Lecture 6 - Project Scheduling-Bar Chart
Lecture 6 - Project Scheduling-Bar Chart
Bar Charts
1- Scheduling Techniques
• Bar Chart (Gantt Chart): The Gantt chart (1917) was
used as a tool for production control in manufacturing
settings.
(Hinze 2012)
(Mubarak 2010)
Material Prepared by Dr. M. Abdel-Raheem
(Mubarak 2010)
1
2
3
4
Tasks
5
6
7
Gantt Chart
8
9
(Hinze 2012)
10
(Mubarak 2010)
(Mubarak 2010)
12
(Mubarak 2010)
14
16
2 500 500
7 700 700
Gantt Chart
8 450 450 450 450 450 450
6- Activity Sequencing
• Planning= WBS + Sequencing of Work
Built-
Built- up
Parking & Gutters
Roof Electrical
Service
System
Area
Exterior
Finishes
Startup
Building Construct Interior
Halpin & Senior 2011
Start & Site Foundation Slabs End
Structure Roof Finishes
Prep.
Prep.
Elec. &
Mech.
Systems
18
7- Examples
• Example 1
Activitity Duration Predecssor
A 5 -
B 8 A
C 6 A
D 9 B
E 6 B,C
F 3 C
G 1 D , E, F
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A
B
C
D
E
F
G
20
7- Examples – Cont’
Cont’d
• Example 2
Activitity Description Duration Predecssor
A Move in 2 -
B Set up Scaffolds 3 A
C Tear off Shingles 3 B
D Inspect Roof Truss & Deck 2 C
E Remove Old Shingles 3 C
F Estimate New Shingles 1 D, E
G Purchase &Install New Shingles 5 F
H Clean up 3 G
I Move Out 2 H
(Mubarak 2010)
7- Examples – Cont’
Cont’d
A Move in 2 -
B Set up Scaffolds 3 A
C Tear off Shingles 3 B
D Inspect Roof Truss & Deck 2 C
E Remove Old Shingles 3 C
F Estimate New Shingles 1 D, E
G Purchase &Install New Shingles 5 F
H Clean up 3 G
I Move Out 2 H
Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
A
B
C
D
E
F
G
H
I
22
7- Examples – Cont’
Cont’d
• Example 3
Activity Duration Predecessor
A 2 -
B 6 A
C 10 A
D 4 A
E 7 B
F 5 B,C
G 3 C,D
H 5 E,F
I 2 G,H
7- Examples – Cont’
Cont’d Activity Duration Predecessor
A 2 -
B 6 A
C 10 A
• Example 3 D 4 A
E 7 B
F 5 B,C
G 3 C,D
H 5 E,F
I 2 G,H
Day
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Activity
A
B
C
D
E
F
G
H
I
24
7- Examples – Cont’
Cont’d
• For the given project, determine the following:
1. Total project duration
2. Total cost of the project
3. Total cost spent up till the first month (Assume uniform
distribution of costs)
Activity Duration Predecessor Total Cost
A 3 - 750
B 2 - 1000
C 5 - 3000
D 3 A 1050
E 4 B 1600
F 4 B 800
G 2 E, F 1400
H 6 A,C 2700
I 3 D,H 2100
Material Prepared by Dr. M. Abdel-Raheem
25
7- Examples – Cont’
Cont’d
• For the given project, determine the following:
Activity Duration Predecessor Total Cost
1. Total project duration A
B
3
2
-
-
750
1000
C 5 - 3000
D 3 A 1050
E 4 B 1600
F 4 B 800
G 2 E, F 1400
H 6 A,C 2700
I 3 D,H 2100
0 Week
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A
B
C
D
E
F
G
H
I
26
5- Examples – Cont’
Cont’d
• For the given project, determine the following:
1. Total cost of the project
Activity Duration Predecessor Total Cost
A 3 - $750
B 2 - $1,000
C 5 - $3,000
D 3 A $1,050
E 4 B $1,600
F 4 B $800
G 2 E, F $1,400
H 6 A,C $2,700
I 3 D,H $2,100
Total Cost $14,400
Material Prepared by Dr. M. Abdel-Raheem
27
7- Examples – Cont’
Cont’d
• For the given project, determine the following:
2. Total cost spent up till the first month (Assume uniform
distribution of costs)
Activity Duration Predecessor Total Cost Cost /Week
A 3 - $750 $250
B 2 - $1,000 $500
C 5 - $3,000 $600
D 3 A $1,050 $350
E 4 B $1,600 $400
F 4 B $800 $200
G 2 E, F $1,400 $700
H 6 A,C $2,700 $450
I 3 D,H $2,100 $700
Total Cost $14,400
Material Prepared by Dr. M. Abdel-Raheem
28
7- Examples – Cont’
Cont’d
• For the given project, determine the following:
3. Total cost spent up till the first month (Assume uniform
distribution of costs) = $5,700
0 Week
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Activity
7- Examples – Cont’
Cont’d
• The given schedule shows the estimated total man-
man-hours for the entire project and the actual man-
man-hours
consumed up till the 18th day. Determine the following:
30
7- Examples
man-hours for the entire project: 7,100
1. The estimated man-
man-
man-hours
7- Examples – Cont’
Cont’d
man-hours utilized until the 18th day: 5,600 man-
2. The actual man- man-
hours
32
7- Examples – Cont’
Cont’d
3. The percentage of cost saving or overrun-
overrun- if any
7- Examples – Cont’
Cont’d
3. The percentage of cost saving or overrun-
overrun- if any
Calculations:
Man-hours @ 18th days= 5,400
Estimated Man-
Man-hours @ 18th days= 5,600
Actual Man-
Percentage of cost overrun= (5,600 – 5,400) /5,400 = 3.7%