CT RATIO: SERIAL NO:

7. EARTH FAULT INDICATOR TEST:

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

Set Trip Level Pickup Value(A) Reset time LED Indication


Earth Fault
Indicator

MAKE: TRIP LEVEL:


NAME PLATE DETAILS FOR EFI MODEL :
SERIAL NO:
Set Trip Level Pickup Value(A) Reset time LED Indication
Earth Fault
Indicator

MAKE: TRIP LEVEL:


NAME PLATE DETAILS FOR EFI MODEL :
SERIAL NO:

Test Equipments Used:

INSTRUMENT NAME SEC INJ KIT Digital Multimeter


SL. NO.
MAKE & MODEL SEVERKER 760, PROGRAMMA FLUKE 179
CALIB. DUE

8. EARTH RESISTANCE:

TRM Body :

TRANSFORMER :

TR.NEUTRAL :

9. RELAY FINAL SETTING :


UNIT I:

In: 1A KVA: CT RATIO:

P/F CURVE : IEC SI

I> t>

I>> t>>

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client MASDAR DISTRICT COOLING PLANT Equipment 22KV RMU
Manufacturer LUCY Date
Contractor Sub Station

t>>>
I>>>
E/F CURVE : IEC SI

Ie> t>

Ie>> t>>

UNIT I:

In: 1A KVA: CT RATIO:

P/F CURVE : IEC SI

I> t>

I>> t>>

t>>>
I>>>
E/F CURVE : IEC SI

Ie> t>

Ie>> t>>

SNAG

TESTED BY CONTRACTOR CLIENT


(SGE) (ADDC )
NAME
SIGNATURE
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client Doc. No.
Project Title Manufacturer
Consultant Date
Contractor Sub Station

TEST REPORT FOR TRANSFORMER


NAME PLATE DETAILS
MAKE
SL.NO
YEAR OF MANUFACTURING
RATING IN KVA
FREQUENCY
TYPE OF COOLING
INSULATION LIQUID
IMPEDANCE AT NORMAL TAP %
TEMPERATURE RAISE OIL/WDG
VECTOR GROUP
RATED VOLTAGE (HV/LV)
RATED CURRENT (HV/LV)
TOTAL WEIGHT

LIST OF TESTS:
1. Visual Inspection
2. Insulation Resistance Measurement Test
3. Winding Resistance Measurement Test
4. Voltage Ratio & Magnetizing Current Test
5. Vector Group Test
6. Functional Test of Supervisory Equipment

TESTED BY CONTRACTOR CONSULTANT CLIENT

COMPANY SGE
NAME
SIGNATURE
DATE
Page 1 of 4
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client Doc. No.
Project Title Manufacturer
Consultant Date
Contractor Sub Station

1. REPORT ON VISUAL CHECK


S.NO DESCRIPTION REMARKS
1 Installing according to drawing
2 No oil leakage & Oil Level Position Correct
3 All drain valves are fully closed
4 No visible cracks or breaks to bushing
5 All bushing connections are fully tightened
6 Main tank grounding corrects
7 Neutral grounding is correct (fixed, tightened &insulated)
8 Pressure relief valve are correctly installed
9 Earthing of cable boxes and other removable parts

2. INSULATION RESISTANCE TEST Ambient Temperature: ◦C


Insulation Resistance in GΩ
WINDING VOLTAGE
15 Secs 60 Secs R60 /R15 Remark
HV to Earth 5 KV
LV to HV 2.5 KV
LV to earth 1 kV

3. WINDING RESISTANCE TEST: Ambient Temperature: ◦C


HV WINDING:
Tap 1U-1V 1V-1W 1W-1U MEAN
Position Rt mΩ at Rt mΩ at 75◦C Rt mΩ at Rt mΩ at 75◦C Rt mΩ at Rt mΩ at 75◦C Rt mΩ at Rt mΩ at 75◦C
Amb Temp Amb Temp Amb Temp Amb Temp
Temp Temp Temp Temp
1
2
3
4
5
R75=Rt x[(235+75)/(235+Amb temp◦c)]
Whereas, Rt = Resistance Measured at Amb temp ◦C
TESTED BY CONTRACTOR CONSULTANT CLIENT

COMPANY SGE
NAME
SIGNATURE
DATE
Page 2 of 4
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client Doc. No.
Project Title Manufacturer
Consultant Date
Contractor Sub Station

LV WINDING: Ambient Temperature: 36 ◦C

Tap 2u-2n 2v-2n 2w-2n MEAN


Position Rt µΩ at Amb Rt µΩ at 75◦C Rt µΩ at Amb Rt µΩ at 75◦C Rt µΩ at Amb Rt µΩ at 75◦C Rt µΩ at Amb Rt µΩ at 75◦C
Temp Temp Temp Temp Temp Temp Temp Temp
3(NT)
R75=Rt x[(235+75)/(235+Amb temp◦c)]
Whereas, Rt = Resistance Measured at Amb temp ◦C

4.TURNS RATIO TEST:


H1 - H3 / X1 – X0 H2 – H1 / X2 – X0 H3 – H2 / X3 – X0
Tap
Ph Ph Ph
Positions Ratio %Error Ie x c Ratio %Error Ie x c Ratio %Error Ie x c
(Deg) (Deg) (Deg)
1
2
3
4
5

PRIMARY SECONDARY HV LV CALCULATED


TAP TAP VOLTAGE VOLTAGE RATIO
1
2
3 -
4
5

TESTED BY CONTRACTOR CONSULTANT CLIENT

COMPANY SGE
NAME
SIGNATURE
DATE
Page 3 of 4
SITE TEST REPORT
SWITCHGEAR ELECTROMECHANICAL
Client Doc. No.
Project Title Manufacturer
Consultant Date
Contractor Sub Station

5. VECTOR GROUP TEST:

Note:
Voltage& Vector group according to rating plate checked by TTR kit.

6. Functional Checks of Supervisory Equipments:


6.1 Vertical Oil Level Switch : OK
6.2 Oil Temperature Indicator : OK
6.3 Pressure Relief Valve : OK
6.4 PT100 Sensor Function : N/A
6.5 OTI Alarm Setting Temperature : 95◦C
6.6 OTI Trip Setting Temperature : 105◦C
6.7 TRF Marshalling Box Heater Function : N/A
6.8 Checking of Alarm/Trip Contacts : OK

TEST EQUIPMENTS USED:


INSTRUMENT NAME MEGGER WINDING RESISTANCE KIT TURNS RATIO KIT DIGITAL MULTIMETER

SL. NO.
MAKE & MODEL
CALIB.DUE

TESTED BY CONTRACTOR CONSULTANT CLIENT

COMPANY SGE
NAME
SIGNATURE
DATE
Page 4 of 4