Commissioning Practice
TORQUE LOG CP-2226
RECORDS REVIEW CHECK SHEET Rev. & Date: (0) 09/01/03
Sponsor: USCPMT
Issued By: C&Q Team
PROJECT TITLE / NO:
PFIZER SITE:
SYSTEM NAME / NO: PROJECT DOC NO:
BLDG NO: BLDG AREA / ROOMS: REV. & DATE: ( )
Procedures
a. Battery limits of the Piping system that was examined should be indicated in the Torqued File report(s) or highlighted
on a copy of the master red lined, As-Built dwgs that should be attached to the report(s).
b. Obtain the Contractor’s Torque File with referenced documentation.
c. The typical Torque File consists of:
1) Torque Map, with Torque Log
2) Certification documentation of Pipe Fitters
3) Approved Torque procedure with appropriate torque values.
4) Third party inspection (if applicable)
d. All document procedures & test results w/referenced attachments to be verified, numbered, & filed in Project
Turnover Package (TOP).
CONTRACTOR: PROJECT RECORDS FILE NO:
PIPING SPEC NO’s: DWG/P&ID NO’s:
Check
Yes / No /
TO BE COMPLETED BY QUALIFIED DESIGNATED PERSONNEL N/A
By Date
(Initial)
1. Have the Torque Maps with Torque Logs been completed per appropriate
code requirements and project specs?
2. Do all the Pipe Fitters indicated in the Torque Log have documented
certifications and/or training?
3. Did the contractor submit calibration documentation for all torque wrenches?
4. Have torque procedures and values been submitted and reviewed for each
Pipe Specification?
5. Were all appropriate initials and/or signatures completed by designated
Contractor and Pfizer personnel/reps?
6. Is all the documentation complete and accepted?
7. Has the system passed acceptance based on the
commissioning scope of work?
Follow-up, Comments, and Clarifications:
COMPLETED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
APPROVED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
Page 1 of 3
Commissioning Practice
TORQUE LOG CP-2226
RECORDS REVIEW CHECK SHEET Rev. & Date: (0) 09/01/03
Sponsor: USCPMT
Issued By: C&Q Team
PROJECT TITLE / NO:
PFIZER SITE:
SYSTEM NAME / NO: PROJECT DOC NO:
BLDG NO: BLDG AREA / ROOMS: REV. & DATE: ( )
COMPLETED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
APPROVED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
Page 2 of 3
Commissioning Practice
TORQUE LOG CP-2226
RECORDS REVIEW CHECK SHEET Rev. & Date: (0) 09/01/03
Sponsor: USCPMT
Issued By: C&Q Team
PROJECT TITLE / NO:
PFIZER SITE:
SYSTEM NAME / NO: PROJECT DOC NO:
BLDG NO: BLDG AREA / ROOMS: REV. & DATE: ( )
Procedure:
COMPLETED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
APPROVED _________________________ _________________________ _______________ DATE: _________
BY: Print Signature Title
Page 3 of 3