Msra - Mobilization
Msra - Mobilization
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
MSRA – Moblization
Submitted to
Checked Authorized
Date Description Prepared By
By By
QAQC SITE ENGINEER Deputy
PROJECT
Engineer GM
30/10/2024 Rev 0 ENGINEER
M.SHAFEEK NADEEM.A RAHUL M.PHILIPS
1 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
Contents
1. General Description and Purpose: ................................................................................... 3
2. Safety .............................................................................................................................. 3
3. Site Team and Responsibilities: ..................................................................................... 21
4. Scope of Work: .............................................................................................................. 24
5. Tools and Equipment ..................................................................................................... 24
6. Site Preparation ............................................................................................................. 24
7. Work Methodology: ........................................................................................................ 25
8. House Keeping .............................................................................................................. 29
9. Sub-Contractor .............................................................................................................. 29
10. Attachments: ................................................................................................................. 29
2 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
2. Safety:
This safety brief is to ensure that the public and workers are protected from construction hazards.
Risk assessment is a process of evaluating the potential risks or hazards associated with an
activity, process, or situation and identifying the likelihood (L) and potential impact/severity (S) of
various risks on individuals, environment, assets, or the overall well-being of an organization or
community. Risk assessment involves the following steps:
- Identifying potential sources of harm or hazards that could lead to negative outcomes.
- Once hazards are identified, the next step is to analyze the list of risks associated with
each hazard by evaluating the likelihood and the potential consequences if it does occur.
- Based on the analysis, risks are evaluated based on their significance and priority which
helps identify which risks require immediate attention and which can be managed through
routine measures.
- Control measures are then implemented to reduce or eliminate the identified risks which
can include modifying the task, introducing a safety measure, providing training, or other
measure as deemed necessary.
- Along the construction, regular monitoring, and review of the effectiveness of the control
measures is needed to ensure the risks remain within the acceptable levels.
Severity and likelihood are all set out based on past incidents, expertise, regulations and
standards, and statistics. Control measures are categorized into several types:
3 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
For this method statement risk assessment (MSRA) detailing the roads works the risks Required
PPEs are the following:
4 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
The following matrix is used for the risk assessment calculation and analysis:
SEVERITY (S)
Likelihood (L)
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Unlikely (4) 4 8 12 16 20
Frequent/Almost 5 10 15 20 25
Certain (5)
These risks are sever/catastrophic that is almost certain that will occur. Extreme
15 - 25 Extreme risk items would likely require immediate attention and more robust mitigation
Risk
strategies, while low risk items might only need routine monitoring.
Absolutely Unacceptably High.
Activity or process should not proceed in current form.
The risks with high to moderate severity that is most likely to occur.
8 - 12 High Unacceptably High.
Risk
Activity or process should be modified to include remedial planning and action and
be subject to detailed OSH risk assessment.
5 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
Risk
Risk
Assessment
Assessment
Activity Hazard Control Measures with Controls
without Controls (Risk*)
L S L*S L S L*S
6 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
7 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
8 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
9 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Solid and liquid • Vehicle maintenance works shall be carried out only at
waste generation designated areas.
(domestic waste, • Fuelling of vehicles will be carried out only at designated
general construction areas.
waste, liquid effluents, • Spill kits shall be provided at fuelling points.
oil, sewage, • Dip tray will be provided at fuelling points as well as oil
hazardous waste etc.) changing area.
• Fire during refuelling • Fire extinguisher shall be provided for all plant and
of vehicles equipment.
• Tipping or
overturning of
vehicles
10 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
11 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
12 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Obstacle present
Plant •Toolbox talk shall be conducted prior to start the activity.
(during site
Equipment • Site Induction course for the operators by HSE Team.
preparation) 3 4 12 1 4 4
Mobilization & • Pre-Inspection to be carried out while mobilizing the
• Caught between,
Demobilization equipment and labelled.
Collision, crushed by
13 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
14 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Damage hand tools, • Cracked tool handles, mushroomed tool heads, sprung tool
Hand tools and
use of incorrect tools, 3 3 9 joints, worn tool teeth) prior to use. 1 3 3
Power Tool • Misusing of tools, • Any tool with defects must be removed from service.
15 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Mushroom shaped • Wear industrial quality safety glasses or face shield when
tools etc the hand tools produce flying, crumbling, chipping, sparking,
• Electricity Wet or splintering debris.
surface • Keep the cutting edge of hand tools sharp, when cutting
• Exposed rotating always cut away from the body.
parts • Electrical circuits should be conducted with RCD. use only
•Defected/improperly industrial weatherproof sockets.
aligned cutting wheel. • Always use the proper hand tool for the job. When finished,
• Trailing cable clean hand tools and store in proper locations.
• Close supervision.
• Shut off the machine when not in use. Plant team to inspect
prior to start using it.
16 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
17 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
18 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
19 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
20 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
21 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
22 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Short term • A competent Scaffolding inspector has to inspect & tag the
exhaustion scaffolding safe to use.
• Collapse of scaffold • All employees working on scaffolds shall use safety
• Slips, trips and falls, harnesses with double lanyards which will be anchored onto
• Unstable ground the ledgers of the scaffolding.
conditions • A safe access, secured adequately for entrance and exit to
• Use of damaged or from the work platform shall be provided.
scaffold • Scaffolds shall not be loaded in excess of the working load
equipment’s and they are intended to, and this load shall be evenly distributed
components on the scaffold platform.
• Incomplete working • Where materials of the scaffolds are handled manually
platform during erection or dismantling, no workers shall stand directly
• Unauthorized entry under the pathway.
into • Partially erected or dismantled scaffolds shall not be used,
scaffolding during and a prominent warning notice indicating that the scaffold is
erection incomplete and not safe to be used (Red Scaffold Tag) shall
phase be posted.
• Absence of Edge • The access to the scaffold shall physically be blocked.
protection • Yellow Tag should be used during the construction phase,
• Incompetent workers which indicates only the entry of scaffolding workers
• Scaffolds and scaffold components shall be thoroughly
inspected by a competent person to ensure that the scaffold
is stable, and capable of supporting the intended loads and
then green scaffold tag shall be posted the after signing it
which indicate that the scaffold is complete and safe to use.
• Ensure that all materials conform with design requirements.
• The use of competent workers under the leadership of
Supervisor who has a good experience.
• Use safety harness, Barricade working area, use safety
helmets, safety boots, tools and accessories to be secured.
• Check with the scaffolding manual before working on the
23 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
24 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
25 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
26 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
on site or whilst being • The work area is to be barricaded using suitable means to
used prevent access and this must be supplemented by the
during dismantle posting of prominently located signage.
• Fall of persons • Materials to be stored by suitable means to prevent
during inadvertent movement i.e. scaffold fittings to be bagged.
erection and • On commencement of dismantling works, an “Incomplete
dismantle Scaffold” sign to be displayed adjacent to the access routes
• Collapse of scaffold and Physical barriers to be erected to prevent access.
when • Scaffolds to be checked by the competent scaffold
dismantling supervisor prior to Dismantle.
• Work at height in • Supervisor will monitor the surrounding working conditions
poor light to ensure that workers are not put at risk and there are no
levels other risky activities ongoing alongside the work.
• Failure of fall • Work at height to be undertaken either in good levels of
protection daylight or with adequate task lighting provided.
equipment • Confirm that the body harnesses are fit for use & are
• Unsafe material inspected on a monthly basis.
handling • Double lanyard type full body harness are only allowed to be
used by the workers.
• It has to be taken care that the dismantled material lowering
should only be done by multiple persons involved in the crew.
The elements that are dismantled & lowered from a level can
be passed down carefully from one person to the other
person who is on lower section.
• Awareness training on Safe posture & manual handling has
to be conducted periodically.
27 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
28 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
• Lane closures and • Lane closures and diversions to be in line with TTM AD
diversions of high- manual regarding warning, transition, stabilization, work, and
speed traffic. termination areas on live roads.
• Pedestrian and • Ensure that where required a flagman is used to control site
cyclist Access/Egress personnel and vehicles crossing traffic routes (only 80kph
becoming blocked. and below).
• Traffic incident due • Ensure that public road surfaces at plant/ pedestrian
to incorrect traffic crossings and adjacent to site works are maintained, clean
management. and free from loose material and debris.
• Uncontrolled entry • The work area adjacent to live traffic shall be protected with
by public into work hard barrier protection to standards and specific to traffic
areas. speeds.
• High noise levels • Priority ensured regarding the protection of public
from traffic. Night-time pedestrians and cyclists, including overhead protection where
works required.
• Adequate road diversion to be maintained according to the
approved drawings from ITC.
• Where works are undertaken at night ensure that the works
areas are well provided with adequate lighting systems.
• Workers instructed on requirements at induction.
• Safe access/ exit to the plant to be determined.
• Man-machine interface to be prohibited.
29 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
30 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
31 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
32 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
33 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
34 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
35 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
36 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
37 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
All works shall comply with safety procedures and instructions set out in projects.
Signboards, advance warning signs.
Basic and related PPE to be worn by all staff.
All equipment, tools and machinery shall be in good condition.
Secure access to the site
QA/QC Manager:
Manage the planning, preparation and implementation and maintenance of the Method
of Statement.
Ensure that the work is carried out as per the approved MS, shop drawing, specification,
and project quality plan.
Ensure that the method of statement is communicated to the workforce before doing the
activity.
Take immediate action if there is any non-conformity observed at the site.
38 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
Safety Manager:
Ensure that RA is consulted and well educated to the workforce through the construction
team.
To assist the hazard of any used chemical and advice the management for the required
resources to execute the activity safely.
Ensure that all near misses/ incidents are reported/ recorded on time and to concerned
parties.
Project Engineer:
The Project Engineer is accountability for the work force before, during and after work.
The Project Engineer is responsible for carrying out the work as per the Method Statement,
Specification and Approved Drawings.
The Project Engineer shall ensure that the resources are available to carry out the work
as scheduled.
The Project Engineer shall be available at site full time for the execution of works as per
schedule and specification.
The Project Engineer will ensure that all approved safe system of work documentation for
the planned activity is available at the work site.
The Project Engineer will ensure that all safety control measures detailed in the safe
systems of work documentation is available and deployed at the activity work site.
The Project Engineer will ensure that an OSH officer is available at the work site
throughout the duration of the activity.
Ensure full compliance with EHS recommendations during execution of the task or activity.
39 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
QA/QC Engineer:
Ensure that all the works are carried out as per the approved drawings and specifications
and with approved materials.
Material Inspection Request to be approved prior to use of the material at site.
Inspect the completed work and request for the Consultant's approval after getting
clearance from CM.
Surveyor:
Responsible for all survey related activities and to maintain accuracy and tolerance in all
site survey at site and to get approval for the same by liaising with consultant
representatives.
To ensure all survey equipment's are having valid calibration certificates.
Maintain complete, accurate log of control & survey works as it progresses.
Draughtsman:
Prepare and submit Shop drawings & as built drawings in coordination with surveyor and
construction team.
To provide the quantity of items in the drawings by AUTOCAD/Civil 3D
To ensure the drawings used/ distributed at site are the latest revision.
Foreman:
The Foreman is responsible to carry out the work as per the Method Statement,
Specification and Approved Drawings.
The Foreman shall be available at site full time for the execution of works.
Ensure that the workforce is trained in the MSRA.
Ensure that welfare facilities are well maintained, and housekeeping is proper during work
execution.
Ensure that daily task briefing is conducted prior to work commencement.
Ensure that head counting is in place after break hours.
Conduct Pre-task briefing to the execution team.
Conduct JSA before commencement of the activity.
The Foreman is responsible for Head counting with Accountability of the work force before,
during and after the work force.
40 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
Safety Officer:
Moving materials to the worksite and ensuring all tools, machinery, and other equipment
are safely set up.
Obeying health and safety codes, as well as the company's principles.
Removing hazardous materials from sites.
Compliance to the supervisor's instruction
Ensuring the work complying with the OSH requirement
Assisting with various works as per the procedures.
Performing site and equipment inspections.
Attending meetings and workshops.
Completing on-the-job training.
Ensuring tasks are completed to deadlines.
41 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
4. Scope of Work:
This document defines the methodology, sequence, control measures, safety and quality
control requirements, including tools and equipment intended to be used in performing site
mobilization works as established in the project specifications and relevant referenced
documents. This method statement is exclusive to accomplishing specific tasks and services
associated with Mobilization activity, at the SAJAA PLANT ELECTRICAL MODIFICATION
AND SEWGA GRID TIE- IN , Site in Al Sajja, Sharjah, UAE.
42 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
6. Site Preparation
Land:
Loyal construction team shall obtain information regarding existing site services that
may have been placed below ground. Services found shall be rerouted and protected
from any damage in an area ensuring no effect on site activities.
Loyal shall check the existing elevations and report to the owner including any
apparent errors or discrepancies.
The existence and location of the surrounding buildings, services and all pertaining
equipment be investigated and verified on site by Loyal before starting work.
Loyal construction team shall obtain information regarding land layout.
Setting out:
Loyal construction team will conduct a site survey to conduct benchmarks.
Loyal construction team will determine drainage system specifications based on project
needs.
Organization:
Obtain necessary NOCs and PTW permit approval (with all attachments including
excavation certificate, HSE plan, drawings) from the authorized departments before the
commencement of work at site.
No work shall start without the proper permits have been obtained, necessary measures
in place and permit validated.
Communicate to all relevant parties regarding the talk (via tool box talk), to check all the
staffs have proper PPE before start of the work and it is well understood.
Banksman with the flag shall be provided to direct the movement of the equipment
7. Work Methodology:
GENERAL REQUIREMENT:
All working areas will be cleared from any other activities or obstacles.
Ensure to obtain necessary approval or written permission from concerned Authorities and
Consultant to commence with the stages of the works.
Temporary roadway widths for main road detours shall be a minimum of 2 lanes
Establish and maintain permanent survey benchmarks on the site in referenced to the
control points.
Installation of high visibility fencing around the perimeters covered by construction as per
Contract/Project specificatio
43 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
The Job hazard analysis & Risk hazard involved in various stages of this activity shall be
thoroughly read from the work location prior to start the activity in coordination with
Contractor /Client/Engineer & local Authorities and based on severity of risk involved (Risk
rating) for each of the activity shall be drawn and dealt with.
SAFETY INDUCTION:
Necessary work induction programme will be arranged and conducted in association with
relevant area authorities for the personnel involved in site temporary facility set up work
as applicable.
All new comers including subcontractor's personnel, on the project site will be inducted in
Safety, & Permit to Work related matters by HSE Engineer/ officer prior to enter to the
Project work site.
44 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
RGCC shall install high visibility fencing across site boundary and all areas to be protected
during the construction progression as shown on the drawing.
Shop drawing should be submitted and obtained approval from the consultant prior to start
execution.
Prior to start execution the site of fence shall be sufficiently cleared of obstructions, and
surface irregularities shall be graded so that the fence will confirm the general contour of
the ground.
Fence lines and the Entrance gates will be set out by a Surveyor as per the Shop drawing
approved by the Engineer.
Corrugated Fence Panel shall be installed and fixed in a concrete block following the
approved drawing details.
Each Corrugated Fence Panels shall be clamped properly with anchor bolts rigidly
fastened in the concrete block. Also, Vertical & Diagonal supports shall be rigidly fastened
for each Corrugated Fence panels to ensure the Fence is integrally robust and secure.
The parameters of the enclosed fence shall be limited as marked-up in the drawing.
Loading & Transportation of Porta -cabins & other heavy equipment's outside Project
premises will be carried out as per Governing traffic rules and regulations.
Porta-cabins will be hooked / fastened and secured properly with Trailer bed to prevent
any movement while travelling.
Proper sign flags, indicators will be fixed on Trailer & Porta-cabin. Defined route, speed
limit and mandatory escorting method will be followed.
Certified Slings, Lifting belts/ hooks, hangers (spreader bar) and D - Shackles will be used
to toe and lift (Loading / offloading / installing) all the Porta-cabins, associated materials
and any other heavy / bulk materials.
45 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
Certified crane operators and trained riggers will be engaged for all lifting operations.
Cranes will be anchored on a firm, clear and levelled ground. We will ensure that Cranes
& associated equipment's / lifting apparatus will be of suitable & of sufficient capacity to
handle the respective tasks. Movement of personnel around the swing area will be
prevented.
Prior to unload Porta-cabins or other heavy / bulk materials any fasteners / hooks will be
removed and Porta-cabins / material will be lifted & moved slowly by crane operator in
continuous coordination with Rigger.
The area where the Porta-cabins to be installed will be make ready prior to offloading the
same with necessary concrete paving / support column to the required line and level. All
location setting up work will be done by Subcontractor's Surveyor and his team.
Welfare facilities will be provided as per the requirement.
Painting & Electricals works will be done to the site office porta cabins as per the contract
specification.
Surveyor will continuously provide, check and verify the location, / line and levels of each
and every facility in line with approved drawing 'Site Temporary Facilities', The Temporary
facilities will be provide in line with Contract agreement & Project specifications, will
consist of facilities includes but not limited to below mentioned list:
- Contractor's Site Office facility Client's Site Office facility.
- Car Parking Facility Necessary Access Roads Project Sign Board Project Site Safety
Board.
- Defined Permanent Material Ware House Lay down Area.
- Rest area for Construction personnel Toilet Blocks
- Defined Smoking Shelters Guard / Security Cabins
- Temporary power & water supply network facility Covered Store
- Defined area for Flammable material storage. Diesel Generators with tank bund all
around.
- Necessary Sanitary network with Septic Tank / Holding Tank facility. Induction &
Training Centre.
- First Aid Center
- Defined Waste disposal area.
- Tent for workers rest area.
46 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
All facility areas will be well connected with roads, walk ways as necessary as per
approved Layout drawing. All earth works, concreting, fabrication and erection works for
temporary facility set up will be in accordance with Contract requirements & Specifications.
All safety precautions, procedure in accordance to approved Project HSE Plan, governing
Rules & regulations and Company HSE Policies will be followed.
Prior to start and after completion of each facility set up work Company will be asked to
verify the facility in all respects and obliged to provide advice if any.
All housekeeping, waste management, traffic management will be followed as per
governing Rules & Regulations, Contract specifications and approved Project HSE Plan.
Site Facility Management Procedure and Emergency Procedure will be followed as per
approved Project HSE plan. Contractor will have exclusive personnel for all necessary
interface activity and coordination between required entities / any other concerned
Authorities like Police, Traffic Department etc. Additional facilities provided if any will be
incorporated in the drawing and revised drawing will be submitted for final approval
Verification of the existing underground services as per the drawings issued by the
Contractor.
Survey marking for the underground services
47 of 48
AUTHORITY CLIENT DEVELOPER MAIN CONTRACTOR SUB CONTRACTOR
PROJECT NAME : SAJAA PLANT ELECTRICAL MODIFICATION AND SEWGA GRID TIE- IN
Method Statement for Site Mobilization
DISPOSAL OF MATERIALS:
The removed materials for dumping shall be remove from the site and dispose to the
approved designated locations
Unwanted soil shall be removed from the site and to be disposed as well.
8. House Keeping:
Site supervisory staff shall ensure that the site remains clean from unwanted waste and that the
ease of access and ingress to and from site is maintained at all time and that the access are kept
free from any kind of dump etc. to provide safe and conducive environment at site. The team shall
provide the water bauzering etc. to protect flying of the dirt and dust in and around the site.
9. Sub-Contractor:
Ensure the work is carried out as per the Method Statement, Specification and Approved
Drawings.
Ensure that the resources are available to carry out the work as scheduled.
Ensure that MSRA trained site supervisors upon approval and prior to work executions, in
addition to periodic training for the MSRA.
Ensure reporting of any new hazard/incidents/ unplanned events to EHS team to review
of the MSRA.
Ensure the availability of competent employees to complete the task.
Ensure the availability of adequate welfare facilities on site.
Ensure the availability of required PPE at site
10. Attachments:
Cut/Fill drawing
Mobilization Plan
48 of 48