James Bent (Author) - Kenneth K. Humphreys (Author) - Effective Project Management Through Applied Cost and Schedule Control-CRC Press (1996)
James Bent (Author) - Kenneth K. Humphreys (Author) - Effective Project Management Through Applied Cost and Schedule Control-CRC Press (1996)
Project
Management
Through
Applied
Cost and
Schedule
Control
COST ENGINEERING
A Series of Reference Books and Textbooks
Editor
KENNETH K. HUMPHREYS, Ph.D.
Consulting Engineer
Granite Falls, North Carolina
James A. Bent
James Bent Associates, Inc.
Bountiful, Utah
Kenneth K* Humphreys
Consulting Engineer
Granite Falls, North Carolina
informa
Visit the Taylor & Francis Web site at
http://www.taylorandfrancis.com
and the CRC Press Web site at
Taylor & Francis Group is the Academic Division of Informa plc. http*//www crcpress com
Preface: A Search for Project Excellence
iii
iv Preface
Index 445
Introduction and Mission Statement
I. MISSION STATEMENT
The focus of this book is on advanced application skills that directly correlate to
all phases of a project, at both owner and contractor levels. When properly
utilized, these skills can lead directly to cost savings or, at the very least, to risk
mitigation, schedule stability and cost containment. This book features, in great
detail, a state-of-the-art project control and trending program, with more than
200 exhibits of reports, techniques, and data. Such a program requires real
business skills, analytical ability, and effective project control techniques. This,
then, results in the constant evaluation of project changes, cause and effect, their
impact on contract conditions and the cost-schedule impact.
Throughout the book, the authors have interwoven information on the three major
overlapping parts of the total project program, namely:
• Programs—defined as techniques, procedures, and methods
• People skills—defined as experience, application, and analytical ability
Culture of project groups—defined as project commitment and working to-
getherness
Figure FM.l is a flowchart, showing the above three parts and their constituent
subcategories. As the first two parts cover the same categories, the subcategories
are then combined into two overall categories:
• What to do—skills and techniques
xiii
XIV Introduction and Mission Statement
J_
(WHAT TO DO ) ( HOW TO POTT)
SKILLS and WORKING
TECHNIQUES TOGETHERNESS
PROJECT
SUCCESS
Current Skill Level - 57% _ § 0 % NECESSARY
6. 1990
DESIGN Q.A. &
VALUE ENG'G
$ $ $ $ $ $ $ $ $
NEW ELEMENTS, impacting on Construction
1955-1975 1 9 7 5 o n . . . . GROWTH OF 1 9 8 4 C.I.I.
GROWTH UNDEVELOPED AREAS ESTABLISHED
+400% • Middle East R&D in Total t
• South America Project Skills t
• Pacific Rim (Asia)
• Japan (Economic)
t
• Weapons - Civil Support t
Change —• Change —•• Change —• Change —• Change
From "Old Texas Redneck" to $ Business Manager
The rest of the book then covers, in great detail, the skills outlined in these
two chapters.
greatly assist in the collection and collation of data that, in turn, is developed
into essential information.
B. A Proactive Role
The best of today's construction management now takes a proactive role through
the newly developed programs of construction preplanning and constructability.
This results in a strong construction involvement at the early stage of the project
to ensure that engineering design and early planning fully recognize the require-
ments of an economic construction program. An example of construction preplan-
ning is backwards scheduling, in which the overall project schedule is structured
around the construction schedule with design drawing issues and material deliv-
eries matched to construction needs. If this is done early in the design stage,
there is no cost impact on design engineering or purchasing, and the construction
cost savings can be considerable, even with the added cost of early construction
involvement.
Business management is now considered of greater value than the old
standard of aggressively pushing the work, with cost and contractual considera-
tions being of lesser consequence.
Note: The timing of new major programs and elements as shown in Figure
FM.2 represents the approximate date when the individual categories were widely
used (proven), not when they were first developed.
Effective
Project
Management
Through
Applied
Cost and
Schedule
Control
1
Benchmarking—The Technical Core of
Total Quality Management
I. INTRODUCTION
The TQM process, first begun in the manufacturing industry in the 1980s, is
now sweeping the construction industry. Operators, contractors, subcontractors,
and suppliers are embracing and implementing it with enthusiasm. In fact, many
companies are making it a condition for doing business that their contractors/sup-
pliers have a qualified TQM program in place.
Many of these firms are ecstatic with their TQM results, and report signif-
icant improvement in customer satisfaction, employee morale/commitment, con-
tractor/supplier relationships, return on investments, and company culture. Other
firms find themselves disillusioned, finding employee dissatisfaction/ poor morale,
failing company relationships, unhappy clients, poor company culture, large train-
ing/organizational costs, and little or no return on investment. Such failures are
unfortunately common, and in 1992, the managing director of one of the world's
largest oil companies was fired for just such a failure; his firing came in con-
junction with the first reported financial loss in the company's history. Current
experience has identified several common reasons for TQM failures.
1. Lack of Senior Management Commitment
The TQM process requires tremendous cultural change, particularly in the areas
of self-examination and employee empowerment. This fact is often not understood
Benchmarking—The Technical Core of TQM
or fully accepted by senior management, who may profess acceptance but are
lukewarm in commitment and enthusiasm. These individuals are usually the
autocratic dinosaurs of yesteryear and, fortunately, are a rapidly dying breed.
Beyond this, however, many existing company policies (such as purchasing for
an initial low price rather than the lowest evaluated cost) may need to be changed
to accommodate TQM. See Chapter 2 for a further discussion of outdated policies
and the need for change.
Another commitment problem arises when TQM is viewed as an event rather
than a process. While management typically includes some funding for quality
training in the annual budget and may even appoint a quality manager, such
actions are rarely signs of actual commitment. To be successful, TQM must be
regarded and implemented as an ongoing, consistent program rather a training
exercise or the management fad of the month. Total Quality Management is a
top-down program whose success requires serious understanding, acceptance, and
commitment from senior management.
5. Lack of Measurement
When and if the problems of management commitment, planning, training, and
experience are solved, the challenge of effective measurement must be met. This
involves monitoring the newly implemented policies, standards, and work pro-
cesses for cost-effectiveness and team-building value. Questions such as the
following need to be posed:
Chapter 1
Without question, TQM failure will result in increased cost and lower return on
revenue or even in a loss. It will also result in low skill levels, poor company culture,
matrix interface conflicts, low morale, loss of resources, and poor public image.
procedures and techniques. The interviews should be conducted with all levels
of personnel and with key interfacing personnel from supporting service groups.
The chart contained in Figure 1.1 shows skill levels of participants in senior,
professional project courses for the period 1991-1994. The participating compa-
nies are all leading companies from USA, Europe, UK, Australia, South Africa,
Middle East, and Indonesia and therefore represent a good international mix.
Even though these are many of the world's leading companies, the skills level
shows an individual group range of 40-71% with an overall average of 58% over
the four years. The author has a second, independent benchmarking database
that has an overall average level of 55%. The correlation of these two independent
Legend: • Total Course Performance, P - Project Management, C - Contracting
TITLE
COURSE PERFORMANCE - PR OJECT CASES/SKILLS JPROJECT
1 111 1
u I 1 111 1
i
wT —j
H
i
if
\
f t 9 2, 1 TTr ==# 99 *
—
5
) r~ 6
10. 1 1I - I 1 _
I 7
*VLL
L L J. F ... 8
_ uME >\
rt JJL QV c' VV FIt-Pl^
K L1L 9
.
- rn • • • # ] % Hi*
w
i-ft
• •
r
10
- 1— 4" rv
'I
— LL
12
S1
ft
— t SraMrH > 7 9t U j\ 1 f/v t
:— fi Or 13
4m X\i
/ 1 ^4i> • •I f\ XL 14
rtr 1/ i
4 L
Six
ZJ •i •n IV •»
rl
•-
r(
t-t
r~ • i -f- • S •- II -•-1 \J Jri
II-
TT
-«•
17"
TT
rti «^ f7f2T IF
JU. 1 A
Ll! 1 u '.«
• • •* • r, J j * j
• *T
T
* »* •
w
* * _JL ft.
-* 21
25
_ 26
—c '- 27
28
• 1 i I ^ 1VI
v
r 29
I
4
JT
ft* LI
\
.i T1
30
31
32
i
TT
R
—•# —
RANGE: 4 0 % - 7 1 % B 35
36
-
USA - Europe - UK 19 9 5 -- 37
'I
39
— P 40
Middle East - Indonesia
_ 1— ^. - _
- 42
j 43
; fl92 05
>- FiU> No.
f •-<^ 19-\ *-] >—- rn , (
I—
- — By JamesA .Bent 4T
s
•— P- Dat
rlt
— J 1 2 1r 1 —»« " <r i*
T
Sh€ el No
5
—
() 49
it'
, i i
-
iJ
PRO JECT 50
i 2 3 4 6 7 8 9 10 I I 12 13 I4 15 16 17 18 19 20 2 l 22 2 3 24 25 26 27 28 2 9 30 31 3 2 33 3 4 35i36|37 Mb 152 53 54[55|56 J57^8|59]60
1 42|43 49
1
0)
JAMES BENT ASSOCIATES, INC.
INTERNATIONAL BENCHMARK - 5 5 %. CONSULTANTS IN PROJECT MANAGEMENT AND PROJECT CONTROL
databases is remarkably close. The skill levels of this chart are determined by
how well course work-groups resolved a wide-ranging set of case histories in the
areas of project estimating, cost control, scheduling, contractual risk, contract
strategy, project organization, project planning and business analysis. These re-
sults confirm many current studies that point to low project management skills
in present-day industry. It is the author's position that skill levels must exceed
80% if the cost savings illustrated in Chapter 2 are to be realized.
IV. SUMMARY
The title of this book features Applied and Effective and is meant to emphasize
and illustrate the skills and techniques essential to a high-quality project control
program. The benchmarking deliverables described in this chapter are, then, a
summary of the skills needed to achieve effective cost and schedule control on
engineering/construction projects. Moreover, there is a distinct relationship be-
tween skill level and project cost, a subject that is discussed more fully in Chapter
2, "The Impact of Personnel Skills on Company Culture and Bottom Line."
The overall assessment by the Construction Industry Institute (CII) that
proper use of these techniques can lead to the U.S. construction industry saving
$15 billion per year is challenging, to say the very least.
It must be emphasized that failure of TQM can impose a significant burden
on any project program. Project personnel must ensure that the impacts of this
burden are properly reflected in their project planning.
The Impact of Personnel Skills on
Company Culture and Bottom Line
I. INTRODUCTION
Most projects, being small ones, are handled in a matrix organization environ-
ment: they are executed by many departments carrying out the work. This is
usually done with a project manager who does not have adequate decision-making
authority. This authority is shared between the departmental managers who
actually do the work and the project manager who coordinates the work.
9
10 Chapter 2
The consensus opinion is that most problem areas are internal, rather
than external in nature. Over 90% of the Project Managers stated that
conflicting interests and struggles with department managers was their
chief problem.
The matrix interface conflicts discussed in this section are common in the engi-
neering/construction industry and are to be found in even the best of today's
leading companies.
In large operating companies, the production company has the budget for all
capital work, and the engineering department provides the technical service and
support for designing and building the capital projects. The production company
can delegate some of its financial responsibility for project development to the
engineering department while still holding final financial approval. On the other
hand, the engineering department is separately charged with technical/economic
viability and must act as technical auditor of the production company. This gives
The Impact of Personnel Skills 11
Company policy requires a 10% quality estimate for the funding of capital pro-
jects. Yet at the same time, company management usually wants projects devel-
oped yesterday! These two objectives are totally incompatible in plant-type
projects, and to accomplish the impossible, engineering lies about the quality of
the estimate. In a total quality management culture, this policy must change.
Company policy does not give the project manager direct control or management
of the project contingency, while at the same time it holds the project manager
directly responsible for every dollar of the approved funds. This situation is
sometimes a result of management ignorance in confusing contingency with
management reserve. Even in our enlightened technical age, many individuals
still do not understand or accept the need for project contingency. In a total
quality management culture, this policy must change.
Companies do not allow project and discipline engineers full access to commercial
information on equipment/material bids. This practice has led many procurement
departments to assume a pre-eminent position in which the tail wags the dog.
Ideally, the engineering and project management functions should include both
business analysis and decision-making roles, particularly for all equipment and
material purchasing. This is becoming a common practice in TQM. In a total
quality management culture, the purchasing department should be in a support
position and provide a full-service function.
Management commonly explains this situation by saying that project per-
sonnel who are aware of prices cannot be trusted to maintain confidentiality or
to give an unbiased, technical assessment. Many owner project managers resolve
this purported problem by delegating this function to outside contractors (usually
12 Chapter 2
on a reimbursable basis) over whom they have more direct control. In a total
quality management culture, this policy must change.
If management feels that discipline or project engineers cannot properly
evaluate technical and commercial considerations or that they cannot be trusted
with sensitive commercial information, then management should train them to
properly handle these responsibilities and provide a culture where these qualities
are commonplace.
One of the essentials of TQM is that the manager must be a role model. This
means being a technical expert over the discipline being managed. Yet in many
companies, the manager of project control is not an expert in estimating, or cost
control, or planning and scheduling. In key positions such as director of projects,
manager of purchasing or director of construction, this lack of technical expertise
is rarely a problem as only senior people with extensive project experience are
The Impact of Personnel Skills 13
Much has been written about the factors affecting efficient execution of engineer-
ing/construction projects, yet all major studies have come to the same conclusion
that two fundamental factors are involved:
adequate or high-level personal skills, and
• quality project management methods and techniques.
A. Impact of Personal Performance
Some companies have analyzed the impact that personal skills and performance
play in executing engineering/procurement/construction projects. During James
A. Bent's career in the engineering department of Mobil Oil Corporation, senior
management initiated a study to determine why then-current project performance
was poor, resulting in major cost overruns and schedule slippages in the capital
projects program. The study was carried out by four of the company's most senior
project managers, who arrived at the following conclusions:
The design basis contributed 80% of cost.
• The complete project management program contributed 20% of cost.
Figures 2.1 and 2.2 show a breakdown of the study team's findings.
As the Mobil Oil study determined, once the process design technology has been
selected and major project elements/objectives are established, the maximum
amount represented by the total project program would be 20%. An effective
project management program includes a combination of project execution meth-
ods/procedures and personnel skills. Effective methods, good personnel skills, and
adequate resources are essential if quality project management is to exist. The
Mobil Oil study team determined that high-quality methods and advanced per-
sonnel skills can result in savings totalling up to 20% of a project's cost. Con-
versely, a poor program and low skills can increase costs by 20% or more, and
14 Chapter 2
E.P.C. Projects
Detailed Effect
E P C Project
Complete Execution
j | 20% COSTJ §
PROJECT MANAGEMENT
PROGRAM Large Small
Project Project
ENGINEERING 4% 3%
PROCUREMENT 4% 3%
CONSTRUCTION 6% 4%
PLANNING & SCHEDULING 3% 3%
ESTIMATING/COST CONTROL 2% 2%
PROJECT MANAGEMENT 1% 5%
TOTAL 20% 20%
NOTES:
1. On large projects, the value of Project Management is low (1%) as the
effect of a single individual is less than that of a cohesive Project Team.
2. On small projects the reverse is true, and the effect of the Project
Manager can be the biggest single factor.
MobU Study
it is probable that the downside risk of cost increases is much greater, sometimes
in excess of 100%.
Figure 2.1, showing the overall impact, tempers the potential 20% savings
with the probability that half the savings (10%) might be influenced by a buyer's
market. It should be noted that a proper assessment of market conditions must
be reflected in the project estimate and contracting strategy so as to prevent
contracting pricing surprises at the later stages of the project.
Figure 2.2, showing a detailed breakdown of the 20% savings, allocates
individual percentages to the six major phases of an engineering/procurement/
construction project and shows the probable variations for large and small pro-
jects. The most significant variation is shown for project management, where the
impact of an individual on a small project can be the largest single factor. This
is especially true when the project manager is the designer, estimator, and
scheduler, as is often the case in the multiple small projects environment.
To meet the general purposes of the study, eight project management categories
were determined to be essential and were examined in detail; they were:
1. strategic project organizing (front-end planning),
2. contracting practices,
3. design effectiveness,
4. project controls,
5. management of quality,
6. materials management,
7. human resource management, and
8. safety.
The detailed composition of each category is shown in Table 2.1.
The Construction Industry Institute then surveyed owners, architect/engi-
neers, and contractors to determine their assessment of utilization and import-
ance of the identified categories. Table 2.2 contains information about survey
participation.
16 Chapter 2
Management
category Scope statement
Strategic This category focuses on principles/recommendations related to
project project organization, establishing objectives, scope definition,
organizing control, establishing communications/information processes, and
constructability planning.
Contracting This category focuses on those principles/recommendations related
practices to contracting strategy (planning, packaging, etc.) and the
utilization of specific contract provisions and/or clauses for
contracts controlled by the initiating party.
Design This category covers principles/recommendations relevant to the
effectiveness evaluation of the design effort, incorporating constructability
concepts into design, and control of design activities.
Project controls This category focuses on principles/recommendations related to
control integration, decision making, scope control, control
techniques, and estimating practices.
Management of This category is concerned with principles/recommendations related
quality to the implementation of quality assurance/quality control and
the documentation of quality effectiveness.
Materials This category focuses on principles/recommendations related to
management planning and utilization of materials management on projects.
Human This category is concerned with principles/recommendations related
resource to the quality of site supervision, field work force motivation,
management training, and site labor practices (substance abuse, overtime, etc.)
Safety This category covers principles/recommendations related to safety
communications, specific practices, and management attitude
toward safety.
Some duplication exists because several of these companies provide engineering and
construction services. They completed both the A/E and contractor questionnaires.
The Impact of Personnel Skills 17
Another part of the CII study analyzed the respondents' utilization of the key
techniques listed in Table 2.3. The respondents were asked to assess those
practices that were performed directly by the company by which the respondent
was employed. Owner/respondents were also asked to assess those practices
required of their engineering design and construction contractors. Table 2.4 shows
that overall utilization ranged from 66-70%, with safety highest at 76-82%, and
project control being second highest, at 72-77%.
Based on this data and taking a conservative approach, a savings of only
10% would result in $24 billion in savings per year. (The construction industry
is estimated to be $240 billion per year). At the indicated 70% utilization level
of high-quality project management skills by the owner (Table 2.4), the resulting
savings would be an annual $15 billion.
In addition to conducting the skills impact study, CII also asked owner/respon-
dents to indicate performance of their current projects. These results are shown
in Table 2.5. Current cost and schedule performance (at 61% and 66%, respec-
tively) is the result of an industry out of control. This is the other end of the
scale from the subjective cost savings discussed previously.
18 Chapter 2
Table 2.3 Cost Benefit of Maximum Utilization of CII/CICE Principles and Recommended
Practices
VIII. SUMMARY
I. INTRODUCTION
A. Quality of Estimates
Estimating is roughly divided into conceptual and detailed. The general range in
the quality of these two phases of estimating is about 40% to 10%, respectively.
The measure of the quality of an estimate is usually categorized by the amount
of contingency that is contained in the estimate. For example, a 10% estimate
would have a 10% contingency. Due to the high development cost and the time
necessary to produce a 10% quality estimate, many companies approve the funding
and full execution of design-based projects at the ±20% estimate quality. It is pos-
sible, in the special equipment areas and building industry, to produce 10% quality
estimates from preliminary design information. With plant projects, the construction
phase can have a 10% estimate, but only when design is 80% complete or greater.
The accuracy of estimates is largely dependent on the quality of the esti-
mating program and the experience of the estimator. Quality is also dependent
on estimating labor and time. The relationship is not linear. Reasonable invest-
ments of time and resources will, usually, provide better cost estimates. Further
improvements become increasingly expensive, with only modest improvements in
accuracy resulting from substantial expenditures of time and resources. A point
is soon reached where estimate quality is almost completely controlled by prob-
lems of forecasting future economic conditions, local project conditions, and qual-
ity of project performance. No significant improvement in estimate quality can
be made thereafter, except by incorporation of actual design and cost information
as the work develops. Often, senior management does not understand or prefers
not to accept this reality and insists that a 10% quality be produced when the
21
22 Chapter 3
B. Purpose of Estimates
This method takes the cost of a similar, previously built facility, and prorates the
cost for the new facility, based on changes for project conditions, capacity, esca-
lation, productivity, design differences, and time. This method is based on some
historical data and a lot of statistical relationships and assumptions. It is, there-
fore, usually accurate to about ±40%.
A historical database is developed for similar plants where the total cost is related
to capacity. This method is usually more accurate, generally around ±30%, but
does depend on the quality of the database. Economies of scale are also built in
Estimating Keys—Establishing a Realistic Cost Baseline 23
with capacity databases. This method is also used, at a lower level of detail, for
individual pieces of equipment and/or process/utility systems.
These conceptual estimating systems are generally used to give a quick and
early indication of required investment level. The resulting evaluations should
only be used for budget purposes and investment possibilities. The information
is not sufficiently accurate to make firm investment decisions. Sometimes invest-
ment decisions are made on this preliminary information, where economic viability
is not the first priority. Projects to meet environmental standards, stay-in-business
criteria, or research and development programs fall into this category. Another
purpose of these early estimating programs is to provide technical and economic
information on investment and resource requirements to advance the technical
basis and estimating quality to a higher level. Thus, many projects are funded
on a partial or phased approach.
This method calculates all other costs as a percentage of the major equipment
cost. Ratio methods are effective with a good database. The accuracy of this
method is generally ±20%. This quality of estimate is usually the minimum
requirement for a full investment decision of a design-build project.
This type of estimate should be produced after completion of conceptual
design and process selection and is an update of the conceptual estimate prepared
during feasibility studies.
The following shows the general design/scope basis:
• overall process flow diagrams,
• heat and material balances,
• onsite and off site facilities and layouts (power, steam, air, electricity, water),
• preliminary plot plant/building layouts,
• equipment list (by size and category),
• preliminary execution plant/organization/resources/schedule, and
• completed survey of appropriate estimating data.
This is an equipment and bulk ratio estimate for direct labor and material costs.
Indirect costs are factored from direct costs. A further statistical breakdown is
made to development engineering and construction jobhours for scheduling and
resource evaluation.
This method is the most accurate, generally ±10%, and is costly and time consum-
ing, as detailed takeoffs must be made of all material units and associated labor
in the project. This method requires that engineering be sufficiently advanced so
that accurate material quantity takeoffs can be produced. It also requires detailed
historical data for applying unit jobhour rates and costs to the estimated quantities.
This type of estimate can be developed only when the process design has
essentially been completed. It will also require a significant amount of detailed
engineering to be completed so that material takeoffs can be developed for civil
work, mechanical, piping, electrical, etc.
24 Chapter 3
Many companies have a policy that requires a detailed 10% estimate before the
project appropriation will be approved. These same organizations (typically manu-
facturing companies), also require that the project be started yesterday. Manufac-
Estimating Keys—Establishing a Realistic Cost Baseline 25
turing and plant management often insist on these two objectives, even though
they are incompatible. In most cases, the practical resolution of this management
inconsistency is for the estimate to be fudged. In other words, the estimate shows
a 10% contingency below the line, with a similar amount of money buried above
the line in individual categories where the risk is deemed to be the greatest.
While this process meets the company financial approval policy, it nevertheless
is poor management practice and provides an inadequate basis from which to
execute and manage the project.
It is also quite common for some companies to execute projects on a crisis
management basis, an approach that will in most cases increase a project's capital
costs. Still, since the project may be able to reach the marketplace at an earlier
time, this approach may increase the economic return as well.
Figure 3.1 shows the quality of estimating in relation to its completion of the
engineering, procurement, and design (EPC) progress curves. This information
is based on historical experience and shows that for a 10% quality estimate, the
percentage completions for a design-build project should be:
Engineering 85%
Procurement 90%
Construction 20%
With an outstanding historical database and high-quality personnel, it is possible
to provide a 10% estimate with lower percent completions of EPC.
Since many companies have a formal estimating section, the relationship between
the estimator and project manager should be clearly defined and properly under-
stood by all parties. The project manager should direct development of the
estimate before it is issued and should ensure the estimate properly reflects:
project objectives and their priorities,
• design scope and design specifications,
• maximizing of quantities and minimizing of factors (numbers of drawings
and construction work units),
correct evaluation of design and labor productivities,
• current project and site conditions (access, congestion, etc.),
• proposed execution plan/contract strategy,
• schedule requirements (economic versus acceleration), and
adequate contingency evaluation.
As can be seen from the above list, the project manager is actively involved in
developing the estimate and is ultimately responsible for the final product.
NOTES : TYPICAL ESTIMATING CATEGORIES
1. ACTUAL PROGRESS PLOTTED AGAINST COMPANY HISTORICAL EXPERIENCE . 1. Proration (40/25**)
2. Cost Capacity Curves (30/20%) IS)
2. EARLY CONSTRUCTION START REFLECTS A PROJECT WITH EXTENSIVE SITE PREPARATION . 3. Equipment Ratio (20/15%)
3. CONCEPTUAL DESIGN HAS BEEN COMPLETED DURING A PHASE I OPERATION . 4. Quantttv/Untt Cost (10/5%)
r— 1 0 0 - • —-
ESTIMATE
"QUALITY
90 -
40/25%H
80 -
ENGINEERING IS A KEY fr-
m
MATERIAL &
SUBCONTRACT
S>
MILESTONE . PROVIDES
ADEQUATE SUPPORT FOR
iz
•
70 - COMITMENTS .) j . T U L L CONSTRUCTION —
c /
PROGRAM I MECHANICAL
o | (PIPING t ERECTKDN)
?TK)N) 11 I |
M 60 COMPLETION
P
m
ill
L
E
T
50 - =r 4--/ H i l
STAlRT OF
CONSTRUCTION } - :g:;:^
-f-
E
40 -
m fcoNSTRUCTIONl
30 -
m 20
10
ADVANCE COMITMENTS
OF CRITICAL MATERIAL
CAN BE MADE IN PHASE 1 .I
o
PROJECT DURATION-
CONCEPTUAL PHASE EXECUTION PHASE
PHASE I PHASE 1 I CO
To ensure that the scope definition is of the required quality, the estimator/project
manager should make a detailed review of all basic design documents, their
revision numbers, and dates of issue, as follows:
check that all major equipment is included and is listed by equipment number;
• review all items shown on plot plans, flow sheets, P&IDs, and equipment
lists to ensure their inclusion in the estimate;
check equipment and system capacities, flow rates, temperatures, and pres-
sures for deviation;
check whether owner costs are to be included or shown separately;
• evaluate deviations in the scope, design, or estimating basis from those
assumed in the earlier estimate, and include them on a puts-and-takes list;
and
• have specialist engineers assigned to the project review and verify the design
scope.
E. Site Preparation
Check soil conditions (i.e., type, frost depth, de-watering, sheet piling, and
drainage requirements).
• Consider possible underground obstructions.
• Be aware that on large, grassroots projects, earth-moving quantities are
often underestimated.
F. Piling
Check the type of piles (e.g., precast, in situ, timber) and the cutting of pile
caps.
• Determine who will do the layout work (i.e., the prime contractor or a
subcontractor).
Following are four methods of preparing a piping estimate. The method chosen
depends on detail and accuracy of the estimate.
Estimating by length. This method is based on historical data and assumes an
average number of fittings and flanges for a standard piping configuration.
Costs are on a unit length basis by pipe size and schedule. Fabrication is
separated from field installation. It is necessary to add only the cost of such
items as valves, pipe supports, and testing to arrive at a total direct cost
for the piping system. Care should be taken to check allowances for unusual
complexity of piping arrangements (especially onsite units or revamps).
Estimating by weight. In this method, piping materials are assumed to have a
value approximately proportional to their weight. Pipe is assigned a cost
per pound for material and a number of jobhours per ton for fabrication and
erection. Adjustments should be made for unusual materials and labor
productivity for the plant location.
Estimating by ratio. This method calculates piping as a percentage of the major
equipment cost. Ratio methods can be used only with an appropriate data-
base. This is not a very accurate method and is usually applied only to
conceptual estimates.
30 Chapter 3
Estimating by unit cost. This method is more accurate than estimating by ratio,
but it is costly and time consuming, since detailed takeoffs must be made
of all labor and material units in the system. This method requires that
engineering be well advanced before accurate takeoffs can be produced. It
also requires detailed historical data for pricing installation labor.
After an estimating method is selected and applied, a piping estimate review
should be performed to examine the method and extent of the takeoff by sampling
line takeoffs and comparing actual quantities and costs with estimates. Such
items as the basis of fabrication and the impact of special materials should also
be reviewed.
H. Electrical
In estimating electrical work, a schedule of the number and size of motor drives
is a basic requirement. Motor control center and power distribution items usually
constitute a major part of the electrical work. Since their prices can vary consid-
erably, budget prices should be obtained from potential suppliers. The cost of
power cable should be estimated in reasonable detail. A plot plan layout is useful
in assessing quantities, while material unit prices may be estimated from his-
torical data. Minor/miscellaneous services, such as emergency lighting, fire
alarms, intercoms, power outlets, and telephone systems, can be assessed approx-
imately or represented as an allowance. Plant lighting may be estimated on an
area or unit length basis. A gross estimate of electrical work based on horsepower
can be inaccurate. The estimate should take into consideration local electrical
codes and area classification. Climatic conditions may require a different type of
cable and hardware, and therefore could affect cost,
I. Instrumentation
J. Insulation
K. Painting
Painting is not usually large enough to justify a detailed estimate, but any
prorated method and values used should be reviewed.
C. Productivity (Jobhours)
Depending on the quality of the estimating base, the preceding jobhours are
normally factored for time and project location. A geographic productivity system
is essential for a quality estimating program. General items (such as handling,
scaffolding, testing, and rework) are on a jobhour percentage basis for a detailed
estimate, and are included in jobhour rates for a conceptual estimate.
D. Labor Costs
subcontract versus direct hire, and what is covered in the all-in subcontract
wage rate, especially field indirects;
average wage rate;
inclusion of appropriate fringe benefits, taxes, and insurance; and
allowances for premium pay on overtime and shift work.
Where possible, ensure that estimates have dimensional sketches showing layouts
of temporary facilities that can then be quantified for estimating.
A. Temporary Facilities
Discuss and check the methods used by the construction group in establishing
equipment requirements. Check for:
• list and scheduled duration of all major equipment;
• small tools (normally estimated as cost per labor jobhour or percent of
direct-labor costs);
• availability of equipment, and start and finish of rental period;
• major and minor equipment maintenance;
• purchased equipment, and rented equipment and its source;
• special and/or heavy lift requirements; and
construction equipment cost per direct-hire jobhour.
C. Construction Staff
Examine the site organization chart and assignment durations of personnel. Also
review:
• relocation costs, travel and living allowances, fringe benefits and burdens,
and overseas allowances;
• total staff jobhours related to total labor jobhours; and
• supervision cost related to the construction labor cost.
Estimating Keys—Establishing a Realistic Cost Baseline 33
Review the estimates of field office supplies, copying, telephone and facsimile,
office equipment, and consumables. These items are usually estimated as cost
per labor jobhour or as a percent of direct field costs.
A. Key Elements
Conceptual estimates vary widely in quality, but generally in the range of 40%
to 15% quality, where quality is defined as the amount of estimating contingency.
For developing a 20% quality estimate, the following are key elements of engi-
neering costs:
• engineering scope review,
• project conditions review,
• key database—hours per piece of equipment,
engineering costs (Fig. 3.2),
large project experience—size effect (Fig. 3.3),
breakdown of home office hours (Fig. 3.4),
home office expenses (Fig. 3.5),
typical data points (Fig. 3.6), and
• project support for approved projects—owners (Fig. 3.7).
B. Engineering Scope Review
To ensure that the scope definition is of the required quality, the estimator/project
manager should make a detailed review that all preliminary-basic design docu-
ments are available and up-to-date (revision numbers and dates of issue); the
estimator/project manager should:
• check that all major equipment is included and is listed by equipment number;
review all items shown on plot plans, flow sheets, P&IDs, and equipment
lists to ensure their inclusion in the estimate;
• check equipment and system capacities, flow rates, temperatures, and pres-
sures for deviation;
• identify unique, special, or high cost equipment; and
• check whether owner costs are to be included.
Before developing the details of the estimate, an overall evaluation should con-
sider the following:
• project location (site characteristics, labor productivity, and local conditions);
• schedule (anticipated project start, fast track, economic, acceleration);
grassroots installation, revamp, and shutdown elements; and
• economic outlook, engineering and construction resources, vendor-material
capacity.
34 Chapter 3
The overall evaluation also should recognize innate characteristics of the project.
Both equipment items and construction elements can add to design engineering
hours. Special handling or foundation requirements of equipment can lead to
more than normal engineering hours. Similarly, construction preplanning con-
structability considerations and unusual installation requirements can, again,
add to engineering hours. Schedule acceleration and lack of skilled resources can
impact on engineering productivity.
The most widely used database for conceptual estimating of engineering is:
Engineering Hours per Piece of Equipment
The engineering hours represent total design hours, including supervision, start-
ing from a completed basic design package to mechanical completion. Feasibil-
ity-conceptual design hours are not included; this category of work is covered
with a follow-up paragraph. Also not included are project management and other
home office services. The total pieces of equipment are represented by the equip-
ment list, which is a standard industry document. The following is a typical
database (U.S.):
Category Engineering hours
Petrochemical, utilities 800-1200
Chemical 600-800
Pulp and paper 500-700
Pharmaceutical 400-500
Metals-mining 300-400
Food 200-300
Mechanical handling 100-200
Selecting a specific number from the above ranges will depend on engineering
complexity and special considerations, as previously outlined, of the individual
project. For example, considering the petrochemical range of 800-1200 engineer-
ing hours per piece of equipment, the following would be typical:
Cracking (complex) 1200
Merox (simple) 800
However, good judgment is required to properly assess the engineering com-
plexity and associated project conditions to determine the correct rate. In excep-
tional cases, it is possible for a project to be outside the normal range. In addition,
it is possible that overseas engineering would require an added factor of 10-20%.
The following descriptions of the figures noted above provide further guidance.
E. Engineering Costs
Figure 3.2 is a chart showing a family of curves for differing work categories/
industries, where engineering is shown as a percent of the total project cost. The
most widely used curve is Curve C, chemical process plants, where the midpoint
of the curve shows engineering at 10% of the total cost. Curve E is used for small
m
S
1
(O
I
Engineering costs are approximately 10% of TIC for intermediate and large
projects. However, experience indicates that this number can increase as
shown in curve F due to size effect, lack of skilled resources, and poor
planning. Ift
90 ^ ^ ' i
E '
i i i i i s
i
I
•
to - "
8" . D
B
c
*——
-^ -^
• L J J •JL am
F
i — M l " • •••
m»^" I (Q
fi)
£ 10 —*— - - ^ -+ -
a
- — -
co 8 -
•——
2 6
o
1
—
*O 5
O
1- o
u
Q-
3 a
2
0.1 0.2
i i i i
0.3 0.4 0.5 0.7 1 2 3 4 15
! 1 1 1
7 10 20 30 40 50 10C 30C 600 1000 140C w
160C 0)
Total installed cost, millions of dollars 1130C
20 0 0 8
Engineering costs as average percent of total installed costs: A, office buildings and laboratories; B,
power plants, cement plants, kilns, and water systems; C, battery-limits chemical process plants; D,
complex chemical and grass-roots chemical plants and pilot plants; E, small revamp/retrofit projects; F,
large process projects.
© 20 - 22 % Norn
20% lllliii Ilil 1 3
1 6 - 1 8 % Norm
revamp/retrofit projects, and it should be noted that the percentage more than
doubles, to 20% plus. Curve F applies to large process projects. Key features of
this curve are illustrated by Figure 3.3.
Figure 3.3 shows data of 16 large projects, over the period 1970-1985, where the
size or scale effect of the previous curve (unit cost reduces as size increases, as
per 6/10th rule) is reversed. This means that the curves, instead of steadily
reducing as size increases, can and do increase when projects reach a very large
size and/or are outside the experience of the assigned project personnel. This is
known as the size effect and is, in fact, a further variation of the learning curve.
Figure 3.4 is a typical breakdown of total home office hours for a contractor who
has total responsibility (i.e., full scope) for executing the project. Other conditions
are:
work completion is mechanical completion,
data does not include feasibility-conceptual design,
• data applies to projects over $5 million,
• owner's support hours are not included,
project's experience over the period 1970-1990, and
• adjustment for increased sophistication of instrumentation is included.
Application
This information can be used to check an estimate or a contractor proposal of
home office hours. It can also be used for early evaluation of home office labor
and schedules when only total costs or hours are available.
Example:
1. For a typical project, we can assess the percent of piping hours. This is
derived by totalling the hours required for piping engineering activities
(plant design, 16.4%; piping engineering, 2.1%; bill of materials, 2.1%; and
model, 0.4%, for a total of 21%).
2. As a percentage of engineering only, piping becomes 21% divided by 0.67,
or 32%. As overall engineering and piping design are often on the critical
path, individual evaluations are frequently required. Where information is
lacking, the following percentages should be used:
engineering hours as a percentage of total home office (65%), and
• piping hours as a percentage of engineering (35%).
Figure 3.5 illustrates many home office services considered part of the expense
category that are often forgotten or underestimated.
• Full scope EPC responsibility for contractor • Work completion at mechanical completion
• Data does not cover conceptual design (Phase 1) • Data applies to intermediate / large projects ($5 MM plus)
Engineering
67% Engineering
Project services
Proposals
Computer control
Scheduling 2.0
Procurement
Purchasing 5.0
General office
Stenographic 4.5
Accounting 7.0
Total 100.0
REPRODUCTION CHARGES
COMPUTER SERVICES
MISCELLANEOUS
Figure 3.6 shows engineering hours, at both conceptual and detailed levels, for
various categories of drawings and documents.
Figure 3.7 is a set of curves used to estimate the owner cost of its project team
throughout the project execution phase. The two curves-databases are for stan-
dard approach cost-reimbursable projects and for a lump-sum approach. Obvi-
ously, the size of an owner project team should be less on a lump-sum job. As
illustrated, the curves are based on actual project experience.
As covered by Figure 3.4 and Figure 3.8, this category is generally 3% of total
project cost.
Engineering
• Jobhours per drawing (total drawings) 150 to 160
• Jobhours per piece of equipment 1000 to 1200
• Jobhours per piping isometric
without CAD 8 to 10
with CAD 4 to 5
• Jobhours per P & I diagram 400 to 500
• Jobhours per plot plan 200 to 300
• Jobhours per material requisition 8 to 10
Covering design, project management, project control, procurement services, construction &
contract administration. With a Managing Contractor, project team is in a monitoring role. For
"Small Projects Program", includes detailed engineering and "full" management of the work.
60001
5000
4000
3000
2000
HOURS
PER 1000 80%
$M. 800
600
40O
200
1 2 3 4 5 7 10 20 30 40 50 10 300 600 1000 1400
1600
Total installed cost, millions of dollars 1800
2000
Schedule - Detailed engineering to mechanical completion
Confidence level at plus/minus 20% with 80% probability.
Figure 3.7 Owner engineering project department standards.
Estimating Keys—Establishing a Realistic Cost Baseline 41
HOME OFFICE
because soil borings are not available. For instance, the earthwork cost might
increase by as much as $100,000. The cost might also be $30,000 less than the
estimate due to competitive market conditions.
After the project team establishes the highest and lowest possible values
for each element in the estimate, these numbers are entered into a computerized
risk evaluation program that performs a Monte Carlo simulation. In this process,
a random sample value for each element is taken, and the resulting total esti-
mates are arranged in order from highest to lowest. The deviations of each total
value from the original estimate are presented in Table 3.1. The certainty column
represents the likelihood that the actual cost will not exceed the original estimate
after the indicated amount of contingency has been added.
This information is provided to management to determine the risk it is
willing to take on the project. For instance, in this example, if management
selects a 70% risk level, the estimate would be $1,306,100 ($1,225,000 + $81,100).
Risk analysis is discussed in greater detail in Chapter 11, "Range Estimating."
XIX. ESCALATION
Escalation is usually included as a separate line item. Escalation rates for ma-
terial and labor costs should be separately identified.
Good assessments of labor productivity are essential for a quality cost estimate.
Cost control, planning, and scheduling can be ineffective without an adequate
evaluation of labor jobhours.
Figure 3.9 shows major elements of a labor productivity system. The rec-
ommended additional factors and associated curves have been developed from
historical data. However, on a specific project, any one or even several conditions
can have an abnormal effect on productivity.
The productivity analysis starts from a general area factor. Additional allowances,
based on the recommended ranges are then made for the listed conditions.
Judgment and experience are necessary for determining these additional allow-
ances. Even if no previous experience of the area exists, this procedure can still
be very effective since the condition productivity adjustments are often of a
greater magnitude than area productivity differences.
44 Chapter 3
INFORMATION SOURCE
SCHEDULED OVERTIME
LABOR OENSITV 1
in
H
- t
1-05
ill]
7
0-95-
0-90
1 i I I ? I . I M Lit 3 J 4 I T i 8
PROJECT CONSTRUCTION JOBHOURS ( MILLION )
JOB SIZE
Note;* Curves do not include loss
for second s h i f t .
PRODUCTIVITY LOSSES DO NOT
NORMALLY OCCUR FOR SELECTIVE
OR SPOT OVERTIME
;i|.!.;;20!:il:;:;|:; : i ^ | : . : :
EXTENDED WORK WEEK
The Base : S.E. USA @ 1.0 (Florida, N & S Carolina etc.) - Non Union;
and has best "Basic Elements", as listed
1 . BASIC ELEMENTS
a) Weather/Geographic-Cold, Ice, Heat, Rain(excess) etc.
b) Inherent Trade Skills & Capabilities - Resources Available.
c) Work Ethic, Culture, Militant Trade Unionism(very negative).
3. INTERNATIONAL
CANADA-1.7 JAPAN-1.1 INDIA-3.0/2.0
MEXICO - 1.5/1.8("sticks") S. KOREA-1.3 PHILIPPINES - 2.5
MALAYSIA-1.9 BRAZIL-1.8 HONG K O N G - 1 . 5
SRI LANKA-2.5 CHINA - 2.2 AUSTRALIA-1.6
SINGAPORE-1.6 INDONESIA-1.9 I N D I A - 2 . 5
NEW ZEALAND-1.5 TAIWAN-1.3 PAKISTAN - 2.2
VENEZUELA - 1.65/1.8("sticks") "sticks"= Remote, undeveloped area,
SOUTH AFRICA - 1.4/1.9("sticks"J with little or no Infrastructure.
4. EUROPE/SCANDINAVIA/MIDDLE EAST
GERMANY-1.1 KUWAIT-2.1 SAUDI ARABIA-1.6
U.A.E.-1.7 ISRAEL-1.8 E. EUROPE - 2 . 0
FINLAND - 1 . 7 RUSSIA - 2.0 NETHERLANDS-1.35
NORWAY-1.75 DENMARK-1.35 SWEDEN-1.35
FRANCE-1.3 BELGIUM-1.3 SWITZERLAND-1.5
EIRE-1.65 ITALY-1.4 GREAT BRITAIN-1.5
SPAIN-1.7 POLAND - 1 . 9
C. Job Size
In addition to staffing levels, as shown in Figure 3.10, job size (in jobhours) has
a significant effect on productivity. This curve shows that the estimating database
reflects a project size of one million jobhours (direct work only). Thereafter, as
job size increases, productivity decreases.
Figure 3.10 shows extended workweek curves for small and large jobs. The
productivity loss adjustment applies to total jobhours and not merely to the
additional overtime hours. Note, however, that during periods of major low em-
ployment, such as recessions and depressions, it is possible that labor productivity
will not follow these curves, since the fear of unemployment can be an overriding
consideration.
E. Area Factors
Figure 3.12 shows the major items to be developed and/or considered before
developing the estimate. In conjunction with the pre-estimating survey, a com-
prehensive checklist can be a significant aid in ensuring that all appropriate
details have been covered. The following is not a complete list, but it will
significantly assist with major considerations:
• plan the estimate,
• cover all items,
serve as a base for your database, and
• cover the three p's—political, procurement, process design.
A. Political Considerations
Section
Project Management Estimating
and
Control Manual Subject
Page
climate:
- humidity,
- temperature,
- prevailing winds,
- seasons,
- storms,
- snow accumulation and ice conditions,
rain (average and seasonal),
- days lost due to weather,
- shelters required,
- special methods of construction necessary, and
- indoor/outdoor equipment.
earthquake factors
• access:
- distance from metropolitan area;
- roads, water, air, railroads;
- road conditions;
- road clearances (tunnels);
- road and bridge capacity; and
ice conditions.
• offshore facilities:
water depth,
- wind forces,
- wave forces,
- sea floor conditioning, and
soil conditions.
50 Chapter 3
environment:
- attitude of the community,
present and future zoning,
- other industry in the area,
- environmental restrictions,
environmental impact study,
required permits—local/state/federal/other,
legal counseling,
- delays in obtaining permits and associated costs in terms of escalation,
requirements for and costs of pollution control (noise/air/water/waste
disposal), and
- considerations of alternate site.
political aspects:
political climate of the proposed site and its prospects for future stability;
- governing authority's encouragement/discouragement of investment,
attitude toward business, tax structure; and
- on overseas projects, the degree of government involvement and the
terms of payment and the probability of delayed payment.
procurement:
source of information about vendors;
- location of vendors;
- methods of transporting equipment and material;
availability of a minimum of three bidders;
- vendor reliability and experience;
- origin of material and equipment;
- import restrictions;
- import duty;
- availability of equipment on reasonable delivery schedules;
- terms and conditions;
- discounts for large purchases;
- consideration of whether purchase orders will be firm, cost plus, or
with specified escalation;
warranties;
- service that suppliers can provide during construction and operation,
and the cost of those services;
provisions for inspection and expediting;
- export packing requirements;
spare parts and their cost;
- currency in which purchases will be made;
- exchange rates;
payment schedules;
- marshalling yard requirements;
- loading and unloading requirements;
lightering;
- demurrage costs;
higher costs due to congested harbors; and
Estimating Keys—Establishing a Realistic Cost Baseline 51
This section includes references, which will be helpful in developing a cost esti-
mate.
Figure 3.8 illustrates the overall breakdown of project cost based on historical
data for projects built in the United States on a prime contract basis during the
past 20 years. Since most costs have retained the same parity over time, the
only significant change to this experience is the increase in instrumentation costs.
Application
When only an overall cost is known, this breakdown can be useful in providing
overall data for a quick evaluation of engineering and construction costs and
jobhours. This can enable cost claim and schedule evaluations to be made.
Example-
Assume that a project has an estimated overall cost of $100 million.
1. Figure 3.8 shows that home office costs are roughly 13%, or $13 million. By
a further assumption that the contractor's home office all-in cost is $50 per
hour, we can derive a total number of home office jobhours:
Number of jobhours = 13>0(^>000 = 260,000
ou
Thus, a gross schedule and jobpower evaluation can now be made.
52 Chapter 3
10 ENGINEERING (D&D) 20
3 HOME OFFICE (SUPPORT)- 5
47 MATERIAL (DIRECT) 40
21 CONSTRUCTION DIRECT - - 17
19 CONSTRUCTION INDIRECT- 18
100% 100%
100% 100%
COST BASIS
(Excluding Material Costs)
PROJECT (EPC)
•
HOME OFFICE
• J INDIRECT HOURS - 30 %
FIELD STAFF - 15 %
2. Figure 3.8 shows that direct field labor costs are roughly 21% or $21 million.
By a further assumption that the direct field labor payroll cost is $25 per
hour, we can derive a total number of direct field jobhours:
TVT u ruu 21,000,000 O/IAAAA
Number of jobhours = — — ^ = 840,000
Applying known and historical relationships allows gross evaluations for
engineering and construction durations to be made. These, in turn, can be
used to prepare labor histograms and progress curves. Note that for larger
projects, the percentage of home office and field overheads may increase.
Figure 3.13 shows the same overall cost breakdown as Figure 3.8 and compares
it with small revamps. The probability for "Grassroots—Large" is 80%, whereas
the probability for "Small Revamp" is 70%, as the variation in small projects
costs is much wider. The data also includes a breakdown of construction direct
labor hours, by discipline. As with the previous figure, these breakdowns/relation-
ships can be helpful in evaluating labor hours, schedules, and labor requirements.
Figure 3.14 shows construction indirect and direct costs. A typical breakdown of
the major indirect costs is also shown. Individual companies might allocate their
indirect costs somewhat differently, but a high degree of conformity still exists
in the contracting side of the industry. Again, it is emphasized that the stated
information only applies to a full EPC project.
A further emphasis of this figure is on the engineering/construction labor
hour relationship. This is shown as the ratio of 1:6 and is for large projects.
Small projects have a 1:3 ratio. In other words, one engineering labor hour
automatically generates 6 direct construction labor hours. This is a very useful
rule of thumb, although the ratio does vary as the design/construction complexity
and size vary.
This relationship highlights the need for design engineers to realize that as
they are designing, they are also generating the construction labor hours. Full
realization of this fact should lead designers to more carefully consider the
question of constructability of their designs. This is the design process of working
to construction installation considerations, as well as working to standard design
specifications. Constructability considerations can result in significant savings in
construction labor. Such considerations are essential in the following types of
construction/conditions:
• heavy lifts,
prefabrication and pre-assembly,
• modularization,
• offshore hookup work,
site problems of limited access, and
• lack of resources at the jobsite.
Cost Capacity Curves - Oil Refinery - Direct Material, $ per Barrel
Bare Material Costs; Data below
not incded: Freight, -|OOO- 10,000 BPD Time Base Mid 1 9 9 4
Taxes, Duties, Spares is of Lesser | Exponent 0.60
or Vendor Services. Quality.
By JAB
900 Date Dec.1994
Material 500-
Per Barrel
300-
200
100
O
Figure 3.15 Cost capacity curves—material costs per barrel.
1
Estimating Keys—Establishing a Realistic Cost Baseline 55
The relationship between engineering and home office support services (such
as project management, project control, procurement, computer, and clerical) is
shown also at 40%. This relationship is in labor hours.
Figure 3.15 is based on 30 years of experience and shows costs for various oil
refinery process units. These are bare bones rates, and the following adjustments
need to be carefully considered:
• bare process numbers (there are usually enhancements/additions);
• assumes cheapest source;
• assumes 20% discount from current pricing levels; and
• does not include inspection, expediting, spares, vendor services, etc.
This is a project approach to estimating, where current market experience
is built into the budget/estimate as targets for the project manager. Overall
project experience has been that, in most cases, the lower costs of cheapest source
and 20% discount are not achieved due to low project-purchasing skills. With
project-specific information and assuming fair-to-average project skills, the above
adjustments can be more than +50% to +60%.
Figure 3.16 shows labor hours for various oil refinery process units. These
are bare bones rates, and the following adjustments need to be carefully con-
sidered:
• area factor, (see Figure 3.10; base is Southeast USA)
area workload, (see Figure 3.9; -10% to +10%)
• job size (large), (see Figure 3.9; -5% to +20%)
• site conditions (extreme), (0 to +20%)
labor conditions (militant unions), (0 to +10%)
field management (quality), (-5% to +5%)
direct hire to subcontract (US only), (-10% to 0)
• schedule/control skills, (-5% to +5%)
If the above specifics cannot be developed, use a general number from the range
of +10% to +30%.
E. Subcontract Estimating
14
Direct
12"
Labor Hours
10-
Per Barrel
8
6-|
O
Figure 3-16 Cost capacity curves—jobhours per barrel. 0)
i
CO
Estimating Keys—Establishing a Realistic Cost Baseline 57
the duration calculation. It is also possible that absenteeism will increase, sometimes
to such an extent that there is no schedule advantage for the increased workweek.
Figure 3.18 presents data compiled from the sources indicated and plots
labor efficiency against overtime hours worked, based on 5-, 6-, and 7-day
workweeks. This data applies only to long-term, extended workweeks. Occasional
overtime can be very productive with no loss of efficiency. The figure shows a
recommended range of productivity loss by project size (small to large). It should
be noted that studies of the Construction Users Anti-inflation Roundtable (now
the Business Roundtable) have concluded that prolonged periods of scheduled
overtime can actually result in a net loss of productivity (i.e., no gain from the
expenditure of overtime hours). Depending upon the schedule, this can begin to
occur after 6-8 weeks and, if the extended overtime continues, the schedule can
actually be lengthened rather than being improved. Scheduled overtime should
therefore be used with great caution.
Application
Figure 3.18 can be useful in an overall evaluation of the impact overtime hours
will have on schedule and cost. It can establish an increase in total labor hours
required for a loss in efficiency due to an extended workweek. However, judgment
should be used on an individual location basis. Some areas, particularly less devel-
oped countries, work 60-hour weeks that are only as productive as 40-hour weeks.
Example:
Assume that a project has a total construction scope of 1 million jobhours and
is based on a 5-day, 40-hour workweek. If the same workweek is increased by
eight hours, look to the chart for eight hours of overtime, and using the NECA
5-day, large project curve, read across to an efficiency of 90%. This indicates
that, due to a loss in efficiency, 10% more hours will be required to accomplish
the same amount of work. Thus the jobhours will be estimated at 1 million x
1.10 = 1,100,000 jobhours. Schedule and cost evaluations can now be made for
an additional 100,000 jobhours, but at an increased level of work. Obviously, a
schedule advantage accrues.
Note, however, that the curves contained in Figure 3.18 do not include
efficiency losses for a second shift, which can be about 20%. However, shift work
01
ECONOMIC BUDGET BASIS
100? 00
90%
80%
70%
OVERTIME H O U R S O
0)
losses depend on the type of work, company organization, and experience. In the
offshore industry, where shipyards traditionally work on a shift basis, losses can
be minimal or even zero.
Figures 3.20A and B illustrate major equipment costs, labor unit rates (direct
labor jobhours per ton), and some dollar rates for fabrication and hookup of major
types of modules); these include:
• module fabrication (can be used if design drawings are available and detailed
quantities taken off),
60 Chapter 3
overall module fabrication (broad data when only overall module weight
and/or category of module is known), and
• site installation/hookup (broad data when only overall module weight is
known).
As indicated in Figure 3.20A, the labor unit rates are for a 1986 European
location. The rates may have to be adjusted for a United States location due to
higher productivity levels at U.S. yards. For well-established U.S. yards (such as
those in Oklahoma and the Gulf states), the fabrication productivity (jobhours)
can be better by 30-40%, and installation/hookup by 20-30%. However, for many
Estimating Keys—Establishing a Realistic Cost Baseline 61
small, inexperienced U.S. yards, these improvements should not be expected. This
data applies to land-based modules as well as offshore modules.
I. General Data
The following figures illustrate historical relationships and data that can be used
in estimating: Figure 3.21, time-escalation data of the the Nelson-Farrar Cost
Index; Figure 3.22, economies of scale; Figure 3.23, an alkylation process cost
capacity curve; Figure 3.24, typical factors in shutdowns and retrofits; Figure
3.25, breakdown/factors of a good construction estimate; Figure 3.26, factors of
62 Chapter 3
Pumps, compressors, etc. 222.5 538.6 1,177.8 1,216.4 1,254.6 1,254.0 1,278.6 1,278.6
Electrical machinery 189.5 287.2 548.1 550.4 555.5 555.9 561.8 562.2
Internal-comb, engines 183.4 348.3 794.4 809.2 820.6 822.6 834.0 836.5
Instruments 214.8 466.4 844.7 865.5 879.3 877.3 886.6 887.4
Heat exchangers 183.6 478.5 772.6 746.6 704.1 704.1 677.9 682.1
Misc. equip, average 198.8 423.8 827.5 837.6 842.8 842.8 847.8 849.4
Materials component 205.9 445.2 832.3 824.6 846.7 850.1 865 2 869.0
Labor component 258.8 729.4 1,533.3 1,579.2 1,620.2 1,624.8 1,660.4 1,664.9
Refinery
(Inflation) Index 237.6 615.7 1,252.9 1,277.3 1,310.8 1,314.9 1,342.3 1,346.5
Fuel cost 100.9 384.5 443.8 425.9 421.5 423.6 449.0 454.7
Labor cost 93.9 145.5 280.8 281.1 286.2 275.0 260.3 261.7
Wages 123.9 314.3 787.4 824.9 868.0 855.2 871.3 871.4
Productivity 131.8 216.1 280.6 293.8 303.4 311.0 334.8 333.0
Invest., maint., etc. 121.7 252.6 511.4 519.2 524.3 526.0 536.9 538.6
Chemical costs 96.7 195.2 228.5 218.8 210.0 209.4 207.3 210.4
Operating indexes
Refinery 103.7 209.3 392.2 393.3 396.3 392.9 394.2 396.3
Process units* 103.6 267.1 418.6 415.1 416.9 414.9 423.1 426.2
RpproH.ir^H hy permission from Oil & Gas Journal, 3050 Post Oak Blvd., Houston, Texas
77056. The Nelson-Farrar refinery construction and refinery operating cost indexes are
piihlished regularly in Oil & Gas Journal.
Cost-Capacity Factors
Six-tenths
Factor Rule:
Example:
C2 - $8,000,000 (200,000 tons/yrr
2
{ 100,000 tons I yr t
= $12,100,000
ECONOMIC DATA
ALKYLATION
1OO
0
k
0 i
c
cj
"c
c
I 10
y • t
10 100
PREPARATORY SHUTDOWN
(6-12 MONTHS) (1-4 WEEKS)
1 CONTROL
b) PLAN EN6INEEWN6-PR0CUREMENT-C0NSTRUCT10N
d) ESTIMATE
4. SCHEDULE/PROGRESS
- PLANNING BOARD
- C . P . M . SCHEDULES
1 1 1
K 0.102 x 0.147 x 0.030 xO 012
•
FRINGE
+
LABOR
1
BENEFIT BUROEN + TOOLS +
COST COST COST COST
FIELD
SUPERVISION
COST
TEMPORARY
FACILITIES
COST
CONSTRUCTION
EQUIPMENT
COST
CONSTRUCTION!
SERVICES C O S T L
DIRECT FIELD LABOR DIRECT FIELD LABOR DIRECT FIELD LABOR DIRECT FIELO LABOR
HOURS HOURS HOURS HOURS TOTAL
CONSTRUCTION
OVERHEAD COST
typical construction overhead costs; and Figure 3.27, historical data (direct hours
per work unit) for construction work.
The following are typical data points for evaluating estimating levels or monitoring
project performance. This data applies to large U.S. process plants. Adjustments
should be made for overseas locations and for small plants. The following rates
do not include handling, scaffolding, testing, or rework.
Civil
• Concrete foundations (incl. formwork, rebar, etc.) -jobhours per cubic yard 20 to 25
Structural Steel
• Erect heavy steel (100 lbs per foot) - jobhours per ton 12
• Erect light steel (20 lbs per foot) - jobhours per ton 36
Equipment
CONTRACTOR 3% 2% SPECIAL
FEE FIXTURES, FITTINGS SYSTEMS
& EQUIPMENT
3. OFFICE BUILDINGS
^y^ 28% ^ v ^ 1% STRUCT%L/CARPENTRY
• Land/Engineering Costs
not Included / \ CONCRETE A> V 3 % SPECIALTIES
/ 24% \ JV ^X^V-2% MOISTURE PROT'r
• Furnishings & Office ^^\JH2% DOORS/WINDOWS
Equipment not
Included MECHANICAL V ^ ^ - 4-3% MASONRY
These specifications are typical but not all-inclusive. Division 1, for example, can vary
greatly in the services to be provided.
1. GENERAL REQUIREMENTS Summary of work, allowances, alternates/alternatives, project meetings,
submittals, quality control, construction facilities and temporary controls,
material and equipment, contract closeout.
7. THERMAL & MOISTURE PROTECTION Waterproofing, vapor retarders, insulation, EIFS, fireproofing, fire stopping,
manufactured roofing and siding, membrane roofing, flashing and sheet
metal, roof specialties and accessories, skylights, joint sealers.
8. DOORS & WINDOWS Metal doors and frames, entrances and storefronts, hardware, glazing.
10. SPECIALTIES Visual display board, compartments and cubicles, louvers and vents, grilles
and screens, wall and corner guards, identifying devices, pedestrian control
devices, lockers, fire protection, operable partitions, toilets and bath
accessories.
15. MECHANICAL Basic materials and methods, insulation, fire protection, plumbing, HVAC,
air distribution, controls, testing, adjusting and balancing.
16. ELECTRICAL Basic materials and methods, service and distribution, lighting,
communications, controls, testing.
A. LANDSCAPING & OFFSITE WORK Plants and lawn, planters, landscaping, sprinklers.
B. ARCHITECT FEES
D. PROJECT MANAGEMENT
E. CONTINGENCY
CONSTRUCTION PHASE
INCREMENTAL
CUMULATIVE * <AVERAGEt»
PRODUCTIVITY
INDEX
15 25 40 80 90 100
% COMPLETE OF CONSTRUCTION
LEGEND
INCREMENTAL PRODUCTIVITY "WEATHER CONSIDERATION"
DOES NOT APPLY TO THIS
• CUMULATIVE PRODUCTIVITY PERIOD.
ing the material handling phase and by 20% during the labor buildup phase. At
labor peak (40% of construction), the incremental productivity is shown as .09, which
is still good. For the last 10% of construction, productivity rapidly deteriorates.
The cumulative curve is calculated and is shown as tracking from poor to
good and ending at 1.0. Additional factors for weather would be superimposed
on the top profile. If the winter occurred at 40% of construction, the 0.9 could be
multiplied by 1.4, resulting in a projection of 1.3 for the period. If the other periods
were as shown on the chart, then the overall productivity of 1.0 would not be
achieved. The weather consideration does not apply during the last 20% of the job.
Evaluation of labor productivity can be made early in the project, and the
method/guidelines provided here can greatly assist in monitoring and forecasting
productivity levels. It should be emphasized that a schedule/activity jobhour
Estimating Keys—Establishing a Realistic Cost Baseline 71
- No Extra Budget
weighting system can also produce productivity analyses, but the results are
normally of a lower quality.
Experience and historical data have allowed reasons for poor productivity during
the last 20% of a project to be determined, including:
• Major work during this period is punchlist/checkout work that has a lower
budget value. Thus the earned value system measures low productivity.
• Remedial work and changes required by the operational and maintenance
staff generally take place during this period. This type of work does not
usually fall into the category of official change orders, since it would then
result in increased budget.
Figure 3.33 illustrates these major elements.
Figure 3.34 illustrates a typical relationship between direct work and indirects.
The data it reflects have been compiled from experience. This figure shows that
the indirect curves are essentially constant throughout the execution of a project.
Early buildup for field organization and installation of temporary facilities is
matched by a late buildup for final job cleanup and demobilization.
Direct work progress is a measure of physical quantities installed, and, as
shown, the direct work curve is identical to the historical/standard construction
curve previously illustrated. Indirect construction progress cannot be assessed by
measuring physical quantities and is usually measured in jobhours. This typical
curve shows the rate at which these jobhours would normally be expended.
Indirect and direct construction curves for any project can be compared with
the curves in Figure 3.34. During construction, actual performance should be
compared with these profiles as well, since doing so can provide an early warning
that the expenditure of jobhours is deviating from the norm.
The percentage breakdowns for craft indirects, field administration, and
direct supervision can be used to check estimates and performances of individual
categories. On very large projects, individual control curves can be developed for
specific categories.
72 Chapter 3
No Workers
ORIGINAL SCHEDULE
1
FIELD STAFF - 15 %
J
FIELD OFFICE EXPENSES
& -35%
TEMPORARY FACILITIES
(material only)
100%
LABOR COST
This approach is for the case of complete, single, or multiple process units and
does not apply to maintenance-replacement work. The author has been involved
Estimating Keys—Establishing a Realistic Cost Baseline 73
f
ENGINEERING
| l . Process.. 100.0
2. Civll/Str uctur a l / Arch'l. 90.0
80 80% 3. Vessels 95.0
4. Mechanica 1 Equipment..., 95.0
5. Ptpingdn c l . model) 75.0
70 / 6. Electrica 1 60.0
7. Instrumen tation 55.0
/ 8. General/M isc 70.0
60 *
7' INS T ENTJ ENGINEERING T 3TAL 30.0
}
ELE )AL
• • • mm
40 ST ART OF
•
MA TERI \ L
30
^PRC
PU RCH> tSINC
A
20
TANJ AGE
10
/ ™
y
0
10 20 30 40 50 60 70 80 90 100
PE CE^ T OF PRO ECT TIMl
DESI 3N A LLd\ fANC E •
100
80
60
*
%
40
20
10%
in three cases of used versus new equipment. In each case, new equipment was
chosen, as the cost differential was insignificant due to:
<Q
I
LMI - Local Material Index
1£
IMI - Imported Material Index LCF - Location Cost Factor P F - Productivity Factor cr
55"
g
CD
0)
76 Chapter 3
Local monetary rates, productivity differentials and benefits and burdens vary
enormously by individual country. Governmental employment regulations, rules
Estimating Keys—Establishing a Realistic Cost Baseline 77
for foreign workers, travel and support costs, religious and cultural differences
must be carefully evaluated. All can impact a location cost factor program. Figure
3.36 shows the detail and location cost factors for a range of countries.
I. INTRODUCTION
Figure 4.1 lists the major objectives of CPM scheduling. Many planning engineers
believe that the end product of their work is the schedule. This figure focuses
on the need for the schedule to be readily understood by the executing project
staff. All too often, a finished CPM schedule is complicated, badly laid out, and
incomprehensible to the user. The planner should be required to produce com-
municating schedules. Even though CPM schedules can be produced manually,
the great strength of this technique is its ease of use with computer programs.
A specific application of this principle is the use of a summary schedule to
represent the complete project schedule. Following development of CPM sched-
uling in 1958, the size of complete project schedules mushroomed to networks in
79
80 Chapter 4
• PLAN
• SCHEDULE
• CONTROL
• ORGANIZE
• IMPLEMENT
excess of 10,000 activities, as it was presumed that greater detail gave greater
quality of critical path analysis. It then took more than 10 years for the industry
to realize that such detail created a paper nightmare, high technique cost, plus
a resulting loss of quality and user confidence.
With skill and a scheduling database, a summary or milestone project master
schedule can first be developed and then followed by detailed networks for separate
project phases. With limited skill and no database, the project master schedule is
generally developed after the detailed networks, with a program summary technique.
Figure 4.2 shows the most widely used CPM formats.
A. Arrow Diagram
B. Precedence Diagram
C. Time-Scaled Diagram
The time-scaled diagram is a visual version of the arrow diagram and gives a clear
picture of the project schedule, as it relates to progress and completion of activities.
A vertical cursor line is drawn at each reporting period, and the activities status
of on, ahead, or behind is clearly visible. It is a favorite tool of management.
Establishing a Realistic Schedule Baseline 81
ARROW DIAGRAM
A c E G
3 I 4 I 2 I 1 I
B D F H
1
2 I 3 I 5 I I
TIME SCALED DIAGRAM
C
10 11 12 13 14 15
Project Control
Scope Initiated Infrastructure Control
Level I
Master Milestone Schedule
(One line per Project)
Level II
Program Schedule
r (Detail of Total Project
— or Phases of a Project)
Level HI
Detailed Project Schedule
(Detailed Activites by Discipline)
SCHEDULING PROGRAM
APPROVED
DESCRIPTION PROJECT RESPONS CONST DESIGN FUNDING TOP NOTE MAY JUNE JULY
PACKAGE ENGR MHRS DRAFTING FCST 20
ID MHRS COST <ANK
Project
Project
ni
T
n
X7
Project
Project
•_ _
Legend
The symbols shall be consistent among all groups (or level I & II Schedules.
\ y Rescheduled Milestone
\Z Scheduled Milestones
showing the overall program are much preferred to bar charts, since they show
the work interfaces and critical relationships. However, bar charts are still widely
used, as CPM type networks require very high skill levels that may not be
available to many companies.
Figure 4.4 illustrates a multiple projects bar chart schedule, with each bar
representing one project. Appropriate project information is listed, and symbols
along each bar show key milestones. This schedule, a summary of more detailed
projects schedules, is used as a senior management reporting tool. It can also be
84 Chapter 4
Activity
Description
SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
PERMITS
11/19
r~l AFE Approved
FUNDING
Pilot 10/1 11/25 BldPkg 1/15 ClarHier Vendor
Test ymr \ y Comp f~l EngrComplete
ENGR/DESIGN
11/23 Order 4/14 Last
• LL Equip Q Delivery
PROCUREMENT
11/25 1/18 Contract Award Const Complete 6/9
CONSTRUCTION D D
•
DOCUMENTATION Bid and Award 6/10
Constr Contract
FCO/STARTUP
OTHER Commissioning
Complete 7/7/88
NOTES: UNIT PERFORMANCE UPGRADE
LEVEL I t SCHEDULE
the sole schedule for multiple, small projects that are too small for individual
schedules.
Figure 4.5 shows a summary milestone bar chart for an individual project. Each
bar represents major work phases and key milestones are illustrated with sym-
bols. This would be used mostly on smaller projects where CPM formats are not
necessary or are not cost effective.
The following standards are mostly Level 3 schedules and provide guidance for
the overall project schedule for the execution phase (Phase 2), contract award to
mechanical completion.
Figure 4.6 is a CPM schedule for an individual project and represents critical
and subcritical activities. It has a unique feature in that it sequences parts of
work, which enables the overlaps to be eliminated. This results in an efficient,
totally linked network and becomes the working project schedule from which
more detailed networks (frag- or subnets) are then developed for each work phase.
^(DURATION N MONTHS) ADD FACTOR FOR :
4. THE LOGIC DIAGRAM SEQUENCES 7. THERE ARE TWO KEY ELEMENTS
J IS F OR A SMALL ACTMTE& HOWEVER, MANY OF OF THIS SCHEDULE*. A) STRAIGHT THRU PROJ.+ 10/15%
J PLANT. RESOURCE THESE ACTMTCS OVB&AP AND
UTUZATON IS OTA.Y L M T B ) CONTNUE FOR LONGER THAN SHOWN. a) TO IDENTIFY EARLY ENGINEERING B) OVERSEAS - EUROPE +10/20% (MECH.& Ptf)
BY SPACE AVA1ABLE T H B t
WOULD BE LOGIC AND DURATION
BUT DURATION t O C A T H ) 6 THE T I C
REQUBED BB=OR£ THE START OF THE
AND PROCUREMENT MILESTONES C)
~* OVERSEAS - UK f 30/40% (MECH.& PIP.) m
b) TO IDENTIFY CRITICAL EQUIPMENT
CHANGES FOR SPEOFIC PROJECTS FOLLOWNG ACTMTY. D) SUBCONTRACT OF
AND REVAMPS. OFFSfTES AND AND MATERIAL ACTIVITIES AND CONSTRUCTION
UTUTES ARE NEGLJQBLE. 5. THIS SCHEDULE ASSUMES THAT MUCH COMPARE WITH PROJECTED
+ 10/20% (MECH.& PIP)
cr
DELIVERY TIMES E) REMOTE JOB SITE +65/76% (MECH.& PfP)
2. CONSTRUCTION IS BASED ON OF THE CONCEPTUAL AND PROCESS
DESIGN HAS BEEN COMPLED DURNG 8. REMOTE JOBSITES MAY REQUWE A F) REMOTE JOB SITE + 3/6M (SHIPPING)
55'
DIRECT HFE WTTH ONLY SfTE
>ARAT10N BENG PHASE I OPERATION. ***«*» LONGER CONSTRUCTION PERIOD
6. CONSTRUCTION SUBCONTRACT 9. 15% CREEP FACTOR ADDED TO (Q
a AS GOVERNMENTAL APPROVALS
AND PERMITS VARY WDELY FOR
AND OVERSEAS PROJECTS WILL EQUIPMENT VENDOR DELIVERY a)
GENERALLY REQUIRE A LONGER TIMES
EACH COUNTRY, NO ATTEMPT HAS
BEEN MADE TO SCHBXJLE THESE ACTTVITEa CONSTRUCTION PERIOD
SL
25 MONTH? ft
LEGEND
I
MATL - MATERIAL
FDN - FOUNDATION
U.G. - UNDERGROUND
PROCUREMENT
lnstruffl6nft&lk)fVA.GL SUB - SUBCONTRACT
VD - VENDOR DRAWNGS CONSTRUCTION
WP - fKHJRE, NEGOTIATE, PURCHASE
CD
FDN&UG
in
b
CO
CONTRACT AWARD
PHASE II OR DETALED
ENGMEERMG RELEASE
TO CONTRACTOR Deiver Heaters (sections)
CIV1DWQ& s~\ A _ROAp6 SUB BASE * 3. AS GOVERNMENTAL APPROVALS AND PERMTT8 VARY WOELY FOR EACH
COUNTRY . NO ATTEMPT HAS BEEN MADE TO SCHEDULE THESE ACTIVATES
I ft. THB SCHEDULE ASSUME8 THAT MUCH OF THE CONCEPTUAL AND PROCESS
ProdttK>n-l>o« A DE8IQN HAS BEEN COMPIED DURMO A PHASE I OPERATION.
_pEL^ERYMCHANQE8(6O»2.
F^ANS SJOWERS_REACTOR2# Q
A _ OEUVERY COMPRESSORS —
ADO FACTOR FOR
M A r L - MATERIAL
FON - FOUNDATION
U.a - UNDEROROUN0
® CRfTCAL PATH
ENOMEERMQ
SUB - SUBCONTRACT
— PROCUREMENT
VD - VENDOR DRAWMOS
MP - MOUVC NEOOTMTE. PURCHASE
• M l CONSTRUCTION
The part activity sequencing and durations have been determined from
considerable experience/research and assume an economic (40 hours), fast-track
approach. This standard network is for the execution phase of process plants and
should be updated as economic conditions change. The notes require full consid-
eration, since corrections must be made for subcontract construction, overseas
work, and remote job sites. Another element of this standard is the sequencing
of equipment delivery and installation, based on historical data, to provide suf-
ficient nozzles for an efficient field piping program. If the plot area is known,
the construction duration can be checked with the labor density-trapezoidal tech-
nique (LD/TT). If there are differences, the LD/TT duration is used and the CPM
durations adjusted. Nevertheless, with skill and experience, there should only be
small differences when using both techniques.
Project schedules should be drawn up as time-scaled networks. A creep factor
is applied to equipment lead times: usually +5% for Japan, +15% for the United
States, and +20 to +30% for Europe. This factor recognizes that the original
vendor-quoted delivery is rarely achieved.
The purchasing/engineering cycle, usually four months for the United States
and Europe, is determined with reference to the proposed project purchasing plan
(cost or schedule driven). The four months represent an economic program of full,
competitive bidding. The network is based on a USA (execution phase) direct-hire
operation, and the add factors are to compensate for an overseas or subcontract
operation. Environmental aspects and governmental regulations are not standard
and must be treated on a case-by-case basis.
Figure 4.7 shows the same technique as Figure 4.6 but for a large, process plant
project. It is also based on actual project experience/research. The same consider-
ations as outlined in Figure 4.6 apply:
• adjust for actual project differences,
• check the standard notes for correct application,
• use the labor density-trapezoidal technique to confirm the overall construc-
tion duration,
• assess the material creep factors,
determine if execution is on a fast-track economic basis,
• find out if construction will be subcontracted,
• identify any environmental or regulatory restraints, and
determine if all resources are available.
Figure 4.8 shows the key relationships and durations for Phase 2 (execution)
engineering of a large, grassroots project. The database is the same as that for
the project master schedule for large projects (Fig. 4.7). The same logic applies
to small projects, but activity durations change significantly. The durations shown
indicate only the amount of work critical to the project schedule. Activities will
extend beyond the periods indicated. Engineering activity will continue through
completion of construction.
Eng-Slte Prep, Roods & Drainage
ENGINEERING SCHEDULE (TYPICAL) - LARGE PROJECTS U.S.A
CO
LU NOTES:
1. THIS SCHEDULE IS FOR A LARGE MULTI-UNIT. GRASS ROOTS
CO PROCESS PLANT. NO LIMIT ON RESOURCES. THERE WOULD BE
LOGIC AND DURATION CHANGES FOR SMALL PROJECTS AND
REVAMPS
£
Compl BUg Design
O final process flow diagrams
final heat/material balances
equipment data sheets
utMty systems
10 water/waste treatment
she selection
Pfteck I plant site layout
Design
O
Structural Steel P&L Dwga preliminary plot plans
project design summary
NNPPVacfc Steel/
3. ENVIRONMENTAL AND PERMIT REQUIREMENTS HAVE *EEN
INITIATED DURING PHASE 1
CO
LU LgpL/R Compl Piping Iso Dwgs 5. DURATIONS INCLUDE OWNER APPROVALS. WHERE
APPROPRIATE
CO
6. PIPING ENGINEERING PROGRAM IS BASED ON USING MODEL TO
DRAW ISOMETRICS. SOME COMPANIES USE MODEL AS
lflO% ENQ. KEY MILESTONE
CHECKING DEVICE ONLY
I PROVIDES ADEQUATE
^7 SUPPORT FOR MECH.
| CONSTRUCTION LEGEND
WP - INQUIRY, NEGOTIATE, PURCHASE
MTO - MATERIAL TAKE-OFF
VD - VENDOR DRAWINGS
SUB - SUBCONTRACT
o
Instr piping hook-up* & location plans UG - UNDERGROUND
FDN - FOUNDATION
PP - PUMP
CPR - COMPRESSOR ^ \
Vj) CRITICAL PATH
HTR - HEATER vj/
utH - UTILITY ENGINEERMG
instr - WSTRUMENT — — - PROCUREMENT
elec - ELECTRICAL
• H M H CONSTRUCTION
Dwgs - DRAWINGS
F'fans - FIN FANS
Bkjg - BULD1NG
-o
ELECTRICAL DWGS. power/ight/controls/groundlng :rana - TRANSFORMER
18 •w. - SWITCH
gen. - GENERAL
specs - SPECIFICATIONS
-o
COMPLETE UTILfTY DESIGN
MCC - MOTOR CONTROL CENTER
P4L - PLATFORMS AND LADDERS
>&lds - PIPING & INSTRUMENTATION DIAGRAMS
This standard (Fig. 4.9) should be used in conjunction with the overall breakdown
(Fig. 4.10) and the project master schedule (Fig. 4.7). These standards provide
for high-quality program development, with progress curves for engineering,
material commitments, and construction. As their underlying database has been
derived from actual experience, planned or actual project performance deviating
from this pattern is an alarm signal for trend analysis. If the deviation is
favorable, evaluation is just as important, since it can be a guide to improvement
for future projects.
A key element of this standard is the sequencing of equipment delivery and
installation to provide an adequate flow of nozzles for an efficient field piping
program. Experience has indicated equipment-piping dependencies to be:
Release of
Equipment piping work
Pipe rack 10%
First 50% of pumps, exchanges, drums 20%
Second 50% of pumps, exchanges, drums 20%
Reactors, fin fans, towers 20%
Field-erected vessels, heaters, compressors 25%
Final punch-out 5%
100%
This listing also shows the general sequence of delivery and installation. As can
be seen, the pipe rack, pumps, exchanges, and drums will enable 50% of the
IOTE8:
OVERALL CONSTRUCTION SCHEDULE . THIS DATA IS APPLICABLE
TO PROJECTS WHICH
CONSTRUCTION HAVE EXTENSIVE SITE
<0
PREPARATION
CONCEPTUAL PROCESS
DESIGN HAS BEEN
COMPLETED DURNG
PHASE 1
sKe preparatk concrete pi >gram . THIS SCHEDULE SHOULD
programmed t be phased IN 5TALL INSTRl MENTS BE USED WITH STANDARD
undergrounc OVERALL BREAKDOWN
access for tet norary
etoctrfcalfo AND STANDARD PMS
i. MANY ACTIVmES
OVERLAP AND CONTWUE
FOR LONGER THAN
SfTE PR EPARATION SHOWN. WDICATED IS
TIME REQUIRED BEFORE
START OF FOLLOWWG
ACTIVITY
i. CONSTRUCTION
SCHEDULES OFTEN HAVE
ONSr E FDNS a U.C CHOICES AND
ALTERNATIVES FOR
DURATION AND SEQUENCE.
THIS SCHEDULE DENTITES
an early pavh CIVI. AND EQUf>MENT
program can MILESTONES FOR AN
significantly '
increase pfpfr ECONOMIC PPMG
productivity PROGRAM
T RNFANS 6. ENGMEERMG ANO
ELS TOWER MATERIAL DELIVERY
TWAES CAN THEN BE
o—o
MORE EASILY DENTIFIED
AT THE EARLY PLANNWG
STAGE WHEN
CONSTRUCTION SCOPE
IS LIMITED
SLEEPE
PUMP O
STATIC fi)
FDNS
i
Figure 4.9 Overall construction schedule.
Establishing a Realistic Schedule Baseline 91
03
CO
1
s
I
3
I
i
O)
92 Chapter 4
piping to be completed and are therefore critical for a maximum piping effort,
since these items are part of the first deliveries.
This standard is mainly used to provide guidance in reviewing a construction
program. A detailed analysis should include a nozzle study, in which the number
of available nozzles per piece of equipment is plotted in a cumulative curve
against time. Budget hour units can then be applied to the nozzles to adequately
plot the available piping erection work. Piping is generally the major portion of
a construction program, and therefore, is part of the critical path.
V. OVERALL BREAKDOWN—ENGINEERING/PROCUREMENT/
CONSTRUCTION FOR A LARGE PROJECT
Figure 4.10 shows the historical database for the standard schedules shown in
Figures 4.6 and 4.7. The actual project data and curves were conditioned and
then summarized into three target curves: engineering, procurement, and con-
struction. The target curves were developed for an 80% probability. However,
on-the-job experience showed the curves to have a 95% probability. This enabled
project curves and performance of projects to be analyzed and forecasted with a
high degree of accuracy.
Two of these target curves, engineering and construction, are represented
in tabular form in Figures 4.11 and 4.12. Typical estimating phases are super-
imposed across the milestone activities as a guide for estimating accuracy in
relation to engineering definition and material commitments. This standard ma-
trix of bar chart and progress curves shows the relationship of major milestones
to related progress curves for engineering, material commitment, and construc-
tion on a percentage-of-time basis. The activity bars only show the amount of
work critical to the project schedule. Engineering and construction curves show
planned physical progress with construction on a direct-hire basis. The material
commitment curve is on a financial basis.
Once the schedule duration has been established from the standard project
master schedule (Fig. 4.7), the specific project schedule and progress curves can
be verified with this data. A detailed program that lies significantly outside the
curves should then be evaluated, in detail, to determine the causes of the vari-
ation. If actual performance falls significantly below the curves, it is probable
that the project schedule will not be achieved. These three curves have a finite
relationship to each other, where the need for an adequate backlog of engineering
drawings and material is vital to support an economic construction program. As
shown in Figure 4.10, the milestone of 80% engineering is keyed to 15% construc-
tion, which is the start of mechanical work in the field. Purchasing slippage will
impact on the engineering program due to lack of vendor data and may also
delay field work. Historical midpoints of material (23%) and construction (65%)
quickly determine the escalation points for estimating.
Examples:
1. What would be the overall duration for piping engineering? Refer to horizon-
tal line 16—marked pipe spools (drawings)—90%. Pipe layouts (thin dotted
line) start at 9% project time and 90% pipe isometrics (heavy dotted line)
finish at 61%. Assume 100% isometrics is at 70% project time; therefore,
Establishing a Realistic Schedule Baseline 93
I
CD
u
1
•8
|
O)
il
94 Chapter 4
- (V -
Q
t o
0
i
i I *
s « so
is 0
•t ? . '
t s *• oo st If a
r
o
o
*
0
a < or. ST. s £ . ^? P..?
i
(D r» • * •
< !T i h S
VA
fi £ f »•
If if —\ ^ If in
\ 6
v
s 5 C r-
*
*
i *
?. jcr f.s cr « I: 3 o
0 < o c c
UJ < J j
SA r* - c 0 0 o o 0 6 0* ^ 0 0 v£
i ( If
tJ o V c £ K)
c P. ai J
?. 5
?
p" r* tP vr ? O* o* <
T
-
o cJ f<* 0 o 5 0
3 J
0 i 0
o 0
r-
0
cr S .<cr
vr sf
o c! C 0
te
N c 0 0 <
<
6 C
T»
c <
r
S s? ? ^ ?? 1
in p* f
*> e c
o
<r o ft * V o
© c J 6 o 0 O 0 c 0 ' 0 0 0 o' 0*
p* 1/ r
UJ
KA po
2?
« 51 .1 cr
*l ( 3 *A ^ ri - • —
o 0 0 0 i 0 ( 0 0 0 o o 0
v!) o 3
4 sI li J
©
«o to 2
& r or .5
&
0 CO »» \
cr * —
Q. in i o
«*• c
f
V
5 I a «P
l? f 8 — -
J
T
3.
?
©. c
1s f
o
u 3f « ?f o
fi
7
T
2- I © o
!» «?!T. "• i 6 o 5 0 O'O K •ffl
Wn
& CO r
r Q
s
o
$ .£, s a.
0
IS
?
rf
5? r <r Pi 0)
"b"
lU
y
i * J a £ ?:&1 * \ si si .!K_ t*Aa.1 % -
0
~7
—3 I n (0
O.
"A Csl
J c.
* of O" ??
%'* i r r
?$ <
r..«.
A, H
it 1
r-
>
>kbb^tt
UJ 0
i 5 sr IO 1:1^ ' t. 1: r
j ...
1
„..
| Y-
•
a)
1 £ 5' 1 f
s J- >. o5! <
$ D' ? v
o* * r *. - -
2 ft 5*w V)
s-
k
2 0' o t 0 ?0 o c ' o* j co
o s s J 25' o J i A i j
1 >
&
^' So f r r r N
<
* * •
<?<rQ <r o.
X % sr j • <r
o ^ o 6 0
* - - 00 5
4
> 0' C
i j*
1 ?1 I
O.
S ^? 3 J
"o"
tr
z
\A
1- or ? -i
i <P
- «4 6 o > 6
rj
\|
I 1t a
f V Q r J
0
vS
oo
^ ^ ' Cf f. -
Is »0
*
' o > o o 0 o
1
$
>, o I
m Jr
c
2
4o o
o
CO O)
- J
•>
-
il
-
CONTRACTOR.CONSTRUCT \OUPR.O&R.LSS *UCJtI 1<***2.
m
0)
2
(Q
I
55"
CD
0)
o.
9O
en
IS s: s
6 0 o o o 6 9 <s r* cr o <3
co rA
T j
0 O
r-
$ 3r 8 u 3" 5; 8
06
r
CO
6 0 Q" es rO cr cr c L" 0
2 !? oo J y i
(0 0 c*. Ob T r*
0 0
" * •
O 6 6 fsj rst ti J
t s/» •4- 0
T »0
i i 1 |- I | jF 1 I
0, «0
6 * o' s* 5 S S?a j& S 5 (M
so :•? ? i 5 5 |
o
i 6 < too sfi CO.
S <? 6
3» s N
O" •ft
% 6 o 0 tsl 3 %• o; tr'
>0
i to
J* 9
o T
if] o o 0' c o !i fs> •0 0
4-
Sr S3 5 s Is s
e
sj
6 o •<*! r
* ft *
0
0 toi r
?
1- 5 jr 8 J 1t J to
I
6 *r
n V \n
vo o o 0 0 •J 0 0
6 0
*>> rr\
r— 65
c*
rsl
0.
o' sF 3 CP ? «
S
•0 2 M A «o cr
5:
ob
7 o 0' d "• 0
vP
si.
Cst
0 0 ^0
;} *<• t- < V1.
% j 3
40
3 r g
Cii
Of
mm 6 o rO $ r 00 So
tO
6 6
«D N ^. %0 J 5- $ 5? •A. <r CO
6 0 0 g
4
0 0 0
o
a ? 3o. % J t t
o »r\ r. •0 rO_
5r c*
7
Si 6 o'
00
m
er >o r-. r 5
A-
VsO
s
si si o' 0 0'
% o' 0 0
s-
cr o°.
1 £ IT 8
s
•0
0
S •st 00
V
6 6 Cs> r ?•
w*
?O -
p CsJ «J r-
0 0 o
00 00
O 0
o 1
Q
J If s 5 8"# ?J
4
Ii
§A CO,
e'
3 6 J) v» • • ••
0 o O or 0. Q M
Io 6 r-
CsJ
ti
0/ q' 0 •0 CJ p 0
I'
Csi •a
r- 0'
<s)
r
r;
Vl' r' 3 $ 3" i- &
r-
r
J
a Q si'
s *
0
it
c*
A.«l
\ r- 5
0 6 6 C*"
5- 5- s 0
i ? ?'
o. op si)
o' ©' o
»•». •0
J
VI N
d \ 0
«o
o i tO'
fsj.
s I is r Si^'
OP
? r 0 §'
>
>
0 s:- s
(0 q •o. o
7.8
I
6 0 0 < J vJ' o' >'
o IT no' ? &' ^J i' 9J
es/
6 0 ??• In ^ s» 00 r
«o
£ i- 5 >
tst r*. 00 0 0 00
o
rO
o fi 00
fi wi' 6 CO
H"
2 3Ms
<\ 6
tC v>
0*. 0
s 5' ri S' f 3Pd; 2"
jsj
9- 3' ?'o*p r 3 O
<- !» 5 (b
r-. •3 •J 0
r*. <r
3
0 CO
6 o -B'
J ? 3f I o i
c. *>.
N 6 6 sj D s»"
§: K), CM
5- £ < 5-
CM -V «o o
0 o «»»• to' 0° CO
1 5' ? 2 —• i
o **;
s)
$ S?'
r
i
o.
c4 0 6 ^ NJ' Jli' "sf •s» r «6
CO
c o o sfi O)
9,
tsl ON CO
- IO CD s) s) si 0 •n •0
il
si
(SJ
Establishing a Realistic Schedule Baseline 97
overall piping design is 70% less 9%, which equals 61% project duration.
For a large U.S. project (Fig. 4.7 shows 33 months), piping design will,
therefore, be 20.
2. What would be the probable start of detailed engineering? The key elements
for the start of detailed design are approval of the process design (P&IDs)
and equipment layout (plot plans). This approval would normally occur at
about 70% of P&IDs and plot plans. Refer to lines 2 and 4 (P&IDs and plot
plans) and approval at 9% of project time. At the same time, foundation
layouts (line 14) and piping layouts (line 16) commence. This is the start of
detailed design.
The main drafting effort will begin with foundation drawings, piping isometrics,
and general arrangements.
Figures 4.11 and 4.12 illustrate the previously shown target curves of Figure
4.10 in tabular format, for engineering/project and construction durations. Note
that the engineering charts show the overall project schedule, whereas the con-
struction charts only cover the construction phase. As previously stated, these
curves have a very high degree of probability and are highly recommended as a
benchmark to monitor a project's engineering and construction progress. Each
table is laid out in the same format—with incremental and cumulative progress
percents against monthly periods. The engineering progress curve table starts at
month 8 and the construction progress curve table starts at month 1. The boxed
incremental numbers for each month show the peak period. The average percent
for this period is given at the bottom of each table.
Substantial use of these curves has shown that slippage from these stand-
ards of more than 4 weeks will probably require acceleration action/cost to
recover. However, if the slippage occurs above the 50% point, then recovery is
virtually impossible for engineering, as there is so little design work remaining;
for construction, recovery is very difficult and high cost. If recovery is not con-
sidered a viable option, then a projection of future completion, from the present
position, referring to the standard curve can predict a schedule extension with
a high degree of probability, sometimes years in advance of the original comple-
tion.
The standard network and progress chart contained in Figure 4.13 (overall break-
down, small projects) is similar to Figure 4.10 and depicts the historical relation-
ships of major activities. The data is based on 50 projects completed between
1955 and 1970, when this type of project program was popular. Today, this
program is rarely used, and it has been replaced by the phased approach; the
costs of these projects ranged from $0.5 million to $10 million. This project mode
results in later midpoints of material (29% project duration) and labor (70%).
The start of construction is also later, commencing at 32% of project duration.
When schedule durations have been established, progress curves can be
drawn using the data from this figure. Schedules that differ significantly from
the standard bar chart and progress curves should be evaluated in detail to verify
the variance. When actual progress falls behind the leading curve, it is probable
CO
OVERALL BREAKDOWN OF ENGINEERMG. PROCUREMENT & CONSTRUCTION 00
ACTIVITY
DESCRIPTION
ENGINEERING
PROCESS - P&I DIAGRAMS
DATA SHEETS - REQUISITIONS
PLOT PLANS
MODELS
FOUNDATIONS(ISSUE)
FND. LOCATION PLANS(ISSUED)
PIPE RACKS/SLEEPERS(ISSUED)
CONSTRUCTION
UNDERGROUND
PIPE RACKS/SLEEPERS
PIPE ERECTION
PIPE FABRICATION
INSTRUMENTATION
ELECTRICAL
EQUIP. SETTING
NOTES:
THIS DATA IS APPLICABLE TO
PROJECTS WHERE THE PROCESS
SELECTION HAS BEEN FINALIZED
SO THAT THE CONTRACTOR SCOPE
IS NOT DIVIDED INTO A PHASE I
- PHASE II OPERATION.
DETAILED PROCESS DESIGN WILL O
COMMENCE AT CONTRACT AWARD.
1
IN ADDITION, THERE IS NO
EXTENSIVE SITE PREPARATIONS
that succeeding curves will not be achieved, which could lead to a delay in
mechanical completion.
Figure 4.13 shows a very aggressive construction program. The monthly
peak rates of progress would generally be too high for large projects unless the
"size affect": is already reflected in the project duration.
Figure 4.14 provides major milestones, logic, and durations for the engineering/
procurement cycle for equipment and bulks. Durations are based on project data/
research. Large, complex projects with worldwide purchasing, multiple engineer-
ing offices, and joint venture partners having consultation and approval require-
ments can increase the 12-18-week procurement cycle. Generally, projects with
a minimum of worldwide purchasing have a 12-14-week purchasing cycle.
To apply this standard, assess project size, complexity, joint venture require-
ments, and proposed purchasing strategy and determine the duration for the
specific project. Check against current project experience that the evaluation is
realistic.
Only the total duration of the engineering/procurement cycle is used for over-
all schedules (see the standard project master schedule, Fig. 4.7) and is normally
the activity designated inquire, negotiate, purchase (INP). Evaluation of the indiv-
idual activities will be required when analyzing and monitoring detailed schedules.
Figure 4.15 shows the general functions, logical relationships, and average du-
rations of a Phase 1 (feasibility) operation. This Phase 1 schedule is used to
provide guidance regarding typical functions carried out in a Phase 1 operation.
Specific activities will depend on the individual project.
Figure 4.16 shows the major phases, logical relationships, and average durations
for a major platform project:
• feasibility study:
- field development,
technology,
- execution plan, and
- economics;
• process/conceptual design:
- optimization,
- case selection (one case), and
bid package;
• funding and contractor selection; and
FRONT END ENGINEERING & PROCUREMENT s
CRITICAL EQUIPMENT ILONQ DELIVERY fTEMSI
4-8W
; OFCRfTICAL
T2-18W
IAS PER ABOVE SCHEDULEI
o
FIRST DATA SHEETS A REQUISITIONS
8-12W
I
SURVEY REPORT FINALIZE IS AWARDED TO
AFFILIATE EQUIPMENT LIST . \ THE PHASE II
'™2lv"T REVIEW 6 APPROVAL CONTRACTOR
CO.ST E.5TIMATE(S) WITHOUT
t
COMPETITIVE O
BIDDING
\ SELECT
I
PREPARE
PHASE I AFE ENVIRONMENTAL FINALIZE
r
3W 1 CONTRACTOR ENVIRONMENTAL IMPACT STUDIES SCHEDULE
SCHEDULE I m
ew 20W \
6W
2/ewmi
3W 2/4W
PERIODIC UPGRADING OF COST ESTIMATE
\ FINALIZE AFE
\ COST ESTIMATE
MANAGEMENT
REVIEW,
5"
• p n * nnos**** T
Att* ArrRK
CD
PREPARE PHASE I 6W
BID PACKAGE BIDS 0)
1
1
#••••••# M H M i i
t 3/4W r 3/4W SOIL/MARINE FINALIZE
PREPARE
PHASE II
I
s
PREPARE CONTRACTOR
SITE SELECTION REPORT PLOT PLANS AFE
SCREENING PACKAGE BID EV \LUA1ION < 7W 5W BW 4W 3W
• •
1
1
ii 2/3w[ OPTIMIZATION
6W
DESIGN
PROCESS
SPECIFICATIONS
12W
FINALIZE
8W
P&I's
CONTRACTOR
RESPONSE \
i IMMU
SUBJECTIVE EVALUATION
2W AND/OR NEGOTIATE FIELD TEMPORARY
START OF
1_J UTILITY FLOW DIAGRAMS FACILITIES, LAYOUTS
CONTRACTOR
SCREEN W
^W"J CONTRACTOR SET-UP 12W PHASE II
CONTRACTORS
i"t CONTRACTOR
ENGINEERING (BEACH HEAD STUDY)
1 1 1 STUDIES PROCESS DESIGN (PIONEER CAMP)
FAC,/PROC. ENG. INPUT < , (SHIPPING)
12W
r
COST £ SCHEDULE
1INPUT ^* AWARD
PHASE I
SPECIFICATIONS, DATA SHEETS
PROCESS/CONCEPTUAL
FEASIBILITY STUDY DESIGN
PROJECT EXECUTION PHASE
12/18 month 6/12 month Generally 36/48 months to tow out for major platform
Economics
DETAILED ENGINEERING(80%)
O
b MATERIAL DELIVERY
immiiiuiiiiiiiiiffiii
COMMISSION
MSF, TOPSIDES -
Steel JacketQiMHiMHO
FABRICATION/INSTALLATION fl
OFFSHORE
T
i
TOW I MINIMUM
MAT
Vv9_UT
)%ma\Cjmmm
| Weather*
Window i
Fast Track Approach
Figure 4.17 depicts a project master schedule for steel jacket platforms and is
based on data and experience from jacket installations in the North Sea. It shows
a straight-through project, engineered in the United Kingdom. Two major critical
paths should be evaluated:
• topsides engineering and module fabrication, and
• steel jacket design and construction.
The following are key considerations:
Basic engineering, (layouts, P&IDs, data sheets, specs, plot plans)
- new technology,
project strategy, execution plan, and size of engineering office(s),
- engineering capability and capacity (resources),
- project organization and engineering consultants,
engineering completed before contract award;
Equipment deliveries. Add a 20% creep factor to the latest equipment delivery
lead time;
Detailed engineering. Engineering needed for module quotations depends heavily
on protect strategy for module contracting. Engineering completions range
from 40% (a practical minimum for reimbursable bids) to 80% (essential for
good lump-sum bids). Unit-price bidding requires an engineering definition of
40-60%. Projects may have a mix of contracts (e.g., lump-sum for steel, unit
price for mechanical, and reimbursable for electrical and instrumentation).
For developing a relationship between project time and engineering
completion, the following method is suggested:
- Use the large project master schedule project duration from Figure 4.7
(33 months).
- Take engineering percentages from straight-through project curves
(Fig. 4.9). This reflects the situation that engineering takes longer for
North Sea projects than for onshore projects.
- Calculate detailed engineering durations before inquiry and mechanical
outfitting for module bids as shown below.
Unit-price and reimbursable bidding. Using judgment and contracting strategy,
assume 50% engineering required before inquiry.
50% engineering occurs at 44% of project time.
0% start of detailed engineering is at 15% of project time.
- Thus, 50% of detailed engineering takes 29% of project time.
- The project duration is 33 months.
- 29% x 33 months = 9.9 months (10 months) for engineering before INP.
80% engineering occurs at 59% of project time.
Project Master Schedule - Steel Jackets - Standard
23456789 10 111 13 14 15 16 17 18 19 20 21 22 23 2 25 26 27 28 29 30 31 32 33 34 35 36 37 3U 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 61
JACKET DC TAIL
OESIG
V l N P JACKET.
I FABN JLYARO
CONTH Y PREP- PREF
.1
AWARD
ENG&
PROC "REFER TO CURVE(
INP MSF JACKET WEIGHT VS FADm
FAB'N (JACKET WT - 19.000 TO
CONTR AWARD
MSF FAB'N
CONTRACT
MODULE SUPPORT
FHAME LOAD OUT
• FABRICATE MODUL SUPPORT FRAME & SEA FASTEN
APPROVE
BID DELIVER,
TAB
AWARD FT & WELD COMPLETE
MODULE FA COMM
DEVELOP MODULE CONSTRAC
IFT& SECURE
MODULES
Figure 4.18 shows a schedule for North Sea offshore platforms based on a concrete
support structure. The latter part of the schedule shows the weather window
OFFSHORE PLATFORM - PROJECT MASTER SCHEDULE - NORTH SEA
o>
A M I / A S0 N D
mm rMATIN^ WEATHER WINDOWS
110 TOW-OUT 1 Q ] ©
DESIGN DRY OOCK CONSTR. (SEE NOTE 3 )
PKCE. BIDS LN.R^ / ^ SKIRTS. BASE. LOWER iffORM UPPER DOMES & COMPL. CONCR. & | TOW TO MATt
IT IS C POSTTENSION [TOWOI/T _
A "*fOW TO MATE
ASSUMED
THAT INST. DEC! TOW OW CONDEEP TO MATING SITE)
CONCRETE CONCEPTUAL I OUTFIT SHAF
STRUCTURE DESIGN HAS
-BEEN THE DECK & OUTFITTING WORK —
COMPLETED COULD BE ADVANCED BY 4 / 5 MO.
DURING WITH A SHIFT-WORK PROGRAM
PHASE I
DECK THIS
PROJECT
EXECUTION
ASSUMES THAT -
ALL OF THE WORK
DECK WILL BE HANDLEC DECK
OUTFITTING UfJ RMNC. MODS.
OFFSHR.HK.UPl OUTFIT.®
OUTFIT 1st MODULES
MODULES
FA8.& DELY. SPM
S.P.M.
FLARE FAB.t DEIY. FLARE
(BOOM TYPE)
SUB-SEA PIPELINE I£B._£J[JJL£i?J
NOTES:
1. DURATIONS SHOWN AS? DEPEND ON 5.SCHEDULE BASED ON CONDEEP SUPPORT
SCOPE, MANNING, SHIFT PROGRAM AND STRUCTURE. U T I L I T I E S IN SHAFT.
MARKET CONDITIONS. 6. NUMBERS IN Q NEXT TO CONDEEP
2. DURATIONS ARE IN MONTHS AND ARE ACTIVITY REFER TO STEPS I N MARINE
INSHORE & OFFSHORE FOR GUIDANCE ONLY. CONSTRUCTION PROGRAM
3. WEATHER WINDOWS: 7.FLARE MAY BE INSTALLED AFTER
FLOAT
TOW TO MATE MAR - SEPT TOW-OUT IF WEIGHT LIMITATIONS OR
SCHEDULE DELAYS OCCUR.
o
E.N.A. EVALUATE, NEGOTIATE AND AWARD MATING FEB - OCT
0)
1
TOW-OUT M A Y - SEPT
• SUBCONTRACT AWARD
4 . A C T I V I S T S MARKED # ARE OMITTED
8 . REFFR TO PROCESS PLANT DATA
FOR ENGINEERING I PROCUREMENT.
I.N.P. INQUIRY, NEGOTIATE & PURCHASE FOR PLATFORMS FULLY OUTFITTED PRIOR
TO TOW-OUT.
sensitivity of some activities: tow to mate, mate, tow-out, install the single point
mooring, and install the subsea pipeline. Durations marked "?" depend on the
scope, labor allocation, shift work program, contracting strategy, work location,
and delivery of equipment.
One major relationship relates as well to offshore platforms as it does to
onshore process plants, that is, the relationship between engineering completion
and the start of mechanical outfitting. For a process plant, historical data indi-
cates that 75-80% completion of engineering is required before the start of field
mechanical work begins in order to adequately support a construction program
on a fast-track approach. Anything less than this can result in construction delays
through lack of drawings and material. This relationship can also be applied to
a platform. The equivalent basis would be 75-80% engineering completion for
the start of the mechanical outfitting of the deck and modules.
A unique element in platform scheduling is the degree of onshore and
offshore installation. Some tasks, such as towing and mating, can take place only
in good weather (the weather window). Each activity has its own historical
weather window. This is dependent on degree of difficulty, location (onshore or
offshore), and financial risk (i.e., mating, February through October; tow-out,
May through September; etc.).
After definition of the labor hours, labor availability, shift work program, con-
tracting strategy, and equipment delivery, a project master schedule can be
developed by evaluating values for the unknown durations. Construction dura-
tions can be calculated by using the labor density/trapezoidal calculation method.
Several factors can necessitate an additional allowance to calculated durations,
including new technology, prototype engineering, multiple engineering offices and
construction sites, heavy government involvement, and restrictive labor practices. If
these factors are significant, an experience factor of 25% should be added to all
calculated durations. This can be reduced to 15% for offshore construction activities.
The following comments relate to durations for the major work elements:
Design—concrete structure. The duration depends on the amount of design work
done before contract award. Information from the designer can help deter-
mine the schedule.
Construction—concrete structure, general. Use information from the concrete con-
tractor when available. This is specialized construction, and historically
schedules have been maintained. The durations indicated are for a very
large concrete structure (100,000-150,000 m3).
Prefabricated cell decks. Consider the number and size of the decks, the degree
of prefabrication, and the total labor hours.
Installing decks, outfit cells, and shafts. Assume a density level and calculate
shaft area and peak labor. The degree of complexity and effectiveness of
labor classify North Sea platforms in the 200-250 sq ft per worker density
category. However, due to schedule criticality, a density of 150-200 sq ft per
worker is used in practice. The resulting reduction in productivity is traded
off against an improved schedule.
Also consider regulatory guidelines, which may restrict the number of
108 Chapter 4
workers within the shafts. Assume a shiftwork program and calculate the
work month (effective labor hours per month). Determine the duration using
the trapezoidal method. Shaft outfitting may not be completed before tow
to mate in order to meet weather window limitations. In such a case, break
the outfitting activity for tow to mate, and allow demobilization and remobil-
ization time in the mating duration.
Equipment deliveries. Add a creep factor to equipment delivery lead times.
Basic engineering (layouts, P&IDs, data sheets, and specifications). Consider the
degree of experience with previous platforms, the number and location of
engineering offices, project organizations, and the magnitude of Phase 1
engineering. The duration can vary from 4 months for proven technology to
8 months for new design concepts.
Detailed engineering, 80%. Use the onshore project master schedule (large proj-
ect) and adjust the project duration for the overseas-UK site by reference
to add factors at the bottom. This will require an add factor of 30-40% for
mechanical-piping work. For example, for a standard project duration of 33
months and onsite piping of 16 months, the adjusted durations are:
- 33 months + 40% of 16 months = 40 months
From "Overall Breakdown," Figure 4.4:
- 80% engineering occurs at 43% of project time;
- 0% (start) of detailed engineering occurs at 9% of project time;
- thus, 80% of engineering takes 34% of 40 months = 14 months.
If required, add 25% experience factor to obtain the engineering duration:
- 14 months x 1.325 = 17.5 months (use 18 months)
Deck fabrication and erection. Use the trapezoidal technique with a density level
of 180 sq ft per worker; consider shift work. Reduce the total hours for
prefabricated work and support work completed away from the deck; eval-
uate the appropriate labor buildup and rundown; make allowance for lost
time, and adjust peak labor if labor is not available. Add a 25% experience
factor if appropriate. Concurrent equipment outfitting will impact on deck
fabrication if both activities share the same working area. Outfitting labor
will build up as deck labor runs down.
Deck outfitting. Use the same method as for deck fabrication. Where outfitting
cannot be completed before a mating date, cut off labor with a sharp rundown
(1-2 months) and carry over the remaining labor hours to onshore-offshore.
Module outfitting. There are two methods. The first method is to evaluate the
module area by adding a 10-foot perimeter to the plan dimensions. Appli-
cation of the density level (180 sq ft per worker) will determine the peak
labor. Use the trapezoidal technique to determine the duration. The second
method is to consider the outfitting labor hours of total modules, divide the
work among several or many subcontractors, and, by judgment, determine
the peak labor for a subcontractor. Then use the trapezoidal technique to
determine the duration. The total hours should be reduced for prefabrication
and support work completed away from the module saturation area. If
appropriate, add a 25% experience factor to give the activity duration.
Consider the fabrication and delivery of the first modules required for the
Establishing a Realistic Schedule Baseline 109
start of the module hookup activity. For guidance, module fabrication dura-
tions are 14-16 months for small modules, and 16-18 months for large
and/or complex modules, assuming a 40-hour workweek. Several modules
in the same shop may require additional time (15-20%).
Module hookup. This starts after the first module lift. It may occur at the deck
site, onshore after mating, and/or offshore. Use the trapezoidal technique to
calculate the durations. The saturation labor is obtained by assuming that
40% of the module area is available (this varies with the degree of module
completion). Apply 180 sq ft per worker. Buildup is short, limited only by
the ability to staff and plan the work. If work is carried onshore, break the
trapezoid abruptly during mating when work ceases—no rundown and build-
up for simplicity. Labor hours carried onshore should be adjusted for lower
productivity. This also applies to deck outfitting labor hours, which should
be combined with hookup labor hours for one calculation. By judgment,
assess the labor level. Labor hours carried offshore require further produc-
tivity adjustment. Further productivity reduction may occur due to drilling
interference (concurrent drilling and construction). Labor buildup and peak
are limited by available accommodations (temporary living quarters, hotels,
permanent quarters). The use of high-cost hotels can greatly increase the
availability of craft labor and reduce the schedule. The available beds must
be discounted for the number of nonconstruction personnel (operational
support, drilling, management, catering). Of the total platform beds, about
50% are available for construction craft labor. The workweek is seven 12-
hour days less 5% absenteeism, etc. Module hookup (and outfitting) should
be evaluated separately from commissioning, since peak labor cannot be
used on commissioning work. Use the trapezoidal technique to determine
the duration. If appropriate, add a 25% experience factor to onshore dura-
tions and 15% to onshore and offshore durations.
Mating and tow-out. Towing the gravity structure to the mating site, mating,
and tow-out are all subject to weather limitations. Weather windows for
these activities are:
Tow to mating site March through September
Mating February through October
Tow-out May through September (the latest start of tow-
out is the first week in August)
To minimize risk, it is desirable not to have all mating and tow-out operations
in the same year. It is preferable to schedule tow to mate in the year before
mating and tow-out. Mating durations of 1 month and tow-out of 2 months
include weather contingency.
Minimum drilling. This is the time required to complete the drilling required for
start-up. Eleven months are required to drill 3 wells, including the conductor
driving. Further time will be required to drill all wells for full production.
schedule slippage became routine. The major reason for this failure was lack of
understanding on fast-track relationships between and within engineering, pro-
curement, and construction. When properly applied, the fast-track project sched-
ule produces the shortest economic program.
Figure 4.19 shows the progress curves for engineering, procurement, and con-
struction in the fast-track relationship for the execution phase of a project. This
is the same data, in summary form, that was established by Figure 4.10. The
economic basis is:
all purchasing and contracting is on a competitive basis;
• construction is executed on a regular 40-hour workweek;
• apart from spot overtime, there are no acceleration procedures; and
• cost is the number 1 project objective.
This project program is the most widely used of all programs.
Figure 4.20 illustrates this technique for the construction program. The TT is
another form of a progress curve, shown as a form of triangle. As illustrated,
there is a build up of labor to a peak of labor, followed by a run down of labor
to work completion (mechanical completion). The area of the trapezoid is the
scope of work in labor hours.
Figure 4.21 shows the scheduling relationship between engineering and construc-
tion for a project on a fast-track program. The schedule relationship/duration
only covers the execution phase, which is sometimes referred to as Phase 2. Phase
1 covers the conceptual design studies and case selection.
As previously stated, the schedules are illustrated as trapezoids. This data
base is extremely important, since it shows that all complex work, at a total
level, is executed within a buildup, a peak period, and a rundown. The specific
relationships (ratios or parts) of these 3 periods has been developed from histor-
ical data for both engineering and construction programs. This base then forms
one of the best methods for determining the overall construction duration, as
shown in the following paragraphs. Work classified as simple (i.e., the task is
performed by a single crew or squad) has no buildup or rundown; Figure 4.22
illustrates/compares the simple and complex arrangements.
Figure 4.22 depicts engineering and shows the calculation of peak personnel
rather than calculation of the duration. The same process can be followed for
construction if the duration is known. The buildup and peak are shown as 22%
and 38%, and in the database of Figure 4.19 these percentages have been rounded
to 20% and 40%.
FAST TRACK - ECONOMIC (Execution Phase) Economic - all competitive bidding m
IOTES : CD
1. ACTUAL PROGRESS PLOTTED AGAINST COMPANY HISTORICAL EXPERIENCE . - 40 hour workweek
2. EARLY CONSTRUCTION START REFLECTS A PROJECT WITH EXTENSIVE SITE PREPARATION
^ 3 . CONCEPTUAL DESIGN HAS BEEN COMPLETED DURlNfi A PHASE 1 OPERATION . - non acceleration (/>'
IT
100-
ESTIMATE H (Q
"QUALITY"" 0)
30
40/25% 5 I
MATERIAL &
: | SUBCONTRACT
C_O_MITMENIS
a
o
0)
(D
a
J5"
I IW ,A GO
fl)
0)
<D
• -mm / u ^ (D
/ boNSTRUCTIONJ
mr i i
IF i i
ADVANCE COMITMENTS T
OF CRITICAL MATERIAL U T
CAN BE MADE IN PHASE
30 40 50 60
PROJECT DURATION -%
CONCEPTUAL PHASE EXECUTION PHASE
PHASE 1 PHASE 11
CONSTRUCTION DURATION
• Process
Release. Ratio/Parts of Overall Duration
• Case
Selection 1(20%) 1(20%) 3(60%)
Engineering Peak
(& Procurement) Men
Peak
Men
This Data is historically baaed on many projects, 187O-94 and is 'Typical" for process projects. Each
protect application should be individually assessed. These diagrams are known as Trapezoids and this
"Relationship" is also called, the Trapezoidal Tachniquerrn.Sce "Progress Charts" for TT(%) numbers.
Figure 4.22 shows the calculation formula for a simple engineering task of
400 hours and the error of then applying that formula to a complex task of 20,000
hours. As shown, the calculation error of 25 engineers instead of 41 engineers is
significant and results in schedule slippage.
For complex work, an alternative method to the trapezoidal calculation is
to use the simple formula and multiply the result by a peak factor (usually
1.6-1.7). This is a common practice of senior professionals and usually produces
adequate results. However, it will not show the required buildup of personnel
over the project schedule.
Figure 4.23 shows the trapezoidal technique for the construction phase. The
calculation procedure shows two formulas:
• Formula 1 is used to determine the peak duration, X, on the basis that the
following information is known or assumed:
- scope in labor hours,
- effective monthly hours per person,
114 Chapter 4
SIMPLE
1. A small engineering task - 400 hours - is required
to be completed in 2 weeks. How many workers
are required?
= 41 workers
( or peak is average x 1.6 )
CONSTRUCTION DURATION
(Trapezoidal Technique)
PEAK
WORKERS AREA = SCOPE (Jobhours)
(X)
scope in jobhours
(1)
effective monthly jobhours
buildLJ
P • peak workers \X. peak workers} peak workers
F. Trapezoidal Technique—Statistical/Standard
Figure 4.24 shows the same earlier data transposed so that the X is now the
overall construction duration, instead of the peak period. The figure shows the
standard trapezoid for large projects (those above 5000 sq ft), and the standard
for small projects (those below 3,000 sq ft). As illustrated, on small projects the
buildup and rundown shortens, and the peak period lengthens. This is due to
the small number of workers required.
Assessing the density level is extremely important. Figure 4.25 contains a work-
ing example of the trapezoidal density method. The first step in the calculation
process is to properly assess the labor hour scope. As shown, allowances were
made for indirect labor working in the same area as direct labor and for the
estimating allowance. An allowance for better subcontract productivity and a 12%
absenteeism allowance were also made.
The buildup duration was determined from a standard schedule that showed
the peak labor period would be reached at 30% of the piping duration. This activ-
ity was preceded by foundation work (3 months) and equipment installation
work (2 months). The total piping duration was 15 months. In the case of sub-
contract labor, the labor hours are reduced to reflect a better productivity rate
than with the direct hire workers (possibly as much as a 10% improvement).
The impact of schedule delays can be determined with the use of the TT. For
many years, the owners and contractors adopted different positions in the appli-
cation of the TT to schedule-related claims. Owners, some with a vested interest,
stated that the delay occurred at the rundown period, where the cost impact was
the lowest. Contractors opposed this position and stated that most construction
schedule delays were caused by multiple changes/additions, occurring throughout
the construction period. This was referred to as the ripple effect of change, and
116 Chapter 4
STATISTICAL/STANDARD TRAPEZOID
STANDARD FORMULA (with construction duration as x)
WORKERS / ! ! V jobhours
jobhours per period per worker
workers ( 0.625*)
0.5x 0.25x 0.25x
WORKERS / \ J \ jobhours
jobhours per period per worker
workers ( 0.8A- )
0.2x 0.6 x 0.2x
Consider two cases: Case 1, direct-hire labor, and Case 2, subcontract labor.
Assumptions:
• Due to criticality, use density of 250 (but 300 is more probable)
• Allow 12% absenteeism to estimate effective jobhours
• Buildup duration from standard schedule (foundations + equipment + piping buildup)
Scope = 556,200 jobhours for direct hire less 10% productivity adjustment for
local subcontractor labor = 500,600 iobhours
r,' i / ! Scope =
Peak X ! 500600
workers / ; jobhours
500,600 = 1 ^ * 2 5 6
153
2. COURT'S POSITION
f + + + I 4 • • t
Multiple Changes - Cause RIPPLE Effect
of Inefficiency of Program,
due to constant Rdjustment
of more Resources
contractors claimed the total impact of the ripple effect was a schedule delay at
the peak period. Figure 4.26 illustrates these two positions. The courts finally
held for the contractor's position and, consequently, for the greater cost impact.
Figure 4.27 shows a family of curves that illustrates the historical relation-
ship of construction directs and indirects. This relationship was again examined
by the courts in claims cases, and the judgment was that costs of indirects due
to schedule delay would be directly proportional to the schedule extension.
Figure 4.27 shows that the indirect curves are essentially constant through-
out the execution of a project. Early buildup forfieldorganization and installation
of temporary facilities is matched by a late buildup for final job cleanup and
demobilization.
Direct work progress is a measure of physical quantities installed, and, as
shown, the direct work curve is identical to the historical/standard construction
curve previously illustrated. Indirect construction progress cannot be assessed by
measuring physical quantities and is usually measured in craft labor hours. This
typical curve shows the rate at which these hours would normally be expended.
Indirect and direct construction curves for any project can be compared with
these curves. During construction, actual performance should be compared with
these profiles as well, since doing so can provide an early warning that the
expenditure of hours is deviating from the norm.
The percentage breakdowns for craft indirects, field administration, and direct
supervision can be used to check forecasts and performances of individual categor-
m
0)
2
TITU
CONSTRUCTION PROGRESS - DIRECT & INDIRECT (PROJECT S T A N D A R D
55
(Q
03
100 -| 1 1 1 1 .
i
A
CRAFT INDIRECTS INCLUDE
a
Oft -
TEMP. CONSTRUCTION BLDGS 10%
TEMPORARY UTILITIES 10%
80 - OTHER TEMPORARY 13% o
^ F.A.D.S. 1NDIRECT C/>
WATER BOYS & CLEANUP 28% HOURS
I
7 ft _
CONSTRUCTION EQUIPMENT 20% o
IDLE TIME 19%
100%
y f'
y
60 - —
S"
OMPL
s CD
u 50 - FIELD ADMINISTRATION AND DIRECT 0}
— Ah .
y
SUPERVISION INCLUDES:
I
\
Oft . y
y
y
j
y' / WAREHOUSE & PURCHASING
FIELD CONTROLS
13%
13%
DIRECT W0 RK FIELD ENGRG.& INSPECTION 10%
y' FIELD OFFICE ADMINISTRATION 8%
10 - 100%
10 20 30 40 50 60 70 80 90 100
1. HISTORICAL-STANDARD CURVES
5. COURT'S POSITION
RS THERE IS MINIMHL BUILDUP & RUNDOWN.
TREHT RS H RECTRNGLE. WHERE THE COST DUE TO
SCHEDULE EXTENSION. WILL NOW BE DIRECTLV
PROPORTIONHL.
ORIGINRL SCHEDULE
I sciedule Extension
ies. On very large projects, individual control curves can be developed for specific
categories. Figure 4.28 shows the indirects TT and the resulting court position.
The chart contained in Figure 4.29 enables instant generation of an overall project
duration, based on construction direct labor hours. The result is not of high
quality, however, but is intended only to provide a preliminary schedule during
the early development or feasibility stage of a project.
The chart provides add factors for straight-through and overseas projects,
as well as curves for projects that were built in the 1950s and 1960s and for
Norwegian-based projects. Additional curves can be developed for other overseas
locations if necessary.
Of interest is the fact that project durations of the past (the 1950s and
1960s) cannot be repeated today. Following are some of the reasons for this:
reduced engineering and construction productivity, which cannot always be
compensated for by additional personnel;
• greater complexity for the same capacity (such as higher temperatures and
pressures);
• increased engineering due to environmental/regulatory requirements;
Establishing a Realistic Schedule Baseline 121
CM - ~T~it~"f~1~
ITT'
TT
•Htf-
LLJ
1
CL
i
i—rr
2 PROJECT EXPERIENCE OF 1950/60sJ "nTT
O i
•
i t i
- \ - ], ji! ] i
;Pitt: xriii::;
21 TTT
"n
J.
Q ._J4_JJ_LLl-
h-
O
--V?H
i_i_. m m
LJJ
X R=F
iw
O 111 1
Q:
"t T !
LL i n ; ; i^ i • ! lo
PROJECT CONSTRUCTION JOBHOURS (MILLION)
NOTES:
1. Project duration is for Phase 2 only (ehgineering/procurement/construction)
A. Complexity
This data can be used to quickly provide a reasonable labor hour estimate
when only the plot/building area is known. However, good judgment is required
in selecting the appropriate labor hour/square foot rate. Current studies indicate
that module complexity is twice that of land-based plant projects. This factor (2)
is shown on Figure 4.30 and applies only to process or utility modules. The
module area (sq ft) would include all levels and allowances for mezzanines. Also,
to allow for workers occupying space immediately adjacent to the module frame,
a perimeter of 10-15 feet is added to the design module area.
C. Density
From Figure 4.30, the density (sq ft per worker) is based on the maximum/eco-
nomic total number of craft laborers working at peak (supervision is not included).
The data is based on historical experience, and the factor is then tied to the
1. COMPLEX (Petro-chemical-heavy)
Fluid Catalytic Cracker Ammonia
Hydrocracker Ethylene
Hydrotreater Methanol/Ethanol (L)
Containment Building (nuclear pwr. stn.)
2. AVERAGE
Crude (H) Coker L.D. Polyethylene
Reformer (H) Alkylation (H) H.D. Polyethylene
C.H.D. tsomerization Platformer (H)
Unsats Gas Sulfur Refiner
Sat. Gas Amine Pretreater
Light Chemicals Industry
Pulp and Paper (partial)
Breweries (partial)
Pharmaceutical Industry (partial)
Mechanical Building for Buildings Complex (partial)
3. SIMPLE
. Small Process Additions (subject to temp. & press.)
. Major Pump Stations . Shipping & Loading Facilities
Food Industry
Materials Handling Facilities (many industries)
Pulp and Paper (partial)
Mechanical Building for Buildings Complex (partial)
Breweries (partial)
Pharmaceutical Industry (partial)
Note: With additional technical features and/or difficult site conditions, any
of the above "Category Allocations" can change (higher).
I ACCOUNT CODE BOIL BRICK CARP ELEC LAB OPER MILL PAIN! PIPE IRON TEAM
*
ISITE PREPARATION
C7>
[FOUNDATIONS
O
I BUILDINGS
(M
M
W
09
(STRUCTURAL STEEL
<N
CN
1 SPECIAL EQUIPMENT
CN
CN
IA
(0
CN
<0
0>
1 HEATERS
1*.
<6
r^
U)
m
CN
(EXCHANGERS
!»•
^>
(0
m
|VESSELS
CO
1 TOWERS
CO
00
00
~*
CN
ITANKS
in
CN
2
(PUMPS-COMPRESSORS
m
m
CO
CO
CN
00
CO
( PIPING
CD
CN
CN
in
00
(ELECTRICAL
CO
CD
00
| INSTRUMENTS
in
IT
( PAINTING-INSULATION
O>
CN
CN
or>
to
in
N
fTEMPORARY CONSTRUCTIO^
m
in
00
M
t\
CO
Chapter 4
Establishing a Realistic Schedule Baseline 125
I. INTRODUCTION
Every owner wants to get the greatest value possible for every dollar spent on
capital construction. To reach this goal requires the application of total cost
management (TCM) techniques throughout a project's life cycle. Economic anal-
yses are used before any money is committed to determine the feasibility of
pursuing the project. Value engineering (VE) may be used to select the apparently
best design concept. Operability, maintainability and reliability reviews fine tune
designs to make them user-friendly (and usually more cost-effective) for operators
and maintenance personnel during a facility's operating days. Constructability
reviews look at designs with the goal of making actual construction safer and
more cost effective. Many other TCM tools come into play during actual design
and construction—planning and scheduling, estimating and budgeting, change
management, cost and schedule control and risk management to name a few.
Once a facility is in operation, TCM techniques such as planning, scheduling,
budgeting, and cost control continue to be used.
There are several TCM techniques which focus on the design itself, the goal
being to create the most cost-effective design which meets all owner requirements.
These are called value management techniques. This chapter describes these
techniques.
127
128 Chapter 5
This is an umbrella term which encompasses the entire field of value studies.
C. Value Analysis
E. Constructability Analysis
These analyses use construction knowledge and experience to make designs more
constructable. Specific goals are:
• to reduce total construction time,
to reduce labor requirements,
• to reduce costs of construction equipment and tools,
• to reduce materials costs, and
• to incorporate features in designs which promote construction safety.
When one speaks of value, there is a tendency to think only in terms of cost.
But there are other types of value that must be considered in any value man-
agement study. These types of value are found:
Cost value. This is the amount of money (or monetary equivalents) that must
be spent to produce or procure an item.
Exchange value. This is the value of an item on the open market should one try
to sell or trade it. The exchange value of a new car drops in comparison to
its cost value as soon as the new owner takes the car from the showroom.
Value Management 129
Use value. This is the value of an item to the user because of the functions or
services it provides. A well-maintained, basic, old car may have little ex-
change value, but just as much use value to the owner as a newer, fancier
car. That use value would equal the cost value of equally reliable replace-
ment transportation.
Esteem value. This is a value "in the eyes of the beholder" or a consequential
value derived from some investment. A gold bracelet has a definite cost
value, its exchange value is usually less than its cost, it has no use value,
but it has an esteem value to an individual who loves jewelry. The esteem
value of a company's reputation can be converted into monetary terms only
if someone sought to buy the company.
Worth. This term is sometimes used as a synonym for value. What is that
painting worth (exchange value)? What is your reputation worth (esteem
value)? However, value is the preferred term.
Value engineering is concerned with the lifecycle costs or value of the facility or
item. Following are potential elements of a facility's lifecycle cost:
• feasibility studies,
• engineering,
• real estate,
• permits and licenses,
• special consultant fees,
• construction,
• legal fees,
• furnishings,
• operating costs,
• maintenance costs,
• insurance,
• rebuild/upgrade costs,
interest payments,
• time-value-of-money on committed capital,
• demolition costs,
• salvage costs, and
• remedial action costs.
There may be value concerns that are not directly translatable into cost but
which will be incorporated into a VE study and given a weighting factor. Exam-
ples are:
• aesthetics (exterior and interior),
• ease of future upgrading or expansion,
• convertibility to other function,
• maintenance and operator "friendliness," and
• working atmosphere for occupants.
130 Chapter 5
In this phase all information providing the basis for the project and relating to
the specific location is assembled. Examples are:
• operational requirements (output, space, etc.);
• project budget;
• client-need dates;
• major equipment commitments already made or intended;
• proprietary processes or systems involved;
• client's design standards;
• design criteria;
• design calculations to date;
• alternatives already identified;
technical memoranda pertaining to the project;
• permit requirements;
• environmental, zoning, and other regulations;
applicable building/construction codes;
• maintenance requirements;
• other facilities potentially affected by this project;
equipment data sheets, process flow sheets, etc.;
• cost estimates to date;
• subsurface investigation data; and
• site constraints (size, shape, existing structures and facilities, access, etc.).
132 Chapter 5
Next, the basic and secondary functions to be provided by the facility are identified.
Functions are described in a generic fashion using an action verb and a noun to
invite visualization of various options. Other typical verb-noun combinations are:
• transmit load,
• illuminate room,
• convey liquid, and
• heat building.
A basic function is a primary function under study. A secondary function is a
consequential or potential additional function. The basic function of a lamp is to
provide illumination; a secondary function may be to decorate the room.
Questions to be asked by the team in this phase include:
What basic functions are involved in meeting facility/product requirements?
• Which secondary functions are associated? Which are essential?
• How is the function accomplished?
• What is the value of a function?
D. Creative Phase
Different ideas for performing the various basic or secondary functions are iden-
tified and listed, based on the functional analysis. For example, heating require-
ments for a structure can be satisfied by any number of options—heat pump, gas
furnace, oil burner, space heaters, fireplaces, electric baseboard heaters, or solar
panels. As another example, transport coal leads to the options of conveyor belts,
trucks, rail, slurry pipeline, etc. It is not uncommon to have 5-25 ideas proposed.
It is worthwhile in this phase to itemize obvious advantages and disadvan-
tages of each idea as a basis for initial screening in the analytical phase,
E. Analytical Phase
Some authorities recommend that only the group leader from the creative phase
continue in the analytical phase. The reason for this is that, if the members of
the team brainstorming an item know they may be required to evaluate its
feasibility and costs associated with the idea, they may be reluctant to add too
many ideas to the list or propose an idea that is difficult to evaluate. This phase
begins with a summary review of the ideas from the creative phase to reduce
the initial list to 2-5 ideas that are worthy of detailed evaluation.
With each remaining idea, the need for each function is validated and each
option for performing a function is examined individually as to feasibility, cost,
and value received. Then, various combinations of these ideas are tested as a
system against the governing criteria for the facility. The most feasible combina-
tions are isolated and given more detailed study. The combination with most
favorable balance of cost and value is further refined through more detailed study.
In this process, the value engineers will employ various combinations of economic
analysis, lifecycle costing, trade-off analysis, sensitivity analysis, estimating, and
other cost engineering tools.
Value Management 133
While total lifecycle cost may be the primary criterion used to rank options,
this is not always true. Another approach, when everything cannot be reduced
to monetary terms, is to list various criteria, weight those criteria, and then
grade each option against them.
F. Proposal Phase
G. Implementation phase
Even though a design concept has been established through formal VE in the
conceptual design phase, the principles of VE should continue during detailed
design. A typical area for VE effort during design is with specifications. All too
often, it is found convenient to utilize specifications directly from a computer
database without questioning the need for them as written. Each should be
questioned as to its need in its present form and the most cost-effective specifi-
cation derived. During detailed design, various design simplifications may also
result from continued value analysis.
Some clients include value engineering clauses in their contracts for construction.
These clauses typically set up a procedure whereby, after review of the construe-
134 Chapter 5
tion documents, the contractor may submit proposals for more cost-effective
designs than those of the contract drawings. If the VE proposal is accepted, the
savings are shared with the contractor. As mentioned previously, such studies
are more properly called value analysis studies since they come after completion
of design.
B. Constructability Analyses
There are occasions when a client's available budget is less than the most recent
cost estimate or less than the selected contractor's cost proposal. In these situ-
ations, the contractor may be asked to join the client in re-examining the designs
for the purpose of value engineering them to fit within budget. In studying these
designs, attention should be initially focused on components or features of the
project which have greatest cost reduction potential:
If an item or function is nonrevenue producing, could it be eliminated
without compromising basic functions?
• If an item or system is complex, is there a simpler way?
• If an item or system has a significant cost, what are the components of this
cost and can any be reduced through redesign or substitution?
If a design for providing some function is new, is it still the best approach?
• If an item has negative constructability (including safety) implications, what
can be done to make it safer or more constructable?
If a design will force hiring of high-wage craft trades in the field, could it
be redesigned to utilize workers from trades with lower wage scales?
• If specifications were copied from other projects, could they be tailored to
fit this project's situation?
• If specially engineered components are involved, could off-the-shelf equip-
ment be substituted?
Additionally, consider the following:
• combining multiple structures into fewer structures,
• using an existing structure or system instead of constructing a new one,
and/or
using modularization or shop fabrication to reduce field labor costs.
IX. SUMMARY
Value management provides a family of useful tools to help assure lowest cost
and/or greatest value for a project. It is not a discipline like structural or
mechanical engineering; rather, it is a series of techniques available to all dis-
ciplines. Applying them takes additional time and money at the time, but advo-
cates are convinced that the returns are many times greater than the initial
investment. All cost engineers should include these techniques in their total cost
management tool bags.
A. J. Dell'Isola, Value Engineering in the Construction Industry, 3rd Ed., Van Nostrand
Reinhold, New York, 1982.
C. Fallon, Value Analysis, 2nd Rev. Ed., Triangle Press, Southport, NC, 1980.
Federal Construction Council, Consulting Committee on Value Engineering, Elements of
an Effective Value Engineering Program, Technical Report No. 92, National Academy
Press, Washington, D.C., 1990.
136 Chapter 5
XL CONSTRUCTABILITY BIBLIOGRAPHY
* By Dr. Klane F. Forsgren, PE, Vice President-Engineering, Sinclair Oil Corporation, Salt Lake City,
Utah.
137
138 Chapter 6
involve the same principles of comparison used for selecting investments, and
also can suggest ways to evaluate options that minimize loss.
Another important decision faced by management is the building of good
will and a good name for the company. In most instances, developing good will
requires a monetary investment. The techniques used to select the best invest-
ments can also be used to evaluate the best options for developing goodwill.
The method described in this chapter relates to the time value of money. The
concept is that the use of money over time has a value and that a person should
be compensated for the use of the money for that period of time. The method
described shows ways to compare the value received for the use of the money.
This value is important, since the return on an investment may be postponed
for some years, is not the same every year, and may be bunched at the front or
the end of the time spectrum under consideration. The method described in this
chapter will help you consider many variables and put them all on an equal
footing for comparable evaluation.
In order to understand the methodology of the time value of money, we must
define some terms typically used in economic discussions. The textbook, Economic
Evaluation and Investment Decision Methods, by Franklin and John Stermole,
has been referenced extensively in developing the definitions. The author's exper-
ience in the oil and power industry serves as the basis of the examples.
The important definitions needed to discuss economic evaluations are the
following:
cash flow;
• rate of return, internal rate of return, or discount rate;
• present value;
• future value;
annual value; and
• breakeven.
A. Cash Flow
Cash flow is the difference between the cash received (income) and the cash paid
out (expenses). Cash received can come from several sources, including sales
revenue, interest on money invested, and services performed. Cash out goes to
expenses such as materials, labor, utilities, taxes, interest, buildings, etc. The
successful business will have more cash in than cash out, or a positive net cash
flow.
In most instances, the cash flow is negative for the first few years of the
operation of a new business or a new process. To adequately perform the economic
evaluation, the business must take this negative cash flow into consideration.
The methods discussed show how to consider the total cash history of the venture
in the evaluation.
A second consideration in evaluating cash flow is that the value of money
changes from year to year due to inflation and deflation—like the difference
between a 1995 dollar and a 1985 dollar.
Economic Evaluation in the Process Industries 139
B. Rate of Return
Rate of return is the interest rate that you would receive if you invested the
amount of money under consideration in a bank and received the same positive
net cash flow as was developed by the investment. The net cash flow occurs over
a period of time, and the time value of the cash flow over that time must also
be considered. Discounting implies reducing the value of something. Future val-
ues are discounted by a factor—the interest rate or discount rate—to their present
worth or present value.
C. Present Value
Present value is the value of the investment over time in today's dollars. It
includes all of the cost of the project, including management costs to get the
project completed, and the hard costs for purchase of equipment, buildings,
material, etc.
Net present value (NPV) is the cumulative present worth of the positive and
negative cash flows where the specified discount rate introduces the time value
of money. A positive NPV means that the future cash flows of the project are
higher than the minimum return established for the project. A negative NPV
means that the future cash flows are not enough to maintain the return estab-
lished for the project. A person or company would be better off investing in an
alternate project.
D. Future Value
Future value is the value of the cash flow in the future in future dollars. This
value is used in comparisons and discount rate formulas, which are available in
tables of interest rates.
E. Annual Value
F. Breakeven
Breakeven is the time that the net positive cash flow pays off the full cost of the
project. The faster a project reaches breakeven, the better the investment, or the
more money that was returned in a shorter time. The time to reach breakeven
can be used as a good rule of thumb in evaluating investment options, as will
be seen later. Table 6.1 shows how cash flows are developed.
Table 6.1 Example of How Cash Flow is Developed. The Cash in is Shown by Positive
Values, the Cash out by the Negative Values. The Net Cash Flow is the Difference Between
Cash in and Cash out.
Year 0 1 2 3 4 5 6
compounded interest rates. It involves taking the annual cash flow from the
business, either real or projected, and applying an interest rate to each year's
flow, while accumulating the previous year's cash flow with associated accumu-
lated interest. This is the value of using compounded interest rates in the
calculations.
The discount rate becomes the minimum return or interest rate acceptable
for investment. The owner of the project usually establishes the minimum return
or interest rate or the discount rate. What determines the selected minimum
return or discount rate? There are several factors:
the interest rate available in the money market at no risk;
alternate investments and their return potential;
• risk associated with the project;
accuracy of the economic analysis, generally based on the quality of the data
available for analysis;
• corporate policy; and
• personal preference.
An investor can normally put money into a very safe investment, such as
a certificate of deposit with a strong government, or into a very stable bank, and
receive a guaranteed return on that investment for the investment period. Since
the return on the money is guaranteed, the interest rates are usually low. This
value would be the least return on investment that one would accept for any
business proposal, since it is guaranteed. The return on another form of invest-
ment may not be guaranteed, and therefore carries risk that the investment may
lose money.
In most instances, several projects compete for the same investment capital.
Within a corporation, for example, several different corporate sites may be trying
to add new process equipment. These projects are in competition with those who
want to buy out complete companies or expand into a new market by building a
completely new facility.
In this situation, a corporation will prepare a financial package, a proforma,
with the projected profit for several years. Then the company will determine the
DCF for each competing project. The project with the highest internal rate of
return (IRR) will normally be selected for funding.
Economic Evaluation in the Process Industries 141
Most business computers have DCF programs built in. You only need to obtain
the net cash flow for the project for a period of several years, put that data into
the computer program, and let the computer develop the DCF. The more years
of cash flow available, generally the better the DCF analysis.
The computer program invests each year's cash flow at the established
interest rate for the established period of time. The sum of the net profit and
accumulated interest from the net cash flow is compared to the income produced
by putting that same amount of money into a bank at the prescribed discount
rate. The two sums are compared to determine whether the project meets the
standard set by the corporation or the owner.
142 Chapter 6
Table 6.2 Impact of Net Cash Flow on Internal Rate of Return (IRR) and Net Present
Value (NPV)
Several factors affect DCF analysis, but four major factors are:
the amount of the investment,
• the amount of net cash flow,
• the timing of the investment, and
• the timing of the return.
Control of these items will greatly improve the return on investment sought
by the investor. The greater the cost of the project, the higher the net cash flow
must be to repay the debt and to return an increase to the investor. It is also
more difficult to get a good cost estimate. This is primarily because few examples
of complex projects exist, and the company is more susceptible to missing an
important piece of the puzzle. To compensate for these difficulties, the net cash
flow and rate of return would normally have to be higher to be acceptable.
The higher the net cash flow, the faster the debt is retired and the greater
the rate of return. Table 6.2 shows three different cash flows with the corre-
sponding net present value at 15% interest and the corresponding IRR.
In Table 6.2, all three projects have the same initial investment of $300,000
spent in 2 years. Case 1 returned $600,000 over just 3 years. Case 2 returned the
same $600,000, but over 6 years. Case 3 returns the same $600,000 over 9 years.
Cases 1 and 2 have IRR values above the 15% standard for this investment and
show a positive net present value. Case 3, with 9 years required to receive the
$600,000, did not meet the 15% standard and thus had a negative net present value.
A good way to understand how this method of economic evaluation can be used
effectively is to do a case study. The United States Environmental Protection
Agency (EPA) recently required that all vehicles that traveled mainly on paved
roads would have to use low-sulfur diesel (0.05 wt%). This required a decision
by the refiner between these two choices:
Should the company spend the money to build a new hydrotreater in its
own facility to reduce the sulfur in the diesel fuel?
• Should the company make a contract with another refinery to have the
diesel fuel produced on a contract basis?
Economic Evaluation in the Process Industries 143
The numbers used in this example are numbers representative of the real world,
but are not intended to represent actual practice.
A. Construction Option
B. Contract Option
Table 6.3 Construction Option for Case Study. Over 7 years, the income is substantial
enough to offset the yearly cost.
Year 1 2 3 4 5 6 7
Table 6.4 DCF Analysis for the Construction Option. Over the 7-year option, the income
is substantial enough to support construction, but how does this option compare to con-
tracting the desulfurization?
Year
0 1 2 3 4 5 6 7 8
Cash flow ($MM US) -15 -25 14.2 13.4 12.4 11.4 10.3 10.3 9.3
The annual cost and income from the contract option is shown in Table 6.5.
Since the construction time is only one year, we have taken the annual cost and
income statement for 8 years. Thus the comparison takes into consideration the
timing of the projects and the timing of the expenditures, as noted before.
Comparing the two options shows which option will provide a better return
on investment and potentially make more money for the owner. Comparing the
analysis shown in Tables 6.4 and 6.5 gives the following:
Table 6.5 Data for Contract Option for Hydrotreating Diesel Fuel
Year 1 2 3 4 5 6 7 8
Price A ($/gal.) 0.10 0.09 0.08 0.075 0.07 0.07 0.065 0.065
Income ($MM) 20.6 18.5 16.5 15.5 14.4 14.4 13.4 13.4
Cost ($/gal.) 0.09 0.085 0.075 0.07 0.065 0.065 0.06 0.06
Cost ($MM) 18.5 17.5 15.4 14.4 13.4 13.4 12.3 12.3
NCF ($MM) 0.1 1 1.1 1.1 1 1 1.1 1.1
When the difference is great, the decision can be quite simple and easy.
When the difference is small, you consider other factors in making the decision.
The contract option only returns 8.8% on the invested dollars, and the construc-
tion option provides a 20.8% return. This suggests that the construction option
should be selected.
Before a company will accept the results of the analysis, especially when
the comparisons are close, it will check the quality of the input data. In order
to make this as easy as possible, it helps to know which data has the greatest
impact on the analysis. This is referred to as a sensitivity analysis.
With the projects set up in the DCF format, you are in a position to modify the
initial assumptions and determine what will be the impact. Some variables have
a major impact on the financial analysis, while others have little effect.
The impact of changes to five items will be evaluated:
• impact of selling price,
• impact of initial cost of the project,
• impact of production cost,
• impact of inflation on both selling price and costs, and
impact of taxes to show value of tax breaks to the viability of the project.
Table 6.6 Impact of a 20% Reduction in Selling Price on the Construction Option
-1 0 1 2 3 4 5 6 7
Selling price ($/gal.) 0.08 0.07 0.065 0.06 0.06 0.055 0.055
Income ($MM) 16.5 14.4 13.4 12.4 12.4 11.3 11.3
Costs ($MM) 6.2 5.1 4.1 4.1 4.1 4.1 4.1
NCF ($MM) -15 -25 10.3 9.3 9.3 8.3 8.3 7.2 7.2
would receive $3 million dollars less with this investment than with an option
that will meet the 15% criteria.
3. Impact of Production Cost
An increase in the operating cost of the project—it costs more to produce the
product than was projected—has the same general impact as does having a lower
selling price. In both cases the net cash flow will be decreased, thus decreasing
the net present value of the cash flow over time. You can run this option to see
how much the decrease is, though the proof is not shown here.
4. Impact of Inflation on Both Selling Price and Costs
Table 6.8 shows the construction option with the lower initial selling price but
now adds a 5% per year inflation rate for the selling price and the costs. Because
the selling price is generally more than the cost, an inflation increase will help
the project because the difference between selling price and cost will continue to
increase as inflation increases. Under this scenario, the project that was not
acceptable now becomes acceptable. The IRR is just above 15%, barely meeting
the criteria standard set for the project.
5. Impact of Taxes to Show Value of Tax Breaks to the Viability of
the Project
The impact of taxes is the same as modifying the cost of production. Taxes must
be taken from the cash stream, and serve to reduce the value of the net cash
flow. If you can, obtain some type of tax break from the local, state, or national
Table 6.7 Impact of a 25% Increase in the Initial Cost of the Construction Option
Year
0 1 2 3 4 5 6 7 8
Annual cash flow ($MM US) -25 -25 14.2 13.4 12.4 11.4 10.3 10.3 9.3
Table 6.8 Impact of a 5% Inflation Factor Applied to Both Selling Price and Costs
-1 0 1 2 3 4 5 6 7
Selling price ($/gal.) 0.08 0.07 0.073 0.077 0.08 0.085 0.09
Income ($MM) 16.5 14.4 15.0 15.8 16.5 17.5 18.5
Costs ($MM) 6.2 5.1 5.4 5.6 5.9 6.2 6.5
NCF ($MM) -15 -25 10.3 9.3 9.6 10.2 10.6 11.3 12.0
governments that adds net income to the cash flow, thus improving the perfor-
mance. Usually the tax break has a limited time that it is in place. Thus this
method of DCF could be projected to beyond the time that the tax break is allowed
to determine the impact on overall project viability.
The DCF methodology has great versatility; it quickly helps to evaluate several
alternatives and to determine how sensitive the alternatives are to variations in
the data used in the analysis. However, the system is very dependent on the
quality of the data used in the analysis. This dependence bears the impact of
cost of the process, selling price of the product, and cot of manufacture. In
establishing any economic evaluation, ensure that the numerical values used in
the process are as close to the real world as possible. Getting an accurate cost
of the project and determining the correct selling price are generally the two
places that economic evaluations fail.
When determining the cost of the project, make the costs equivalent between
competing options. The project manager of the economic evaluation must demand
that the project costs are complete, current, and realistic. The manager must
define the total extent of the process being considered. In the case study, the
desired hydrotreater must be carefully defined in terms of size, location in the
148 Chapter 6
Earlier in this chapter, information on determining the selling price was dis-
cussed. Developing good selling price information is crucial to the success of a
project analysis. To help you develop good information, you will also need to
consider the following:
commodity versus new product pricing,
reaction of the competition,
• government impact,
availability of product, and
• raw material costs.
The selling price of an existing product class is established by the market.
The likelihood of increasing the selling price of the product to the consumer is
limited. However, tougher regulations may demand more of businesses without
allowing them to pass some of the costs to the consumers. Currently, oil compa-
nies are required to add oxygenates to gasoline that is sold into ozone nonattain-
ment air quality areas. The oxygenates are added by blending ethanol or a
chemical called MTBE (methyl tertiary butyl ether) into the gasoline. These
additives cost 50-75% more than the gasoline. The additive can be as much as
10% of the total blend, yet the oil company cannot get enough for the oxygenated
gasoline to cover the increased cost. The consumer is used to paying the estab-
lished price for the product regardless of the improvements to the product.
Economic Evaluation in the Process Industries 149
The whole purpose of these examples is to require that the economic eval-
uator pay special attention to the selling price used, and basically assume lower
prices. Lower selling prices are true more often than the higher prices promoted
by marketing personnel.
If the product for sale is a new product, you have more price flexibility, but
again the analysis should look at generally lower prices than projected.
In established markets, economic analysis should evaluate how the compe-
tition will react. The competition will fight to keep their market share. The fastest
way to respond to new competition is to lower prices. In some instances, the
competition will take a loss for a period of time to keep new competitors out.
The government can have a major impact on selling price. Complaints from
the public on price fixing can lead to expensive, time-consuming defense. Gov-
ernment requirements to modify a product for environmental reasons but with
no opportunity to increase the selling price can be detrimental.
VIII. SUMMARY
Economic evaluations are developed to help us make the best investment choice
of the options available. Discounted cash flow analysis, which uses compound
interest rates to determine the new present value of a future net cash flow, is a
versatile tool; it compares many alternatives and helps to determine which eco-
nomic factors provide the greatest change in the analysis.
Keys to Controlling and Reducing
Environmental Costs*
I. OBJECTIVE
Few people realize how costly environmental cleanup is and how costly it may
be to prevent environmental problems in the future. The U.S. cost of complying
with environmental regulations from 1972-1992 was about $1.4 trillion. The cost
will be about $1.6 trillion in the remainder of the 1990s.
This chapter identifies proven methods for remediation and discusses the
expected costs attached to each method. It also identifies the role and attitude
of the governmental regulators and illustrates how to save expenses through
initial negotiations with the regulators. It identifies cost reduction options for
closure and postclosure care.
Finally, it provides some basic guidelines to estimate remediation costs. It
is extremely difficult to estimate remediation costs because a project always
changes as it progresses. Still, it is important to estimate costs well to develop
budgets and to adopt and monitor cost control activities.
This chapter is based on remediation activity to be conducted under the
Resource Conservation and Recovery Act (RCRA) and Underground Storage Tank
(UST) guidelines. These guidelines are similar to other remediation strategies
and illustrate the methods proposed below for cost control of remediation projects.
By Dr. Klane F. Forsgren, PE, Vice President-Engineering, Sinclair Oil Corporation, Salt Lake City,
Utah.
151
152 Chapter 7
Regulation Description
One good point about the procedure for environmental remediation is that cleanup
is basically the same regardless of which act applies—RCRA or the Comprehens-
ive Environmental Response, Compensation, and Liability Act (CERCLA). For
ease of discussion, the remediation activity will be based on the environmental
media affected.
For cleaning contamination in soil or in groundwater, the remediation pro-
cedure (Fig. 7.1) includes the following:
1. Report any release of contaminants. A release can be identified by seeing a
spill or deposit of waste, finding contamination in groundwater, discovering
contamination during excavation, or suspecting contamination exists be-
cause of how the site looks or from knowledge of past activities on the site.
2. Investigate the site for contamination. Determine if contamination exists; if
so, explore the extent of contamination. Write a report and submit it to the
controlling agency for approval.
3. If contamination is found, conduct a further investigation to determine how
widespread it is. A written report is provided to the agency for approval.
4. Once the extent of contamination is identified, write a remediation plan and
submit it to the controlling agency for approval. The approval process usu-
ally includes public hearings.
5. Implement the approved plan according to a negotiated time schedule.
6. After reducing the contamination to acceptable levels, formally close the
remediation work.
7. Monitor the site to ensure that it remains clean.
Keys to Controlling and Reducing Environmental Costs 155
REPORT OF
CONTAMINATION
NO
PRELIMINARY CONTAMINATION f
SITE
INVESTIGATION
CONTAMINATION
BELOW
REMOVE EXTENT THRESHOLD
AND OF
STOP CONTAMINATION
EXTENSIVE
REMEDIATION
PLAN
CORRECTIVE
ACTION
CLOSURE
PLAN
CLEAN
NO FURTHER REPORT AND
AGENCY APPROVAL
ACTION
GROUND LEVEL
GROUNDWATER
FLOW DIRECTION DISSOLVED PLUME
V/////////A
SATURATED ZONE
Figure 7.2 General path of contaminant that is released into the soil with groundwater
present.
C. Remediation Options
Many remediation options are available, some more successful than others. In
order to organize the options, this section will deal first with soil remediation
options and then with water remediation options. As indicated, air problems tend
to be fugitive and control of pollutants is generally done by process changes. Thus
there are generally no remediation problems with air pollution.
1. Soil Remediation
Soil remediation strategies can be divided into two general categories: treatment
by removal or treatment in situ (on site).
Keys to Controlling and Reducing Environmental Costs 157
GROUND SURFACE
9.6' BOREHOLE
BENTONITE SEAL (VOLCLAY OR
BENTONITE GROUT)
4" SCHEDULE 40 PVC WELL CASING
(FLUSH THREAD)
CONTAMINATED
SOILS
u—i
is that the water or solvent used to complete the washing must be disposed of.
If the level of contamination is low and the materials removed by washing are
acceptable to the local public treatment plant, disposal can be fairly simple. If
the materials removed are not compatible with the local public treatment plant,
water treatment may also be needed, driving the cost up very quickly.
EXHAUST
AIR
FLOW
EXTRACTION WELL
V7
SATURATED ZONE
CONTAMINATED STABILIZER
SOIL
binder and left in place. The binder sets up and reduces access to the contaminant.
In this fashion, the contaminant is held and will not escape into the groundwater
or move any further in the soil. Generally the location of this disposal area must
be located on the plat map of the site so that any future purchaser of the property
knows there is a solidified waste deposit on the land and its exact location.
2. Groundwater Remediation
Treating groundwater is difficult, time-consuming, and costly. If the contaminant
is a hydrocarbon, with limited solubility, the contaminant will float on the water
as well as dissolve in the water. If the contaminant is metal, it generally has
low solubility and must be removed chemically. If it is organic and heavier than
water as some chlorinated solvents are, then it almost has to be removed mechan-
ically and treated. There are many variables that can impact the cleanup and
they are generally not controllable. Some general categories of remediation tech-
nologies are listed next to give the reader some idea of the methods that are
used. A more thorough discussion of methods can be found in most textbooks on
remediation. The methods used most are pump and treat, vapor extraction, air
sparging, air sparging in conjunction with vapor extraction, and bioremediation.
Pump and treat has been used most historically, but has not been able to
clean up the contamination to acceptable levels. Experience suggests that only
about 30% of the contamination can be cleaned up with this method. Its main
value is in hydraulic control to keep contaminated water from flowing onto other
property.
Pump and treat systems involve installing wells around and in the contam-
inated area. Pumps are installed and the water is pumped to the surface. This
creates a cone of depression in the aquifer. If there is free hydrocarbon on top
of the groundwater, this cone allows free hydrocarbon to accumulate in greater
depth at the cone. A pump can then remove the free water and product into a
tank (see Fig. 7.7 for a schematic diagram of a pump and treat system). An
alternative is to place two pumps into the well. The first pump causes the water
cone and pumps only water. The second pump removes only free product.
The water removed by the pump is contaminated and must be treated before
it is disposed. Treatment can be with air strippers that will remove the contam-
inant if it is volatile or semivolatile. It can be a rapid sand filter or settling basin
if it can be chemically treated and precipitated. It can be in an aerated lagoon
Keys to Controlling and Reducing Environmental Costs 161
AIR (TREAT?)
OIL/WATER
SEPARATOR
A WATER
GROUND LEVEL ^ DISCHARGE
LNAPL
GROUND
WATER
EMISSION
CONTROL
UNIT
SATURATED ZONE
AIR
FLOW
Control of remediation costs starts very early in the process. Cost savings begin
with the studies that are completed to define the nature and extent of the
contamination. Cost saving methods are discussed for each of the phases of the
remediation process.
Remediation activities are almost always done with the approval of the respon-
sible agency, EPA or state. Normally a remediation plan is submitted and ap-
proved before any activity is allowed to proceed. The plan that is approved
controls what will be required and must be negotiated with great care.
In most instances, the agency will follow the guidance manuals prepared by
EPA. These guidance manuals have been developed by regulators who have not
had much actual experience or by consultants who want to be sure they have
covered all the possible conditions. Accordingly, the guidance documents tend to
be very conservative and will overkill rather than miss something. It is wise to try
to negotiate a scope of work that will accomplish the necessary objectives with the
minimum amount of expense. Some specific examples are discussed below.
During the study phase of a remediation project, the analytical costs can be 40%
of the total cost. Therefore the number of samples taken and the amount of
chemical analysis required on each sample are very important. Also the method
of taking the samples can make a great difference. Drilling wells will cost between
$50 and $75 per foot. Alternatives are pushing a probe into the aquifer to take
a sample and then removing the probe. No further sampling is required and the
cost is about 25% of drilling. Another option is digging a hole with a backhoe to
test groundwater. It is much less expensive than drilling. Also, the geotechnical
analysis is more complete and easier as it comes from visual observation of the
complete area rather than visual observation of core samples.
If there is a well on the site, the regulator will want it sampled, generally
on a quarterly basis and occasionally on a monthly basis. If there is no well, no
sampling can occur.
The cost to perform an analysis of volatile materials such as benzene, ethyl
benzene, toluene, and xylenes is about $100. The cost to test eight metals nor-
mally required for RCRA investigations is about $100. These two samples will
tell about all that is needed initially for hydrocarbon contamination. The agency
people are told in the guidance documents to require a complete Appendix IX
chemical analysis; this includes about 222 chemicals that EPA has designated
for testing in groundwater monitoring. This will cost about $1,000 per sample.
If the requirement from the agency also requires toxicity characteristic leaching
procedure analysis of the soils, the total cost will be about $2,000 per sample.
With this in mind, the number of sampling sites, the method of obtaining
the samples, the types of chemical analysis required, and the type and frequency
of sampling over the term of the study and remediation are very important. It
is not uncommon for the agencies to approve a lighter sampling and analysis
plan after the initial sampling is done. For example, they may require an Ap-
pendix IX analysis for the first sampling event and allow tests the next three
quarters for only those contaminants found in the first round or expected because
of the nature of the process causing the contamination.
The agency may require the complete chemical analysis again at the start
of the second year. Following these sampling events, they may allow analyzing
only for the contaminants found for the rest of the sampling and analysis work.
This approach can reduce the cost of analytical work to 25% of the cost recom-
mended in the guidance manuals.
G. Writing Reports
Historically the reports sent to the agencies have been very large and very
involved—and thus very expensive. The agency is no more excited about reading
these large documents than the author is about writing them. In many instances,
the original plan of action includes much background information on the site and
the contamination. This background information may cover geological informa-
tion; surface water and groundwater location and use; location of receptors and
pathways to reach them; previous work at the site; potential to emit contami-
nants; and general information.
The guidance manuals suggest that even though this information does not
necessarily change, it should be included in each subsequent report. Discussions
with the agency people during the acceptance of the plan of action can often lead
to reductions in report size by referencing the previous work. This is especially
true with data that has been generated and reported previously.
164 Chapter 7
The final report for a major study can be an accumulation of reports written
after each phase of the study. Normally the agency will require interim reports
outlining the progress of the work. These interim documents should be written
so they become various chapters of the final report thus reducing dramatically
the cost to assemble the final report.
The use of electronic methods to report data is becoming more widespread.
Baseline data used in assessing cleanup or in establishing permit conditions can
be reported by disc rather than written page. Eventually, extensive volumes of
data will be handled by computer disc.
H. Writing Permits
to $17,000,000. Had they known the full extent of contamination at first, they
would have chosen an in-situ stabilization approach or a no-action approach.
A. Cost Estimates for Simple Sites (Less than One Acre in Size)
Simple sites can be defined as those areas smaller than one acre. These sites
may be service stations or underground storage tanks. Such sites tend to be
similar and not very complicated. In these simple sites, there may be two to
three levels of assessment. Assessment costs generally run $2,000-5,000 for the
initial assessment and $20,000-25,000 for the verification assessment (which uses
4-6 ground monitoring wells). If additional extent of contamination work is
needed, it may require additional wells and will likely cost between $15,000-
25,000 more. By the end of the assessment phase, the best remediation method
will be determined and the total cost of the cleanup can be estimated.
Wells for product recovery and/or monitoring usually cost $50-75 per linear
foot of depth. Vapor extraction wells or soil venting wells will be a little more
expensive, generally $60-80 per linear foot of depth. If air sparging is added to
the system, more wells are needed and air sparging will generally add an addi-
tional $20 per well for existing wells. About $100 per foot is a typical cost for a
new combination vapor-extraction, air-sparging system.
Analytical work for simple sites such as Leaking Underground Storage
Tanks can generally be limited to those analytes anticipated either due to process
knowledge or previous analytical data. Testing for any additional chemicals is
expensive and adds nothing to the study. Table 7.2 gives examples of analytical
costs that are usually involved in remediation activity. Installation of pump and
treat systems generally costs about $16,000 per operating well. Operating costs
generally run about $1,500 per well, per year.
Installation of vapor extraction with no air treatment will cost about $4,000
per well. The cost for addition of air treatment to vapor extraction will range
between $40,000 and $100,000 per site. The annual operating costs for vapor
extraction and air sparging are generally about the same and range between
$1,200 and $1,500 per well, per year.
Cleanup costs at smaller sites will generally run from $10,000 (no remedi-
ation) to $500,000 (major remediation) and average about $150,000.
Table 7.3 compares the various elements of a remediation project for medium-
and large-sized sites with simple sites. The estimate should include all of the
Assessment
Initial 2-5 5-15 20-50
Second 20-25 50-75 100-200
Extended 15-20 40-60 100-150
Pilot test 15-20 15-20 20-40
Analytical
Initial 1 3 5
Second 10 30 50
Extended 10 30 50
elements shown. The following rules of thumb can be helpful in estimating the
cost of the remediation.
• The assessment will involve determining the extent of contamination, which
will likely involve monitoring wells. Establish enough to locate all potential
releases. The wells will cost the amounts shown previously.
Analytical work will generally run about $2,000 per well for the first sam-
pling event. Later events will be less. Knowledge of the site history and the
processes on the site can help establish the possible analysis. From this cost
laboratory work costs can be estimated.
• The cost of consultants is generally 50% of the total cost of the work in the
assessment phase. With the number of wells estimated and the laboratory
costs estimated, the total cost of the assessment phase can be determined.
Table 7.4 is a summary of the cost of disposal in today's market. The trend in
cost of disposal has been declining as the industry becomes more competitive
with more disposal sites and available disposal ideas. Get price information from
several sites before deciding on the contractor or the method. Most disposal
systems will negotiate on price.
Once the extent of contamination and the components of the contamination
are understood, the remediation methods can be evaluated and cost estimates
made.
Of major importance is the selection of the disposal site if one is used. There are
ample case histories of improper disposal at sites that required the original
suppliers of the hazardous waste to clean up the site. A company in Utah was
accepting waste oil, solvents, and other volatile organic compounds for disposal.
The site was licensed with the state so everyone using the site felt it must be
okay. The truth was that the hazardous material was not being handled according
Keys to Controlling and Reducing Environmental Costs 167
Incinerate:
Liquid wastes $0.60/lb plus shipping and analytical costs
Solid wastes $l/lb plus shipping and analytical costs
Used as fuel for $0.22/lb plus snipping and analytical costs
power generation
Excavate and move $35/ton for nonhazardous materials, plus shipping and
analytical costs
$100-$300/ton for hazardous materials that meet land disposal
regulations, plus shipping and analytical costs
Vitrify $l/lb plus shipping and analytical costs
Stabilize in place $60-$100/ton plus analytical costs
to regulations. The site was finally shut down by EPA. The disposal company
went broke, the owner was indicted, and there was no company money to clean
up the site. The Environmental Protection Agency required the site to be cleaned
up under CERCLA jurisdiction. As a result, each company that deposited any-
thing there is legally responsible for its share of the remediation costs. With the
addition of legal and attorney fees, the problem became very expensive.
Before selecting a disposal site, it is crucial to evaluate the site carefully.
The evaluation should include but not be limited to the following:
Contact the state and EPA about condition of the disposal site's license. Ask
if the site has had any violations in the last 3-5 years.
Check the financial strength and insurance of the site in case of failure to
perform.
• Visit the site and perform a personal audit or evaluation to ensure that the
site is well managed and in compliance.
• Negotiate a contract that gives as much protection as possible.
Estimates of closure costs are also site-specific. Closure usually involves capping
the waste in place, stabilizing in place, or a combination of the two. Table 7.4
gives the cost to stabilize. The cost of capping can be determined by classical
civil engineering estimating once the permeability of the cap has been decided.
Engineering costs for closure activities usually run about 20% of the total cost
due to the need for certification of the closure and the extra supervision required.
Postclosure care for sites that have affected the groundwater can go on for 30
years. If the closure is without impact on the ground or groundwater, then the
sampling is usually completed in less than 5 years. If the site is in-between, then
the monitoring can go on for several years.
168 Chapter 7
the agency may allow use of nature to help without causing harm to human
health or the environment. The remediation activity that occurs on the property
can then be integrated with other normal operational activities and dramatically
reduce the cost.
Once the above activities are complete, the remediation method for the site
can be selected. The time frame required, the points of compliance, and the levels
are now known. If time permits, the remediation may be implemented in phases.
For example, hydrocarbons may exist as a free product and as dissolved constit-
uents in the groundwater. If the groundwater is not moving very quickly, a vapor
extraction system may be implemented first to see how it performs. If the cleanup
is too slow, the system can be enhanced by introducing air sparging. If vapor
extraction will do the job alone, why include air sparging or a skimming pump?
The remediation method can be simple and still accomplish the task.
B. Selecting Contractors
The same principles used in selecting contractors for normal construction work
apply for seeking contractors to perform studies, design and install remediation
systems, and run analytical tests. In the case of environmental work, additional
sets of safety issues must be addressed, especially if the hazardous materials are
highly toxic. Remediation work may require special and expensive clothing, res-
pirators, and equipment. If the contractor is not sure what will be required, the
bid price may be increased to cover these unknowns. Therefore, invite the contrac-
tors that bid on the project to see the site and have a clear understanding about
the work.
The whole market for environmental work has developed much slower than
most expected. There are several treatment, storage, and disposal (TSD) facilities
that were built expecting very large projects and large amounts of material to
be handled. They expected their services to be very important and unique, and
therefore charged high prices to cover the many unknowns they faced. Because
of good management by industry, these markets have grown slowly and are very
competitive. The costs to use TSD facilities continue to fall. It is important to
compare options and find the best fit for the company.
The cost of professional services are more likely to be negotiated now than
a few years ago. The conditions change, but by discussing the project with a
contractor and then working with the consultants to define a scope of work that
fits the needs, costs can be reduced. The cost can be negotiated based on the
work and the time frame needed to accomplish the work.
Part of the remediation work may be closing sites that were used in the past to
dispose of hazardous materials. The purpose of the closure is to stop any hazard-
ous material that may be deposited on the site from leaching into the groundwater
or from contaminating adjacent soils.
Regulations require that the cost of performing the site closure be estimated
as if an outside contractor would do the work. This will ensure that if the cleanup
must be managed by an agency, the agency will have adequate monies to complete
the work. Unfortunately, many consultants perform the cost estimates using
170 Chapter 7
standard methods and rules-of-thumb rather than dealing with specific sites. This
leads to excess costs for mobilization, per diem expenses, earth moving, etc. The
cost hurts twice as it is used to determine the size of the financial instrument
used for financial assurance.
Postclosure care is required for most sites, even in facilities that continue to
operate. If a hazardous disposal site is taken out of service, or if the agency
requires a site to be closed according to regulations, a postclosure care plan will
be required. Normally this requires a series of monitoring wells be placed around
the closed site to determine if a release of hazardous materials occurs from the
site in the future. The monitoring frequency and the chemicals monitored become
critical to the cost and to the amount of financial assurance needed.
The location of the facility and the site-specific risk assessment should be
central to renegotiating closure and postclosure activities. Agencies can be per-
suaded to follow a less aggressive program or allow leniency in the time frame
to reach cleanup standards when they are convinced that the project is being
well-managed and is under control. Closure and postclosure plans need to em-
phasize the management plan and how it will keep the site from becoming a
hazard to human health and the environment in the future.
After the first few years of monitoring, a reduced level of sampling and a reduced
chemical list can be negotiated with the agency, based on one or two years of
data that show that nothing is happening. If the agency will not agree in the
initial plan, sample for one or two years, gather good data, and obtain a revision
of the postclosure care plan to reduce the level of analytical work required.
VI. NOMENCLATURE
I. GENERAL OBJECTIVES
173
174 Chapter 8
A written contract is the document by which the risks, obligations, and relation-
ships of all parties are clearly established, and which ensures performance of
these elements in a disciplined manner. For the owner, the contract is the means
by which the contractor can be controlled, and ensures that the work and end
product satisfy the owner's requirements. For the contractor, the contract speci-
fies risks, liabilities, and performance criteria, and outlines the terms and con-
ditions of payment.
V. CONTRACT RESPONSIBILITY
The project manager should be responsible for the contract strategy that is
developed as part of the project strategy. However, the proposed division of work,
contracting arrangements, forms of contract, and bidder's lists should be devel-
oped in conjunction with the company's contracts department and the engineer-
ing/construction groups.
In the contracting process, dividing responsibility between the project man-
ager and the contracts department can lead to inefficiencies, disagreements, and
delays, since the organizational conflict can have a negative impact on the project
Contracting 175
cost and schedule. Close coordination and effective communications must exist
among all groups to ensure complete agreement and commitment to the proposed
contracting program. This is particularly important in all submissions to contract
committees and/or senior management.
The project manager must obtain agreement from the company's legal,
contracting, and insurance departments before committing to contractual lan-
guage regarding liability, indemnity, or insurance.
WORK/PROJECT
INITIATION • GOOD SCOPE DEFINITION
Identify
a Need
DEVELOP • QUALITY PLANNING
QUALITY
Conceive Solutions S.O.R.
and Son:
• EFFECTIVE APPROVAL/DECISION MAKING
Estimate and Feasibility I ???
Analysis
Large Project Approach
!• EPCTURNKEY CONTRACT*.
DESIGN
CONTROL
POINT "0 General Contractor • *
Estimate
Construction
Only
Invoicing
Expenditure
• ORGANIZATIONAL COMMITMENT
• PROJECT "DISCIPLINE"? ? ? ? ?
Fixed Reim- Fixed Reim- Fixed Reimb- Fixed Reim- Fixed Reim- Fixed Reim-
Price bursible Price bursible Price bursible Price bursible Price bursible Price bursible
C - Contrac or
a. Complexity of design O/E O/E Labor Relations L L
b. Completeness of O/E O/E
E - Engineer
engineering drawings a. Jurisdictional disputes C 0
S - Shared
c. Construction procedures C O/E b. Illegal strikes and walkoffs C 0
and methods c. Contract expiration strikes C 0 L - Low
KA KAckri'n tm
A. Introduction
Once the decision is made to contract, there is a wide variety of single or multiple
contracts from which the project manager may select a contracting strategy. These
fall into two major categories: fixed-price, in which the contractor has primary
cost responsibility, and cost-reimbursable, in which the company has primary cost
responsibility. Variations and combinations of these two types can be formed,
depending on the degree of risk assumed by either party. The three objectives of
cost, time, and quality must be placed in an appropriate priority, since tradeoffs
will probably be necessary in deciding on the specific contract.
If the contractor is to assume direct cost responsibility, a fixed-price contract
is appropriate. However, the total project time is usually longer with this type
of contract, since the project drawings and specifications must be more complete
before bids are solicited. The bidding time is longer as well.
Cost risks must be balanced against the need for speed—an increasingly
important aspect if borrowed funds are being used to finance construction in an
era of high interest rates. With a cost-reimbursable contract, it is more difficult
to predict the final cost, but shorter construction schedules can usually be a-
chieved. The schematic drawing contained in Figure 8.3 illustrates the wide range
of schedule tradeoffs that project managers must consider in formulating a con-
tracting strategy. The project manager can also specify the particular quality
objectives or other performance goals that are desired. Under either type of
contract, the level of quality must be established through the specifications.
In addition to the company's goals, the contractor's objectives should be
considered. On large and long-term projects, for example, a contractor is reluctant
to accept the risk of a fixed-price contract. On the other hand, if there is vigorous
competition for work due to economic or other reasons, contractors may readily
accept fixed-price contracts, which should result in lower bid prices.
As covered in the project strategy, the following are major considerations when
developing a contract strategy for the project:
When and how will the work be divided up? Should it be EPC turnkey or
separate EPC?
• How will the division of work affect client/project team/main contractor/ven-
dor/subcontractor interfaces? This division enables the project coordination
procedures to be properly prepared.
• What type of contract should be used? Segment the project into discrete
work packages to facilitate management, and subject the work packages to
available resources. Consider the contract philosophy, the type of contract
best suited to the project, contract interfaces, bid evaluation techniques, and
bid documentation. This enables the contract strategy to be produced in
liaison with the contracts department.
What roles are licensors and consultants expected to play? This allows
arrangements to be made for prequalifying suitable contractors, issuing
invitations to bid, evaluating bids, and making award recommendations.
180 Chapter 8
©L
• ENGINEERINC
r /
©1
f
1 REQUIRED /
• TO START
H CONTRACT
1
1
©1
¥
-1m
H
-ST/5 RTOF CONTRACT
f
f\
oon tct*T
I \ COMPLETION
1
(T)m 1
PROJECT DURATION
Are there potential conflicts of interest with other owner projects in con-
tractor offices, vendor workshops, or fabrication yards? Such conflicts can
have an impact on the bidder's list.
What is the availability of skilled labor? What is the local industrial rela-
tions climate at fabrication yards and the construction site? Lack of labor
can delete a contractor from the bidder's list.
What is the quality and availability of personnel to develop, evaluate, and
administer the required type of contract/contract conditions?
What is the total financial risk to bidder's financial strength?
Three principal types of contracts exist: reimbursable, measured (unit price), and
lump-sum. The following forms of contract are typical of these types:
• cost-reimbursable (time and materials),
• cost-reimbursable with percentage fee,
• cost-reimbursable with fixed fee,
• cost-reimbursable plus cost/schedule bonus and/or penalties,
• measured unit price (mostly construction),
• guaranteed maximum price, and
• lump-sum/fixed-price.
The objectives of cost, time, quality, risks, and liabilities must be analyzed and
prioritized, since tradeoffs will probably be necessary in deciding the type of
contract to be used.
Contracting 181
A. Reimbursable-Cost Contracts
These require little design definition but need to be drawn in a way that allows
expenditures to be properly controlled. The major advantage of a reimbursable-
cost contract is time, since a contract can be established during the early stages
of a project. This type of contract presents a disadvantage to an owner, however,
since poor performance by the contractor can result in increased costs and be-
cause final costs are the owner's responsibility. Further, the final or total invest-
ment level is not known until the work is well advanced.
Reimbursable-cost contracts can contain lump-sum elements such as the
contractor's overhead charges and profit, which is usually preferable to calculat-
ing these costs on a percentage basis. Reimbursements may be applied to such
items as salaries, wages, insurance and pension contributions, office rentals, and
communication costs. Alternatively, reimbursement can be applied to all-inclusive
hourly or daily rates for time spent by engineers on the basis that all office
support costs are built into these rates. This form of contract is generally known
as a fixed-fee or reimbursable-cost contract, and can be used for both engineering
and other office services as well as for construction work.
Such arrangements give the owner greater control over the contractor's
engineering work, but reducing the lump-sum content of the contractor's remu-
neration also reduces its financial incentive to complete the work economically
and speedily. Further, it lessens the owner's ability to compare and evaluate
competitive bids, since only a small percentage of the project cost is involved.
Finally, it is possible that the best contractor may not quote the lowest prices.
1. Requirements
• flexibility in dealing with changes (which is very important when the job is
not well defined), particularly if new technology development is proceeding
concurrently with the design;
• early start can be made;
• useful where site problems such as trade union actions such as delays or
disruptions may be encountered; and
• owner can control all aspects of the work.
3. Disadvantages
• contractor may assign its second-division personnel to the job, make excessive
use of agency personnel, or use the job as a training vehicle for new personnel;
owner carries most of the risks and faces the difficult decisions; and
• biased bidding of fixed-fee and reimbursable rates may not be detected.
Target contracts are intended to provide a strong financial incentive for the
contractor to complete the work at minimum cost and within minimum time. In
the usual arrangement, the contractor starts work on a reimbursable-cost basis.
When sufficient design is complete, the contractor produces a definitive estimate
and project schedule for owner review, mutual negotiation, and agreement. After
agreement is reached, these become targets. At the end of the job, the contractor's
reimbursable costs are compared with the target and any saving or overrun is
shared between the owner and the contractor on a pre-arranged basis. Similarly,
the contractor qualifies for additional payment if the contractor completes the
work ahead of the agreed-upon schedule. The main appeal this form of contract
has to the contractor is that it does not involve competitive bidding for the target
cost and schedule provisions.
1. Requirements
• competent and trustworthy contractor,
• quality technical and financial supervision by the owner, and
• competent estimating ability by the owner.
2. Advantages
• flexibility in controlling the work;
almost immediate start on the work, even without a scope definition;
economic and speedy completion (up to a point) encouraged; and
• contractor is rewarded for superior performance.
3. Disadvantages
• final cost initially unknown;
no opportunity to competitively bid the targets;
• difficulty in agreeing on an effective target for superior performance;
variations are difficult and costly once the target has been established
(contractors tend to inflate the cost of all variations so as to increase profit
potential with easy targets); and
• if the contractor fails to achieve the targets, it may attempt to prove that
this was due to owner interference or to factors outside the contractor's
control; hence, effective control and reporting are essential.
quantities, and the contractor assuming the risk of a fixed unit price. A quantity
increase greater than 10% can lead to increases in the unit prices.
/. Requirements
adequate breakdown and definition of the measured units of work,
good quantity surveying/reporting system,
• adequate drawings and/or substantial experience for developing the bill of
quantities,
• financial/payment terms that are properly tied to the measured work and
to partial completion of the work,
• owner-supplied drawings and materials must arrive on time,
• quantity-sensitivity analysis of unit prices to evaluate total bid price for
potential quantity variations,
ability to detect biased bidding and/or front-end loading, and
contractor experience with this contracting arrangement.
2. Advantages
good design definition is not essential (typical drawings can be used for the
bidding process);
very suitable for competitive bidding and relatively easy contractor selection
subject to sensitivity evaluation;
• bidding is speedy and inexpensive, and an early start is possible; and
• flexibility (depending on the contract conditions, the scope and quantity of
work can be varied).
3. Disadvantages
final cost is not known at the outset, since the bills of quantities have been
estimated on incomplete engineering;
• additional site staff are needed to measure, control, and report on the cost
and status of the work; and
• biased bidding and front-end loading may not be detected.
D. Lump-Sum/Fixed-Price Contracts
7. Requirements
2. Advantages
3. Disadvantages
variations are difficult and costly (the contractor, having quoted keenly when
bidding, will try to make as much as possible on extras);
• an early start is not possible because of the time taken for bidding and for
developing a good design basis;
contractor will tend to choose the cheapest and quickest solutions, making
technical monitoring and strict quality control by the owner essential; sched-
ule monitoring is also advisable;
contractor has a short-term interest in completing the job, and may cause
long-term damage to local union relationships by doing such things as
setting poor precedents/union agreements;
bidding is expensive for the contractor, so the bid invitation list will be short;
technical appraisal of bids by the owner may require considerable effort;
• contractors will usually include allowances for contingencies in the bid price
and they might be high; and
• bidding time can be twice that required for other types of contracts.
While the same risks/liabilities can be established for most forms of contract, the
price for those risks/liabilities can vary significantly, depending on contracting
skills and the business environment/market place.
Contracting 185
1. United Kingdom
Institution of Civil Engineers (ICE). Mainly for civil and construction-only contracts.
Federation Internationale des Ingenieurs-Conseils (FIDIC). Primarily for offshore
and overseas work.
Institution of Mechanical Engineers (IMechE). Primarily for design and erection of
mechanical plants).
2. United States
American Institute of Architects (AIA). Mainly for engineering work and project/
construction management; the architect/engineer usually functions as the
owner's agent on a fee/reimbursable basis;
Associated General Contractors (AGC). Mainly for construction work and con-
struction management; the contractor usually functions as an independent
contractor on a lump-sum/fixed-price basis;
The Engineers Joint Contract Documents Committee (E JCDC) Standard Agreement
Contract Documents. Issued jointly by the National Society of Professional
Engineers, American Consulting Engineers Council, American Society of Civil
Engineers, and Construction Specifications Institute, Inc., and approved by the
Associated General Contractors; often used by many engineering firms. In
addition, it is becoming more prevalent for an owner to develop a form of
contract that is specifically customized to fit its particular needs. Similarly, an
engineering/construction contractor may develop its own form of contract for
use on projects where it acts as the construction/project manager for the owner.
At least two basic options exist:
- use one of the standard contracts and customize it to fit a particular
project; and
use the boiler plate or front-ends developed by the engineer/contractor
for use on projects where it is responsible for preparing the bidding
documents and where the owner does not have its own form.
The owner must have the contractual right to exercise control adequate to
ensure the success of the project, but the temptation to assume excessive
control should be resisted.
Control and responsibility go together—the greater the owner's control, the
less responsibility is carried by the contractor.
Additional liability/risk should result in greater profit to the contractor.
Finally, the form of contract must be decided early in the course of project
development, and the choice must be made known to the engineers before
they write the specification. Obviously, the specification will be much more
precise and comprehensive if it is to be used for a lump-sum contract than
would be required for a reimbursable contract.
The risks accepted by the contractor through the contractual language can be
difficult to define in absolute terms. Still, the implied risks in practically any
contract, if not tempered by insurance, can drive a contractor into bankruptcy if
the risks become realities. A wide range of expertise in developing contracts,
coupled with the many vicissitudes of give and take in contract negotiations, can
yield contract provisions that range from minimal impact to possibly catastrophic
consequences for contractors. Thus, an owner's project manager can unwittingly
increase the project costs by being overly protective when using contract language
to require a contractor to assume risks over which the contractor has only
minimal control at best. Apart from refusing to bid, the contractor's only defense
is to carefully evaluate the risk and potential cost of the over-protection, and to
increase the cost of the proposed services accordingly. The market place, of course,
has an important bearing on risk and liability. When work is in short supply, it
is possible to get contractors to accept greater risks due to a very competitive
buyer's market. This also means that the buyer (owner) can dictate the contrac-
tual conditions to a much greater degree than usual.
Development of the form of contract and the contractual language may be
the direct responsibility of the contracts department, working under direction of
the project manager. In many cases, bid proposals will be reviewed by two groups
of company personnel—the project team and contract/legal personnel. The project
team has total evaluation and selection responsibility, but concentrates on the
contractor's project execution capability. This leave contracts/legal personnel to
advise on contract conditions, language, liability, guarantees, and other pertinent
areas.
Assuming the bidders are allowed to take exceptions and/or offer alternatives,
this essentially covers the following two objectives:
• detecting any deviations from the prescribed bid basis that would require
resolution before award of the contract, and
analyzing the contractor's exceptions to the proposed contract that could
affect the selection.
187
Contracting
The allocation of costs to the fixed-fee and reimbursable categories can vary in
a contractor's proposals. Even though the bid documents specify the required
division of costs, it is very difficult to cover every detailed cost element. Contrac-
tors will therefore provide terms and conditions that are clearly different or
ambiguous so as to allocate items as reimbursable when, in fact, they were
intended by the company to be part of the fixed fee. Following are examples of
areas in which this can occur.
1. Home Office Services
Contractor personnel policies should be thoroughly reviewed in relation to
the conditions outlined in the contract agreement. Are training and recruit-
ing reimbursable, or are they part of the fee? Are contractor-quoted salary
ranges fixed for the duration of the project, or are salary increases auto-
matically passed on to the company? Are travel expenses and proposed trips
subject to company approval before the fact or afterward? Are transfer and
assignment of overseas personnel subject to approval by the company?
• A common point of contention is payment for home office engineers tempo-
rarily transferred to the job site. The overhead on field personnel is generally
half that of home office personnel. What rate should apply?
• Is there adequate identification of the personnel and services that are in-
cluded in the fee and those that are reimbursable?
• Purchasing policies, vendor service personnel, insurance, duties, inspection,
and expediting services are costly items. Are adequate procedures contained
in the contract agreement?
Payment for reproduction and computer services should be thoroughly re-
viewed. Payment of costs for resident company personnel should be clearly
outlined. These would include offices, equipment, services, secretarial, and
typing assistance.
2. Construction Services
Personnel policies for construction staff are quite different from those for
home office personnel and need to be clearly stated in the contract agree-
ment. Such topics as jobsite allowances, home leave, completion bonus,
family and bachelor status, relocation, and replacement should be clearly
outlined, particularly on overseas projects.
Payment conditions for construction equipment, maintenance, small tools,
and consumables should be clear and not left open to interpretation, since
they can become points of contention. What is the relationship between
188 Chapter 8
Both parties need to carefully develop, evaluate, and agree on all risks that are
required and contained in the proposed contract terms and conditions. From the
owner's viewpoint, the major thrust will be to develop contract risks and liability
for poor performance/schedule slippage. As detailed in the contractor's proposal
section, the contractor must carefully review all documentation to fully under-
stand the scope of work, services to be provided, working conditions, and the
proposed reporting requirements/owner involvement. There must be strong com-
petitive market conditions for EPC turnkey contracts, which requires that a
sufficient number of qualified and competitive contractors be willing to bid.
Beyond these, the activity level in the relevant contract market must be such
that contractors need more work than is available to them under other, lower-risk
contracts. Then there is the people risk consideration: it is one thing to identify
the risks inherent in a specific project, but it is quite another matter to properly
analyze the competence of company personnel to properly handle those risks.
Recognizing personnel capabilities and limitations is essential with an EPC turn-
key contract, especially from the contractor's viewpoint.
Contracting 189
Project size must be acceptable so that contractors have the financial strength
to bear the risks. There must be stable economic, political, and social conditions
at the project location, as well as for the relevant materials, equipment, and
labor market conditions. This is required in order to minimize the need for
bidders to include large risk contingencies.
C. Estimating Capability
The ability to produce a ±10 to 15% estimate is essential. This requires historical
experience/data, a quality estimating program, and experienced estimators. Own-
ers will use the estimate to evaluate the contractor's proposed price, and con-
tractors will use the estimate to establish the price.
An appropriate, detailed execution program is essential in developing a
detailed estimate. The anticipated working conditions should be carefully evaluated,
and organization requirements and schedules should be developed. The estimate
should be based on quotations for all major equipment. Bulk materials should
be estimated with quantity takeoffs from plot plans, P&IDs, layout drawings,
and specifications. Engineering jobhours and costs should be based on numbers
of drawings/documents. Direct construction labor should be estimated from equip-
ment/material quantities multiplied by unit jobhours multiplied by jobhour labor
rates. Construction indirect such as construction equipment, supervisory/admin-
istration staff, and field office expenses, should be individually estimated.
D. Cost of Bidding
Since these systems can sometimes take many months before they become
effective, it is possible that a certain percentage of the lump-sum price or fixed
fee could be made available at contract award. The contractor may propose the
figure and provide an explanation to justify it.
C. Front-End Loading
This practice applies to unit-price contracts where the purchaser adds more profit
to the early work activities by reducing the profit of later work items. As the
work starts and progresses, the bidder earns additional profit and greatly improves
its cash flow. There is also an added work risk to the purchaser, in that if the
bidder defaults on the contract, the remaining funds are insufficient to complete
the work. Again, negotiation should attempt to reduce or eliminate this practice.
There are two forms of low bidding: the deliberate low bid, and a low bid produced
by lack of experience and/or a poor purchaser bid package (see next section). By
definition, a low bid is less than the purchaser estimate by 20% or more. Since
192 Chapter 8
Apart from performance problems, there is the legal risk of the process of cer-
tainty, which requires that the purchaser make certain that the other party fully
understands the scope of work. When there is a lack of experience, lack of
certainty can be a direct result. Thus, clarification meetings and further technical
analysis of the proposed bidder's programs are essential. If lack of certainty is
present, the award of a low bid can be rescinded or can lead to successful claims
by the bidder.
Cost and Schedule Trend Analysis-
Forecasting of Baselines
The project manager is directly responsible for creating an environment that will
enable project control to be properly exercised. Thus the project manager must
seek counsel, accept sound advice, and stretch cost/schedule personnel to the
extent of their capability. Team building and team stretching are key elements
of successful project management.
On smaller projects, where the project manager is also the project control
engineer, it is essential that the project manager possess project control skills
and/or motivate the supporting/service groups to provide the quality information
that is needed for creative analysis and effective decision making.
Effective project control requires the timely evaluation of potential cost and
schedule hazards and the presentation of recommended solutions to project man-
agement. Thus the cost/schedule specialist must be a skilled technician and also
be able to effectively communicate at the management level. Sometimes, an
experienced project control engineer's performance is not adequate because of
poor communication skills. Technical expertise will rarely compensate for this
lack. As in all staff functions, the ability to sell a service can be as important as
the ability to perform the service. On larger projects, project teams are usually
brought together from a variety of melting pots, and the difficulty of establishing
effective and appropriate communications at all levels should not be underesti-
mated. In such cases, the project manager must quickly establish a positive
193
194 Chapter 9
V-it —
\ V
\
E. A Cost-Effective Program
All project control programs must live up to their own principles and be cost
effective. Many large and allegedly sophisticated architect/engineering firms and
contractors over-control and over-report. This occurs because of the ever-present
tendency, as projects become larger or more complex, to create additional levels
of control, reporting, and personnel. Yet more is not necessarily equivalent to
better. Project managers and project control supervisors must carefully evaluate
their company's program against project needs, eliminating all instances of over-
control and over-reporting.
The initial step is to ensure that key decisions makers—the project manager, the
engineering manager(s), the procurement/contract manager, and the construction
manager—base their decisions on sound business practice. When these people
are not motivated by a solid business ethic, cost overruns and schedule delays
become both common and inevitable.
B. Business Information/Analysis
The second step is to ensure that all information needed for making sound
decisions is available at the right time and in the right place. All too often, the
information necessary for analyzing options and alternatives is not available or
simply hasn't been developed. Yet much of this information can be found in a
firm technical scope of work, a quality estimate, and a good schedule. When these
items are not available, decision-making may be flawed or ineffective.
The early stage of a project is often the time when significant business
decisions have to be made; consequently, having quality information is vital at
that point. Yet firm information may not be available at this point: technical
196 Chapter 9
options are still being considered, and execution plans and contracting strategies
are still being developed. Creative analysis and experienced judgment is, there-
fore, essential to bridging this gap, sometimes referred to as the blackout period.
This is discussed at greater length later.
C. Communication Channels
The third step involves the project manager's responsibility for actively promoting
project consciousness with all involved departments and key personnel. This
ensures that the project team and/or service groups work toward the agreed
project objectives and execution plan. Active and open communication channels
are also critical to properly coordinating and interfacing with the client to estab-
lish a positive atmosphere for making decisions and obtaining approvals. Limits
of authority, lines of communication, degrees of responsibility, and approval re-
quirements must be clearly established in the project coordination procedures.
Personnel motivation and leadership skills are essential qualities in a project
manager if project consciousness and effective communication channels are to be
established.
A. Typical Program
As most operating company accounting systems are commodity based, they are
unsuitable for project accounting. Therefore, an effective organizational arrange-
ment is to establish a project cost accounting group within the general accounting
department but with a cost coding system that is project driven. The group
concentrates solely on accounting for capital projects and reports directly to
project management for day-to-day activities. It is, however, often difficult to
establish such a group, as accounting managers, fearful of losing authority, may
resist the project approach. A more common and less efficient approach is to have
the project group develop a second set of books and associated coding system,
which is then maintained by project/cost personnel. It is to be hoped that such
Cost and Schedule Trend Analysis 197
A difficult time for cost control occurs during the transition from the feasibility
estimate to the full funding estimate. This is often called the blackout period,
during which time the estimate is upgraded to a higher quality (but is still a
conceptual estimate) and on large projects this period can last six months or
longer. During this time, many engineering decisions are made without full
recognition of their cost impact. Accordingly, having an effective and cost-conscious
project team is absolutely vital, so that full and proper trending of project-design
development and project change is generated by all to all. Cost-consciousness,
especially on large and complex projects, can only be achieved by direct leadership
of the project manager, in conjunction with a highly effective team building
program. The weekly trend meeting then builds on this program with detailed
development and analysis of all change.
4. PROJECT/CONTRACTUAL CONDITIONS
• Plant Operations
• Breach of Contract
• Site Conditions
7. POTENTIAL TRENDS
• Early Identification Can Prevent OR
• Assessment of Cost Increase/Schedule Slippage
Of the many meetings held during the execution of a project, the weekly trend
meeting is probably the most important. This is not a decision-making meeting
but a time when information is gathered and shared by key technical/services
specialists. The project manager generally leads the meeting, and the project cost
engineer often serves as secretary. All current and potential influences, changes,
extras, and trends are reviewed and discussed. The key meeting objective is the
o
I
a
I
Description
(All Costs Shown in 1.000's)
i
a
>
(/>
55'
The end products of an effective project control program are accurate cost and
schedule forecasts. These forecasts generally consider:
• current trends of time and money;
• scope deviations, changes, and claims;
• changes in project conditions;
• changes to the project execution plan;
• rundown/usage of contingency;
• failure to meet contractual conditions;
• engineering and construction progress/productivity;
• subcontractor dollar performance;
• equipment/material bid experience (under and over budget);
• actual versus planned commitment levels;
• cost escalation factors;
currency exchange rates; and
• impact of changes in governmental-environmental regulations.
The following techniques are at summary, intermediate, and detailed levels. Their
use will depend upon the contracting arrangements and associated risks to the
parties (owner, general contractor, subvendor) in conjunction with each party's
skills-capability and the need to work at summary or detailed levels. It is some-
times the case that a project need is not matched by a party's skills or, alterna-
tively, abundant skills can result in over-control and reporting.
1. A Slush Fund
On many projects the contingency is the largest single cost item. It should,
therefore, be an item that is constantly and carefully evaluated. Rarely is this
the case, as too many project managers treat contingency as a slush fund. This
occurs when a project manager uses the contingency to balance the monthly plus
trends, without properly evaluating the plus trends with a good risk analysis
program. To reduce the contingency by the amount of the plus trends in order
to maintain the previous monthly cost forecast can be a dangerous technique. In
such cases, it is quite common for the contingency to be spent well before the
project ends. Contingency is, essentially, to be used for unknowns, and these
unknowns only become known when commitments are made. It is then that the
cost reality and validity of the estimate-project budget becomes apparent.
Cost and Schedule Trend Analysis 201
This simple but practical method covers risk on work yet to be com-
mitted and work committed but not yet paid for.
2. Rundown Routine
Figure 9.4 represents a simple but effective calculation routine to run down the
contingency over the life of a project. The calculation process shows a rundown
that is calculated on the basis of risks inherent in uncommitted and unspent
costs. The computations are made as shown in the figure.
This simple and practical method covers risk on work yet to be committed
and work committed but not yet paid for. The basic presumption is that, until
the last and final invoice has been paid, there is still a risk that cost increases
will occur, quite often due to late, missing, or lost invoices. Construction labor
and subcontracts are usually the most volatile items and, as shown in Figure
9.4, carry the greatest contingency percentage. The maximum contingency that
this set of numbers will develop is 13%, and such a low percentage is too low
for controlling a conceptual estimate/project budget. Alternatively, if the project
had a detailed estimate with a 10% contingency, then the illustrated percentages
should be reduced. This set of numbers, which is based on historical data, is
appropriate for use in a project control estimate where the contingency is gen-
erally in the 12-15% range.
3. Startup/Commissioning
A further risk consideration is the amount of contingency required at mechanical
completion to ensure that funds are available for late changes, commissioning
202 Chapter 9
accidents, material startup requirements, and final invoices or claims that were
not anticipated earlier. If adequate funds have already been allowed in the
estimate for these considerations, then further hold-back would be unnecessary.
7. General Objectives
The major objective of cash advances and the bank handling procedures is to
ensure that the project is funded by the responsible party in accordance with the
contract. On reimbursable-type contracts, a cash flow forecast is usually prepared
for a two-month period and presented on a biweekly basis for cash advances. A
good forecast should generate no more than a 5% excess requirement. Payments
terms for a lump-sum contract usually require an initial payment (approximately
10% of the contract value) at contract award, followed by monthly payments
directly tied to the physical progress of the work. Progress is mutually verified
and agreed upon.
2. Documentation (Reimbursable-Type Contract)
As soon as practical after the last day of each month, the contractor should
prepare a complete statement of the amounts actually paid. This is supported by
copies of invoices, payrolls, bank statements, and properly executed waivers of
lien for each contractor and subcontractor.
3. Banking Arrangements (Reimbursable-Type Contract)
A commonly used banking arrangement is the zero bank account system. This
assumes that the contractors do not finance the project and that owners are
required to advance sufficient funds (in accordance with the cash flow forecast)
to the contractor's bank. Interest accruals will be credited to the owner. This
procedure should form part of the contractor's proposal and should specify pen-
alties to the owner for failure to provide timely funding.
Figure 9.5 depicts a typical format for a project total cash flow curve, showing
planned and actual cumulative curves on a monthly basis. The planned curve
should be evaluated every month to ensure accuracy of the short-term (three-
month) forecast compared with the overall budget. This curve, plus appropriate
backup, should be presented for approval on an agreed periodic basis.
1. Overview
When overall percent complete for a combination of unlike work tasks or for an
entire project must be determined, an essential technique called the earned value
system (EVS) is used. (The terms achieved value, accomplished value, or physical
quantity measurement can also be used). A project's budget is expressed in both
jobhours and dollars, and earned value is keyed to the project budget. Most
projects are constrained by fixed budgets; others have floating, or variable, bud-
Cost and Schedule Trend Analysis 203
PROJECT
PROJECT CASH FLOW CURVE
JOB NO.
REPORT NO.
DATE
REVISE BUDGET ,
BUDGET
1
{
REPORT
DATE
1
FORECAST y / S
$ MECHANICAL
COMPLETION
>
TO DATE / g
PLANNED / J
. • i ^ ^ ^ T O DATE
^ ^ ^ ^ ACTUAL
1 1 1 1 1 1 1 1
TIME • (PROJECT DURATION)
REMARKS
EXPENDITURES
THIS PERIOD
TO DATE
CURRENT BUDGET
FORECAST
gets. Earned value techniques can be applied in both situations, although differ-
ences exist in the detail of application.
2. The System
When developing a control system, a project should be segmented into its con-
trollable parts. A work breakdown structure (WBS) is developed, which includes
all work tasks to be used in determining project progress. Each task should have
its own dollar and jobhour budget. A project cost breakdown structure (CBS) is
204 Chapter 9
created by adding to the WBS all other project accounts that have either a cost
or a cost and jobhour budget, but which are not used to measure progress (e.g.,
management, quality control, or administration). In other words, the WBS is
incorporated within the CBS.
Under an earned value system, a direct relationship is established between
percent complete of an account and the budget for that account. This relationship
is expressed by the following formula:
Earned value = (Percent complete) x (Budget for the account)
As can be seen from this equation, a portion of the budgeted amount is earned
as a task is completed, up to the total amount in that account. One cannot earn
more than has been budgeted. For example, if $100,000 and 600 jobhours have
been budgeted for a given account, and the account is 25% complete, $25,000 and
150 jobhours have been earned to date.
Since progress in all accounts can be reduced to dollars and earned jobhours,
earned value provides a way to summarize multiple accounts and to calculate
overall progress. The formula for doing this is:
p f if Earned jobhours or dollars all accounts
Budgeted jobhours or dollars all accounts
1. Introduction
The concepts just discussed provide a system for determining the percent com-
plete of either single or combinations of tasks. The next step is to analyze the
results and to determine if the work is proceeding according to plan. The earned
value system allows such an analysis.
2. The System
To the budgeted and earned jobhours or dollars must be added actual jobhours
or dollars, since it is a combination of these three measures that provides a full
analysis. The earned value system defines these terms as follows:
• budgeted jobhours or dollars-to-date represent what is planned to be done.
This is called budgeted cost of work scheduled (BCWS).
• earned jobhours or dollars-to-date represent what was done. This is called
budgeted cost of work performed (BCWP).
• actual jobhours or dollars-to-date represent what was paid for. This is called
actual cost of work performed (ACWP).
Schedule performance is a comparison of what was planned to what was done.
In other words, jobhours were budgeted and earned. If the budgeted jobhours are
less than the earned jobhours, more was done than planned, and the project is
ahead of schedule. The reverse would place the project behind schedule.
Performance against budget is measured by comparing what was done to
what was paid for. To do this, earned jobhours are compared to actual jobhours.
If more was paid for than was done, the project is over budget.
Cost and Schedule Trend Analysis 205
or = BCWP + ACWP
A positive variance and an index of 1.0 or greater denotes favorable performance.
Figure 9.6 a plot shows the relationships between BCWS, BCWP, and ACWP
Other earned value systems are covered later in this chapter.
This allowance, identified as a separate line item in the estimate, is not part of
contingency. It is a known condition that is very common on fast-track projects
and represents money that will be used to cover design changes after an equip-
ment purchase has been made. The fast-track approach requires early placement
of all critical equipment, even before the design has been completed. As the design
advances to completion, changes can and do occur to the already-committed
equipment. This, then, leads to change order requests from the equipment ven-
dors. The design allowance is used to cover these added costs.
^—»••—»**<>
^ ^
Budgeted - BCWS
3
O
#™
3r Work-r
I SV
j cv
sv = Schedule Variance
cv = Cost Variance
AT = Time Variance
Time, Days
Figure 9.6 Relationships between BCWS, BCWP, and ACWP.
206 Chapter 9
DESIGN ALLOWANCE
ENG INEE *ING PRO IRES 3/CO WPLE TION
—100
95% I X at 8C
90 ENGINEERING * £"oinee ring
1. Process lOO.O
80%
f ^ 2. Clvll/Structural/Arch'l. 90.0
80 3. Vessels <»«; n
4. Mechanical E q u l p a e n t . . . , 95.0
f
5. P l p l n g d n c l . model) 75.0
70 6. Electrical 60.0
7. Instrumentation 55.0
8. General/Misc 70 0
60
J' INS ENT ENGINEERING TOTAL JiO.O
% 5 0 1 I
ELE :TRI /AL
•;••• ST ART OF
l-
40
MA TERI \ L
30
£ES \ EQI *
• « • • PU RCH> ,SINC
20
y
0
10 20 30 40 50 60 70 80 90 100
•
80
60
%
40
20
0
V.V.V.V.V.V.V.V.V.'.V.V.V.
10%
curves for a full, economic fast-track program. The top curve shows the historical
engineering progress curve, with separate material category bars for the start of
purchasing. The lower curve is a guide to indicate the percent of design allowance
that should be available as engineering advances. The example assumes that
design allowance has been estimated at 10% (of total equipment), and the curve
shows the allowance being run down to zero at 95% completion of engineering.
At that stage, no risk of design changes should exist. The control of design
allowance is by both procurement and engineering. This technique is also covered
in Chapter 3 as it relates to estimating.
1. Purpose
As construction approaches mechanical completion, an efficient rundown can be
difficult to achieve, especially if a contractor has low workload and does not want
to lay off staff. On large projects, this situation can be particularly serious and
lead to increased costs. Moreover, the earned value system is ineffective at this
point, since the weight of accumulated performance now obscures incremental
performance. As punchlists and completion lists are generated, it is difficult to
ascribe a measurable scope of work to a multitude of different items, many having
top priority for completion. One effective technique for reducing these problems
is shown in Figure 9.8. It involves preparing a detailed estimate of the remaining
work items, with work activities/punchlists, and then individually controlling, by
item, on a daily/weekly basis. The figure graphically depicts a rundown program
for direct labor on a reimbursable project. In addition to field labor, other costs
must be considered as well.
2. Material
At this stage, field-purchased material usually reaches a peak, due mainly to
design changes and rework. An estimate of these expenditures should be made,
with planned dollar expenditure curves drawn for major categories and actual
expenditures plotted.
3. Subcontracts
Direct-hire forces can be replaced at this time, and the remaining work completed
under subcontracts. The subcontracts are often awarded on a time-and-material
basis, making dollar expenditure curves the only way to retain proper control.
There is also the need for closing out the regular construction subcontracts, many
of which may require settlement of claims and extras. Resolution of these items
requires time and attention.
Figure 9.9 depicts a typical monthly cost report. This is a summary report and
should list major accounts or cost centers. Columns 1 and 2 contain committed
and expended costs. Columns 3, 4, and 5 cover the original budget, updated with
approved changes. Columns 6 and 7 carry the forecast and variance of forecast
to the current budget. The same format can be used for detailed as well as
summary-level reports. The monthly cost report is a key management document
and, as such, should be timely, accurate, and readily communicate an overall cost
evaluation.
Figure 9.11 shows incremental and cumulative curves for overall home office
jobhours. Planned curves should be developed, and actual experience plotted on
a monthly basis. This example shows a significant overrun against the plan as
of month nine. Evaluations of individual elements of the home office confirm that
the overrun is irrecoverable; therefore, a final overrun is forecast. With a curve
format, this trend was really discernible in month six. Depending on the accuracy
ro
©
PROJECT
JOB NO
PERIOD
i
CO
Cost and Schedule Trend Analysis 211
PROJECT
PROJECT FINANCIAL REPORT
JOB NO.
REPORT NO.
COMMITMENTS AND EXPENDITURES
DATE
PROJECTION
120
FORECAST mmmmmmm0
mmut ••••
r
_i_j-
1
100
Q .;
CO CONTROL BUDGET g.J
v
A
- \ / CURRENT BUDGET
\ \ "
8 f
V /K
COMMITMENT f
f
40
/ EXPENDmJRE
20 /
/ /
YEARS
of the planned curve, a potential overrun, evident in month six, becomes a reality
by month nine.
Nevertheless, in this particular example, a jobhour overrun does not neces-
sarily mean a cost overrun. It is possible (though not probable) for an underrun
in expense budgets and personnel costs to compensate for an overrun in jobhours.
Consequently, it is also important to monitor jobhour costs as well as jobhours.
Figure 9.12 shows planned and actual expenditure curves of home office costs.
Planned curves are developed by judgment and historical experience and can be
compiled from profiles of more detailed elements.
CONTRACTOR'S NAME
PLANNED
CO
o
MECHANICAL
Id
> COMPLETION
3 PLANNED
ACTUAL
FORECAST
CD
PROJECT
REPORT NO.
DATE
FORECAST PROJECTION
CONTROL BUOQET
•
!
i—
\ j
CURRENT BUDGET
A
*•••'
i
DOLLARS
/
PLANNED / f ACTUAL
Trend curves are widely used, as shown in the engineering, procurement, and
construction sections that follow.
This report is The Report, as it contains the total status of the project, current
problems and future predictions. It needs to be comprehensive, but concise and
dynamic so as to fully recognize all aspects of the work. An effective and efficient
monthly report requires much experience and skill to produce. It should include
a list of current problems, critical activities and narratives of cost and schedule
status, progress curves, productivity curves, and personnel histograms for engi-
neering, procurement, and construction. The composition of the monthly progress
report is so important that it should be a matter of much discussion and agree-
ment between all the major project parties immediately following contract award.
As this report is generally the direct responsibility of the managing contractor,
its contents should have received attention during the precontract negotiations.
If the contract were lump-sum, the negotiations should have been very detailed
and the report contents a matter of contractual agreement. On reimbursable
projects, the discussions and agreement can take place after contract award.
Narratives for the reporting period should include status, trends, and crit-
icality. Significant cost and schedule deviations should be highlighted. Actions
should be proposed for remedial action. Where recovery is not possible, a cost
and schedule impact evaluation should be made.
A minimum package for the monthly report should include:
• executive summary;
• project cost report;
• project status report:
- engineering progress,
- material commitment progress,
- construction progress,
- engineering productivity and personnel curves, and
- construction productivity and personnel curves;
• project master scneauie;
• subcontracts report (if the project has major subcontract elements);
• trend report; and
• contingency rundown curve.
A brief narrative should:
• outline the progress for the period, the cost status, deviations, and trends;
• highlight critical activities; and
• provide a forecast of cost and probable schedule completion.
The executive summary is the key to a quality report; it must be short,
sharp, and attention-getting. Also, maximizing graphical content of the monthly
cost and progress reports will enable management to more quickly absorb the
status, trends, and forecast for the project.
Cost and Schedule Trend Analysis 215
In addition to a weekly activity report (major and critical items) and the detailed
monthly cost and progress report, a brief monthly report should be produced for
executive management. This is a vital document as it is probably the only project
document that is studied by senior management and it can, therefore, obtain or
lose executive management attention and support. Figure 9.13 illustrates a suitable
one-page report. The report should be written in a terse style and should include:
• concise, but complete, financial statement;
• brief report on project progress versus predicted schedule; and
• description of any anticipated delays.
• If appropriate, the executive summary of the monthly cost and progress
report can be added to this report.
Each monthly report should reflect a complete statement of project status
and should not rely on previous reports for a detailed picture of the financial
and schedule status. Actual versus planned progress curves for engineering and
construction should be known.
N. Backcharge Register
Charges against vendors or contractors for extra work can be significant. Backcharges
result from poor vendor-contractor workmanship, schedule delays, lack of resources,
failure to clean up, etc. Accurate record-keeping and documentation are vital.
Several important points should be observed regarding backcharge admin-
istration:
Documentation. All pertinent costs associated with backcharges should be re-
corded and updated regularly;
Early notification. The vendor or contractor should be advised in writing of a back-
charge, including an estimate of the associated cost, as soon as possible; and
Cost forecast. The actual cost should be discounted when taking credit for po-
tential recoverable backcharges in a cost forecast, since full recovery is very
unlikely, often falling in the range of 20-40%.
Figure 9.14 illustrates a typical backcharge register. The data compiled on this
form can be used for:
• assessing the financial impact on project costs as backcharges are settled
with vendors, and
highlighting problem vendors and contractors for quality control purposes.
The greatest proportion of design changes (in-scope and out-of-scope) will occur
during the engineering phase. These changes can impact on all or many phases
216 Chapter 9
FINANCIAL
AFEEST1MA T E - DATE
REVISED A F E - DATE
REVISED A F E - DATE
SCHEDULI
ORIGINAL A FE SCHEDULE REVISED TO DATE
REV6EDTC DATF.. REVISED TO DATE
CONTRACTOR
CONTRACT BASIS
PROJECT STATUS-COMMENTSJ
_E NF:FF [fyj 9r pi IP N
1Afl
90
80
70
60
50
40
30
20
10
PROJECT COST
ESTIMATE
COST CONTROL
PROJECT SCHEDULE
PROCUREMENT
CONTRACTING
STRATEGY
CONSTRUCTION
3. HISTORICAL EXPERIENCE
2. ACTUAL V ESTIMATES
3. TRAVEL , REPRODUCTION . COMMUNICATIONS
AVERAGE RATE
BUDGET
1. BY MAJOR GROUPS AND TOTAL
2. ESTIMATED V ACTUAL
QUANTITY CONTROL
— :
- 1. BY MAJOR CATEGORY
The objective of the engineering change log (see Fig. 9.15) is to track changes
and their cost impact. This log is a vital part of the project trending program
220 Chapter 9
Good evaluations and quality bid tabulations are essential for effective cost
control. Preference choices with accompanying cost additions should be thoroughly
investigated. Compatibility with existing plant equipment, ease of maintenance,
and operating costs are appropriate requirements for equipment selection. All
cost differences generated during the technical review should be brought to the
cost engineer's attention.
PROJECT
JOB NO.
JOBHOUR EXPENDITURE CURVES - ENGINEERING
—
REPORT NO.
DATE
POTENTIAL
| OVER RUN
_ BUDGET
REVISED ESTIMATE
REPORT PERIOD §
i
a
MECHANICAL >
COMPLETION
1
1
55"
t REVISED ESTIMATE
JOBHOUR
TOTAL ACTUAL A
y
^' ' ^^ORIGINAL PIPWG PLAN
£ROCESS ACTUAL
This method is used on small projects where separate curves and jobhour rate
profiles are not cost effective. Figure 9.19 shows planned and actual trend curves
PLANNED RATE
ACTUAL RATE
^^
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 2 4
I 1993 I 1994
MONTHS
Figure 9.18 Engineering jobhour rate curve.
Cost and Schedule Trend Analysis 223
PROJECT
ENGINEERING COST CURVES
JOB NO.
REPORT NO.
DATE
BUDQET
FORECAST/ / 1
•'•'A
/ /
MECHANICAL
COMPLETION
$
' / TO DATE
TO DATE M / PLANNED
/
REPORT
DATE
1 1 1 1 1 1 1 1
TIME m* (PROJECT DURATION)
REMARKS
EXPENDITURES
THIS PERIOD
TO DATE
CURRENT BUDQET
FORECAST
for total engineering costs. A planned curve should be developed with judgment,
using the engineering schedule and related historical data.
This example shows actual expenditures following a similar profile as planned
but consistently at a higher level. It is, therefore, reasonable to predict a final
overrun with a projection following the same rundown profile but starting from
the actual value (overrun) at the month twelve reporting date.
224 Chapter 9
Figure 9.20 illustrates a very efficient and concise format for reporting the status
of engineering. The report graphically depicts the trends of the three significant
control elements: physical progress, productivity, and labor. Because of its strong
graphical message, this is a powerful report for senior management and other
project supporting groups. The same report format would be effective for major
design disciplines on large projects.
Figure 9.20 shows progress slipping, leading to a possible schedule overrun
and added costs. The actual labor requirement has greatly exceeded the planned
level in conjunction with a low level of productivity. It is probable that engineering
jobhours will overrun substantially.
The key elements for effective control of engineering are a firm process design,
jobhour estimate based on the number of drawings, labor curves, and a physical
earned value measurement system that tracks progress and productivity. Figure
9.21 contains a flowchart of an engineering scheduling system that is based on
these key elements and is a recommended program for larger projects.
The earned value system is the most effective method of all project control tech-
niques, but it is also the most expensive. As such, it is only used on intermediate
or large projects. Figure 9.22 shows a typical format of an engineering progress
and productivity report. In this example, the columns (by number) contain:
Column 4. An assessment of physical completion of drawings and documents, by
discipline and/or department, where work in progress is evaluated using the
guide outlined below;
Column 5. Weighted factor, based on budgeted hours for each discipline or de-
partment (weighting will not change for minor revisions to the budget);
Column 6. Weighted percent complete, determined by multiplying physical com-
pletion times the weighted factor (Column 4 x Column 5); addition to the
bottom line total will give overall engineering progress;
Column 7. Earned jobhours, an allocation of budgeted hours based on physical
completion (Column 3 x Column 4);
Column 8. Jobhours expended, the actual jobhours charged to the work;
Column 9. Productivity, the actual jobhours divided by earned or budgeted hours
(Column 8 -s- Column 7); and
Columns 10, 11, and 12. Used for historical records if necessary.
The stages of completion given in Table 9.1 are a guide to determining the percent
complete of specifications or drawings. These percentages are determined by
discipline supervisors. The guide covers only drawings and specifications. Other
items (such as coordination and supervision) within the engineering scope are
PROJECT
JOB NO.
REPORT NO.
ENGINEERING STATUS REPORT DATE
PLANNED PROGRESS
ACTUAL PERCENT
PROGRESS
BUDGET
«-u^ _, CUMULATIVE
Initialy poor performance ACTUAL
due to learning experience
Revised
O due to poor performance * ^~ ~^N
V-
LAB
PLANNED
LABOR N
r \
>
X
v. ACTUAL \ % v
LABOR %%% \
T
THESE PRODUCBJ FOR (pWTCAUPEAKlPERKX) ONLY
UST OF CRTTTCAL
VENDOR DWGS. * 18. 17. 16.
I WEEKLY
ByUnfXnd
Tofal Weekly
h
II
II
By Unit
•-n 11
j By Section Weakly j
I OrBHWeeklytoauel
I I
, 11 •« i
LABOR REPORT
CONCRETE CURVES SO CURVES
i
a
t
0)
TOTAL
%
complete
Specifications
Complete draft 20
Write specification 70
Check specification 85
Issue for approval 85
Issue for construction 85
Issue revisions as required 95-100
Architectural drawings
Complete sketches and general arrangements (GA) 15
Issue sketches and GA for approval as required 25
Complete drawing 75
Issue for approval 85
Issue for construction 90
Issue revisions as required 95-100
Civil drawings
Complete preliminary site plan (building locations and site elevation) 10
Issue preliminary site plan for approval as required 25
Complete design calculations 30
Complete drawing 80
Issue for approval 85
Issue for construction 95
Issue revisions as required 95-100
Concrete and foundation drawings
Complete design calculations 25
Complete drawing 60
Check drawing 85
Issue for approval 90
Issue for construction 95
Issue revisions as required 95-100
Steel and superstructure drawings
Complete design calculations 25
Complete drawing 60
Check drawing 85
Issue for approval 90
Issue for construction 95
Issue revisions as required 95-100
Cost and Schedule Trend Analysis 229
complete
Electrical drawings
Complete design calculations 15
Complete drawing 75
Check drawing 85
Issue for approval 90
Issue for construction 95
Issue revisions as required 95-100
Instrumentation drawings
Complete design calculations 50
Complete drawing 70
Check drawing 85
Issue for approval 90
Issue for construction 95
Issue revisions as required 95-100
Mechanical general arrangement drawings
Complete design calculations 15
Complete preliminary GA drawings 20
Issue preliminary GA drawings for approval 40
Complete drawing 65
Issue for approval 75
Issue for construction 80
Issue revisions as required 95-100
Mechanical and piping drawings
Complete design calculations 10
Complete drawing 65
Check drawing 85
Issue for approval 90
Issue for construction 95
Issue revisions as required 95-100
Flow sheet drawings
40
Complete design calculations
60
Complete drawing
70
Check drawing
80
Issue for approval
95
Issue for construction
95-100
Issue revisions as required
230 Chapter 9
not so easily quantified. These should be treated as below the line items and
given the same measure of completion as the quantified work.
Figure 9.23 shows a detailed and efficient format for reporting the status of
engineering/drawings. The report covers progress, schedule, and jobhours. It
provides source information for the project report documents and for evaluating
engineering progress. Individual drawing and document status is evaluated by
discipline supervisors. Due to schedule pressure and over-optimism, it is common
for engineering supervision to overstate the progress of the work, therefore it is
essential that the numbers be verified.
The curves shown in Figure 9.24 monitor overall cumulative engineering prog-
ress. Actual and forecasted progress are shown relative to the original or revised
schedule curves. Overall progress is compiled from the individual curves devel-
oped for each engineering discipline. Progress should be physical measurement
based on completion of drawings and engineering documents, in accordance with
the techniques outlined above.
Work unit tracking curves for production drawings provide a substantial
part of the data needed to assess overall engineering progress. Jobhour expendi-
ture can be a poor basis for reporting progress; it is, however, a temporary
alternative that can be used until drawing and document quantities are known.
IAT" 1
ENGINEERING/DRAWING STATUS REPO RT
A?
COMPUTION DATES % COMPLETION XJDGE1 ACTUAL
ACCT. ACT./ ACTIVITY START REMARKS
ORCNa DATE ORKL REV. flEV. 10 20 30 40 50 60 70 80 90 100 HOURS HOURS
CO
I
s o
A
S
s <5"
S
A
S
A
S
a)
A
S 3'
A
s
A
S
A
S
A
S
A
S
A
S
A
S
A
S
A
is:HIED FOR: CONTRACT NO. SECTION REPORT NO. STATUS AS OF TOTAL THIS SHEET
4 -/mwu
c - COKSTWCTKH CUSTOMER
1- K S i C N GRAND TOTAL
M DRAWING NO. SHT.NO. DATE DEPT.
t -rmausi PLANT compled by
Q-ownnoii
irUHI
90
X^-^FORC •CAST
RE VISEC> SCI-EDUL E —-i J
fr 1
/
cRiGir IAL_S CHEO ULEr:
f
ACTl AL !
% PHYSICAL PROGRESS
I
/
|
MONTHS"
E.
0)
O
(D
a
o
1 i i
Ia
1
i
0 UGIN AL F 3REC AST
i Si
• • • • • • •
"- 1 1
••••••a
1.
o • * * * •!**
— • —
0)
o i !
o
ES TIMA rE BASE
ACTUAL • REVISED .FORECAST
MONTHS
ro
CO
CO
234 Chapter 9
O. Personnel Allocation
The planned personnel and progress curves are drawn by weighting together
curves for individual disciplines. Comparing them with historical standards can
validate the assessment. Overall and individual personnel curves based on the
engineering budget and the Level II schedule should be developed. Figure 9.27
shows such curves. Since early control is essential, these curves should be drawn
up as soon as possible. As it is probable that these curves will be developed by
project/scheduling personnel, concurrence and commitment of engineering super-
vision must be obtained.
In conjunction with developing the process design, plot layouts, and engineering
specifications, the requisitioning of equipment is normally on the critical path.
Thus, plotting the actual issuance of requisitions against time can provide an
excellent overview and control of the work.
Figure 9.29 shows an engineering material requisition control curve. Tabu-
lated data can be detailed further by showing material categories if desired. This
example shows that actual issues are behind the planned curve. If the planned
curve has been drawn from the detailed engineering schedule, the situation could
be serious and require further investigation at the detailed level.
The curves represent the planned and actual issues of material requisitions
from the engineering department to the procurement department. The procure-
ment department will then require another two to four weeks to add the com-
mercial sections and issue the completed inquiry package. A curve representing
the later issue is shown in the procurement section of this chapter.
o
o
TITLE: ENGINEERING PRODUCTIVITY REPORT
MONTHLY CUMULATIVE FORECAST TO COMPLETE TOTAL FORECA8T
a
NO DATE EARNED ACTUAL
PROD
EARNED ACTUAL
PROD
EARNED ACTUAL EARNED. ACTUAL
PROD
a
OOMP H H OOMP H H COMP H H H H
SL
1.
I f ^ ^ S * ~ CUMULATIVE ACTUAL ^
PRODU
FORECAST ^ *
POOR
1
\ PLANNED PERSONNEL
\
DURATION
PROJECT MANAGEMENT
PROJECT CONTROL
ENGINEERING DISCIPLINES .
TOTAL
CUMULATIVE TOTAL
NUMBER
OF
REQNS.
DURATION - ^
A^ ,,
T SCHEDUL ED ~
ACT UAAL — ACTU
~ * - ^ _ ^ PERIOD
ACCOUNT * ^ - ^ _
^ "
^y^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ y ^ ^ y ^
^ * ^ y ^ / ^ ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^
^ ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^
S ^
^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^y<^ ^ y ^ ^ ^ ^ ^ ^ y ^
^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ ^ ^ y ^ ^ y ^ ^ y ^
^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ ^ ^ y ^ ^ ^ ^ y ^ ^ y ^
^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ ^ ^ y ^ y ^ ^ y ^
^ ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^
^
y
y
^
^ ^ ^ ^ y ^
[/^
^ y ^
y ^ ^ y
^ y ^
^
^ ^
^ y ^ y
J l
^
y^
y
^ y ^
^
^ y ^
TOTAL ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^ ^ y ^
CUM. TOTAL y ^ y ^
PERFORMANCE
X . PLANNED
^^W A CUMULATIVE
UNIT BUDGET
RATE
\ • •* ^ v .
^ * V V ACTUAL
<^ CUMULATIVE
INCREMENTAL
| 1 1 1 TIME 1
PRODUCTION
NO. ~
*"*"^-'^y ^^^^f^ ^^V^ PLANNED
COMPLETE-
^ T ^ ^ CUMULATIVE
^^^ . • i INCREMENTAL
^rf i - - - -n
-
1 1 1TIME
PERIOD
PERIOD PLANNED NO.
ACTUAL NO.
CUM. PLANNED NO.
ACTUAL NO.
PERIOD PLANNED RATE
ACTUAL RATE
CUM. PLANNED RATE
ACTUAL RATE
spondingly late delivery of materials and equipment to the job site. Feedback of
the vendor's information to engineering is also affected, which in turn can delay
the engineering program. For these reasons, careful monitoring and control of
the material requisition program is essential.
Since piping design is often the critical path, detailed schedules and programs
should be developed for this work. Figure 9.31 provides an example of a curve
for this work. It shows a typical relationship among major piping design activities
for a single unit and weights them together for overall progress. Personnel
resources should be applied to the individual activities.
Projects can vary considerably in their process design, plot layouts and
detailed engineering philosophies, so this typical schedule should be adjusted for
project-specific circumstances. Project-specific schedules should be drawn against
a calendar base. The typical schedule shown is based on return data and can
therefore be used to develop a project-specific schedule.
STEA4TRACE* HYDROPtCKAQES
50
JOBCLIXNUPOFINGNEERtQHOLDS
40 40
30 30
20
30 40 50 60^
TIME (%) - 70% OF PHASE II PROJECT DURATION
o
0)
>
Si.
55
3 . BY MAJOR ACCOUNT
I DESIGN ALLOWANCE
4. FREIGHT , DUTY & SALES TAX
CURRENCY FLUCTUATIONS
5. P.O. SCHEDULE / DATES
2 . COMMERCIAL REVIEW
3 . TECHNICAL REVIEW
4. SCHEDULE EVALUATION
COMMITMENT CURVES
1. BY MAJOR ACCOUNT
2. ACTUAL V BUDGET
merit register should be maintained by prime account and separated for the
following major categories:
• firm-price equipment orders,
open-ended bulk material orders, and
• field-purchased materials.
Curves showing actual versus planned commitments should be considered for
these categories, for larger projects and where schedule/progress is critical.
Generally, bid groupings exceeding the control budget by 20% should be
thoroughly investigated. Such deviations could signal a fat design, poor bid
documents resulting in a high bid, tight market conditions, or a poor estimate.
Several major considerations must be taken into account when planning for
procurement cost control:
• optimize commercial terms by taking advantage of cash discounts for quan-
tity and by making prompt payments;
• on large projects, maximize discount terms by ordering similar items on a
single purchase order;
• minimize import duties and taxes by requesting special waivers from host
countries or by reclassifying items to lower duty categories;
• minimize freight charges by careful selection of carriers; and
• after evaluating potential quantity increases, make a sensitivity analysis of
unit price bids to verify that an apparent low bidder is in fact still lowest.
Material on a critical path could require premiums for vendor drawings and
shorter delivery. Alternatively, special expediting arrangements, such as teams
resident in vendor shops, can be required, as can air freight and special handling.
Such requirements often lead to additional costs. Refer to the section later in
this chapter on procurement scheduling for additional information on the pur-
chasing plan for critical material.
The bid tabulation procedure should cover preparation, control, review, and ap-
proval requirements of bid tabulation documents. Levels of approval should be
defined, and instructions for opening of tenders and evaluations of tender docu-
ments should be given. Budget comparisons should be made, and a negotiations
philosophy stated. Bid tabulations should also contain information based on
knowledge of or experience with specific bidders if this may have a bearing on
their selection.
Figure 9.34 shows a purchase order commitment register listing purchase orders
placed, date placed, vendor, value, currency, and delivery date. Design allowances
should be carefully reviewed against the latest supplement to a purchase order.
PROJECT
JOB NO.
8
REPORT NO.
PURCHASE ORDER COMMITMENT REGISTER DATE
1 2 3 4 5 6 7 11 12
REQD. DESIGN VARIANCE
REQN. P.O. DATE
P.O. ALLOW. FORCAST
NO. NO. PO. ITEM VENDOR COMMITTED EXPENDED FORECAST
DATE BUDGET BUDGET
As engineering advances, so the need for design allowance reduces. Freight costs,
duties, and taxes should be segregated and monitored.
The purchase order commitment register just discussed may become voluminous.
For this reason, it is recommended that the major cost purchase orders be segre-
gated and reviewed each month for a final cost forecast. Design allowances for
fast-track projects are of particular importance, and currency fluctuations, esca-
lation, and delivery conditions should all be carefully considered.
Figure 9.35 illustrates a monetary commitment curve for equipment. The curve
tracks actual cumulative commitments relative to a planned profile, but only
indicates a trend of total commitments. The curve can be used:
• as a graphical representation of work status, and
• as a guide for procurement progress, assuming the planned curve reflects
the current schedule.
Significant deviations of actual versus planned values can provide a trend
for schedule and cost deviations. Separate curves should be drawn for equipment,
bulk material, and major package units that are supply and install.
Figure 9.35 shows an overrun of commitments versus the plan, although
the overrun could simply be that commitments have been made ahead of the
plan and not that costs are overrunning. Alternatively, a schedule check can
reveal that the work is on or behind the plan, which would indicate a potential
cost overrun. As shown, there is a revised budget (increase), indicating that cost
was a problem.
G. Procurement Scheduling—Overall
Major elements for effectively scheduling purchasing work are an accurate ma-
terial requisition list, a purchase order schedule, and a viable purchasing strat-
egy. Figure 9.36 illustrates key techniques and shows methods by which effective
control can be exercised:
equipment purchase schedules (level IV),
• material requisition curves for inquiry and purchase,
• short-range purchase plan,
• material status report,
list of critical vendor drawings, and
• material logistics schedule.
The key activities are developing and using:
• a purchasing plan for critical material;
• a project buying strategy and purchasing program (i.e., quality worldwide
purchasing and the use of overseas satellite offices);
• effective vendor lists;
246 Chapter 9
PROJECT
JOB No.
REPORT No.
EQUIPMENT COST CURVES DATE
BUDGJET I . — •-"""•""-"""""""" •
0 4
FORECAST ~ * * \ \ ' * * ^ - - " '
MECHANICAL
COMPLETION
PLANNED /
COMMITMENT
if Men '
$
/
i/
THIS PERIOD
TO DATE
CURRENT BUDGET
FORECAST
5
248 Chapter 9
Like the purchasing schedule, the material status report is voluminous. Again,
special abstracts and summary information are essential in achieving effective
control. The most important information contained in the material status report
is the anticipated date equipment will arrive at the job site.
Cost and Schedule Trend Analysis 249
NOTES : 1. THE QUOTATION ISSUE CURV E SHOUL D GENERALLY FOLLOVH THE ENGINEERING MATERU
REQUISITION CURVE BY 2 - 3 WEEKS.
2. THE PURCHASE ISSUE CUFT/ E WILL GENERALLY REQUIF E THAT ENGINEERING
UPDATE THE DATA SHEET,5 AND SPECIFICATIONS PRIO R TO PURCHASE UND ER
COMMITTMENT .
NUMBER OF
MATERIAL
REOJ5.
R PURCHASE
/
DURATION *•-
SCHEDULED . - - - - SCHEDULED
ACTUAL
ACTUAL — — —
^ ^ * — ^ ^ ^ PERIOD
ACCOUNT ^ - ^ ^ ^
y ^
^y^ ^ ^ ^y^
^y^
^ ^ y^ ^ ^ ^y^ ^y^
^ ^ y^ ^ ^ ^y^\ ^y^
^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^y^ ^y^
^ ^ ^ ^ ^ ^ ^ y ^
^ ^ ^ ^ ^ ^ ^ ^ ^ ^ y^ ^y^
y^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^y^ ^ ^
TOTAL y ^
CUM. TOTAL
L. Bid Tabulation
Bid tabulations should include schedule evaluations. When schedule is more im-
portant than cost, the schedule evaluation should then reflect the probability of
quoted delivery dates being accurate. The evaluation should also cover the delivery
of vendor drawings. The schedule engineer should participate in vendor review
meetings to check out schedule details with vendors of all critical equipment.
The ability to effectively control and forecast construction costs starts with the
quality of the field budget. Too often, a lack of care and attention to construction
work begins as early as the project control estimate. This lack becomes particu-
larly evident in the field indirects estimate. Factors are applied to direct-labor
costs instead of developing quantity takeoffs. This requires drafting layouts for
temporary facilities, developing a detailed organization for the field staff, and
preparing detailed construction equipment lists as well as time-frame schedules.
Many projects experience overruns in field indirects due to a poor estimate rather
than a lack of control and poor site management.
o
o
8000- (D
a
7000-
6000-
PEAK DELIVERY
OF MATERIALS
TONS
5000-
1
0)
III mill
1000
TIME DURATION
SUBCONTRACT REPORT
SUBCONTRACT 1. BY INDIVIDUAL SUBCONTRACT
COST REPORT 2. MONTHLY OR Bl WEEKLY I8SUE
3. QUANTITY OR WORK ELEMENT COMPLETION
4. 8COPE AND CLAIMS ALLOWANCE
INDIRECTS REPORTS
INDIRECT8 EXPENDITURE
1. TEMPORARY FACILITIES
CURVES 2. FIELD OFFICE EXPEN8E8
3. 8MALL TOOLS & CON8UMABLE8
4. CONSTRUCTION EQUIPMENT
TEMPORARY FACILITIES
FIELD STAFF 6. FIELD 8TAFF
CONSTRUCTION EQUIPMENT 6. INDIRECT LABOR & MATERIAL
INDIRECT LABOR
D. Machinery Protection
Long schedules and schedule extensions can cause additional costs for equipment
maintenance. Further, failure to properly protect machinery can result in serious
cost increases and scheduling delays. Vendor recommendations should be written
into an overall procedure to protect machinery from the time it leaves the factory
to the time of operational acceptance. It is important that vendors be advised of
the length of time their equipment will remain unoperated, since this could affect
packaging specifications, costs, and guarantees. The field staff should identify
instances of additional protection or winterization requirements.
1. Progress/Jobhour Report
Figure 9.40 depicts a format for reporting actual jobhours and earned budget
value in the earned value system (EVS). Progress is measured by budget jobhours.
Ajobhour prediction is based on a judgment analysis of productivity versus actual
hours. Productivity is derived from actual hours expended versus budget hours
earned. Indirect jobhours should be shown separately. Indirect jobhours are not
quantity based. It is recommended that an indirects budget or equivalent earned
value be based on direct work progress and judgment for each major indirect
jobhour account.
Cost and Schedule Trend Analysis 255
JOB NO:
REPORT N O :
UNIT:
SUMMARY REPORT (PRIME ACCOUNT) PERIOD:
HOURS SPENT BDGT. FOR WORK DONE TOTAL I PRODU TIVITY TOTAL
THIS TO THIS TO BUDGET COMPL. THIS TO PREDICTED
DESCRIPTION CLASS WEEK DATE WEEK DATE WEEK DATE HOURS
EARTHWORK
FOUNDATIONS
HEATERS
1
SUBTOTAL DIRECT
TEMPORARY FACILITIES
TOOLS ft EQUIPMENT
UNALLOCABLE
SUBTOTAL INDIRECT
ITEM CLASS QUANTITIES QUANTITIES UNIT RATE THIS WK. TO DATE THIS WK. TO DATE REMARKS
BY
INDIV.
WORK
CATEGORY
i
CO
TITLE: CONSTRUCTION PRODUCTIVITY
9
0)
MONTHLY CUMULATIVE FORECAST TO COMPLETE TOTAL FORECAST
I
o
2L
1
i
5
FOHBCAST ^ *
POOR
1
to
Figure 9.42 Construction productivity form.
258 Chapter 9
Figure 9.44 shows cumulative planned and actual profiles of the direct-labor
hourly rate. This rate represents total labor costs divided by total direct hours.
The monthly status is tabulated as shown. Significant deviation of actual versus
planned values can indicate a potential overrun. Rate overruns can occur because
of different craft mixes, union contract changes, governmental regulation changes,
and excess premium costs for overtime and shift work. This example shows the
curves tracking closely for the first six months, then an underrun is apparent.
If this trend should continue, a significant cost savings would be possible.
Cost and Schedule Trend Analysis 259
PROJECT
JOB NO.
REPORT NO.
CONSTRUCTION JOBHOUR CURVE DATE
REPORT
DATE
/
/ TO DATE MECHANICAL
/ PLANNED COMPLETION
TO DATE
ACTUAL
- (PROJECT DURATION)
INCREMENTAL
Abrupt changes in a cumulative profile do not generally occur when the job is
well advanced, since there is too much weight of past performance to allow instant
or abrupt change. A turndown or underrun can indicate the use of lower-paid crafts,
escalation lower than anticipated, or failure by trade unions to achieve pay demands.
The following elements are typical for profiles of process projects:
low at first due to low-skill civil workers (laborers);
• increasing to peak due to highly paid equipment operators, millwrights, pipe
fitters, and electricians; and
a slight downturn due to lower-paid insulators and painters.
260 Chapter 9
PROJECT
JOB NO.
REPORT NO.
LABOR RATE CONTROL CURVE
DATE
BUDGIET
L
COST
PER HOUR "
r*
- CONTRACT
ERMINATION
UNION AGREEMENT
PLAN NED t ^"^ INCREASE
^ ^ -f
ACTUAL
i
1
CURRENCY-
PERIOD
PERIOD RATE
CUM. RATE
BUDGET RATE
REMARKS
7.0
6.0
HOURS
PER UNIT CUMULATIVE
5.0
^INCREMENTAL
4.0
3.0
TIME
Jobhour expenditure and rate profile curves could also be used to monitor indirect
labor costs.
As indirect labor budgets are often poorly estimated, tracking curves should be
developed for major indirect categories. The technique described in this section
would be appropriate for use on larger projects. Figure 9.46 shows a typical
indirect jobhour tracking curve. Hours and hourly costs should be tracked sepa-
rately. A separate curve for average hourly rate can be drawn, or, alternatively,
the hourly rate can be entered on the jobhour chart. The monthly status is
tabulated as shown, and forecasts are shown. Forecasted hours multiplied by the
anticipated hourly rate will give forecasted costs.
As shown by the example, and as is often the case, a significant jobhour
overrun exists. The overrun started in month ten and escalated further in month
thirteen. A significant overrun was evident at that time. The hourly rate is also
shown to be overrunning.
Indirect labor covers hourly paid labor not directly involved in the construc-
tion of permanent facilities; indirect activities can comprise as much as 30% or
more of direct labor, and can include:
• erection of temporary buildings, roads, etc.;
• erection and maintenance of temporary utility systems;
• site cleanup during and after construction;
• materials handling and preservation (warehouse operation);
scaffolding;
• equipment maintenance;
lost time (weather, union allowances, training, etc.);
o
o
sa
a
CO
o
TO DATE | 466,000 \
HOURLY RATE
BUDGET, ACTUAL
I
5"
1400 14.50
ACTUAL TO DATE ] 560,000 1
MONTHLY
FtAWED
ACTUAL
FORECAST
PLAftJED
/ FORECAST
CONSTRUCTDN DURATDN,
CO
PROJECT
JOB NO.
REPORT NO.
INDIRECT COST REPORT
DATE
COMMITTED EXPENDED
1 2 3 4 5 6 7 8 9
O
Figure 9.47 Indirect cost report.
i
CD
Cost and Schedule Trend Analysis 265
Indirect material costs generally do not require curve techniques and can be
monitored with a monthly status report. Figure 9.47 illustrates a typical monthly
status report of field indirect material costs. Individual items are identified by
account code; commitments, expenditures, the budget, forecasts, and variances
are reported.
M. Construction Equipment
O
Figure 9.48 Field supervision listing and schedule. fi)
CO
PROJECT o
PROJECT NO.
I
0)
DATE
5"
1.
3
s
ro
PROJECT
JOB NO.
REPORT NO.
CONSTRUCTION EQUIPMENT - RATE CONTROL CURVE DATE
REPORT DATE
MECHANICAL
- INCREKIENTAL
COMPLETION
ACTUAL
N \ > \ CUMULATIVE
EQUIPMENT COST
\ > C \ ACTUAL FORECAST
t BUDGET
PER DIRECT f OVERRUN
S BUDGET RATE
LABOR HOUR
PLANNED (HISTORICAL)
CUMULATIVE
TIME
CO
Cost and Schedule Trend Analysis 269
JOB NO.
REPORT NO.
DATE
REVISED m
BUDGET i
MECHANICAL
COMPLETION
I I (PROJECT
I DURATION)i I i i i i r
EXPENDITURES REMARKS
CURRENT BUDGET
This record of monthly and cumulative rental costs against direct labor hours
could give an evaluation of equipment commitments in relation to labor buildup.
This could indicate that equipment was brought to the site too early or that a
projected labor buildup was not achieved. In either case, equipment was underused.
For cost elements that are not quantifiable (such as temporary facilities, small
tools, consumables, and field office expenses), financial expenditure curves can
provide meaningful evaluations. Planned curves, based on history or judgment,
270 Chapter 9
can be developed and actual costs plotted against these curves. Figure 9.51 shows
incremental and cumulative expenditure curves. Actual costs are plotted against
planned costs.
O. Construction Scheduling—Overall
P. Construction Preplanning
A) MANUAL BAR-CHARTS
B) FOR NDMDUAL WORK TASKS
C) TME AND LABOR ONLY (No O's)
D) ISSUED WEEKLY
PRODUCTIvTrY PROFLES
A major method for illustrating construction progress is the bar chart. The bar
chart is also a technique for totalling the progress requirements and achievements
in individual areas. Figure 9.53 shows a construction progress bar chart for
process units. It is used to monitor progress and to evaluate total project (job)
progress requirements, which can then be used to develop a construction progress
S-curve. In this example, progress figures for two process units and offsites are
combined to determine total planned progress and actual, reported job status.
Total job progress is computed by aggregating the weighted percentage
completion for each process unit and total offsite. Weighting is based on budgeted
jobhours. The total job progress values obtained are then used to develop the
overall project curve. In this particular example, the barlines have been revised
to indicate completion two months later than originally scheduled. The status of
each section is indicated by the position of the progress barline relative to the
vertical report dateline. Section progress is the addition, on a weighted basis, of
individual lower-level activity progress figures.
Overall progress can also be determined or verified with historical data. It
would be unlikely that historical experience could be used for lower-level activities
such as shown in Figure 9.54. The mechanical erection of an equipment account is
shown in this illustration. In addition to a relative weight breakdown, activities are
defined by quantities and jobhours. This chart also tracks scope definition as quan-
tities and/or jobhours are revised during field operations. The example shows the
work being ahead of schedule, with overall progress at 38% versus a plan of 30%.
These are detailed area and/or discipline schedules and cover a two-to-three-month
period of the total schedule program; however, they are expanded and modified to
show current requirements. They could be CPM networks or bar charts, showing
detailed activities, duration, and labor requirements. It is vital that this slice of the
overall program be updated to reflect changed circumstances and current require-
ments. Major changes may require an update of the overall schedule.
The technique described in this section is a very detailed program and is only
cost effective on larger projects. It is the most effective of all detailed work
o
o
1
1.
M 0)
" 1 I | I I- - - - - O 29.7 36.3 44 51.9 6O.7 69.4 77.9 85.6 52.2 97 99.3 100
VACUUM UNIT 35 : •:: - - - - - R
- A
18.9 24.0 29.7 36.3 44 51.9 60.7 69.4 77.9 92.2 97 99.3 19°
19.0 24,0 30.0
- - - - - N 36.3
— : : . . i::::© 42.3 49.8 55.3 61.1 100
FCC UNIT 50 ....
- A
_ - - . - N 23.0 26,0 30 34,6
L - - - - O 28.1 36.8 45.8 51.6 57.5 63.4 69.9 77.1.. 83.1 J U L 94.4 97.3 99.4 100
—
OFFSITES ft 16.3 20,1 28.1 36.8 45.8 51,6 57.5 63.4 69.9 77.1 83.1 89.1 94.4 97.3 99.4 J00
1 III [
N 22,0 29.0 36.0 45.8
o
R
A
N
3
CO
PROJECT
JOB NO.
REPORT NO.
CONSTRUCTION PROGRESS BAR CHART - WORK CATEGORY
DATE
PROGRESS CATEGORY
REVB, CUM,
programs, but requires considerable skills and full commitment and discipline
from the construction supervision. In practice, it can use a computer program.
The weekly work program is a two-to-four-week forecast, supported by an
overall schedule and detailed estimate. With proper supervisory support, it is a
very efficient method of achieving control. It readily adapts to a dynamic con-
struction environment where priorities, material deliveries, craft hour content,
site conditions, resources, and weather can change very rapidly.
The essential requirement is identifying and itemizing specific pieces of work
through the use of:
• quantities of measurable units,
• application of budgeted unit hourly rates,
• adjustment for current productivity,
craft labor assessment,
planning of extra work and rework (hours and craft labor), and
reconciliation of weekly program to overall plan.
The flowchart contained in Figure 9.55 shows the elements of the weekly
work program. It also shows the flow of information, including the overall sched-
ule for the month's work, the budget estimate for the work in labor-unit direct
hours, together with quantity takeoff sheets for detailed scope. This is for direct-
hire work; subcontractor work is shown separately.
Work lists are then drawn up, usually by construction personnel, (assisted
by the field planning group) who then ensure that material and engineering draw-
ings are available. The look-ahead list will be in less detail than the current week's
program, and a good system will define 80% of the work for the second week, 60%
of the work for the third week, and 40% of the work for the fourth week. Control
of subcontractor work depends on the contractual agreements and the capability
of the subcontractors. Subcontractors can be controlled on a milestone schedule
and craft labor basis alone, or by full incorporation into the weekly work program.
The field planning group should work with the work list to evaluate required
hours and craft labor and to coordinate direct-hire work and subcontract work.
Figure 9.56 shows a typical report format for the weekly work program. The
following explanations refer to the use and function of each numbered column:
1.
Check that all engineering information is available;
2.
Check that all material is available;
3.
Abbreviated description of work items;
4.
Total quantities of measurable units for work item;
5.
Budget direct hour rate for this piece of work;
6.
Quantities of measurable units for work planned for week;
7.
Budgeted hours for the planned weekly work (Column 6 + Column 7);
8.
Extra work and/or rework (rework many times has no measurable quantities
or hourly rates; in such cases the work should be estimated and entered in
Column 8);
9. Remarks on priority, constraints, resource requirements, and crew sizes are
appropriate;
10. Planning reconciliation (when the weekly program has been calculated and
finalized, it is necessary to compare the projected output of the weekly program
against the overall progress requirement, both weekly and cumulative);
OVERALL SCHEDULE SUBCONTRACTOR SCHEDULES
ONE MONTH LOOK AHEAD 1. GREATER DETAL WfTHN MLE8TONE8 OF
FOR FORWARD PLANMNG PfttME CONTRACTOR OVERAU. SCHEDULE
2. NPUT TO WEEKLY WORK UST
3. N P W TO WEEKLY PROGRAM IS DEPENDOIT
ON DEGREE OF CONTROL OF
SUBCONTRACTORS
I
STATUS SCOPE THIS PERIOD
BUDGET EXTRA
BUDGET
QUANT. QUANT. HOURS WORK
RATE REMARKS
5T
CD
f
0)
LABOR
PLANNING RECONCILIATION 10 BUDGETTEO WEEKLY PROGRAM 11 12
1. WEEKLY PLAN WORK TEAM
2. WEEKLY PROGRAM 13 CURRENT PRODUCTIVITY ADJUSTMENT % 14 TOTAL LABOR
3. PLANNED CUMULATIVE
TOTAL WEEKLY PROGRAM 15 16
A ACTUAL CUMULATIVE
10
11
12
TOTAL
Note that when craft labor is a restraint, either not available or fixed due to a
lack of accommodations (as in offshore work) or saturation, the calculation process
is worked backward.
Figure 9.57 is a weekly work summary report. This document summarizes
individual discipline programs. Planned direct hours and total craft labor are the
same numbers shown on individual work programs marked in Columns 15 and 16.
The craft breakdown is derived by applying a historical labor standard for ap-
propriate disciplines.
The planning reconciliation provides for evaluation of the weekly program
against the overall program.
In summary, this weekly work program is the most effective of all detailed
work programs. When properly developed and operated, it will be a major contrib-
utor to the success of the construction effort. However, it requires a high degree
of construction-scheduling skills and the full and constant support of construction
supervision. In fact, construction supervision must lead and direct the program.
S-curves (Fig. 9.58) can provide more meaningful analysis of progress than bar
charts, since deviations are more easily recognized and trends or recovery plans
can be more easily developed. The planned curve can be determined by using
judgment, historical data, and the bar chart evaluation.
10
^*- » • * /
80
F FP )R1 INC D TE Llh F - / ^
1 /
f
FOI EC \ST R :coMJL\ Y »LAN
o PL AN 4EC PR OG $-
o
1 >
«^— - - A CTl AL PI OG tES s
20
/ 1
WEEKS
% COMPLETE
CODE EARNED ACTUAL PROD. FORECAST
ACCOUNT BUDGET
HOURS
WEIGHT
ACCOUNT PROJECT
( 4+S)
HOURS
( 3+ 5 )
HOURS £xioo
3
9
%
1 3 5 8 9 10
800 PAINTING 80 4 - 80
Cubic Weighted %
Discipline yards Weight % % Complete complete
1000 - civil (1) (2) (3) (4)
Total account 50
contained in this section covers major categories of work. Each discipline is listed,
and work items are broken down into major tasks and recommended percentages
for completion of the work are shown :
Site preparation and earthwork: report by percent of total cubic
yards involved
Earth tank pads
percent of compacted earth in place 85% (85)
final dressing 100% (15)
Concrete: report by percent of total cubic yards involved, with
the following allowances:
rebar in place 20% (20)
forming complete 70% (50)
concrete poured 80% (10)
stripping complete 95% (15)
dressed and patched 100% ( 5)
piles: report by number in place as percent of total required
paving: report by square feet installed against total square
feet required
sewers and access holes (prefabricated)
access holes and catch basins installed 65% (65)
hookup and connections complete 90% (25)
test and checkout complete 100% (10)
Steel structures, piping supports, and miscellaneous steel
report by tons erected in place 90% (90)
bolting tension checked and completed 100% (10)
Buildings (excluding foundations)
shelter-type (no interior work)
steel erected 50% (50)
walls and roof complete 90% (40)
checked out complete 100% (10)
masonry-type
walls erected 30% (30)
roof framing complete 50% (20)
doors and windows installed 65% (15)
interior complete 100% (35)
Equipment installation
columns and vessels
shop-fabricated, no internals
set in place 60% (60)
secured and grouted 90% (30)
tested and bolted up 100% (10)
shop-fabricated, with trays or internals
set in place 25% (25)
The first number represents cumulative percent of the job. The number in parenthesis represents
the incremental percent for the indicated step.
Cost and Schedule Trend Analysis 283
* This section outlines a simplified piping approach; many systems use more detailed approach
to measuring completion of pipe erection.
Cost and Schedule Trend Analysis 285
Figure 9.60 shows a status report by total project or unit-area. The top section
of this figure shows planned and actual cumulative progress curves. Backup data
for the curves would be obtained from construction progress bar charts. The
center section shows planned and actual incremental and cumulative productivity
curves. The bottom section shows planned and actual cumulative craft labor levels.
The report shown in Figure 9.60 enables an overall evaluation of current
status and future predictions to be made quickly and accurately. It is an excellent
management report, since it graphically shows the overall status of the project
on a single sheet of paper. The labor histogram should be prepared from the
progress curve and labor hour budget. Appropriate allowances should be made
for lost time.
For areas of limited labor resources and for larger projects, detailed labor
resource evaluations are essential (a part of construction preplanning). They
should evaluate both other and future work and cover:
• local labor availability;
travelers and imported labor;
local practices and regulations for labor;
• infrastructure (housing, transportation, medical, educational, religious);
• training requirements; and
• wage rates and allowances.
Installing concrete foundations and fabricating and erecting pipe spools are often
critical areas of construction and should, therefore, be carefully monitored. Work-
unit tracking curves, shown in Figure 9.61, are strongly recommended for this
monitoring.
286 Chapter 9
PROJECT
JOB NO.
REPORT NO.
STATUS REPORT
DATE
PLANNED PROGRESS
ACTUAL PERCENT
PROGRESS
Performance Improving
p Rattening out Lack of measured work
due to wetf* of as work moves Into
HISTORICAL / 1 * work moves Irom accomptshment rework* punch Hst
CUMULATIVE N / temporartes to <*sct and checkout.
PLANNB)
LABOR
PERFORMANCE
HOURS
PER
UNIT
ACTUAL
CUMULATIVE
INCREMENTAL
i i iir i TIME
I I I 1 IT
PRODUCTION
-J 1 INCREMENTAL
1 1TIME 1 1 II II
ACTUAL NO.
CUM. PLANNED NO.
ACTUAL NO.
PERIOD PLANNED RATE
ACTUAL RATE
ACTUAL RATE
Monthly and cumulative hourly rates and quantities completed are plotted.
Numerical data for the reporting period is tabulated at the bottom of the form.
The reporting frequency may be increased from monthly to biweekly or weekly
during the critical periods of control. This technique is recommended for any
critical item that can be readily quantified.
X. Material Control
The construction equipment account is a major cost item and detailed cost control
is recommended. Making optimal use of construction equipment depends on many
factors, and good planning is one of them. Adequate construction preplanning
should identify major requirements. Thereafter, monitoring numbers of equip-
ment, timing, and effective short-term planning should ensure an adequate supply
and proper use. The following are recommended techniques to monitor the cost
of the construction equipment.
1. Typical Cost Report
Figure 9.62 shows a typical listing for scheduling and monitoring construction
equipment allocations and their associated costs. All construction equipment,
other than small tools, is listed by type and number against a time frame. Since
cranes are generally the most important item, they should be separated and
individually controlled.
Planned periods should be evaluated against the construction schedule and
staffing plan. Numbers and types of equipment should be evaluated against the
control budget. An average crane usage would be in the 60-70% range.
2. Overall Cost Analysis
Figure 9.63 is an excellent type of chart as it plots the total cost (monthly, $1000)
of construction equipment against the buildup (monthly) of labor and, therefore,
should show if the buildup of costs is compatible with the buildup of its user,
the labor. In this example, earthmoving equipment costs and associated labor are
excluded as the work was subcontracted. This case shows, graphically, a potential
loss due to construction equipment being brought on to site too far in advance
of the workers; the actual requirement is not indicated by the figure. This case
shows mismanagement, however, since the overall monthly equipment cost is
being significantly reduced as labor is increasing. This should not occur, since
equipment cost should be compatible with labor buildup. Equipment building
should just lead labor so that labor is not held up and that the cost of wasted
equipment is contained.
Project control personnel should ensure that the planning and scheduling
of construction equipment is compatible with the labor program. This is a difficult
PROJECT 2
JOB NO..
REPORT NO.
CONSTRUCTION EQUIPMENT COST REPORT a
i|
DATE
SCHEDULE (PLANNED VERSES ACTUAL) PURCHASE PRICE TO DATE FORCA8T FORFCAST
EQUIPMENT BUDGET
OR RENTAL RATE COST PERIOD COST
i
a
>
/
400 •^ /
1600
1500
E A / \
;s^^
1400
1300
300 *^ 1200
^*
>
\t * • * /
f \ / 1100
$k \. /
\ r
/
1000
t: ^>T
900
200 800
tft*>/
700
600
500
V
100 400
f\ MRNHGEMENT
200
100
J F M A M J J A S O N D J F M A M
WELDING MACHINES
500 e g geTjL>—.i»4>, T
OVER SUPPLY OF MACHINES OR
DELAY IN LABOR BUILDUP
400
300
200
AUG SEP OCT NOV DEC JAN FE6 MAR APR MAY
9 PER. DATE PER. DATE PER. DATE PER. DATE PER DATE
This section assumes that work will be done in several or many areas.
Immediately after the contract is awarded, the subcontractor should be required
to carry out the functions, prepare the reports, and monitor progress as follows:
quantities (on unit price subcontracts)—report monthly:
- report installed quantities by geographical area,
- report installed quantities by total subcontract,
- predict final quantities;
• hours—report weekly: total hours by total subcontract;
• craft labor—report daily: daily workforce report;
scheduling—report monthly:
- overall critical path method or milestone schedule bar chart,
progress curves (area and total),
- craft labor curves (area and total), and
- quantity progress curves for designated work categories.
These reports and progress updates should be issued five days after the cutoff
date. Progress curves can be developed on a financial basis and/or a weighted
craft hour basis.
One of the objectives of this specification is to have subcontractors do the
reporting and to avoid situations where the general contractor and/or the owner
has to carry out this function. Subcontractors should be required to state in their
ro
2
OTH COURSE
7TH COURSE
8TH COURSE
9TH COURSE / — -60
10TH COURSE
ROOF
1 —
TESTMQ
f
PAtffMQ
• MMMMT -30
DEMOBUZATON
J
1
* -10
- TOTAL
COMMENTS: TWO TANKS ONLY NDtCATED ON THS SfCET
i
CD
Cost and Schedule Trend Analysis 295
proposals that they will meet the criteria of this specification or that any objec-
tions will be stated in writing.
Figure 9.66 breaks down the major operations, on a financial weighted basis, of
a tankage subcontract. Individual activities are scheduled, and an overall planned
completion curve is drawn based on the weighting. Physical completion of the
activities is measured, and target jobhours are recorded. The addition of actual
and planned labor levels completes the status picture.
This report is usually prepared by the general contractor from subcontractor basic
information. Figure 9.60 shows a typical status report of actual progress, perfor-
mance, and staffing against planned or historical data. This type of report applies
equally well to a total project or to a subcontract. It is an excellent visual tool
for correlating the status of the three variables and evaluating the requirements
for a specific completion date or, alternatively, a likely completion date based on
the current trend.
The anticipated performance profile (in dollars) is based on historical data;
as shown in Figure 9.60, early poor results are due to initial learning experience
and work on temporary facilities, but performance quickly improves as the pro-
portion of direct work increases. The curve will then flatten out due to the weight
of work accomplished and it is normal for the performance/productivity to then
gradually reduce, due to the low value of the final punchlist and checkout work.
See the performance evaluation method (discussed on p. 299) for details of
applying this technique.
The quantity progress report is an efficient visual tool for scope trending and
evaluating schedule performance, and can be used for many categories of work.
Another technique would be to correlate the craft direct hours to the quantity
and evaluate performance on a unit-hour basis. This also provides historical data
for estimating purposes.
Figure 9.67 shows the quantities of mass excavation and fill for a large
grassroots site. The original quantities are scheduled, and actual field installation
is plotted. It is interesting to note that in this example the scope quantities
increase by 20-30%. Additionally, the actual progress shows a schedule slip of
nine months.
F. Measurement
SUBCONTRACTOR... _ 1
IOR NO 1
QUANTITY PROGRESS REPORT REPORT NO
2500
Schedule 2,270
500
Q
N D j F |M|A jM j J J A S O| N| D J|F|M|A|M|J|J
1500
Scheduled 1.435
" Actual _ _ 1
^ I X 1.237
1.200#
Met ers
o
".o / • • • • • • ' • v ^
<J
/::•"> ••::•:. i/
o
sands
o / • . ' • . * " /
x:
J-
•*. -x . - * "-X
Q
N | D J | F ] M | A |M J J|A S]O|N D J |F M1 A M]J|J
G. Cost Control—Overall
The first step in cost control is evaluating the contractual documents and the
contract agreement. The evaluator should look for contractual anomalies, pricing
discrepancies, and conditions that might lead to future cost risk. Careful consider-
ation should be given to schedule commitments, warehousing agreements, laydown
and material handling requirements, and whether previously stated commitments
can be maintained during execution of the subcontract. It is particularly import-
ant that a review of associated interface work by others, job-site areas, free-issue
material supplies, and services be made, since these items often provide the
source for major claims.
A log should be maintained of all engineering and contractual changes that
have taken place in the agreement. All changes and appropriate cost trends of
such changes should be recorded. These potential cost deviations should be esti-
mated as definitively as possible for use in future negotiations with the subcon-
tractor.
The following sections discuss procedures and provide examples of recom-
mended cost control techniques.
Major subcontracts should be evaluated individually and tracked from the orig-
inal contract price to the final cost forecast. Figure 9.68 shows a form that a
general contractor can use to document such tracking. Costs are broken down
into material and labor components. The control sheet shows the price of the
original agreement, accumulates current experience, assesses outstanding work,
and forecasts a final predicted total cost. The form is vertically divided into two
parts, the top portion showing the physical scope of the work, and the bottom
portion covering claims. This enables progress measurements to be made based
on a financial assessment of the labor scope of the work.
Separating material and labor of lump-sum bids allows higher-quality esti-
mating evaluations to be performed. It also enables future assessment of labor
claims and conditions that do not affect material prices. The definition of scope,
type of work, current conditions, and contractual agreement will largely deter-
to
CONTRACT FOR : PROJECT CO
SUBCONTRACT COST REPORT JOB NO.
00
CONTRACT NO.
CONTRACTOR REPORT NO.
ORKIINAL CONTRACT PRICE
(LABOR & MATERIAL) CURRENCY DATE
LABOR MATERIAL
1 MAIN CONTRACT
(O
4 OTHER (SPECIFY)
(a)
(b)
(a)
(b)
(c)
TOTAL O
mine the makeup of the items listed on the form. Claims generally will fall into
one of several categories:
• change in original scope of work,
• schedule delays caused by others,
drawing and material delays,
• interference by others, and
• changes in site conditions or site regulations.
Some subcontractors tend to greatly exaggerate adverse conditions and submit
inflated claims. Consequently, it is essential that such items as daily logs, sched-
ules, and work programs be maintained for all major subcontracts.
By industry definition (custom and practice), a low bid is a bid that is under your
estimate by 20% or more, assuming your estimate is a good estimate. If an evalua-
tion indicates a low bid, a further allowance should be made for covering the prob-
ability of future poor performance, financial difficulties and/or default by the
subcontractor. A low bid can result from ignorance and/or a subcontractor buying
the job. Subcontractors sometimes turn in a survival bid to attempt to break into
a new market or to try to block competition. Perhaps they have found deficiencies
in the contract conditions which they can turn to their financial advantage, but
they first have to get the contract with a low bid. Such situations can result in
low bids that can, in turn, lead to serious cost and schedule consequences for an en-
tire project if the subcontractor gets into financial difficulties and/or performs badly.
The opinion is often expressed that a subcontractor in financial trouble will
maximize its field effort to finish early and get out. Yet the opposite is usually
true: a subcontractor in financial trouble will generally reduce its field effort to
a minimum in an attempt to improve its unit costs. This results in low levels of
construction equipment and supervision and often leads to schedule extensions
and poor quality. Apart from specialty subcontracts, most categories of work
require subcontractors to stay until the end of the project. Thus it is rarely
possible for major civil and mechanical subcontractors to finish early and get out.
7. Performance Evaluation (Dollars)
This section describes a powerful method of assessing a subcontractor's financial
performance, which can then lead to a determination of future work performance
and associated problems. Where there is a poor financial return, the risk of poor
performance, contract default, or claims is high. Thus, a subcontractor's financial
problem can,' very quickly, become the general contractor's or owner's problem.
Performance evaluation is a technique for measuring and monitoring a subcon-
tractor. Poor subcontractor financial performance increases the risk for potential
300 Chapter 9
schedule slippage, poor quality, claims and, ultimately, contract default. When this
performance evaluation technique is used properly, it provides an early warning
of potential problems and then allows time for developing alternative solutions.
2. Performance Evaluation Method:
All subcontracts should be listed, in total, on the progress report shown in Figure
9.71. The report summarizes current cost and forecasted final values and iden-
tifies scope, claims, and potential trends. The figures are taken from predictions
shown on the subcontract cost report (Fig. 9.68) which is a technique recommended
for major subcontracts. Should this report not be used for small subcontracts,
then allowances should be changed, as appropriate, to reflect small contracts. It
PROJECT
JOB NO.
REPORT NO. OS
SUBCONTRACT QUANTITY REPORT a
g
DATE
TO DATE
I
CONTRACT FORECA8T VARIANCE
UNIT
ITEM UNIT RATE QUANT. CO8T QUANT. CO3T QUANT. CO8T QUANT. CO8T
i
a
>
1
0)
REPORT NO.
SUBCONTRACT PERFORMANCE REPORT DATE
O
fi)
Figure 9.70 Subcontract performance report form. "2
<D
CO
PROJECT
JOB NO.
REPORT NO.
I
fi)
SUBCONTRACT SUMMARY REPORT DATE a
I
ORIGINAL CHANGES
CONTRACT
CONTRACT &
NO.
CONTRACTOR WORK SCOPE BUDGET VALUE EXTRAS CLAIMS FORECAST COMMD. EXPEND.
XI. SUMMARY
The most powerful and effective techniques for monitoring and controlling pro-
jects are effective:
front-end planning, and
trending programs.
Such techniques require real business skills, analytical ability and efficient
project control techniques. If we get it right at the front end, we have a chance
of success, though it is not guaranteed. If we do not get it right, then we have
no chance of success. This is then followed with the constant evaluation of
changing circumstances and their impact on cost and schedule.
This chapter illustrates a comprehensive and wide range of analytical-trend-
ing techniques and skills that, when properly applied, will lead to success and
result in the desirable condition of no surprises.
Front-end planning is covered separately in Chapter 5.
10
Change Control and Risk Analysis
I. INTRODUCTION
Changes in the project cost and schedule baselines are as much political problems
as technical problems. Even with high-quality trend analysis, as illustrated in
Chapter 9, changing the baseline requires the understanding, support, and com-
mitment of all parties to the project, especially the client or customer. This
support and commitment can only be achieved when both project manager and
project control analysts have competence, credibility, and effective communication
channels with project parties. It is recommended that when current baselines
are no longer realistic, revised baseline targets should be developed. There can
be endless discussions about the definition of "realistic," but the setting of pro-
grams to unrealistic or impossible baselines is to be avoided, since it leads to
reduced management credibility and poor project morale.
305
306 Chapter 10
major political problems and result in loss of confidence, low project morale, and
defensive engineering. This would be especially true if attempts were made to
improperly assign blame for such problems. Consequently, carefully analyzing the
cost forecast and carefully selecting the timing of publication are critical.
Industry practice and company policy are not as consistent with schedule perfor-
mance as with cost performance. Very few companies have a specific schedule
quality that is a companion to the funding requirement of contingency (probability
and accuracy). A funding schedule of 80% probability is recommended. When such
a schedule is slipping, and trend analysis shows that appropriate acceleration
options have low probability, then the schedule baseline should be revised. It is,
of course, possible that a major cost problem has a companion schedule problem.
Trying to force a program to impossible completion requirements is of little value
and often results in added costs with no schedule advantage.
Major industry studies have shown that the majority of cost increases and sched-
ule slippages have been directly due to scope increases (after funding approval).
Poor early definition, lack of design control, poor project interfaces, and conflicting
objectives are major contributing factors to this situation. It is recommended that
true scope increases, as distinguished from normal design development, should
be processes for additional funds and schedule adjustment. With a lump-sum
contract liability, this would be normal in a contractor operation. With owner
operation, however, it is common for senior management to require that scope
increases be covered with the project contingency; such poor practices are common
and should be eliminated.
V. SCOPE REDUCTION
In most instances, scope reduction occurs when cost trending at the early project
stage shows a cost overrun situation. Such reductions are effective during early
project development, and it is essential that when the project scope and funding
have been reduced to acceptable levels, the reductions are not then allowed to
be reinstated. It is a common practice that operations/maintenance personnel will
agree to the reductions and then, as design proceeds, will attempt to slip in the
previously agreed reductions. True engineering enhancements that result in sub-
stantial economic advantage should always be properly considered, but preferen-
tial engineering and gold plating should be strictly controlled.
Risk analysis is a tool or method for quantifying uncertainties and their inherent
risk. It is a formalized structured approach defining the uncertainties and as-
sessing the probability of risk associated with each uncertain item and/or event.
Performing a risk analysis allows the project manager to qualify and quantify
the sensitivity of risk to the major facets of a project and to include appropriate
cost and time allowances as necessary.
The tools of risk analysis vary from intuition or "gut feeling" and judgment,
to simple manual models, to computerized simulation models. Regardless of the
tools used, it is usually very effective to obtain a broad review of the risks by
available third parties. Other project leaders and involved groups (e.g., construc-
tion, purchasing, and facility planning) can provide valuable insights from a
different perspective regarding the distribution of risk factors and elements.
B. Decision-Making Process
C. Decision Analysis
Another aspect of EMV analysis is the magnitude of the risk for considerations
of investment cost and cash flow. For example, since it is not known how long
the 50:50 probability will take, the question arises whether the investor can afford
the time it will take for the odds to even out. Consider the stakes being raised:
$100.00 (win) to $80.00 (loss)
$1,000.00 (win) to $800.00 (loss)
$10,000.00 (win) to $8,000.00 (loss)
There may come a time when an individual or a company can no longer afford
a very good business gamble because of the high investment level and because
the return will not occur for several/many years. The decision rule for EMV
choices is to select the alternative that gives the largest positive EMV. Any
number of alternatives can be selected, so long as the probability for all alter-
natives adds up to 1 or 100%. The worth should always be of a monetary nature.
E. Decision Trees
Decision trees graphically and logically show decision and chance options in the
form of a logic diagram, as shown in Figure 10.1. The diagram shows four options,
each with its own costs (net present value, NPV) and probability, and the final
EMV. The diagram shows two types of nodes—the square and the circle. The
square denotes a decision node: work or no work. The circle denotes a chance
310 Chapter 10
DECISION I /(2) O4 __
4 0 16
NODE \ / >
5
°75
015
— (20) (5)
4-21.75 M$
node: a decision was made, and this is the possible result when the risks of the
various options are assessed.
Decisions tree analysis is one of the few instances of working backward to
solve a problem. The process begins by calculating the NPV for any given con-
dition, and then working from the final outcome to the commencement of the
work, applying the appropriate factors. Totalling the individual EMVs gives a
positive $21.75 million, indicating the work decision to be favorable, depending
on further analysis of investment funds and cash flow considerations.
Combining EMV analysis with the decision tree method results in a powerful
and graphical program that is a favorite tool of senior management. The most
crucial aspect of the process is the probability factor: if it is not realistic, then
the analysis will be useless and misleading to the decision maker.
G. Breakeven
A planning tool developed at the beginning of the century, the breakeven chart,
plots the relationship between cost, revenue, and profit. Figure 10.2 shows two
scales, both expressed in dollars and with an identical value. The horizontal scale
represents sales volume (revenue), and the vertical scale represents expenses.
Change Control and Risk Analysis 311
BREAKEVEN POINT
$400 OF SALES
#
^-T , , -H 1 •—r
100 200 300 400 500 600 700
SALES VOLUME
Figure 10.2 Breakeven chart.
The first element to plot is fixed cost, such as rent, which is shown as a horizontal
expenditure and which does not change with sales. Then variable costs can be
plotted over the fixed costs. Again, if there is no deviation in the proportion of
variable costs to sales, this would be shown as a 45° line. Finally, the revenue
line is drawn. Where the revenue line crosses the combined expenses line, the
breakeven point occurs. This is the point of zero profit, or where losses stop and
profits begin.
Breakeven is not a pure form of risk analysis but is more a form of economic
analysis. It also lends itself very well to management decisions, since the normal
output of the breakeven method is a graph.
The risk analysis method discussed in this section represents a simplified manual
technique combining several of the steps discussed earlier. Because the approach
is simplified (when compared with the Monte Carlo technique), the results ob-
tained are inflated, especially at the extremes of the probability distribution.
Whereas the Monte Carlo technique uses a random number generator, the manual
method simply adds the probabilities of underrun and overrun of the several
variables; thus there is no randomness in the calculation. Nevertheless, the
assessment of the base estimate value as to whether it lies to the left or right
of the adjusted estimate (the 50:50 point) is a valid conclusion.
Manual risk analysis involves the following steps:
Change Control and Risk Analysis 313
Monte Carlo simulation replaces the randomness and dependency of the manual
method. Monte Carlo risk analysis begins with constructing a model made up of
314 Chapter 10
0
10
20
^ - ^ ~ ~ ~ ~
30
% 40 Base Estimate^. y<
Probability 50
/
of Cost
Overrun
60
70
7 Base Estimate and Contingency
at the 50/50 Point
80
90
100
3000 4000 5000 6000 7000 8000
. Contingency = 250
TARGET
EXPECTED VALUE)
8
O
time
o
O
Completion Cost/Schedule
$240 Risk Envelope |
maximum cost S231M
a
$200- expected cost $196M
o
fi)
$160--
SIS
39% Probability of
Attaining Cost
$120- >-
fc
=J
CD
<
CD
t
$ 80- O
100%
IVE
80%
$ 40- 60%
11% Probability 40% -j
Attaining Schedule
Target 20%
0% O
CO
Oi
316 Chapter 10
the various parts of an estimate. This procedure uses a computer to solve the
model a number of times (typically between 100 and 1,000) based on different
random values generated within the distribution. The Monte Carlo process sum-
marizes the results from all the model solutions, allowing probability statements
to be made about the analysis. Through Monte Carlo simulation, an interactive
modeling language incorporates risk analysis into an automatic model. It requires
no restructuring of estimates, and the estimated value is replaced with distribu-
tion ranges, which are themselves a part of the modeling languages.
A probability distribution function describes a distribution range. For each
Monte Carlo iteration, the system obtains a random value from that range and
applies it to each defined function. In most systems, there is a range of from 100
to a maximum of 1,000 iterations that can be run on any single model; the more
iterations, the more accurate the analysis is. The most accurate form is the Monte
Carlo 1000.
Once a Monte Carlo simulation has been run, the results must be interpreted
from the output tables. These include the frequency table, which contains the
10% and 90% range numbers; the sample statistics table, which contains the
mean that is used to calculate contingency (mean or most probable = contingency);
and the histogram (which is the data values plotted in graphic form). The data
on these tables indicate whether there is a normal distribution of values or if
the values are skewed to one end or the other, and if the results can be accurately
used for risk analysis. Figures 10.5 and 10.6 provide examples of Monte Carlo
analysis probability curves.
11
Range Estimating"
Many organizations are just beginning to learn that sophisticated software pack-
ages do not necessarily create sophisticated users. People often understand a
package's functions but not the underlying decision technology. This is particu-
larly true with Monte Carlo Simulation (MCS). Range estimating was developed
to correct the deficiencies as well as to capitalize on the strengths of MCS in
order to bring the benefits of risk analysis to nonstatisticians—without compro-
mising the validity of the technique.
Since it was first coined in 1970, the term range estimating has been widely
misinterpreted. To some, range estimating includes any attempt to measure un-
certainty with ranges rather than single-point numbers (i.e., estimating ranges).
To others, range estimating is MCS itself. Both interpretations are wrong.
In 1970, range estimating was defined as a combination of the good part of
MCS (the sampling process), an active application of Pareto's law (defined later)
and, most importantly, powerful heuristics which make the entire process easy
to apply. A computer and range estimating software are needed—it cannot be
applied manually.
The key differences between range estimating and basic MCS are:
range estimating's simplified inputs, as ranges and probability factors are
used rather than traditional probability density functions (PDFs) and their
parameters; and,
• range estimating's ability to identify, quantify, and rank critical elements
according to their contributions to bottom line risk and opportunity.
*By Michael W. Curran and Kevin M. Curran, Decision Sciences Corporation, St. Louis, Missouri.
Copyright 1995 by Decision Sciences Corporation. All rights reserved. Reprinted by permission.
317
318 Chapter 11
Am I a statistician?
i
YES NO
| I
Proceed with caution. Good Luck!
Determine which elements are critical
I
Select the proper probability density function (PDF) for each
Selecting the incorrect PDF or
assigning a PDF to a noncritical element
will likely lead to iatrogenic risk
I
1A 9
Uniform Triangular Normal Step Beta, E>iang>
ixponential,
Gamma, etc.
1
Input parameters for each PDF
1
Mean Standard Varianc e I
Deviation etc.
[± or X
III. NUMBERCLATURE
Everyone knows it is virtually impossible to predict the bottom line exactly. What
then does the decision maker strive to do? Manage uncertainty, that's what. But
uncertainty can only be managed if it is measured and monitored!
The proper tool must be selected when measuring. The spreadsheet is a
poor tool for measuring uncertainty. To select the proper tool, one must first
understand the nature of the number to be measured. The are three categories
of numbers: knowns, known-unknowns, and unknown-unknowns.
A. Knowns
B. Known-Unknowns
C. Unknown-Unknowns
Assume a decision maker has prepared a cost estimate for a project with hun-
dreds or thousands of cost elements and a bottom line target of $1,000,000. In
that estimate there is an item of equipment for $145,000. Due to a contractual
arrangement with the equipment manufacturer, the decision maker is assured
that the actual cost will be exactly $145,000. This cost element is a known—it
contains no uncertainty. If there is a cost overrun on this project, it won't be due
to this element!
In this same project, 800 meters of material must be installed. The estimated
labor cost for this is $22 per meter, and the decision maker's experience indicates
it could go as low as $15 or as high as $29 per meter. In other words, the potential
variability of this labor cost translates into a potential variability of $5,600 (plus
or minus) at the bottom line.
The crucial issue is an element's variability, not its magnitude. Since a range
is used to measure the uncertainty in UNKs, and since most of the elements in
a plan are UNKs, does that mean that most of the elements in the plan require
ranges? No!
Range Estimating 321
Not all elements have the potential for changing the bottom line by a
significant amount. In fact, just as few elements will account for the largest
percentage of the bottom line's magnitude, it is also true that few elements will
account for the largest percentage of the bottom line's variability. This phenom-
enon is called the law of the significant few and insignificant many, the 80/20
rule, or Pareto's law.
Vilfredo Pareto, a sociologist/economist, discovered that most of the wealth
in a nation is concentrated in a small percentage of the population. This same
phenomenon occurs in planning. A few elements account for the vast majority of
the bottom line's potential variability. Typically, these elements number between
10 and 20—regardless of the bottom line's magnitude or the nature of the decision
process. This has been demonstrated innumerable times in decisions up to $12
billion.
Those few UNKs which can cause substantial changes in the bottom line
are called critical elements. (All other UNKs and knowns within the plan are
called noncritical elements.) Unfortunately, a majority of critical elements behave
adversely with predictable regularity and thus spoil plans. That's why even good
plans often produce poor decisions and poor outcomes. That's also why the vari-
ability of each critical element must be measured by a range.
V. CRITICAL ELEMENTS
Extreme care must be taken not to apply ranges to too many, or the wrong, ele-
ments. If significantly more than 20 elements are ranged, it is highly likely that an
understatement of true risk will result. Understating true risk is a risk in itself.
In simplest terms, the risk analyst adds risk by understating true risk. Such
analyst-induced risk is called iatrogenic risk and is a frequently encountered pitfall
for many MCS users. Range estimating actively guards against iatrogenic risk.
Each UNK contributes to bottom line uncertainty. But how much change to the
bottom line must an UNK be capable of generating to qualify it as a critical
element? Seven years of research during the late 1960s and early 1970s resulted
in the development of a highly effective and easy-to-apply critical variance matrix
for identifying critical elements. The use of this critical variance matrix depends
upon the type of bottom line (expense or profit) and the type of planning process
(detailed or conceptual).
• Expense versus profit. Determining the type of bottom line is a simple
matter. If increasingly larger values of the bottom line are undesirable, it
is an expense type bottom line. If increasingly larger values of the bottom
line are desirable, it is a profit type bottom line.
• Detailed versus conceptual. If a plan measures all that it can be reasonably
expected to measure, it is a detailed plan. Otherwise, it's conceptual.
Each percentage in the critical variance matrix (Fig. 11.3) defines the amount of
change to the bottom line which an UNK must be capable of generating in order
for it to qualify as a critical element. This hurdle, whether stated as a percentage
322 Chapter 11
shown in the matrix or expressed in units of the bottom line, is called the critical
variance of the bottom line.
While it may appear that use of the critical variance matrix will uncover
many critical elements, such is not the case. Typically* there are 10-20 critical
elements—regardless of the type of plan or the magnitude of its bottom line!
There are exceptions, of course, but they are infrequent and nonviolent; once in
a great while there may be as many as 25 or so critical elements.
The critical variances in the matrix have been successfully applied in thou-
sands of decisions since 1972. Therefore, use of the values contained in the matrix
is strongly recommended. The critical variances in the matrix are minima. They
should never be made smaller since this will incorrectly classify noncritical
elements as critical and will likely introduce iatrogenic risk.
Occasionally, there may be a desire to increase the critical variances in the
matrix to reduce the number of critical elements to fewer than 10-20. This is
not likely to introduce significant error if the critical variances are increased to
no more than twice their values shown in the matrix; however, this is not a
guarantee. The best advice is to adhere to the original critical variances in the
matrix. (When the bottom line target is zero or near zero, the critical variance
matrix guidelines for identifying critical elements do not apply. Good judgment
must be used to locate the typically 10-20 critical elements.)
The critical variance, in bottom line units, is determined by multiplying the
bottom line target by the critical variance percentage in the matrix. For example,
a conceptual plan having a bottom line expense target of $1,000,000 has a bottom
line critical variance of $5,000 (found by multiplying $1,000,000 by the 0.5%
critical variance in the matrix). In this example, a critical element is:
• one which can vary enough—either higher or lower—to cause the bottom
line to vary (higher or lower) by $5,000 or more, and
one which is not composed of any other element that can do the same.
Critical elements can be located quickly and reliably by applying the pyramid of
criticality method (Fig. 11.4). All of the elements in the plan are imagined in the
form of a pyramid with the apex representing the bottom line target. Critical
elements are found by a downward search of the pyramid, starting at the apex.
In effect, the search is a series of successive questions and answers predicated
on the critical variance matrix.
Range Estimating 323
PYRAMID
OF CRITICALITY
MUST BE RECOGNIZED
Once the critical elements have been identified, the variability (uncertainty) of
each must be quantified. If one were using MCS, each critical element would
have to be specified in terms of a PDF (e.g., uniform, triangular, normal, beta,
etc.) along with its parameters (e.g., mean, standard deviation, shape variables,
etc.). Using range estimating, all such tedium is eliminated without impairing
the quality of decision making. For each critical element, the user supplies the
target, the probability factor, and the range.
A. Target
In the traditional plan, each critical element has a single-point value. It may be
called an estimate, budget, plan, forecast, etc. In range estimating, it is called
the target.
B. Probability Factor
Probability factors of 0% and 100% are valid. Such a value indicates that
the target is located on a boundary of the range or that it lies outside the range.
A target located on one of the two boundaries is rare; it is highly unlikely that
the critical element's lowest or highest value will be identical to its target. On
the other hand, a target which lies outside the range is not unusual. This
frequently occurs in cost-to-complete estimating. For example, a target estab-
lished earlier may become infeasible. As time progresses, the range may shift
completely above a critical expense element's target.
C. Range
A range of possible values is specified for each critical element in the plan by
specifying the lowest and highest values the critical element can assume. These
lowest and highest values are set so far apart that there is greater than a 98%
probability that the actual value of the critical element will materialize within
the resulting range. Specifically, the "lowest" value is set so low that there is
less than 1 chance in 100 that the actual value will be any lower; similarly, the
"highest" value is set so high that there is less than a 1% probability that the
actual value will be any higher. If there is substantial uncertainty about the
actual value of the critical element, its range will be quite broad. A lesser degree
of uncertainty will be reflected as a narrower range for the critical element.
The lowest and highest values are independent of the probability factor. It
is quite possible that a given critical element could have a fairly small difference
between its target and lowest value and yet have a high probability of its actual
value materializing in that narrow part of the range. Examples of this often occur
in expense elements where it is not unusual to have a very small chance of the
actual exceeding the target but, if it does, the amount by which it can exceed it
is very large.
Some people have difficulty with the idea of supplying a range; some even
claim that the range is nothing more than a lot of guesswork. But that's precisely
why the range is valuable in decision making; it involves a lot of educated
guessing by qualified people. On the other hand, the single-point value involves
only a little guessing—so little that it can lead to serious errors in decision
making. There is nothing wrong with guessing; Nobel prizes have been awarded
for shrewd guessing!
The number of people involved in preparation of the range can vary from
one to several dozen. The collective effort of a group of knowledgeable people—a
group devoid of dominant personalities capable of introducing bias into the pro-
cess—tends to produce the best range. Such a group is likely to steer clear of
the chief pitfall—developing a range which is too narrow! The varied perceptions
of a group's members translate into a wider range, one more apt to capture all
of the possible values of the critical element. However, if only one person is
qualified to specify the range, that is better than no one doing it!
The need to make the range wide enough to capture over 98% of all possible
values cannot be over emphasized. People tend to make the range far too narrow,
particularly on that side of the target which represents adverse performance! Feeling
comfortable about a range which is too narrow is a mistake which is easy to make.
Besides using the group approach, this problem can be minimized by challenging
questions. For example, if the proposed lowest value is $500, the challenging ques-
326 Chapter 11
tion could be, "Can it possibly go as low as $490?" Such challenging questions
often produce ranges which are much wider than they otherwise would be.
A wide range should not be interpreted as a lack of expertise. Experienced
planners are not omniscient. They cannot consistently predict actual values of
critical elements with high degrees of accuracy. In fact, it can be argued that
their most important contribution in decision making is their understanding of
what they don't know as well as what they know. A wider, more realistic, range
reflects a professional judgment and not a lack of knowledge on the part of the
professionals who developed it.
In the world of cost estimating, the range is nothing more than basic
contingency for the element. For a cost element, that part of the range above the
target is the positive contingency for that element whereas that part below the
target is its negative contingency. Range estimating combines the ranges (basic
contingencies) of all such elements to determine the proper basic contingency for
the bottom line.
If the traditional cost estimate includes a separate line item for basic con-
tingency, that amount must not be included in the bottom line target of the range
estimate. Otherwise, basic contingency will be accounted for twice and thus will
produce an inappropriately higher bottom line.
D. Frozen Values
There are two types of noncritical elements: the known and that sort of known-
unknown (UNK) which cannot cause the bottom line to vary, either up or down,
by at least the bottom line's critical variance. Since such elements have little or
no variability (uncertainty), they are not ranged. Each is frozen at its target,
unless there is a likelihood that its actual value will be different than its target.
In that case, the noncritical element is frozen at that other value.
Although noncritical elements are frozen rather than ranged, more often
than not they are frozen in groups rather than as individual noncritical elements.
The reason for this stems from the manner in which critical elements are iden-
tified—in the downward search through the pyramid of criticality. In the process,
a group of numerous noncritical elements will often be collectively accounted for
in a single balance or summary level total figure.
VII. SIMULATION
During simulation a random value is selected from the range for each critical
element, and these random values are combined with the frozen values of the
noncritical elements to determine the value of the bottom line. Each such oper-
ation is a single simulation of what the real world holds in the way of bottom
line results. There are many synonyms for the word simulation, including itera-
tion, trial, sample, and scenario (the most popular). Many scenarios are evaluated
in order to obtain a reliable bottom line profile.
Ideally, when a risk analysis is performed, a truly random number process
should drive the results. However, probabilistic computer simulation typically makes
use of what is called a pseudorandom number generator (RNG). A properly designed
RNG will produce numbers which, when subjected to stringent statistical tests,
Range Estimating 327
would be capable of convincing a statistician that such numbers were likely the
result of a truly random process. Most RNGs require a seed before they can produce
their pseudorandom numbers (i.e., the seed number is a primer); the RNG produces
the same sequence of random numbers when the same seed number is used.
It is useful to know that the results obtained in 1,000 simulations will, in
fact, be identical to the results obtained from a second set of 1,000 simulations—
as long as all input values are the same, the same number of elements are
simulated in the same order, the same number of simulations performed, and
the same seed number used. Although changing the seed would indeed produce
different bottom line results, those results would not be statistically different
than the first set of results. In range estimating, the same seed number is always
used to ensure that differences in results are 100% attributable to differences in
inputs—not statistical noise!
Range estimating never allows selection of a value outside of the specified
range—this is contrary to some MCS applications and PDFs. Second, range
estimating honors the probability factor in the selection process. For example, if
the probability factor is 25% for a given critical element, there will be 3 chances
in 4 that the value selected will be greater than the critical element's target.
Third, range estimating's heuristics tend to select numbers closer to the target
rather than farther away (if the target is feasible, of course)—the chance that
the actual value will materialize near either end of the range is less than the
chance it will materialize elsewhere in the range.
Whether basic MCS or a hybrid technique such as range estimating, elements
in the simulation are assumed independent of one another. If this assumption contra-
dicts reality, steps must be taken to include any significant interdependencies in
the simulation. For example, if reinforcing bar (rebar) is directly related to con-
crete, the dependent variable (rebar) should be expressed as a percentage of the
independent variable (concrete). The application of more sophisticated formulae
to relate interdependent elements will likely produce little more than increased
frustration and confusion in communicating the results to decision makers.
Most range estimates require no more than 500-800 simulations to reach
stability. However, to preclude nonproductive discussions between planners and
decision makers about sampling theory and to further ensure stability, a total of
1,000 simulations is highly recommended. If the results fail to stabilize after
5,000 simulations, it is extremely likely that there is an inordinate and inappro-
priate amount of detail in the range estimate, and the results are almost certainly
afflicted with iatrogenic risk.
opportunity at the bottom line and what can be done about them today to
increase the probability of success and/or reduce the exposure in this decision?"
In the case of expense bottom lines, range estimating also provides answers to
these two questions:
4. "How much contingency is needed to cover unacceptable bottom line risk?"
In other words, "How much contingency must be added to (or subtracted
from) the bottom line in order to achieve a desired level of confidence of not
experiencing a cost overrun?"
5. "Where should the contingency go?" In other words, "How can the total
contingency be distributed back into the critical elements based on each
critical element's risk and opportunity contributions?"
The 1,000 simulations are performed and the resulting 1,000 bottom lines re-
tained for analysis. The number of bottom lines which are at least as favorable
as the target bottom line is expressed as a percentage of the total number of
simulations. In 1,000 simulations, for example, if there are 220 bottom lines at
least as favorable as the target bottom line, range estimating reports a 22%
probability of success, as shown in Figure 11.5 . If the bottom line is an expense,
that means a 78% probability of a cost overrun.
The exposure in the decision is determined by comparing the bottom line's target
with the bottom line's worst value. But, what does "worst" mean? Does it mean
the absolutely farthest out bottom line value the critical elements could generate—
a theoretical worst, so to speak? Or does worst mean a bottom line not that far
out but highly improbable nonetheless—a practical worst, for lack of a better term?
A theoretical worst bottom line value is calculated by setting each critical
element at the most unfavorable value in its range, combining those values with
the frozen values for all the noncritical elements and then determining the bottom
line. What chance is there that this worst case scenario will occur in the real world?
Consider a decision in which there are 10 independent critical elements, each
with 1 chance in 100 that the most unfavorable value in its range will materialize.
In such a case, the probability of the theoretical worst case bottom line scenario
occurring is 1 chance in one hundred quintillion (100,000,000,000,000,000,000).
Obviously, the chance is vanishingly small that the actual bottom line will
approach the theoretical worst case bottom line. In other words, the theoretical
worst case bottom line (and best case bottom line for that matter) is so far out
that it is useless for decision making. For this reason, the practical worst case
bottom line is used to define the exposure.
* Figures 11.5 through 11.7 were created with the use of the range estimating program for personal
computers (REP/PC). REP/PC is a product of Decision Sciences Corporation, Box 28848, St. Louis,
MO 63123; phone: 314-739-2662; fax: 314-536-1001.
Range Estimating 329
^Q* $6,800-
O $6,600-
sz
to
O $6,400-
O
|
h- $6,200-
2 * $6,000-
CL
$5,800-
$5,600-
10 20 30 40 50 60 70 80 90
% Probability of Success
Figure 11.5 Probability of success (Key Question 1) and practical exposure (Key Question 2).
In the case of an expense type of bottom line, the practical exposure is the
difference between the target bottom line expense and the highest bottom line
value found in simulation—the practical worst case bottom line. In the case of
a profit type of bottom line, the practical exposure is the difference between the
target bottom line profit and the lowest bottom line value found in simulation.
Although it can provide answers to the first, second, and fourth of the five key
questions, MCS cannot answer the third or the fifth question. In other words,
MCS can determine if there is a problem and how large it could be, but it cannot
determine the steps needed to be taken today to improve the chance of success
and/or reduce the exposure in the decision.
330 Chapter 11
Very often, decision makers wish to reduce the chance of a cost overrun by adding
a contingency to the target bottom line. If 1,000 simulations are performed and
the 1,000 bottom line results placed into an array in order of magnitude, the
array can be imagined as a ladder with 1,000 steps. The lowest bottom line found
in simulation occupies the first step and the highest bottom line found in simu-
lation occupies the 1,000th step.
The range estimating user supplies a desired level of confidence in not
having a cost overrun. Range estimating first locates the bottom line value in
the ladder of results required to attain that goal. If 80% is the desired level of
confidence, for example, the required bottom line value is found at step 800 in
the ladder—20% (200) of the simulated bottom lines were greater than this value.
In other words, there is an 80% chance the actual will materialize at or below
the bottom line value found at step 800. The amount of total contingency is the
difference between the located bottom line value and the target bottom line.
Although uncommon, negative contingencies, where the target bottom line is
Range Estimating 331
ALLOCATION OF CONTINGENCY
Critical Element Percent Add This Unit
Figure 11.7 Contingency required (Key Question 4) and allocation (Key Question 5).
reduced rather than increased, are possible, especially in overly pessimistic es-
timating and aggressive competitive bidding.
Range estimating suggests the portion of the total contingency each critical
element should receive, thus distributing the total contingency back into the
critical elements (Fig. 11.7). Range estimating bases its suggestions on the an-
swers provided by the third question (the prioritized list of critical elements) and
the fourth question (the total contingency).
The portion of the bottom line's contingency which each critical element
receives is based on that critical element's net risk contribution (i.e., the differ-
ence of its risk contribution and its opportunity contribution). In other words, if
a critical element contributes three times as much net risk as another, the first
critical element receives three times as much contingency as the second. To
further facilitate this allocation, range estimating determines the necessary ad-
justment to each critical element's target value to reflect its suggested amount
of contingency. This information is crucial in contingency management and line-
item bidding decisions.
X. BIBLIOGRAPHY
Anonymous, Range Estimating Provides an Edge in Running the Race Against Risk,
Engineering News-Record, 198(25):94-99 (1977).
Anonymous, Range Estimating Gains Support, Engineering News-Record, 213(12):106 (1984).
K. M. Curran, and W. P. Rowland, Range Estimating in Value Engineering, Transactions
of the American Association of Cost Engineers, pp. G.3.1-G.3.5, 1991.
K. M. Curran, Range Estimating: User-Friendly Risk Analysis, Proceedings, First Congress
on Computing in Civil Engineering, American Society of Civil Engineers, Washington,
D.C., 1994.
M. W. Curran, Range Estimating: Conquering the Cost Overrun, BE Technology, 49(3):10-
14 (1988).
M. W. Curran, Range Estimating, Cost Engineering, 31(3):18-26 (1989).
M. W. Curran, Range Estimating Reduces Iatrogenic Risk, Transactions, American Asso-
ciation of Cost Engineers, pp. K.3.1-K.3.3, 1990.
L. Lewis, Range Estimating—Managing Uncertainty, AACE (American Association of Cost
Engineers) Bulletin, Nov.-Dec.:205-207 (1977).
L. Lewis, Range Estimating, Advanced Management Journal, 45(Spring) (1981).
M. R. Weaver, Improved Estimating Practices using Range Estimating Decision Technol-
ogy, M.S.C.E. thesis, University of Maryland, Baltimore, MD, 1989.
H. J. Welker, Range Estimating: An Owner's Experience, Constructor, 59(8):20-22 (1977).
H. J. Welker, Range Estimating as a Project Management Tool, Engineering and Contract
Record, June:26-27 (1978).
12
Contracting—Claims and Extras
It is extremely difficult to properly and fully define the scope of work, technical
quality, risk, and liability in any contract. This leads to a high probability that
extras and claims will occur. Further, the inherent dynamics of any project on
which scope and costs are estimated means that those estimates are always at
risk as the realities of the work become known. Technical changes, material price
variations, and construction conditions are rarely fixed and stable elements. In
order to pass on some of these risks to the contractor, owners enter into lump-sum
contracts, where many of the risks are included in the pricing agreements. In
turn, contractors must properly estimate the cost of these risks and include them
in their pricing proposal.
333
334 Chapter 12
The following list, while not all-inclusive, illustrates common changes, some
of which often result in disputes as to whether or not they are scope changes:
• all scope changes;
• design changes/development, such as:
- in early design phase,
by owner engineers,
by contractor engineers,
- in design change log,
- in cost/schedule consciousness, and
by gold-plating;
• scope reduction programs;
• project/contractual conditions, such as:
in plant operations,
- in breach of contract, and
- in site conditions;
execution plan changes, such as:
- in priority of project objectives, and
- in schedule acceleration.
C. Definition of Claim and Extra
By simple definition, a claim or extra occurs because an item of cost was not
covered in the contractor's estimate and the item can be demonstrated to be
outside the contractor's work scope and/or terms and conditions.
D. Quality Estimating
The key to reducing claims and extras is quality estimating: the ability to properly
identify all scopes, responsibilities, liabilities, and unknowns (contingency) and
to then properly put a cost/price on these items. Quality estimating for lump-sum
bidding is absolutely essential.
In claims disputes that result in litigation, the detail and quality of the estimates
often form the cost baseline from which to measure damages caused by project
changes. It is therefore highly recommended that lessons learned from all litiga-
tion/estimate analyses should be fed back into the estimating process to ensure
that system weaknesses and technical or data errors are eliminated.
II. CLAIMSMANSHIP
Owners say that contractors devote too much effort and personnel resources to
pursuing additional revenue rather than to efficiently executing the work. Con-
tractors justify this activity by responding that owners place unfair and unpriceable
Contracting—Claims and Extras 335
III. RECORDS—DOCUMENTATION
The key to effectively meeting the objectives of both the contractor and the owner
is records. There can be no substitute for accurate documentation, which should
start at the precontract stage and continue to the final certificate of contract
completion. Logs, diaries, minutes of meetings, memoranda, letters, notices, tel-
exes, faxes, reports, and other such items should be current, efficiently collated,
and filed for easy access and retrieval. Developing an effective filing system,
which usually is included as part of the project coordination procedure, is a
demanding task. Special notices and attention must be given to changes, delays,
extra work, and all matters that appear to be out of the ordinary and that are
therefore potential items for a future claim.
It has been the author's experience that many projects are executed where the
project and construction personnel have little or no understanding of the contract
conditions. This experience applies to both owner and contractor personnel, but
especially to owner personnel. In large contracting and owner companies, it is
common for contracts to be developed and negotiated by a contracts department.
At contract award, the contracts are then handed to the project team for execu-
tion. The lack of continuity and the project team's lack of knowledge about
front-end activities are significant failures of the contracting process that can
directly result in claims of negligence and breach of contract situations.
The following list, while not all-inclusive, outlines the more important legal
relationships, liabilities, and risks inherent in the United States, United King-
dom, and Napoleonic legal systems.
General Contractor liability. Of the three parties—owner, architect/engineer, and
general contractor (owner, A/E, and GO—the GC is legally considered to be
the expert. As such, the GC is legally required to foresee every and all
reasonable situation that can occur to the work from start to finish. If the
GC fails to foresee, it is liable for the consequences of its failure.
336 Chapter 12
Generally, a breach of contract can only occur when the following three conditions
are present:
the item must be contrary to the contract terms and conditions;
the item must be contrary to the intent of the parties; and
• the injured party must actually sustain additional or excess costs; if there
are no additional costs, there is no breach even though the action might
have been contrary to the contract terms.
In most cases, breaches of contract result in claims rather than legal action. The
project manager must, therefore, ensure that neither the project manager nor
any member of the project team creates a situation that breaches the contract
and leads to a claim.
The following breach categories should be carefully evaluated and under-
stood by all contracts officers, construction managers, and project managers to
ensure the associated liability and risk are properly covered in the contract terms
and conditions. The list represents the claims and damages items or situations
that are most commonly experienced on engineering and construction projects.
Acceleration, constructive. The contractor actually incurs additional or excess
costs because of accelerating the schedule when the need for schedule ac-
celeration is not due to the contractor's poor performance.
Access denied. Every contract allows the contractor an implied right to enter,
leave, and occupy the work site as required to reasonably perform the work.
Certainty, lack of. Genuine misunderstanding of scope, uncertainty of meaning,
or lack of understanding/agreement based on intent and logical interpreta-
tion of the contract terms and conditions.
Damages, punitive. Damages assessed only to serve as punishment to a party
that maliciously or fraudulently causes a breach of contract. Also serves as
a deterrent to others. Actual malice must be proven for successful recovery.
Damages, special. Those costs that follow directly from the breach itself but
which result directly and as a consequence of the breach. Recovery is granted
if such damages were foreseeable by the parties at the time the contract
was executed.
Delay, compensable . Delay caused by actions or omissions of the owner and
which entitle a GC to an adjustment in price and/or an extension of time.
338 Chapter 12
Delay, concurrent . Two or more delays in the same time frame such that the
owner and GC are each responsible for delay in completing the work. If the
court can properly allocate the costs to each party's delay, the recovery is
then apportioned to each party. Recovery is denied and the case dismissed
if each party's delay costs cannot be properly determined.
Delay, excusable . A delay that is caused by forces beyond the control of and
without the fault of negligence of the GC.
Delay, inexcusable. Delay that is within the GC's control and which thus bars a
GC's request for an adjustment in price or time.
Differing site conditions. Some of the significant construction contract risks/un-
knowns that can be experienced by a new GC are the site and working
conditions. Nevertheless, careful study of the contract documents, a site visit
with a careful evaluation of existing conditions, and the application of good
construction experience to the conditions and job requirements, should great-
ly reduce the risks and unknowns.
Most contract conditions require GCs to assume the risks of site con-
ditions, particularly where the work is in an operating plant. Under some
conditions, excessive standby time due to delays in work permits might be
allowed on fixed-price contracts. Extreme conditions, such as those found in
the offshore industry, might also be considered excusable.
As can be seen, a claim based on differing site conditions could be
justified (for example, an unusual ground condition that could not be fore-
seen on a grassroots site project). On new offshore platform projects, detailed
investigation and research is usually undertaken, so such claims rarely
occur. Nevertheless, conditions on existing offshore platforms change con-
stantly due to weather and operating requirements, and claims based on
differing site conditions may still arise.
Frustration ofpurpose I commercial frustration . This excuses a contractor's non-
performance whenever the purposes or objectives of the contract have been
so frustrated that performance by the parties no longer has value to them.
This situation applies regardless of whether actual performance is easier or
more difficult than the parties had expected. (See Impracticability.)
* These categories, particularly "Delay, compensable," form the major portion of total claims presented
by contractors for schedule delay. Therefore, these categories should be fully understood and all
claims carefully evaluated as to merit and applicability. More important, owner-to-GC and GC-
to-subcontractor activities should be reviewed constantly to prevent situations that may lead to claims
and damages.
Most contracts specify that a contractor/subcontractor is excused from liability for delays due to
changes in the work force majeure, major labor problems, and owner negligence/misconduct. However,
if a delay results from a foreseeable situation (such as a labor dispute) and action by the GC could
have prevented the delay, then the delay is inexcusable. The following are typical owner actions/
negligence that can lead to compensable delays: failure to meet promised material supply dates;
quality of material is out of specification; failure to meet promised drawing issue dates; delay in
engineering reviews and approvals, work permit delays; failure to notify of changing site con-
ditions, lack of site access; poor overall management/coordination of multiple, prime contractors;
and scope changes of +10% of contract price.
It should be recognized that even though the completion date is achieved, a GC/subcontractor
can still successfully pursue a claim for owner negligence when an owner delays the work from
earlier completion. A GC can justifiably claim that its price was based on a completion earlier
than the contract completion.
Contracting—Claims and Extras 339
Impact or disruption costs. The additional costs resulting from changes in the
work over and above the direct costs of the original work. The entire basis
for recovery of an impact or ripple claim is that the effect of changes can
and does create costs beyond those attributable to the changes themselves.
Impact costs may be viewed in two ways: 1) those arising out of each change
viewed individually, or 2) those that result from the cumulative impact of
changes. These costs often result in a GC claim and is generally referred
to as a disruption claim.
Impossibility . The inability to meet contract requirements because the event
is physically incapable of occurring. This is otherwise known as actual impos-
sibility and is a common law doctrine accepted by all United States courts.
Impracticability . The inability to perform because of extreme and unreasonable
difficulty, expense, injury, or loss involved. This is sometimes called practical
impossibility. It is a matter of difficulty of performance, as opposed to
frustration, which is a matter of the value of the performance.
Interference. Conduct that interrupts the normal flow of operations and impedes
performance. Every contract contains the implied condition that neither
party will do anything to interfere with progress of the other party or
parties. Actions by owners often lead to GC claims of owner interference or
wilful misconduct.
Interference, contract I intentional I malicious. These changes of interference refer
to actions of third parties that impact on the contractual relationship or
bidding process of an owner and GC. The GC will claim that the party is
acting outside its responsibility and is, therefore, interfering with the con-
tract or the prospective contract. This typically occurs when an A/E or a
consultant offers advice or proposes actions in an owner/GC dispute. If the
third party has no clear responsibility or contractual right to involvement,
then the GC's claim of interference may stand up in court. This type of
interference is also known as prospective advantage.
Malpractice. This is usually a charge brought against an A/E for incorrect engi-
neering work or when an engineer moves out of the design responsibility
into contracting and construction execution matters (assuming the engineer
has no project or construction management responsibility). It is difficult for
GCs to successfully prosecute this charge, since engineers have a protected
position in most legal systems.
Material difference. As used on changed conditions situations, a deviation from
that expected or expressed in the contract to such a degree that it can
provide the basis for recovery under the changed conditions clause of the
contract.
Misrepresentation. This occurs mostly during the contract proposal stage, when
any of the parties can misrepresent either their capability or the scope of
the work (e.g., differing site conditions). Misrepresentation can result in a
claim for legal defect or fraud, which can in turn lead to voiding the contract.
These three conditions form the legal doctrine that excuses a GC for nonperformance. However,
the courts require that the GC clearly demonstrate the extreme nature of the condition. Mere delay
or circumstances that are very difficult or very hard are not usually sufficient for a claim of this
nature to be successful.
340 Chapter 12
The selected contracting arrangement must properly represent the scope defini-
tion and project objectives, and must be fully subjected to the process of certainty
before the contract is awarded.
Drafting contractual terms and conditions requires great skill and experience to
ensure that all risks, responsibilities, liabilities, and guarantees are properly
defined and correctly assigned to all parties to the contract.
If a claim is substantiated, the final cost agreement can depend on the negotiating
skills of the parties.
A force majeure condition can create changes and can lead to claims at any time. Even
the highest degree of skill cannot forecast the possibility of force majeure conditions.
G. No Contractual Surprises
I. INTRODUCTION
In large operating companies, there is often a wide gap in the skills, experience,
and management effort between the large project programs and the small project
programs. To some degree, contractors have a similar situation, since they often
assign less experienced personnel to a client's small projects. While numerous com-
345
346 Chapter 13
2. Intermediate:
$10 million to $100 million 110 33 480 23
($50 million case)
3. Large
$100 million to $500 million 550 165 2400 33
($250 million case)
36
4. Mega: Execution
2200 phase to
Above $500 million 660 9600
mechanical
($1000 million case) completion.
panies have experienced engineering groups that use sophisticated project manage-
ment programs on large projects, a significant number of them do not appear to
recognize that many of the same skills and programs are also needed on the smaller
projects being handled by their plant project engineering departments. It is possible
that this gap exists for two reasons: first, plant management is largely made up of
production people and not project people, and second, the capital project budget
forms only a small part of the plant operating budget. So, a lack of understanding
of the project business often leads to a poor commitment by management to sup-
port an effective project management program. Many times there is also a failure
to recognize the very real economic benefits that a quality program can bring.
Beyond the lack of management commitment to the modern project approach,
however, there is often a lack of skilled personnel assigned to the smaller project.
Too often, plant operations and maintenance personnel are assigned to the project
engineering group without the experience of project work and without having
been through adequate training in effective project management procedures.
A common fallacy is that small projects are simple and easy to manage. Project
plant engineers faced with the not uncommon situation of a lack of personnel
may have to personally handle many aspects of estimating, scheduling, cost
control, contracting, construction, and project management. In other words, they
need to be more versatile than their counterparts on large projects, where many
of these tasks are handled by separate, individual experts.
Managing Small, Shutdown, Retrofit, or Outage Projects 347
First, training and educating plant managers in project management will resolve
many of the problems outlined in the preceding paragraphs. Career development
and/or rotational assignments through plant operations, maintenance, and project
engineering can also reduce and eliminate these problems.
Second, the project engineering group can be divided into "small" and "large"
project departments. This division, however, can create a secondary problem:
quality of assignment. Project professionals may believe that their careers may
be damaged if they remain in the small project department too long. They may
think that the large project environment more quickly expands their skills,
experience, and (above all) management recognition. It is therefore recommended
that careful career planning be developed for all personnel as they proceed
through the two departments.
V. PROJECT DURATION
Many small projects have schedules of between 3 and 6 months, which not only
allows minimal time for program development but for reaction to and resolution
of problems as well. It is essential, therefore, to have a project control program
that can easily, quickly, and accurately provide information and performance data.
A computerized reporting program is usually the answer, but developing a
new computer program requires careful planning. Thus the recommended method
is to first develop a manual program and to then computerize it with a proven
software package.
On larger projects, the most effective method of project control is the proven
program of physical measurement/quantities/earned budget/actual hours/produc-
tivity/progress. Another program is the cost/time/resource (CTR) approach, which
integrates cost and scheduling and can provide equally good results.
Nevertheless, both programs require time to develop and are the most
expensive of all methods for effectively managing and executing a project. It is,
therefore, most probable that such programs are not suitable for managing small
projects.
Jobhour control programs are probably best suited to small projects, but it must
be recognized that jobhour methods have significant weaknesses, particularly in
measuring progress. These inherent weaknesses can be properly handled with
an adequate system of checks and balances, based on good personnel experience,
adequate historical data, and with reference to the scheduling program.
348 Chapter 13
ENGINEERING PROJECT
PROJECT
CONDITIONS ESTIMATE
I CONTRACT
STRATEGY
10%
HOUR PROGRESS
- EXPENDITURE CURVE(S)
CURVECS)
engineering |
construction |
y
PERSONNEL
MONETARY
EXPENDITURE HISTOGRAM(S)
CURVE(S)
PROGRESS
REPORT
COST REPORT
computer
SUBCONTRACT
CONTROL
schedule
changes &
extra work
project approval. This execution plan would outline the project management/con-
trol program or plan to be used. A project control flow chart is shown in Figure
13.2. The program is indicated as the "Project Control Plan."
In addition, a range of supplementary techniques should be developed, which
in turn may be used for the larger small projects or for those projects that have
critical needs and/or unique features. The standard program should be formalized
into a written document (project manual) that contains guidelines for using the
350 Chapter 13
The 80:20 rule (Pareto's Law) is a common and proven statistic of the project/con-
struction business, and shows that 80% of the total costs for all projects or
programs are found in 20% of the projects. Similarly, for each individual project,
80% of the total cost is found in 20% of the major items (usually material).
Based on this experience, it is recommended that the major project man-
agement effort be concentrated on the 20% of projects (normally the larger size
grouping), with the minimum of attention paid to the other 80%. This recom-
mendation is based on the practical reality that most companies' small projects
programs are understaffed. An exception to this approach is a small value project
that is essential to the operating efficiency of the plant.
Development of the standard program outlined in this section would, then,
be built around this statistic so that the program has a minimum and maximum
degree of control, plus intermediate levels, for the dollar size grouping of projects.
The use of computers is strongly advocated, but care must be exercised to ensure
that the software programs are user friendly, simple to run, and require a mini-
mum of personnel resources. Figure 13.2 shows the major techniques for project
control on the top end of a small projects program (i.e., the maximum approach).
Managing Small, Shutdown, Retrofit, or Outage Projects 351
The project control plan shows the routine program, including any supplementary
techniques that are required. It is part of the project funding and approval
documentation.
B. Trending Program
A formal trending report should be issued, showing all deviations (costed out) to
the reporting cutoff date. The report should be accurate and timely. Responsibility
for the report and the inputs from all groups and departments should be clearly
established. The evaluation of potential trends should be emphasized. The trend
report is then a key source for the project cost report and for all decision making
and cost forecasts.
Figure 13.3 represents a control for a contractor's total home office budget, in
cumulative and incremental hours. This includes engineering and all other sup-
port groups. The effectiveness of this technique is directly dependent on the
accuracy of the planned curve. The curve can be developed from schedule analysis
of the component groups and/or historical data. The example contained in Figure
13.3 shows a consistent overexpenditure of hours from the beginning. This need
not result in a budget overrun, since the work might be ahead of schedule. A
schedule status evaluation and analysis of the component parts should determine
ahead of schedule or overrun of hours. In most cases, overrun is the more likely
alternative, which is what the forecast shown in the figure indicates.
Figure 13.4 covers the overall project budget, showing actual cumulative curves
for commitments and expenditures. This case was estimated at $8 million, but
the high value of commitments at an early stage was matched by an increasing
forecast to $10 million in year one, and $12 million in year two. The changes to
the control or current budget, barely averaging $1 million, did not properly reflect
the rapidly increasing commitment curve. This indicates a project with a poor
estimate or a case with many changes, where additional budget is not being
allowed. Nevertheless, the trending and forecasting program is properly showing
the true costs.
The project cost report is usually produced on a monthly basis using a compu-
terized program. Committed costs and expenditures are provided by the account-
ing group. Budgets and forecasts are the responsibility of the project engineering,
with assistance from the project services group and/or the engineering, procure-
ment, and construction departments. Figure 13.5 illustrates a typical project cost
report format. The keys of this report are an accurate forecast, identification of
variances, and reporting on time.
CONTRACTOR'S NAME ro
PLANNED
MECHANICAL
COMPLETION
PLANNED
ACTUAL
FORECAST
3 45 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Sheet No .
PROJECT DURATION (MONTHS) PROJECT
O
fi)
PROJECT
PROJECT FINANCIAL REPORT JOB NO.
REPORT NO.
COMMITMENTS AND EXPENDITURES
DATE
PROJECTION
120
FORECAST
...i 8 : » . ' \m
mm
a ^V -^ ^ ^
1 :""
• aaaaaaaaal
r T :
aaaaaal
100
a
a
a
CO CONTROL BUDGET
'A
/ CURRENT BUDGET
v/
- \
f
/
60
40
20 /
\/EXPENDmJRE
YEARS
1
2
3
4
5
6
7
9
10
11
12
13
14
15
16
• •" in • I . •• — 1 — ^
17 • •••!••! '• —^" —-
O
Figure 13.5 Project cost report. 0)
(D
Managing Small, Shutdown, Retrofit, or Outage Projects 355
Figure 13.7 shows a combined set of progress and personnel curves. These are
cumulative curves with planned and actual profiles. The CPM computer program
could be used for progress measurement, with subjective evaluation of the prog-
ress of individual activities. The effectiveness of this program is dependent on
the accuracy of the estimated hours and the level of detail of the activities.
Progress and personnel curves can be part of the computer program, but
again, dependent on the level of detail. For effective computer application, there
needs to be sufficient activities to properly represent the total work and total
estimate. This requires a balance between increasing detail and the increasing
cost of the program.
The example shown in Figure 13.7 indicates an increasing personnel level
versus the plan, and also indicates a failure to make the planned progress. This
situation would be due to increasing scope of work and/or poor productivity. A
detailed evaluation would be required to pinpoint the cause.
40 Hour Week
(discounted)
(1000 Hrs. )
INSTALL PIPING
RELEASE PIP
CREW.(i) TO
VESSELS
AND PUMPS
Tower Piping
TOWEJRS PIPE ERECTION
Assume 2 pipe crews of 6
or 1 pipe crew of 12
o
I
Figure 13.6 Construction schedule.
Managing Small, Shutdown, Retrofit, or Outage Projects 357
PLANNED PROGRESS
ACTUAL PERSONNEL
NUMBER
OF
PERSON «
DURATION
A low bid can result from ignorance and/or a subcontractor buying the job.
Subcontractors sometimes turn in a survival bid, attempting to break into a new
market or to block competition, or perhaps they find deficiencies in the contract
conditions. Such situations can result in low bids that can, in turn, lead to serious
cost and schedule consequences for an entire project if the subcontractor gets
into financial difficulties.
C. Claims
Subcontractor claims require detailed analysis and in most cases are a combination of:
• change in scope,
• schedule delays caused by the owner and/or the main contractor,
• drawing and material delays,
• interference by others, and
changes in site conditions or site regulations.
The subcontractors may greatly exaggerate adverse conditions and submit in-
flated claims. Consequently, it is necessary that daily logs, plans, work schedules,
contractual situations, etc., are maintained by project/site staff for all major
subcontracts. It is essential that project/site staff respond promptly to claim
submissions. It is also important to consider all related claims together, or there
may be common influences and consequential impacts.
358 Chapter 13
All subcontracts should be listed, in total, on the control form shown in Figure
13.8. The form summarizes current cost and forecasted final values and identifies
scope, claims, and potential trends. The figures are taken from prediction cost
summary reports (for major contracts) and individually assessed for small con-
tracts. It is recommended that assessments of changes/extras and claims be made
at contract award.
Figure 13.9 illustrates a simple but adequate format for the complete project.
The major phases of the work are shown with individual bars, and starts and
finishes are indicated against a calendar time frame. Key milestones are identi-
fied with separate symbols. Status updating takes place monthly, and a vertical
cursor is drawn at the reporting date to show the status of each bar. As milestones
are achieved, the respective symbol is blacked in.
This is sometimes known as the zero approach. Again, based on the assumption
that the 80:20 rule applies, this approach is applied to a major portion of the
many small projects.
After preparation of the authorization for expenditure (AFE) estimate and
associated schedule bar chart, the major effort is to review and approve all
Managing Small, Shutdown, Retrofit, or Outage Projects
O
eo
REPORT NO. I
1 SUBCONTRACT SUMMARY REPORT 1DATE 1
t
ORIGINAL CHANGES
ONTRACT
CONTRACT
NO.
CONTRACTOR WORK SCOPE BUDGET VALUE EXTRAS CLAIMS FORECAST COMHD. EXPEND.
359
Activity
Description
SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Draft 9/5 11/5 12/4
Issue Permit
PERMITS
11/19
f~J AFE Approved
FUNDING
Pilot 10/1 11/25 BidPkg 1/15 ClarHier Vendor
Test Comp Q Engr Complete
ENGR/DESIGN
11/23 Order 4/14 Last
Q LL Equip Q Delivery
PROCUREMENT
11/25 1/18 Contract Award Const Complete 6/9
CONSTRUCTION D D
a
DOCUMENTATION Bid and Award 6/10
Constr Contract
FCO/STARTUP
OTHER Commissioning -n
Complete 7/7/88
LEVEL I I SCHEDULE
o
Figure 13.9 Level II schedule.
1
Managing Small, Shutdown, Retrofit, or Outage Projects 361
As previously outlined, this chapter does not cover maintenance planning. This
section emphasizes major shutdowns of 1 or more weeks, and on retrofits with
schedules of 3 months and greater.
A. Key Considerations
These projects are very difficult to estimate and, as a direct result of work/scope
uncertainty, can be difficult to plan, schedule, and manage, especially as they
increase in size. Successful execution of shutdowns, retrofits, and outage projects
(SROs) requires a thorough investigation months in advance of the work to be
performed. As construction is often the major cost center, this is particularly true
of all construction work. In addition to problems of scope definition, a further
key consideration is the type of management for these projects. Due to lack of
project experience, many plant managers assign the management responsibility
to an inexperienced engineer or maintenance supervisor.
The project and construction management of SROs, especially as they get
larger, is one of the most difficult and demanding of project assignments. It
requires intensive, creative, and careful evaluation to develop a quality project
management program and execution plan. Contracting considerations require
detailed analysis to ensure that both the project and the company receive the
best business arrangement.
As soon as plant management has determined the need and timing for a SRO
and has completed the basic engineering that evaluates the need, the information
should be transmitted to the project engineering or construction group with a
formal request to execute the work. At this early stage, it is vital that plant
management allows sufficient time to properly develop the work scope to execute
the project. Poor plant management planning and/or lack of project understanding
can lead to inadequate time to properly plan and execute a SRO.
As soon as the notice or request for a SRO is received, the following major
activities need careful evaluation and immediate development:
project objectives,
preliminary execution plant,
work scope,
362 Chapter 13
As soon as the SRO date has been set or a plant request is received, a preliminary
execution plan (PEP) should be developed. This plan should be developed in
conjunction with plant management to ensure correct timing, design basis, avail-
ability of plant personnel; coordination with operations personnel; and identifi-
cation of regulatory requirements and the contracting program for the planned
division of the work.
A preliminary schedule similar to the one shown in Figure 13.10 should be
developed in conjunction with the PEP. In fact, the schedule could actually be
the PEP. At its very earliest stage, the PEP should then be approved by plant
management to ensure their full commitment to the proposed program. Securing
such a full commitment means that plant management will allocate adequate
plant personnel, time, and resources to the program.
A major decision that must be made during the early stage is delegating
responsibility for managing, contracting, and inspecting the construction work.
Most companies and plant organizations have separate maintenance and engi-
neering departments, either of which can be responsible for the construction work.
SHUTDOWN / TURNAROUND 0)
2
THIS PROGRAM IS BASED ON THE CONCEPT OF HIRING A CONTRACTOR
(Q
WELL IN ADVANCE OF THE SHUTDOWN SO AS TO USE THE CONTRACTOR (/>
IN ASSISTING WITH THE FINAL, DETAILED PLANNING OF THE WORK* ft)
THIS ACTION SHOULD GIVE THE CONTRACTOR A GOOD UNDERSTANDING
OF THE WORK SCOPE.
PRELIMINARY PREPARE CONTRACT
EXECUTION PLAN (PEP^PACKAGE
CONTRACTOR B I D S &
.^CONTRACT AWARDS
I
2/3 Mos. 1/2 Mos
i
DEVELOPED IN CONJ?
WITH PLANT
MANAGEMENT.
PREPARATION AND FINALIZE FINAL/DETAILED
PLANNING OF WORK ESTIMATE & \ PLANNING WTffl
SCOPE _ -WORK SCOPE. CONTRACTOR
2 / 3 M o s . 1 1/2 M o s . 1/2/3 IMos.
1/2/3
Wk. = weeks
Mos. = month DEVELOP PROJECT (D
yMDJOR REVISIONS
MANAGEMENT PROGRAM
S
By OWNER
BASIC
1 Mo.
I
0)
PLANT
ENGINEERING f A P P ' i ? M A N A G B E W /FlWDING/APPICWaL REGULATOFY/PEFMITS
DETAILED
JLL Wk.
FINALIZE ENGINEERING t
L.
ENGINEERING
By A / E MATERIAL AND EQUIPMENT DELIVERY
• project organization,
• project control/reporting,
• schedule(s), and
• worker resource histograms.
As shown on the PEP (schedule) contained in Figure 13.10, the project manage-
ment program should be developed within one month after approval of the PEP.
Structure of the owner's organization will depend on whether or not the actual
construction work is contracted out. As previously stated, the assumption of this
program is that this is the case. Again the organization will depend on the
contracting arrangement with (and the responsibility of) the contractor. A full
responsibility, fixed price contract based on a well-defined scope-of-work, let to a
competent contractor, requires a reduced project organization. Conversely, a reim-
bursable or unit rate contract (which is usually the case), requires a full project
organization. In such instances, the project management responsibility and lia-
bility is with the owner. Depending on the contract terms and conditions, a fixed
price contract may still place the liability for schedule with the owner. In sum-
mary, the project organization is directly affected buy the terms and conditions
of the contract agreement.
As engineering and purchasing are the responsibility of the owner and/or
the A/E, the project organization will require allocation of specialist engineering,
purchasing, contracting, construction, estimating, cost control, and scheduling
resources. The personnel allocation is a combination of part- and full-time work-
ers. During the actual shutdown period, the construction staff greatly increases
from the staff level during the preparatory period.
For larger projects, the project manager should be selected carefully. Good,
all-around experience in the plant, engineering, contracting, planning and schedul-
ing, and construction are desirable. The personal attributes of dedication, leader-
ship, creativity, and a calm nature are essential. For SROs, a project manager
needs to be a workaholic. During the potential 24-hour workdays of an SRO, the
project manager has to be mentally prepared for any and all things to occur. Crisis
management, risk analysis, and decision-making skills are essential capabilities.
Figure 13.11 shows an organization chart for a $6 million SRO. The chart
outlines the organizations for the owner, a separate A/E responsibility for detailed
engineering (15,000 hours), and construction being handled by one subcontractor
(50,000 hours) for the three-week, two-shift shutdown program. The construction
organization for the earlier five-month preparatory program is not shown.
H. Project Control/Reporting
Generally, this consists of two distinct phases. First comes design, procurement,
and construction preparatory work. All construction work that is not constrained
by the actual shutdown should have been completed before shutdown. This earlier
construction work is often scheduled on a daily or weekly basis, and the engineer-
ing/procurement on a weekly or bi-weekly basis. Second, the actual construction
shutdown work should be scheduled on a hourly basis, with work being performed
366 Chapter 13
Proc. -1
Mech. -1
Cost &
Sched. -1
Acts. -1
SUPVR.
1 shift
SUPVR.
2 shift
1ADMIN. 1
Elect. -1 Clei3!. -1 Sched. -2
Instr. -1 1- Civil Civil -1 Engg. -1
Misc. -3 2- Mech. Mech. -2 Proll. -1
7- Pipg. -7 Mat'l. -1
3- Elect. Elect.-3 Act's. -1
D'men 3- Instr. Instr.-3 Clerl. -2
Safety included-• 3- Misc. Misc. -3
20 in misc.
Labor Labor
A/E. TEAM - 34*
230 230
CONTRACTOR TEAM - 50 (excl. labor)
on a two-shift basis. Planning and scheduling is the main project control program,
with cost reporting and analysis being carried out as an accounting function.
It is common for work to be executed on a work order system, with CPM-type
schedules and planning boards showing plan and progress of the work. In most
cases, jobhours identify scope of the work and are also used to measure progress.
This requires accurate jobhour estimates for effectively planning resources and
measuring progress. All work orders are individually estimated, and the field
accounting system allocates and collates actual jobhours to each work order.
Prompt analysis of deviations of actual versus estimated hours is necessary for
an effective project control program. A field computer system is necessary to
provide timely and accurate commitments, expenditures, and jobhour data.
Scheduling of shutdown work should allow for unforeseen circumstances,
with overstaffing factors and additional construction equipment forming part of
the resource calculations.
Engineering and procurement activities should be generally scheduled with
a simple method. However, it should be recognized that engineering design also
has a retrofit nature, with field investigations providing input to actual design
drawings. On major SROs, a field design office is often essential to effectively
progress the engineering effort.
Apart from an overall program, it is very difficult to use detailed CPM
schedules/computer systems during the shutdown period. Due to the rapid time
changing of work tasks per individual shift, such changes and the required dis-
play flexibility are best accommodated with a large, manual planning board. This
board is usually mounted on a wall in the project office and is the focal point of
the planning and execution program. Work tasks/orders are mounted on magnetic
tape and placed on the board by priority for each shift. Thus they are highly
visible for all to see. As new work is identified, the work tasks/orders are mounted
in a different color so that the accumulation of new work can be clearly tracked.
J. Personnel Curves
These should be generated by key discipline for the A/E's engineering program
and the construction shutdown work. A planned and actual progress curve for
the work might be needed or useful to show overall progress against plan.
K. Contract Program
A lack of good scope definition severely limits contracting options, which are also
affected by the current financial state of the marketplace. SROs, by their very
nature of cut-and-fit, operational unknowns, schedule acceleration, and overstaff-
368 Chapter 13
INITIAL STRESS
ALIGN FINAL RELIEVE
SET ALIGN PIPING
PUMPS & GROUT PUMPS / FLOAT
K2
(9)
INSTALL
PIPE (1000)
SUPPORTS F L 0 A < VESSELS/PUMPS PIPING FLOAT
2. ^>a&\ 8 (5)"
BLIND AND (400)
GAS FREE FOUNDATIONS VESSELS/PUMPS
ELECTRICAL
1 3 & INSTRUMENTS
j (680)
TOWERS ELECTRICAL FLOAT
TOWERS P&L, & INSTRUMENTS
SUPPORTS
REMOVE
PACKING
AND C/O (2000)
TRAYS TOWERS P I P I N G
ing, are difficult to estimate. This difficulty has a direct impact on the contracting
process. As a result, the reimbursable type of contract is widely used. With this
form of contract, it is also quite common for the owner to take responsibility for
management and execution. Thus the contractor acts as a labor broker, supplying
labor, construction equipment, and supervision under direction of the owner's
construction management. If a good scope definition can be established, and if
project conditions (such as unplanned acceleration) remain firm, then a fixed
price and/or unit price contract is possible.
The following are typical reimbursable contracting arrangements:
1. Reimbursable Hourly Rates
This is the simple (low contractor risk) form of contract, since the contractor
quotes all-inclusive rates (including overhead and profit) for labor, supervision,
and construction equipment. The rates may be on an hourly or weekly basis.
Miscellaneous services and expenses are reimbursed at cost. The number of
resources is specified by the owner. This is known as a time and material (T/M)
type of contract. Purchasing is carried out at cost, with a percentage markup
added to the cost to cover the contractor's administrative costs.
2. Fixed Fee/Reimbursable
This is similar to the T/M contract, except that the contractor's overhead and
profit are removed from the hourly rates and included in the fixed fee. The
fixed-fee/reimbursable contract has a higher risk than the T/M contract, since
the contractor takes a risk on the fixed-fee portion.
The fee does not change with a change of the reimbursable hours, so the
contractor will not recover its overhead or an a profit if the scope of work is
underestimated. Most SROs experience an increase rather than a decrease in
hours, so the contractor must evaluate this risk carefully. Many contractors will
not accept the risk and will attempt to negotiate it away. This can be achieved
by a formula, or percentage, arrangement that ties the fixed fee to the reimburs-
able hours or the total cost.
3. Adjustable Fee/Reimbursable
This arrangement is a risk compromise of the full, fixed-fee arrangement. The
fixed fee is determined on estimated or target jobhours and then adjusted on a
percentage basis for jobhour variations. There also may be additional bonus/shar-
ing on jobhour underruns and a penalty on jobhour overruns, such as an hourly
rates reduction on a percentage basis.
4. Percent Fee/Reimbursable
This arrangement is similar to the adjustable fee/reimbursable form of contract,
except that the fee is determined as a percentage of the total reimbursable costs.
There are usually no bonus/penalty arrangements. The problem with this ar-
rangement is that there is an incentive for the contractor to increase the costs,
which will result in a larger fee.
All reimbursable-type contracts have the general problem for the owner that
poor contractor performance will increase the jobhours and costs, resulting in
greater profit to the contractor. Obviously, poor performance should not be re-
warded.
370 Chapter 13
Site fabrication facilities Letters of credit & bonds Recruiting & training
RETROFIT / REVAMP
Hazards - work limitations Health factors Security
• Workers Contractor training Clearance
• Equipment Standby allowance Permits
XVII. SUMMARY
I. INTRODUCTION
The major emphasis of this chapter is on the project control function, not on
project management, where assessments of all facets of project execution are
outlined. In essence, at the end of a project, a detailed assessment should deter-
mine the success, or otherwise, of the following key factors:
• project objectives achieved,
• personnel skills of all key players,
• project organization (project control),
team building,
techniques and procedures,
project cost consciousness (trending),
• lessons learned,
• failures,
• recommendations for change, and
• historical data.
This list is not all-inclusive and can be modified for application to specific projects.
The resulting information should be included in a confidential report, since some
of the issues would be sensitive and, perhaps, critical.
The project control objectives, by simple definition, are completing the project on
time and within the approved cost appropriation. Achieving early completion and
a cost underrun may be clear evidence of superior project performance. Unfortu-
nately, current studies clearly show that cost overruns and schedule slippage are
373
374 Chapter 14
the norm, although most companies have the policy that a cost deficiency of up
to 10% equates to successful within-budget completion.
A detailed analysis of final costs versus the approved estimate will identify,
at the operating code of accounts level, the individual variance as well as the
total value.
An assessment will focus on all major parties and individuals: owner, engineer,
contractor, and subcontractors. The assessment should cover key individuals
directly responsible for the estimating, cost control, and scheduling operations.
The report should name individuals and their positions, with assessments of their
skills and experience.
This evaluation should cover the effectiveness of the total project control group,
since specific individuals should be included in the preceding section.
The evaluation should include factors such as sufficient project control per-
sonnel; project relations; communication channels; work done in engineering
offices and at the construction site (separate analyses); the interface between
engineering and construction; the coordination of contractors at the site; and the
interface with procurement.
Of great significance is the interface with the project manager. Was it direct
or otherwise? Did the cost engineers consider themselves bean counters or did
they feel they were strong, active contributors throughout the project? Was the
cost control effort properly coordinated with the cost accounting group?
V. TEAM BUILDING
In relation to the preceding comments, was the project control group an active
participant in the team building effort of the total project organization? Did it
obtain the right information at the right time? Within the group (depending on
the size of the project), did appropriate team-building efforts take place to ensure
that all required inputs and all necessary outputs were effective?
One of the keys for successful cost and schedule control is the proper
development of relationships and contacts so that a full and steady stream of
information is obtained. Without this information, effective trending is impossible.
Did the responsible project control personnel attend all appropriate progress and
status meetings, both within the project and within the company?
This part of the report should focus on all major techniques and procedures,
listing them with appropriate descriptions of their use, application, and effective-
ness. The assessment should cover the range and level of techniques and proce-
Project Closeout—Lessons Learned and Historical Data 375
dures as well as their quality. However, with large contractors and sophisticated
owners, there is always the tendency to over-control and over-report.
Management and leadership skills, especially on large projects, are required
to ensure a cost-effective program. Particular care should be given to assessments
of computer programs.
This section should deal with positive issues, covering items that were modified
and deficiencies that were covered. Such items could include personnel, organi-
zation, techniques, or procedures. The items should be of significance, so that
lessons learned would then become standard operating procedures in the future.
The analysis needs to be as objective as possible.
IX. FAILURES
This section, as with lessons learned, covers only items of significance. It assesses
individual and/or company performance, methods, techniques, procedures, and
organization, and should focus on situations that should not recur on future
projects. This is a sensitive area, so care is essential in properly identifying these
items, especially if some of them reflect poor performance by an individual.
The major issues identified in the "Lessons Learned" and "Failures" sections are
further evaluated, resulting in a series of specific recommendations to change
376 Chapter 14
XL HISTORICAL DATA
Before project startup, all project control feedback data should be properly iden-
tified. This includes both estimating/cost data and scheduling information.
Since this information can be voluminous and therefore costly to compile,
care should be taken to ensure that the data is actually needed. It is normal for
estimating and cost data, at the detailed code of accounts level, to be required.
However, further analysis is probably required to obtain accurate costs for each
equipment item and category of material. As far as it is practical and cost
effective, identifying feedback requirements enables a cost accounting system and
scheduling program to all these items to be reported when the system is being
established.
15
Project Management Fundamentals—Key
Essentials
I. INTRODUCTION
If we get it right at the front end, we have a chance of success, though not
guaranteed. If we do not get it right, then we have no chance of success.
Almost all companies have personnel who are trained, skilled, and dedicated to
the execution of projects for the company. The individuals who lead these efforts
are called project engineers and/or project managers. Supporting these project
managers are such personnel as design engineers, procurement personnel, con-
tracts officers, estimators, cost engineers, planners, construction managers, and
a variety of technical specialists.
In many cases, the type, size, and complexity of projects vary greatly and,
therefore, the skills and experience of project engineers, project managers, and
support personnel similarly can vary in capability.
A. Major Factors
Figure 15.1 shows the essential major factors for the successful execution of projects.
1. Cost Management
Many projects have project cost as the top objective and this, then, requires the
project to be completed at, or less than, the budgeted cost. Adequate business
skills are essential to meet this objective.
Project Management Fundamentals—Key Essentials 379
Critic*) Path
Engineering
• Procurement ( EPC )
Construction
Figure 15.1 Major factors essential for successful project execution.
2. Time Management
To meet the cost objective, it is necessary to manage time efficiently. This means
the predetermined schedule, upon which the cost was based, must be met and
met economically. Some projects may have schedule as the top objective. In such
cases, acceleration programs are planned, and it is probable that there will be
corresponding cost increases to the economic-based project.
3. Human Resources
Of all the resources required for plant projects, the people resources are the most
difficult to manage. Interpersonal skills and the effective motivation of people,
at all levels, are essential for successful project execution. Lack of human re-
sources, plus a corresponding lack of the correct mix of people skills, are becoming
380 Chapter 15
.Affiliate
COMPANY ^Operations
PLANNING ^Maintenance
ANNUAL
FIVE YEAR
J
ENGINEERING
REQUEST
(See Detail)'
ENGINEERING
DEPARTMENT!
PLANT
PROJECT
CENTRAL |
DEVELOPMENT BUDGETING I
(See Detail
& I
MANAGEMENT
APPROVAL |
(See Detail)*
PROJECT
EXECUTION
Small Projects Larger Projects
• COST PLUS ENG'G • E.P.C.
• L.S. CONSTR'N • L.S. or COST PLUS
an increasing feature of the project business. One of the most abused people
resource concepts is the 'lean and mean" program. The management intent is
that a reduced group of people, through advanced skills, can execute as effectively
as a larger group and, therefore, reduce costs by reducing staff. There is some
merit in this concept but in many cases it is a device used by poor management
to cut costs. If there is a significant lack of people, there is almost certain to be
a corresponding inefficiency in project execution, coupled with an increase in costs.
4. Communications
A formal and informal structure of effective communications is absolutely essen-
tial for successful project execution. In addition to weak people skills, many
company organizations and cultures have poor administrative practices that also
form barriers to project success. These barriers are common to all companies and
are generally referred to as matrix interface conflicts (MICs). The conflicts or
barriers are caused by departmental jealousies, rivalries, and failures by man-
agement to create a culture where project consciousness and esprit-de-corps are
common to all personnel. The total quality management programs sweeping the
industry are an attempt to solve these problems.
Project Management Fundamentals—Key Essentials 381
'""ENGINEERING I
I I
| REQUEST I
I . 1 SOLVE
PROBLEMS
UPGRADE-
QUALITY
ADDITION-
QUANTITY
ENVIRONMENTAL
STAY-IN-
BUSINESS
ENGINEERING
DEPARTMENT '
Figure 15.2 shows the general steps common to all plant projects. Experience in
this process, recognition of each company program's individualities, and the skills
of bridging the MICs, are necessary for project success. Getting the front-end
planning right is the key to success.
C. Engineering Request
Figure 15.3 illustrates the major factors that generate the capital project work.
Timely and quality assessments of plant requirements are difficult to achieve but
are essential for company profitability. Such assessments result in formal engi-
neering requests for the project work.
D. Project Development
Figure 15.4 shows the major components for developing the scope of each project.
Each of these components (technical, project conditions, regulatory, cost, econom-
ics) is then further defined and prioritized. It is vital that the priority be clearly
established.
Development of the scope in terms of risk, cost, time, and resources is followed by
approval, partial approval, or rejection of each proposed project. Figure 15.5 shows
382 Chapter 15
r PROJECT
r
1
DEVELOPMENTi
I , I
TECHNICAL
PROJECT
CONDITIONS
REGULATORY
CONCEPTUAL
COST ESTIMATE
ECONOMICS
BUDGETING &
MANAGEMENT
• APPROVAL.
T BUDGETING"^!
MANAGEMENT L
APPROVAL J
FPHASED
L APPROACH
PARTIAL-FULL
FUNDING
ESTIMATE
QUALITY
EXECUTION
STRATEGY
PROJECT
RESOURCES
PROJECT
EXECUTION
3
(D
O
0)
0)
(Q
<T)
(D
r~ 1 a
PHASES
r~
PROJECT
a>
MAJOR — OCMMISSION
r~
J
1 Ifor/cscope EfiTAIL OCKSTEUCT &
Project Deficit DESIGN & ION START UP
r Design
r Case
Selection £
Execution £
Contracting
ion
BASIC
PROCUKEMBM
ENT
6
7
CO
384 Chapter 15
THE
BEAN-COUNTER
SYNDROME
the budgeting and management process, which is closely followed by the devel-
opment of the project strategy and project organization. The correct assessment
of the people resources, especially the key people, is essential at this early stage.
The time and interface relationship of major project phases is shown in Figure
15.6. Assuming a fast-track program, most of these phases will overlap, and the
degree of overlapping will depend on the work content of each phase and the
efficiency of decision-making present in the project.
Finally, Figure 15.7 poses the question of company personnel working as a team.
Without question, this matter has become the vital issue to profitability, especially
as companies downsize and reduce the core. Greater personnel efficiency and
increased operational quality are essential requirements in today's difficult busi-
ness environment. The bean-counter syndrome is highlighted. This dangerous and
unacceptable practice is covered in Chapter 9.
16
Managing the Feasibility Study
(Preproject Planning)
I. INTRODUCTION
This discussion is based on the typical approach to feasibility studies for larger
projects, where a combined owner-contractor team is executing the work, usually
on a cost-reimbursable basis. The project manager is generally from the owner's
engineering group, and most of the work is coordinated with the owner's internal
operating groups. Due to the number, independence, and lack of project experi-
ence of these groups, the coordination of the work with them is normally far
more difficult than is the working relationship between owner and contractor
personnel.
385
386 Chapter 16
I Project
I Case
Execution &
Contracting
Company &
I Design
Options &
Cases
Selection &
Optimization
CONCEPTUAL
PROJECT
PLANNING
STUDY 3
Market FEASIBILITY
Strategy STUDY 2
DEVELOPMENT
PLANNING 1
1O OVERALL OBJECTIVE
2. TYPICAL PROBLEMS
3. WORK INITIATION
6. KEY DELIVERABLES
Figure 16.1 Early project phases and major elements of a feasibility study.
quate work scopes, preliminary plans, and necessary resources. This, then, de-
velops into basic engineering with a resulting conceptual cost estimate, schedule,
and assessment of project visibility for owner review and approval.
The deliverables of the feasibility-conceptual design study are:
technical program (preferably, a single case),
cost estimate for funding or further development,
• associated risk analysis, and
• preliminary execution plan (schedule, project organization, etc.).
This early work needs to be of the highest quality, as many significant problems,
such as poor scope definition, inadequate planning, lack of resources, organiza-
tional and owner-contractor-A/E conflicts occur at the early stage of a project.
If these typical early problems can be identified, prevented, or reduced, then the
subsequent execution of detailed engineering, procurement, contracting, and con-
struction is greatly enhanced. In other words, the project manager should set up
the project at the earliest stage, with proper planning, quality organization,
skilled/experienced personnel, good owner relationships and effective communi-
Managing the Feasibility Study (Preproject Planning) 387
cation channels. This will not necessarily guarantee success but will greatly
increase the probability of success.
The following breaks down typical problems encountered by the project
manager in the preproject planning stage:
• poor owner scope definition,
failure of owner and engineering division to recognize that each party has
a differing interpretation of the project requirements,
• unclear priorities and priority conflicts of project objectives,
• inadequate planning,
• lack of resources,
organizational difficulties of the matrix,
• internal owner conflicts,
• inexperience/lack of understanding of involved parties,
• new/changing technology, and
difficult project conditions (site, operating plant).
It is essential that these typical early problems be clearly identified, prevented,
or reduced by the project manager.
The project manager must assume the leading role in developing effective communi-
cation channels and good working relationships with all interested groups. Lack
of proper liaison and poor coordination, especially in the early stages of a project,
will add to the preceding problem list and, during project execution, lead to:
• lack of commitment and support,
• lack of discipline during project execution,
• poor personnel relationships,
• ineffective approval/signatory procedures, and
• inadequate owner-contractor relations.
Prior to contract agreement for the execution phase, owner communications,
reporting requirements, authority levels and approval procedures should be out-
lined in the project coordination procedure, so that contractors can properly
respond during the bidding period.
The project manager must work very closely with operations/maintenance to en-
sure proper technical definition (a precise, unambiguous definition of requirements)
and project scope definition leading to an approved statement of requirements
(SOR). Thereafter, the project manager must maintain an effective interactive
working relationship to gain the operator's full understanding, acceptance and
commitment to the project strategy, project objectives and implementation plan,
including development of the project finance memoranda (FMs) and authoriza-
tions for expenditure (AFEs).
The most cost sensitive part of virtually any project is changes to the scope.
Such changes can easily arise from early failure to allocate total corporate at-
388 Chapter 16
tention to the project scope in general and scope control in particular. Scoping
must not be solely confined to the producing facilities (e.g., oil/gas/chemical/food
production) but must also include all major peripheral facilities, such as power,
water, shipping, storage, communications/telemetry, fire protection, flares, build-
ings, roads, regulatory/environmental, etc.
It is also important to note that, during development of the SOR, many
potential impediments are likely to arise, particularly in scoping minor facilities.
It is essential to avoid all unimportant delaying factors and to allow small
uncertainties to be covered by the estimating methodology and incorporated into
the contingencies element of the overall cost estimate. It is probable that the
project will gain from early release of an approved SOR document rather than
delay to await clarification of minor areas of uncertainty.
The roles of the various owner groups in authorizing, approving and decision-
making must be clearly established as early as possible in the life of the project.
Until the project coordination procedure has been developed, these approvals may
have been determined by verbal discussions and agreements. It is good practice
for the project manager to confirm such verbal agreements with an internal
memorandum, copied to all involved parties.
Sometimes individual owner groups deviate from the agreed project and contract
procedures, change priorities, develop additional scope, delay decision-making,
work directly with the contractors and/or other groups, and then, after the fact,
inform the project manager of these actions. Such behavior can be very damaging
to the effective execution of the project and to the establishment and maintenance
of firm contractual and technical control. Cost increases, schedule slips, and lower
morale due to poor working relationships can rapidly develop. The project man-
ager must therefore work to eliminate or reduce the potential for poor owner
project discipline.
The required inputs and relationships with service divisions inside and outside
of an engineering division (ENG) in support of the project must be properly
developed, established, and coordinated. Project work undertaken by an ENG on
behalf of an owner should be initiated by the universal service request (USR)
system, which also provides a means of monitoring and controlling the work.
A project normally commences when ENG receives a USR from an owner,
along with a statement of requirements (SOR), which may be a broad outline at
this stage. These requests are handled by the engineering/development group
whose responsibilities include the preparation of feasibility studies and engineer-
ing proposals to establish preliminary project programs and cost estimates (con-
ceptual technical definition). At this stage of project development an overall
project strategy is prepared together with the consolidation of the SOR, as agreed
by all parties. Approval and funding, via the AFE control system, will then enable
the project front-end engineering design to be implemented. Before full funding,
management may require further front-end engineering design to be developed
to give a clearer technical definition and identification of risks.
commissioning;
safety, environmental and hazard studies; and
project strategy requirements:
- organization,
- communications,
reporting,
- mobilization for engineering design and construction,
- contracts, and
- spares policy.
One of the earliest and most critical project decisions revolves around the follow-
ing key questions:
• How much front-end engineering (FEE) do we need, to select the best
technology?
• How much FEE do we need for an acceptable estimate?
• How good an estimate do we need to properly assess the financial risk?
How much should this FEE cost?
Should we contract out this FEE?
There are no simple, or single answers to these questions. The answers very
much depend on a company's technical strength, estimating skill, management
bias and preference to a specific process and, ultimately, on the skill to properly
balance technical viability with economic need. Time consciousness and discipline
are vital as the project program is being formulated. Of equal importance is the
ability of management to authorize full funding from preliminary design project
cost information and market strategy.
From the project viewpoint, there is a direct correlation between the quality
of technical-project information and estimate quality. However, the continuous
funding for further engineering development to improve the estimating and hence
lower the financial risk, has a point of zero or minimal cost return. In general,
industry practice has established two approaches.
Approach 2. Develop a minimum design package and execute the project on a
cost-reimbursable basis. This method assumes that the economic return of
the shorter execution period is worth the risks that are inherent in the
cost-reimbursable arrangement. With lack of adequate front-end engineering
definition, it is difficult to obtain good or acceptable lump-sum bids. Many
companies have reduced the inherent reimbursable risk by developing a
strong company project management capability, to contain this risk. This
minimum design package is usually referred to as a basic design package.
However, the degree of definition can vary widely.
Approach 2. The second approach is to develop a maximum design package and
execute the project on a lump-sum, turnkey, basis. With a better design
package, a much greater identification of risk/cost is possible, and contrac-
tors will generally respond positively, subject to current/future market con-
Managing the Feasibility Study (Preproject Planning) 391
ditions and the size of the project. This maximum design package can be
referred to as front-end engineering design (FEED).
There can be other considerations which can increase the time and/or add
to the cost of both approaches. New technology, with a higher risk of engineering
changes, would favor Approach 1. Management with a top priority of low cost
risk, would favor Approach 2. Inappropriate and/or unnecessary cases would add
to the cost of both approaches. Lack of coordination between operations, mainte-
nance engineering, owner, contractor and management can add substantially to
the costs of both approaches.
Figure 16.2 illustrates the cost of feasibility studies for Approach 1, where
process design is categorized at 20%. Add factors for cost (30-40%) and time (2
months) are shown for Approach 2, where process design is shown as 60%.
Figure 16.3 (see p. 393) shows a typical arrangement of the major project phases,
overall key deliverables, and an overall schedule for Approach 1. Figure 16.4 (see
pp. 394-395) is a list of detailed key deliverables (31 items) for Approach 1, where
process design is approximately 20%. Figure 16.5 (see pp. 396-397) is a similar
list for Approach 2, where process design is approximately 60% (FEED).
GO
CO
4
% OF AFE
•
N
•
>
3
• (
•*•
mm
• i\ "5 • •"
1-
o
Managing the Feasibility Study (Preproject Planning) 393
KEY DELIVERABLES
mASCS I
PROJECT
r~
r~
MAJOR COMMISSION
r Project
Execution *
Horkscopo DETAIL
Deflnit
Ion
DESIGN S.
PRXURB1EM
CONSTRUCT
ION
it
START UP fi
r Case Contracting 7
r
Design Selection £ BASIC 6
Company andOptions * Optimization PROJECT DESICN 5
SELECT
ENVIRONMENTAL FINALIZE
CONTRACTOR ENVIRONMENTAL IMPACT STUDIES SCHEDULE
6W
FINALIZE AFE
PERIODIC UPGRADING OF COST ESTIMATE COST ESTIMATE
SOIL/MARINE FINALIZE
SITE SELECTION REPORT PLOT PLANS
8N
PROCESS
OPTIMIZATION DESIGN SPECIFICATIONS FINALIZE PHI'S
•••
6W 12W 8W FINALIZE
BID PACKAGE
FIELD TEMPORARY
UTILITY FLOW DIAGRAMS FACILITIES, LAYOUTS] EARLY
12W PURCHASING
PLAN
FOR CRITICAL
(BEACH HEAD STUDY) EQUIPMENT
ENGINEERING
STUDIES PROCESS DESIGN (PIONEER CAMP)
(SKIPPING)
12W
EQUIPMENT LIST
GENERAL
ENGINEERING
10. Process P&IDs 25% complete. Line and control valve sizing,
control loops, and instrumentation indicated
22. Above ground (A/G) and underground (U/G) Approximately 15% complete
piping layouts
24. Line and valve sizing material and selection 45% complete
GENERAL
ENGINEERING
10. Process P&IDs 75% complete. Line and control valve sizing,
control loops, and instrumentation indicated
22. Above ground (A/G) and underground (U/G) Approximately 50% complete
piping layouts
24. Line and valve sizing material and selection 75% complete
I. INTRODUCTION
399
400 Chapter 17
It is an obvious, but not well understood fact, that it is people in single, medium, or
large-size groups who design and build projects, not companies. Therefore, there
must be a consistent and long-term interest in people needs, their development,
and their training. When there is little interest, or the interest is not genuine,
the long-term success of the company is unlikely. The entire total quality man-
agement (TQM) program is built around the needs and development of people, and
there is unanimous acceptance by industry that TQM is the key to success. In
essence, develop the people and, in turn, the people will develop the profits.
Different skills and different numbers of personnel are directly related to con-
tracting arrangements (i.e., lump-sum, reimbursable, unit price, PSC, agent,
independent contractor, etc.). From an owner's perspective, reimbursable con-
tracts can require three times as many owner personnel as a lump-sum contract
and require personnel with extensive analytical skills. For a lump-sum contract,
a good design package and strong project discipline (with no/little design changes)
are essential. Often there is a mismatch of people resources in relation to contract
arrangements. Having both the wrong contract and the wrong organization/people
is a recipe for disaster. Also, a poor management application of the "lean and
mean" principle will result in a serious lack of resources, leading to poor project
execution and cost overruns/schedule slippage.
Figure 17.1 is a flowchart that outlines the major work activities and
associated decision points.
Front-End Planning and Project Organization 401
WORK/PROJECT
INITIATION . GOOD SCOPE DEFINITION
Identify
tNNd
DEVELOP! . QUALITY PLANNING
QUALITY!
Conceive Solutions
8.O.R.
and Sort
. EFFECTIVE APPROVAL/DECISION MAKING
DESIGN
CONTROL
Decision to Proceed
\U EPCi TURNKEY CONTRACT ' * •
J
Develop Design j ) 9 General Contractor • *
POINT Basis
• **•»• • • • • ^ • (
\ to Lump 'Sum /••/.• ..;
• SmaP Project | Estimate [ Engiiu
Approach t ~"
Detailed Engrg.
and Speciffcation
Construction
Only
MatVEqp't I Purchase Order
Purchase
. ORGANIZATIONAL COMMITMENT
. PROJECT "DISCIPLINE"? ? ? ? ?
The answer should address the technical expertise, project experience, business capa-
bility, leadership ability, and people skills of the proposed person. Project, business,
and people expertise should have greater consideration, especially for larger projects.
On smaller projects and feasibility studies, technical skills are more important.
Significant experience has now shown that the project task force (PTF) is more
efficient for larger projects. The close working relationships allow more efficient
communication channels and a more efficient decision making process. The chal-
lenge of welding together many individuals from many parts of the company is
a substantial task. The organization structure should follow the current state-of
the-art, which has added the new function of a business manager.
F. Business Management Receiving the Correct Emphasis
There is often the conflict of quality versus quantity. On large projects it is easy
to make the mistake of over-substitution of numbers of people to satisfy lack of
skill. It is a question of degree as some substitution is commonplace. In most
cases, lack of good contracting personnel is a major problem.
Personnel planning (to project team) needs to be early, resulting in effective
scheduling of all required personnel. Careful consideration should be given to the
timing of all key managers and supervisors.
contractors. The balancing force to contain this risk is the quality and skill of
the owner's project team, both in the precontract activities and the postcontract
work execution program. An equal partner relationship (EPR) is an essential
requirement and should be built in to the agreement with the appropriate con-
tract clause.
These precontract activities should be undertaken by the project team; they
are to ensure that contractor provides competent personnel. It is a contractor
practice to train new/inexperienced personnel on their client's reimbursable pro-
jects since the major cost risk is to the client.
The individual must have full authority to make both design and cost decisions,
with appropriate limits of authority and management reporting requirements.
On reimbursable projects, the authority of the contractor project manager must
be adequate so as to allow efficient day-to-day operations.
Many hold the concept that cost control should be an audit function of the project
and, therefore, report to higher/senior management. The author does not support
that concept as it can lead to an adversarial relationship and dilute the trust
and cooperation that is absolutely essential in the cost effort in the project. There
are always independent, periodic cost reviews by senior home office personnel
that should be more than adequate for a management audit need.
404 Chapter 17
In many cases, the process of developing objectives can also assist in building
team commitment and understanding. Objectives will always be a compromise
among quality, cost, and schedule and are used as a guide to make decisions.
These major objectives then guide development of more detailed goals, procedures,
technical criteria, cost targets, and individual milestones. Ideally, a common set
of objectives should guide owner, engineer, and constructor. These objectives
provide the work direction to all parties and, as such, have to be compatible and
acceptable. The key to successful acceptance by all parties is a set of well-defined
objectives.
A. Client Satisfaction
B. Scope Objective
The objective is that the technical and project scope, as identified in the approved
project budget appropriation, will be achieved. A well-written, but brief, scope
definition is developed for issue to all.
D. Quality
E. Other
If project objectives are not properly organized and constantly maintained, then
acceptance leading to commitment will be lacking. Establishing clear priorities,
with each objective having its relative priority, will allow the multiple groups to
work in harmony with each other. Thereafter, a constant effort (part of team
building) must be made to keep the project objectives viable.
Achieving proper design input from all project parties is a formidable task. This
work is usually the direct responsibility of the project engineering manager,
strongly supported by the project manager. If there is no project team, then it
is the responsibility of the project manager.
All parties (and especially the design decision makers) must reach consensus
and full understanding, as well as approval, of the design basis. The design basis
must be shared openly with all participating parties. When the design basis is
sensitive or proprietary, security procedures must be established. In addition to
406 Chapter 17
design, the project execution plan and financial program must be part of the
approval process.
The purpose of the feasibility study is to develop a well-defined scope (see Chapter
16, "Managing the Feasibility Study," for greater detail). However, the quality
and extent of the early design and project work is a matter of management
decision and can vary widely. A poor design package at the start of detailed
engineering will result in significant change, rework, and substantial cost in-
crease.
The major deliverable of the feasibility study is the basic design package—
statement of requirements (SOR). It should consist of well-written documents
that properly define the technical requirements and have sufficient depth to
provide clear direction for all major design issues. The package should clearly
communicate the intent to the designers and set appropriate boundaries on the
project design for detailed decision making.
The scope document should cover:
• project description:
project justification, project objectives;
- economic justification, if pertinent; and
- facilities description;
• design basis and specifications:
- process definition:
description of process,
process flow diagrams,
tabular heat and material balance,
process conditions/special conditions,
materials of construction, and
startup and shutdown requirements;
- mechanical definition:
P&ID preliminary sizing and tie-ins,
preliminary plot plan,
preliminary general arrangement, and
preliminary equipment list;
- instrument definition:
defining primary control points and purpose, and
defining instrument set points/low-level alarms, etc.;
- safety system:
hazards analysis (hazops),
list of safety devices and their design criteria, and
interlock logic description and diagram;
Front-End Planning and Project Organization 407
Project trending and reporting systems, such as the design change order log, are
essential. The weekly trend meeting and regular progress meetings provide much
of the early identification of change. An effective design control program is
centered around an engineering milestone, called the design control point (DCP).
If the feasibility study is extensive the DCP could be operational at the end of
the study and, thereafter, all changes would be formally documented. If the
feasibility work was minimal, then the DCP would be established at the early
part of the project engineering phase. The DCP is reached when the project's
original scope is properly defined, agreed and approved by all parties. As this
approval is reached, the project manager will inform all appropriate parties that
the DCP has now been implemented. On very large projects there can be multiple
DCPs. It is emphasized that the DCP is not a design freeze as viable design
changes should always be an option.
Figure 17.2 illustrates the format of a design change order.
V. COMMUNICATIONS—INFORMATION UTILIZATION
The requirement is to turn data into useful and useable information. Current
computers and software systems make the gathering and collation of data a
relatively simple task. Thus, correctly establishing the available input data re-
sults in obtaining the required output and information. With the establishment
408 Chapter 17
Project.. Y N
Within Scope • D
No./AFE_ Value Added D •
Funding Revision Required • •
Location^
The execution plan should be a dynamic document, being revised and updated
as conditions/scope change, with proper/timely inputs from all parties. Commit-
ment to the plan must then be achieved with all project parties and, especially,
management.
These are the three major categories of a good execution plan:
What is the scope of work? (discussed earlier),
• How is the work to be executed? and
• When is the work to be carried out?
1. How is the Work to be Executed?
• statement of project objectives;
• proposed division of work:
- in-house,
- work contracted out, and
- development of work packages;
• contract strategy:
required scopes and degree of definition,
- forms of contract, and
- risk allocation versus cost of liability;
• detailed engineering;
• procurement program:
- competitive,
domestic and international,
single source, and
- plant compatibility and spares requirements;
• construction:
- preplanning program (critical highlights),
- prefabrication/modules, and
precommissioning and testing program;
• commissioning and startup;
• quality assurance—control and inspection;
• project organization (described earlier); and
• project coordination procedure (as follows).
• resource analysis:
engineering/construction availability, and
- skills and trade union climate;
marketing interface (limitations or constraints);
• cash flow limitations;
• access problems (weather windows, traffic limitations); and
• shutdown (retrofit program).
B. Other Requirements
• All scope-cost matters are routed through the project manager to ensure
project consciousness and dynamic trending.
A team cost culture is developed on the project and is essential for inform-
ation utilization.
• An internal project charter program is a method for motivating working
togetherness. It is a one- or two-page document, signed by all parties, lists
all major parties and their responsibility/accountability as well as the project
objectives.
• All project parties need to maintain open communication lines at all times
to foster effective organization, project commitment, working togetherness,
and leadership.
A project coordination procedure (PCP) clearly defines communication chan-
nels to all. It includes:
- limits of authority,
- responsibilities of parties,
- correspondence procedures,
- filing and reporting codes,
- document and action schedule (for all drawings, documents, and re-
ports),
- public relations procedures,
- security and safety procedures, and
- project close-out report.
Weekly trend and progress meetings are a must for the project manager.
They are a vital communications tool and are detailed in Chapter 9.
• The project management information system needs effective levels of detail.
Information must be accurate, timely, and useful. Because unnecessary de-
tail can easily be generated with today's computer, a vigorous screening
effort is called for.
VII. SUMMATION
It is again emphasized that FEPPO, as reported by CII, is the number one activity
on any project, and when this work is properly executed, the dollar payout is
immediate and substantial.
If a project is started with a good scope definition and good organization
and all parties are committed to working togetherness, then project success is a
reality.
412 Chapter 17
Prepared by
The Construction Industry Institute A Special CM Publication
Strategic Planning Committee April 1990
The Construction Industry Institute also reports that this program, FEPPO,
is the least used of major project management methods; current research shows
its utilization at an average rate 54%. Figure 17.3 is a chart of the CII study.
18
Managing Engineering—Project Control
Keys/Interfaces
I. INTRODUCTION
413
414 Chapter 18
A. Conceptual/Feasibility Definition
With complex projects, the best case requires a great deal of design effort in
order to properly ascertain the time and cost to complete the project and to
develop clearer technical definition. This front-end engineering design (FEED)
phase can equal 10% of the total design effort. The work is led by an owner
project team and often involves the assistance of an A/E or engineering contractor.
In addition to efficiently determining the best case, another major objective
is to provide a good design basis that will enable lump-sum bids to be sought
for the final engineering phase. However, a lump-sum approach requires good
project discipline in limiting design changes as the work proceeds. If there is a
significant probability of design changes, then a reimbursable approach is recom-
mended.
due to design error, normally about 5% of total design engineering hours, and
for field design rework due to construction error, again about 5% of total design
engineering hours. It is common for this rework to be hidden or under-reported.
Accurate records are essential for proper tracking. Design and scope changes are
easier to track as design contractors doing the work will ensure that these are
fully recorded.
The final part of engineering design is the development of the conceptual design,
resulting from FEED, into full working drawings. This then allows procurement
activities and construction planning to commence. This detailed design work may
be done in-house by the owner, by an A/E, or an engineering contractor.
Detailed design packages are then developed to match construction work
packages which can then be contracted on a lump-sum basis, insofar as is
possible. This can only be achieved with quality construction preplanning.
As the design engineering group has the primary responsibility for design integ-
rity, the role of the project manager is mostly that of business management and
project direction, as follows:
• working with operations/maintenance to develop a quality SOR,
• ensuring an economic design (no "gold plating"),
managing/limiting the impact of operations/maintenance design changes,
• motivating the engineering group to work to the schedule,
ensuring that the design/estimating interface is effective,
• ensuring that the design/procurement interface is effective,
• ensuring that the design/construction interface is effective, and
• ensuring that the design/contracting interface is effective.
416 Chapter 18
From the cost control system, a constant assessment is made of actuals versus
budget for:
• engineering productivity, through an earned value system;
• hourly cost;
• expense and other support costs;
design cost as percent of total cost (typically 10%);
• total engineering hours per drawing (typically 120-150);
hours per P&ID (typically 400-500 for high process severity); and
• hours per piping isometric (typically 4-5 for CAD systems).
The status of these criteria will, in turn, demonstrate the status of this bench-
mark. Chapter 9, "Cost and Schedule Trend Analysis," fully illustrates techniques
that will determine these assessments.
Full application of this category is in the exercise of value engineering and the
application of a quality assurance program. The ongoing design needs to be
constantly evaluated for design characteristics that are not part of the originally
approved design basis and/or are preference items.
As with the cost benchmark, the engineering schedule must also be constantly
assessed for actual progress against plan. Overall progress should always be
measured and on larger projects, individual disciplines should also be measured.
The following are key milestones that should be assessed:
Were IFC drawings issued to schedule?
If not, what was the slippage (by discipline)?
• Did design packages meet purchase order dates?
If not, what was the slippage (by discipline)?
Did design slippage cause material delivery delays?
If so, give details.
• Did design delay cause delay in letting contracts?
If so, give details.
D. Ease of Start-Up
This benchmark is assessed by comparing the actual cost and schedule of com-
missioning against the estimated or budgeted numbers. On larger projects there
Managing Engineering—Project Control Keys/Interfaces 417
is an individual group or crew for commissioning and start-up, and the effective-
ness and interaction of this group with the regular construction staff can also be
part of the assessment of this benchmark.
The following are key milestones that should be assessed:
• Did start-up program meet schedule?
If not, give details.
Did start-up costs meet budget?
If not, give details.
Was the assigned start-up team adequate (numbers and skills of personnel)?
If not, give details.
The cost of equipment and material can be more than 50% of the total project
cost. As such, it is vital that full and proper business considerations be in place
in the selection of all equipment and materials. It is very common for engineers
to select on a technical preference basis or for operations/maintenance personnel
to ignore capital costs and select on compatibility (existing equipment), spares
availability, maintainability and operating characteristics. Both technical and
business considerations are equally important, and their relative priorities should
have been properly identified as part of the value engineering-quality assurance
program.
A. Lump-Sum Basis
As the contractor has most of the financial risk, the major activities of the project
team (subject to contract conditions) are:
B. Reimbursable Basis
As the owner has the major financial risk, the contractor monitoring effort is
much more detailed, and the contractor requires the following major procedures:
• detailed cost control/reporting system;
engineering change log (weekly) maintained by design groups to show design
changes from the approved for expenditure (AFE) design basis and then
evaluated by the cost group for possible impact on project cost/schedule;
• detailed planning and scheduling, complete with the progress/completion
curves, staffing histograms and productivity profiles;
earned value progress/productivity measurement system (larger projects);
• hours tracking program/curves (small projects);
• purchasing/procurement plan;
quality equipment bid summary procedure; and
• trending system/weekly trend report.
• progress measurement,
productivity analysis, and
• trending and forecasting.
On reimbursable projects, the daily interaction of the design group with the
contractor personnel should achieve the desired quality of design/procurement.
Managing Engineering—Project Control Keys/Interfaces 419
With most companies, projects are executed with a phased approach, and the
funding of the execution phase of a project is often referred to as full funding.
The early development stage of a project is usually funded by the operations/
production group from its own budget or from company expense.
Full sanction requires a specified quality of cost estimate so that manage-
ment can evaluate the financial risks when approving/authorizing the funds.
These funding or appropriation estimates generally range from 10-20%. The
manufacturing industries normally require a 10% quality estimate for full sanc-
tion, whereas the petrochemical industry normally requires a 20% estimate. This
lower quality estimate is accepted because of the larger size of projects, plus the
need to execute these projects with the fast-track approach. The fast-track method
works from a lower degree of engineering definition and, therefore, only allows
a lower quality of cost estimate.
A quality feasibility study and FEED will allow a Class II (+20%) or better
cost estimate to be completed for subsequent application for sanction (manage-
ment approval) of full funds. To obtain a Class I (+10%) cost estimate, the
engineering and procurement has to be greater than 80% complete. Work carried
out in producing the feasibility study and FEED are funded by the client division
ESTIMATING QUALITY vs STATUS OF E.P.C. - PHASE 11. PROJECT
NOTES : TYPICAL ESTIMATING CATEGORIES
1. Proratlon (40/25%)
1. ACTUAL PROGRESS PLOTTED AGAINST COMPANY HISTORICAL EXPERIENCE . 2. Cost Capacity Curves (30/20%)
2. EARLY CONSTRUCTION START REFLECTS A PROJECT WITH EXTENSIVE SITE PREPARATION . 3. Equipment Ratio (20/15%)
3. CONCEPTUAL DESIGN HAS BEEN COMPLETED DURING A PHASE 1 OPERATION . 4. Quantitv/Unit Cost (10/5%)
I g:;||| /_ CONSTRUCTION!
ADVANCE COMITMENTS
OF CRITICAL MATERIAL I
CAN BE MADE IN I
PROJECT DURATION - %
CONCEPTUAL PHASE EXECUTION PHASE O
PHASE 1 PHASE 11 Q)
-a
Figure 18.1 Estimating quality versus status of EPC.
oo
Managing Engineering—Project Control Keys/Interfaces 421
from the sanction of a Class III (+30%) or better cost estimate. Figure 18.1
illustrates the historical quality of the cost estimate in relation to completion of
engineering and procurement.
All required technical approvals must be prompt and/or meet the required con-
tractual timing if the work is contracted. Likewise, the associated handling
procedures must be effective to prevent delays. This is to ensure that the con-
tractor cannot accuse the owner of compensable delays and/or negligence, as these
are common claims.
19
Managing Procurement—Project Control
Keys/Interfaces
I. INTRODUCTION
Effective procurement means getting the right material to the right place at the
right time at the right price. Procurement comprises the three functions of pur-
chasing, expediting, and inspection. The work is carried out in accordance with
the contract and procurement strategies developed by the project manager during
the preproject stage and in compliance with corporate purchasing policies. Figure
19.1 illustrates these essentials.
The best procurement policy within the private sector obtains the best value for
the lowest cost. In addition to price and delivery, best value takes into account
other commercial and services considerations, as follows:
• appropriate quality of materials and equipment as per the technical speci-
fications (i.e., reduce/eliminate extra quality);
• terms of payment, conditions of purchase, performance guarantees, quantity
discounts, import duties and taxes, etc.;
• availability and cost of vendor services, startup support and spares;
• quantity sensitivity analysis of unit price tenders to evaluate total tender
price;
• standardization/compatibility with existing plant and equipment; and
• potential for future price increases due to changing specifications.
There are two distinct policies in relation to price negotiations. The first is
a sealed bid/lowest competitive price, which precludes price negotiating if there
are not technical/contract condition changes. Price negotiations, then, are only
423
424 Chapter 19
1. Right Material, to
2. Right Place, at
3. Right Time, and at
4. Right Price
5. Procurement Program
• Purchasing
• Inspection
• Expediting
6. Pre-Project Strategy & Execution Plan
7. Compliance with Corporate Policies
The following activities, illustrated by Figure 19.2, are essential for a quality procure-
ment program. Such activities are necessary for effective execution and control:
developing a purchasing plan for critical material;
establishing a current and approved bidders list;
• using sealed bids and/or price-alone negotiating;
• preparing quality bid summaries;
• issuing material requisition and purchase orders in a timely and proper
manner;
• using effective vendor drawing control;
expediting items adequately, including material status reports;
maintaining close liaison with planning engineer on delivery times and
MSRs;
• keeping to an inspection schedule;
keeping an efficient material receiving and inspection system;
• having adequate material documentation/control system;
• forecasting final costs of major purchase orders/contracts;
• maintaining close liaison with cost engineer on prices and bid summaries; and
evaluating carefully spare parts for plant startup.
The most difficult, and in many respects, the most important of the above
activities is forecasting the final cost of major purchases. This activity requires
considerable skill in developing accurate forecasts and should be a regular part
of the monthly project cost forecast. Figure 19.3 shows and emphasizes these key
elements.
426 Chapter 19
Essentials
1. Critical Material Purchasing Plan
2. Current Approved Bidders List
3. Formalized Price Negotiating Policy
• Sealed bid and/or price alone
4. Quality Bid Summaries
5. Effective MR & PO Procedures/Timing Issue
6. Good Vendor Drawing Control
7. Coordinated Expediting & MSR's
8. Close Liaison with PlannerOn Delivery Times
9. Inspection Schedule
10. Efficient Material Receiving
& Inspection System
11. Adequate Documentation/Control System
12. Periodic Forecasting of Costs of Major PO's
13. Close Liaison With Cost Engineer on Prices
14. Careful Evaluation of Spare Parts
With a lump-sum design and procurement contract, the contractor is fully liable
and responsible for the quality and cost of all the materials and subcontracts.
Full liability and responsibility is termed an independent contractor relationship.
However, quality should be carefully monitored to ensure that all materials meet
specification and that checks are made on the progress, schedule, and execution
of the work.
The project buyer is a buyer from corporate purchasing who has been assigned
the purchasing function for a specific project. The individual is resident in the
corporate office. This provides the project with the facility for fast-track purchas-
ing when the work is being done in-house.
Corporate services and expertise are generally utilized on small projects. Alter-
natively, corporate services can be required by the owner's PPC due to high
workload problems or the need for specialist services. When there is no assigned
project buyer, the lack of designated responsibility can result in purchasing delays
and a poorly coordinated program. The impact on the project(s) can be disastrous.
Using corporate purchasing division services can result in more advanta-
geous terms being obtained for price, delivery, conditions of purchase, terms of
payment, maximum net discounts for volume and bulk purchases, etc. It also has
the added advantage of enabling other owner project material surpluses to be
assessed for compatibility with the project materials requirement.
E. Construction Contractor
V. PROCUREMENT PROCESS
A. Inquiry
Inquiries should only be issued to companies with adequate and proven capability.
These companies should be shown on the current bidders list. The practice of seeking
bids only for budget/estimate checks is to be avoided if at all possible. If there is no
serious purchasing intent, the supplier/contractor costs increase due to the cost of
spurious bidding, and the business credibility of the company is impaired.
The project bidders list should be developed by the PPC, in conjunction with
corporate purchasing and approved by the project manager.
The technical requirements contained within a material requisition should
be as complete as possible in terms of specification, inspection documentation re-
quirements, etc. The information should be stated in a concise and unambiguous
manner to obtain quality bids from suppliers. Requisitions should be properly
checked against the control estimate, prior to authorization by the project manager.
<Q
SPECIFICATION PURCHASMG PLACE *O.
* DATA SHEET
ENGJNEEWNG MATERIAL **CKAGE VENDOR
OPTIMIZATION REQUSmON BOPERKX)
(D
2W 2W 2W 4-8W
THE EARLY F € A S -
WLJTYAOPnMC-
ATION WORK VIR-
1
E S GREATLY FOR
EACH PROJECT ENGINEER*** PROCUREMENT
4W 12-18W
o
s
GENERAL EQUPMENT & BULKS
8-T2W
8-t2W
8-T2W
8-12W
is>
Figure 19-4 Front-end engineering and procurement. CO
430 Chapter 19
Competitive open bids solicit supplier's best prices and a satisfactory price is then
achieved through the open negotiating technique, after bids are received and
evaluated.
Competitive negotiated bids follow the same procedure as above, except that the
negotiating commences immediately following receipt of the inquiry docu-
ments by the suppliers. This method saves the time of waiting for the formal
bids and also forces the suppliers to prepare their bids quickly. The method
is used when time is critical.
Single-source competitive bids are solicited from a single supplier, without the
supplier being aware that it is the only bidder. The open negotiating tech-
nique is then used.
Single-source negotiated bids are solicited from a single supplier, with the supplier
knowing that it is the only bidder. The opening negotiating technique is
then used to obtain the best deal in the noncompetitive situation.
Competitive sealed bids require all bids to be sealed on submission by the sup-
pliers and opened simultaneously in the presence of a company's confidential
bid committee. The bids will then be recorded and signed, timed, and dated
by the committee members. There may be little or no price negotiating.
Single-source sealed bids follows the same procedure as above, except there is
only one bid, and the bidder may not be aware of that fact.
Subsequently, a bid tabulation should be prepared summarizing the evaluation
of the bids on a technical, delivery, financial, and commercial basis and including
an award recommendation. A final cost forecast should be part of the evaluation,
and this analysis should consider potential changes that might occur in the future
due to design development and/or project and site conditions changes.
C. Ordering
Following approval of the bid evaluation by the appropriate project authority, the
order is placed promptly. Any negotiations between receipt of bids and placing of
orders should be carried out with the involvement of the appropriate procurement
personnel (i.e., PPC, project buyer, corporate purchasing, or contractors).
Many other countries have a similar program, and such restrictions should
be recognized in their cost estimate, project schedule, and purchasing program.
E. Expediting
Expediting covers both the delivery program and the submission dates for draw-
ings and certification. This requires a close liaison between the project planning
engineer and the expeditor. Construction frequently takes over the progress
chasing materials where critical site delivery problems are anticipated.
Project materials status reports (MSRs) are produced regularly by suppliers,
contractors, and corporate purchasing. These are collated and updated by the
PPC and distributed to appropriate members of the project team for input and
action. The prime purpose of MSRs is to highlight potential problem areas so
that appropriate action can be taken.
F. Inspection
G. Delivery
The method of delivery and delivery responsibility must be clearly defined when
ordering. Equipment and goods must be properly checked by the site materials
controller against the order details for correctness, completeness, and transit
damage. A goods receipt notification is then issued and the goods, if not im-
mediately required for installation, should be suitably protected before being
consigned to stores.
The lack of materials during construction can have a disruptive and costly effect
on a project; it is equally important that project funds are not wasted by over-
ordering. Disposal of surplus materials normally recovers only a small fraction
(typically 5-10%) of the original cost of the materials. In order to minimize the
amount of surplus materials, the project manager and his team need to take the
following steps:
1. When possible, ensure early completion of detailed engineering and accurate
materials takeoff prior to purchase.
2. When accurate materials takeoff cannot be achieved at the time materials
must be ordered, take particular care to ensure the accuracy of the estimated
quantities.
3. Use manufacturers' standard products and stock materials wherever possi-
ble. This approach will:
- reduce purchasing lead time and costs,
- render surplus materials attractive to a wider market, and
- increase the potential recovery from sales of surpluses.
4. Carefully monitor the contractor's procurement to prevent excessive over-
ordering.
5. During the course of the project, undertake periodical reviews of bulk ma-
terials to identify any that are unlikely to be used or are clearly surplus.
This should be done by the PPC.
6. Dispose of surplus material early to increase the chances of higher rates of
cost recovery as the opportunities to sell these materials to the operations
group, other company projects, or third parties are likely to be most favor-
able.
7. Transfer surplus materials available during and at the end of a project to
other company projects at, or approaching, the purchase value, provided:
- they are required,
- they are in good condition, and
- necessary certification is available.
20
Managing Construction—Project Control
Keys/Interfaces
433
434 Chapter 20
% Wt'd
Wt. Actual %
1 Construction Manager 20
Properly Motivated by
Business Considerations
3 Cost of Construction 35
vs. Estimate
4 Performance Against 25
Original Construction Schedule
TOTAL 100%
Remarks:
There are, in addition, many other interdependent activities that require early
attention. For instance, the payout of quality preplanning, in improved construc-
tion efficiency and productivity, is very significant.
Many companies are now developing the project schedule/execution plan back-
wards. This means concentrating on the construction schedule and developing at
this early stage, the most economical construction program possible, usually referred
to as the EPC. Engineering and material delivery requirements are then matched
to the construction program. The matching must not be a force-fit, as such an
action would render the program invalid by producing an impossible schedule.
On EPC projects the typical relationship between engineering and construc-
tion labor hours (direct) is the ratio of 1:6. Thus, the deliberate attention to
Managing Construction—Project Control Keys/Interfaces 435
Remarks:
preplanning and constructability at an early design stage can reduce the ratio
and save construction labor hours. The potential cost saving is substantial.
The following is not all-inclusive but is typical of major preplanning consid-
erations:
When the work is contracted out, the owner project team function:
provides overall site coordination,
• ensures an acceptable quality of construction,
ensures that work is installed to the drawings and specifications,
• evaluates the contractor performance,
• interfaces with the operating group, and
institutes correct handover procedures.
On small projects, the owner construction management function is often handled
by the project manager. However, this dual function is rarely effective on inter-
mediate/larger projects, as the construction manager responsibility is too demand-
ing. It is strongly recommended that owners only assign experienced, professional
construction managers to larger projects.
It is now widely accepted that today's construction managers need to be
professional project managers. They need to be:
• organizers,
planners,
• motivators,
leaders,
communicators, and
• business-oriented.
and cost engineers. Quantity surveyors are also used in measuring work done
and administering contracts based on measured work/unit prices, usually sup-
ported by one or more contracts officers/administrators.
The project manager, construction manager, and staff have a sensitive and im-
portant interface with the existing or future (on grassroots sites) operating staff,
particularly on matters of safety and handover. The sensitivity occurs at the
precommissioning stage when the project/site team and operating staff have a
joint responsibility for an efficient plant start-up. At this stage the site team has
the task of full cooperation with the operating staff and, at the same time, must
resist excessive changes requested by the operating staff. This, therefore, requires
sensitivity and tact to meet the project cost objectives and maintain a good rela-
tionship with the operating personnel. An effective way to enhance a good working
relationship is the early assignment of an operating individual to the site team
to act as a permanent liaison/coordinator for all operating/plant matters.
A further interface takes place with external regulating authorities and bodies
in the implementation of national and local regulations, work permits, environ-
mental reports, etc.
When the work is contracted out, the construction manager has a coordination
role which, if not properly executed, can lead to serious legal implications and/or
contractor claims. In this coordinating position the construction manager has to
ensure satisfactory overall management of the project schedule, site safety, and
labor relations. The safety and security of the site or location as a whole is his/her
responsibility. Although each contractor will be responsible for the safety and
security of its own working area, it is necessary to ensure that common and
adequate standards are observed by all site contractors.
As the project manager's representative onsite (particularly on remote and
large multicontract sites), the construction manager has an overview of all aspects
of the works and their relative priorities. Thus the construction manager may
directly administer those contracts covering general site services such as staffing
buses, catering, medical facilities, and camp accommodations.
An owner can assign this coordinating liability to a managing contractor/con-
struction manager, but the owner must step back and allow this representative
full, total, and day-to-day management of the site.
438 Chapter 20
Remarks:
Figure 20.3 Benchmarking assessment: efficient site management and multiple con-
tractor coordination.
Remarks:
Figure 20.4 Benchmarking assessment: correct labor resources as to skill and number
workers.
Remarks:
Figure 20.5 Benchmarking assessment: effective work planning and scheduling at all
levels.
Of the many effective monitoring techniques, as listed, the single most effective
technique is the weekly trend meeting and trend report.
To ensure that the transition from each stage is clearly defined for any particular
section of the project, a series of certificates is used, typically referred to as:
• mechanical completion certificate,
• takeover certificate,
performance certificate,
• certificate of completion, and
• final acceptance certificate.
The potential hazards arising during the changeover from construction through
precommissioning to commissioning are probably greater than at any other time
during construction or subsequent fulltime operation. This reflects the transfer
of responsibilities, the involvement of commissioning and operating personnel
unfamiliar with the plant, and the introduction of potentially hazardous materials
into previously safe areas.
It is, therefore, essential at this stage that the responsibilities of all parties
for complying with safety requirements are clearly defined and understood. Fur-
thermore, it is also essential that the permit to work system, to cover the safe
use of utility systems during precommissioning activities, is taken over at the
appropriate time by the operating company in order to cover all plant systems.
Index
445
446 Index