Engineering Quantity
Engineering Quantity
Chapter # 01
Introduction
1.1. Review of area, perimeters and volumes of various plane and solid
geometrical figures.
1.2. Estimate and its types.
1.3. Data for estimating.
1.4. Various units of measurement and their conversion. (FPS, MKS and SI
Units)
1.1. Introduction:
Quantity surveying is an assessment of the cost based on certain rates of
materials and labour. An estimate should be realistic assessment should be
made on actual conditions of market. Estimation is undoubtedly one or the
most important aspects of a construction project. A good estimation saves
the expenditure to a great extent and ensures optimum use of materials.
Estimation is very much technical. It requires good knowledge on structural
design, properly or engineering materials and essentially practical
experience.
Essentials in a good Quantity Surveyor: He must be able to describe clearly in
proper unambiguous language the requirement of the Architect and so
arrange his bill of quantities (BoQ) that the Builder can quickly, easily and
accurately arrive at the estimated cost or the work. The Quantity Surveyor
must have a sound knowledge or building materials and construction and or
customs prevailing in the trade. He must be accurate in his work and
calculations.
Page 1
CHAPTER # 01 INTRODUCTION
Page 2
CHAPTER # 01 INTRODUCTION
Page 3
CHAPTER # 01 INTRODUCTION
Page 4
CHAPTER # 01 INTRODUCTION
Page 5
CHAPTER # 01 INTRODUCTION
(a) Taking out dimensions and squaring them i.e. the dimensions of the
various items of work are taken from the relevant drawings and are
multiplied (i.e. squared) to obtain its quantities and are entered in the
‘Measurement Sheet Form’.
(b) Abstracting i.e. the quantities of the various items of work calculated as
above are multiplied by the rates of those items obtained either from the
schedule of rate or worked out by rate analysis and are entered in the
‘Abstract Sheet Form’. If ‘rate’ and ‘amount’ columns in the abstract sheet
form are left blank (to be entered by the contractor) then it is termed as the
‘Bill of Quantity’.
Page 6
CHAPTER # 01 INTRODUCTION
Page 7
CHAPTER # 01 INTRODUCTION
In order to work out the quantities of various items of work, a complete set
of detailed drawings consisting of plan, elevation, sections and foundation
details etc. is required.
The relevant dimensions i.e. length, breadth, depth or height of the items,
whose quantities are to be worked out, can be measured from such
drawings.
After the quantities of various items of work involved are calculated, they are
to be multiplied by the current market rates of those items.
The Government department such as Buildings and Communication,
Irrigation and Power Department prepares schedule of rates for all items of
work pertaining to the department for a district or area, on the basis of
analysis of rates of items.
A booklet called ‘Market Rate System’ (M.R.S) is available in such
Government Organizations.
Page 8
CHAPTER # 01 INTRODUCTION
1.4.4. SI system:
SI unit is an international system of measurements that are used universally
in technical and scientific research to avoid the confusion with the units.
Having a standard unit system is important because it helps the entire world
to understand the measurements in one set of unit system.
In this system the units used for measurements of quantities are as follows;
Length = Meter (m)
Mass = Kilogram (kg)
Time = Second (Sec)
Amount of substance = mole (mole)
Page 9
CHAPTER # 01 INTRODUCTION
P a g e 10
CHAPTER # 01 INTRODUCTION
P a g e 11
CHAPTER # 01 INTRODUCTION
1.6.2. Rectangle:
Let us consider a rectangle of length 'l' units and breadth 'b' units.
P a g e 12
CHAPTER # 01 INTRODUCTION
1.6.3. Triangle:
If a, b, c are the sides of the triangle, then the perimeter of triangle = (a + b +
c) units.
● Area of the triangle = √(s(s - a) (s - h) (s - c))
The semi-perimeter of the triangle, s = (a + b + c)/2
P a g e 13
CHAPTER # 01 INTRODUCTION
P a g e 14
CHAPTER # 01 INTRODUCTION
1.6.5. Parallelogram:
ABCD is a parallelogram with base (b) and altitude (h).
1.6.6. Trapezium:
P a g e 15
CHAPTER # 01 INTRODUCTION
1.6.7. Circle:
The distance around the circular region is called its circumference. The ratio
of circumference of any circle to its diameter is constant. This constant is
denoted by π and is read as pie.
Circumference/Diameter = Piei.e., c/d = π or c = πd
We know that diameter is twice the radius, i.e., d = 2r
C = π × 2r ⇒ C = 2πr
Area of circle = πr²
P a g e 16
CHAPTER # 01 INTRODUCTION
V=l×w×h
l = Length
w = Width
h = Height
1.6.9. Cube:
V = a3
a = Length of edge or side
1.6.10. Cylinder:
V = πr2h
r = Radius of the circular base
h = Height
P a g e 17
CHAPTER # 01 INTRODUCTION
Sphere:
V = (4⁄3)πr3
r = Radius of the sphere
1.6.11. Pyramid:
V = (1⁄3) × B × h
B = Area of the base,
h = Height of the pyramid
Figure 1.13.Pyramid
P a g e 18
CHAPTER # 01 INTRODUCTION
1.6.14. Ellipsoid:
V = (4⁄3) × π × a × b × c
a, b, c = semi-axes of an ellipsoid
EXERCISE
M.C.Qs
Encircle the correct statement.
1. An assessment of the cost based on certain rates of materials and
labour is called:
(a) Quantity surveying (b) Surveying
(c) Mapping (d) a&b
2. A rough calculation on quantities of various works & their
expenditure.
P a g e 19
CHAPTER # 01 INTRODUCTION
P a g e 20
CHAPTER # 01 INTRODUCTION
Short Questions
1. Define quantity surveying.
2. Define estimate.
3. Enumerate the types of estimates.
4. Define approximate estimate.
5. Define detailed estimate.
6. Define plinth area estimate.
7. Define annual repair estimate.
8. When revised estimate is prepared?
9. Enlist the data required for estimation.
10. Enlist the systems of measurement.
11. Differentiate between FPS and SI system.
12. Write down the formulae to calculate circumference and area of
circle.
P a g e 21
CHAPTER # 01 INTRODUCTION
13. Write down the formulae to calculate perimeter and area of triangles.
14. Write down the formula to calculate volume of sphere with the help
of diagram.
15. Write down the formula to calculate volume of right circular cone
with the help of diagram.
Long Questions
1. Define quantity surveying and give its importance. Also, describe the
qualities of a good quantity surveyor.
2. Define estimate and give brief description of the types of estimate.
3. Describe the data required for estimating.
4. Briefly describe the various units of measurements.
5. Write down the formulae to calculate area and perimeter of the
following figure:
a. Rectangle
b. Triangle
c. Rhombus
d. Parallelogram
e. Circle
P a g e 22
CHAPTER # 02 SPECIFICATIONS
Chapter # 02
Specifications
1.5. Definition and purpose of specifications
1.6. Principle of writing specs
1.7. General specifications.
1.8. Detailed specifications of all items of work.
1.5. Introduction:
A Specification is a special description or a particular subject. An engineering
specification contains detailed description or all workmanship and materials
which are required to complete an engineering project in accordance with its
drawings and details. The technical drawings of a structure will show, the
proportions and relative positions of the various components of the
structure. It is not often possible to furnish the information on the drawings,
regarding the quality or materials to be used and the quality of workmanship
to be achieved during construction, due to shortage of space. This data
regarding the materials and workmanship is conveyed in a separate contract
document, which is known as the "specifications" for the work. Thus the
drawings with the specifications “will completely define the structure”. The
“specification” is furnished separately along with the drawings and is an
essential part of all engineering contracts.
(b) Specifications of a work are required to describe the quality and quantity
or different materials required for a construction work and is one of the
essential contract documents. Thus a contractor can make a programme to
procure the materials required for a project and the owner can check the
quality of materials conforming to the specification avoiding dispute with the
contractor.
P a g e 23
CHAPTER # 02 SPECIFICATIONS
(c) This also specifies the workmanship and the method of doing the work.
Thus specification of a work serves as a guide to the supervising staff of the
contractor as well as to the owner to execute the work to their satisfaction.
(d) A work is carried according to its specification and the contractor is paid
for the same. Any change in specification changes the tendered rate.
P a g e 24
CHAPTER # 02 SPECIFICATIONS
1.7.2. Workmanship:
It should be clearly mentioned that how new work will be protected from
rain water, temperature, freezing and other atmospheric changes. New work
includes excavation, brick masonry, concrete pouring, plaster etc…
1.3.5. Expression:
Expressions should be very clear. Specifications have legal value, therefore
sentences should be short and complete. For conveying complex
information, short sentences should be used. It break up information into
smaller and easier to process units. Long complicated sentences can confuse
reader and doubtful the main point. Every single paragraph should only be
limited to only one issue.
Vocabulary should be such that it not creates a dual meaning. It should be
such that every reader grasps the same meaning. Language, format and
usage should be consistent. Beside this, specifications must also be
consistently enforced. Specifications only remain effective, if it is consistently
enforced. Without it even well written specifications become ineffective.
P a g e 25
CHAPTER # 02 SPECIFICATIONS
1. General Specifications.
2. Detailed Specifications.
They are used to show aspect, standard, and type of constructional work.
Detailed Specifications of the items used in ordinary projects are printed that
are used for contracts.
P a g e 26
CHAPTER # 02 SPECIFICATIONS
a) Standard Specifications.
b) Special Specifications.
a. Standard Specification.
So, these are known as Standard Specifications that are published in the form
of books and generals.
P a g e 27
CHAPTER # 02 SPECIFICATIONS
b. Special Specification.
Some specifications of the construction work are of the special form, and
they are not officially written and published in Standard Specifications.
P a g e 28
CHAPTER # 02 SPECIFICATIONS
vii. Mixing shall be done on masonry platform or sheet iron tray if mixing
is to be done by hand.
viii. Stone ballast, sand and cement shall be put into cement concrete
mixer to have the required proportions.
ix. Regular slump test should be carried out to control the addition of
water and to maintain the required consistency. A slump of 7.5cm to
10cm may be allowed for building work.
P a g e 29
CHAPTER # 02 SPECIFICATIONS
xi. Concrete shall be laid gently (not thrown) in layers not exceeding
15cm and compacted by pinning with rods and tamping with wooden
tampers or with mechanical vibrating machine until a dense concrete
is obtained.
xii. After about two hours of laying of concrete, when the concrete has
begun to harden, it shall be kept damp by covering with wet gunny
bags or wet sand for 24 hours.
P a g e 30
CHAPTER # 02 SPECIFICATIONS
P a g e 31
CHAPTER # 02 SPECIFICATIONS
vii. After laying the concrete of 24 hours, it should be cured minimum for
7 days.
viii. After completing the curing properly, the surface should be left to dry
out to get the cover of hot bitumen.
ix. After drying the concrete surface, it should be cleaned with brushes
and with a kerosene soaked cloth piece.
x. Finally, the treated concrete surface should be filled uniformly with
hot bitumen in specified quantity.
EXERCISE
M.C.Qs
Encircle the correct statement.
16. Document containing data regarding the materials and
workmanship is:
(a) Drawing (b) Estimate
(c) Specifications (d) None of these
17. An essential part of all engineering contracts.
(a) Drawing (b) Estimate
(c) Specifications (d) None of these
18. The cost of unit quantity of work is governed by:
(a) Drawing (b) Estimate
(c) Specifications (d) None of these
19. Brief specifications are known as:
(a) General specifications (b) Detailed specifications
(c) Standard specifications (d) Special specifications
20. Specifications that are published in the form of books by
departments.
(a) General specifications (b) Detailed specifications
(c) Standard specifications (d) Special specifications
P a g e 32
CHAPTER # 02 SPECIFICATIONS
Answers
11.a
Short Questions
16. Define specifications.
17. State four purposes of specifications.
P a g e 33
CHAPTER # 02 SPECIFICATIONS
Long Questions
1. Define specifications and describe its purposes.
2. State the principals of writing of specifications.
3. Describe the data required for estimating.
4. Briefly describe the types of specifications.
P a g e 34
CHAPTER # 03 BUILDING ESTIMATE
CHAPTER NO. 3
BUILDING ESTIMATE
Introduction
Basically building estimate is of two types . First one is rough cost estimate
and second one is detailed estimate. Rough cost estimate is used to calculate
the cost that is not perfectly accurate but it is an approximate estimate
which helps to decide whether money can be arranged for the building or
not. This estimate is prepared with different methods for different types of
buildings. Rough cost estimate is applied to get administrative approval.
When it is decided to build a building another type of estimate is made this is
called as detailed estimate. Estimates are made in different ways according
to different buildings such as public work departments, military engineering
services etc. In addition, English method is also used in some departments
and private firms, but basically it is always implemented in following two
ways.
A. First one is center line method
B. Second one is individual method or long wall and short wall method.
P a g e 35
CHAPTER # 03 BUILDING ESTIMATE
While preparing the estimate, some of the amount is included for the items
which are applied at the construction stage with the approval of the owner
or project manager or site engineer. For example door and window and their
fittings, water supply fittings are to be decided at the time of fitting
according to the choice of the owner or engineer incharge .For the execution
of such items a reasonable amount is kept in the estimate as prime cost and
the same is also provided in bill of quantity. The actual cost of article is paid
to the contractor, he is not allowed to any profit to prime cost articles.
3.1.6 Premium
After the schedule of rate is ready, rates of the market increase, due to
which when contracting with the contractor, the rates more than the
schedule of rates are included, called premium.
P a g e 36
CHAPTER # 03 BUILDING ESTIMATE
3.1.7 Rebate
After the schedule of rates is prepared, if the market rates goes down, the
contractor will contract the schedule at a lower percentage of schedule of
rates. The decreased percentage from the scheduled rate is called the
rebate.
3.1.8 Contingencies
There are items of works in the estimate that cannot be listed under any
particular title. An additional 3% to 5% of the total estimate is added to cover
these expenses. These are called contingency charges.
P a g e 37
CHAPTER # 03 BUILDING ESTIMATE
3.1.13 FIDIC
External Services
Plinth Area
The area built on the floor is called Plinth Area, It also includes verandahs
other passages over which there is a roof. This area is measured Up to the
outer edges of the outer walls.
Floor Area
It covers the interior area of all the rooms. The rooms also include kitchen,
washroom and stair. It does not include are of walls.
Carpet Area
P a g e 38
CHAPTER # 03 BUILDING ESTIMATE
The area of the living rooms of the building is called Carpet Area. It does not
include the area of kitchen, washroom, stair and verandah etc.
There are different methods are applied to prepare rough cost estimate.
P a g e 39
CHAPTER # 03 BUILDING ESTIMATE
of estimate is a little bit more accurate than above mentioned methods and
mostly suitable for multi storied buildings
Cubic content estimate = Volume of the building X unit cubic rate (known
value)
Volume of the building = plinth area (length X breadth of the proposed
building) X height of the building (floor to roof top)
Solution
Plinth area of the building= 2080 sft
Rate of construction = 3050 rupees/sft
Cost of construction of building = 2080 x 3050 = 4,888,000 Rupees
Cost of water supply and sanitary = = 391,040 Rupees
Cost of electric supply = = 391,040 Rupees
P a g e 40
CHAPTER # 03 BUILDING ESTIMATE
Solution
Plinth area of the building= 280 M2
Rate of construction = 12500 Rupees/M2
Cost of construction of building = 280 x 12500 = 3,500,000 Rupees
Cost of water supply and sanitary = = 280,000Rupees
Cost of electric supply = = 280,000Rupees
Cost of gas supply = = 140,000 Rupees
Total cost = 3,500,000 +280,000+280,000+140,000 = 4,200,000 Rupees
Contingencies = 4,200,000 x = 126,000 Rupees
Grand total = 4,200,000 + 126,000 = 4,326,000 Rupees
Example No. 3.3
Prepare the rough cost estimate for a proposed commercial plaza from the
following data.
P a g e 41
CHAPTER # 03 BUILDING ESTIMATE
c. Gas arrangement @ 5%
d. Fluctuation of rates @ 5%
e. Contingencies @ 4%
f. Contractor profit @ 10%
Solution
Cubical contents = No of storey (Plinth area x height of each storey)
= 3(535x3.50) = 5,617.5 M3
Cost of building = 5,617.5 x 2250 =12,639,375 Rupees
Water supply & sanitary arrangement =12,639,375x =1,011,150 Rupees
Electrification =12,639,375x = 884,756.25 Rupees
Gas arrangement = 12,639,375x = 631,968.75 Rupees
Fluctuation of rates =12,639,375x = 631,968.75 Rupees
Contingencies = 15,799,218.75x = 631,968.75 Rupees
Total cost = 12,639,375 +1,011,150 +884,756.25 +631,968.75 +631,968.75
= 15,799,218.75 Rupees
Contractor profit = 15,799,218.75x = 1,579,921.875 Rupees
Grand total = 15,799,218.75 +1,579,921.875 = 17,379,140.625 Rupees
Example No3. 4
Prepare rough cost estimate of given line plan. The rate of construction is
570/sft. Add 8% for electrification, 4% for water supply, 4% for sanitary and
3% contingencies.
Solution
Outer size of building
Length = 14’+18’+
9”+9”+9”=34.25’
Breadth=
14’+8’+9”+9”+9”=24.25’
Covered area of building = 34.25x24.25’ = 830.5625 sft.
Rate of construction= Rs. 570/sft
Cost of construction= =
830.5625x570= 4,73,420.625 Rs
Electrification charges = = 37873.65 Rupees
P a g e 42
CHAPTER # 03 BUILDING ESTIMATE
P a g e 43
CHAPTER # 03 BUILDING ESTIMATE
Detailed Estimate
Detailed Estimate of a building is determined by finding out the quantity of
its various items. After finding their quantity it is multiplied by their unit
rate and hence cost is measured. These items are called Item of Work.
Numbers of certain items are found out in numbers such as door and
window fittings , water supply fittings and sanitary fittings etc. Some items
are expressed in length only and their quantity is recorded in meters or foot.
For eexample sun shade Skirting and concrete joints etc. Some items are
measured in area such as Plaster, Pointing, White Washing and Painting etc.
Some items are measured in volume, such as earth work concrete and
masonry work, etc. Some items are measured with respect to their weight,
such as steel bars and other sections of steel.
The units for measuring the various items of a building are as follows
Sr. Description of work Units of Unit of rate Units of Unit of
No measure- measure- rate
ment. ment
1 Earthwork Cu. m Per% cu m cft Per ‰ cft
Earth work in excavation in any type of
soil
2 Clearing of sites, brushwood and small Sq m Per sq m sft Per% sft
trees
3 Earthwork in filling (with sand or loose Cu. m Per% cu m cft Per ‰ cft
earth) in foundation trenches or plinth.
4 Surface dressing Sq m Per sq m sft Per% sft
5 Brick work. Cu. m Per cu. m cft Per% cft
Brickwork (with lime or cement mortar)
of one or more than one brick wall
(one) brick thick walls when length of
brick is parallel to the thickness of the
wall.
6 Brickwork in Arches. Cu. m Per cu. m cft Per% cft
7 Reinforced brickwork. Cu. m Per cu. m cft Per% cft
8 Honeycomb brick work Sq m Per sq m sft Per% sft
9 10 cm(4 ½”) or half brick walls or thin Sq m Per sq m sft Per% sft
10 Brick flat soling (one or two layers). Sq m Per sq m sft Per% sft
11 Cornices, string courses, drip courses rm Per rm rft Per rft
etc.
12 Cutting openings in existing brickwork Cu. m Per cu. m cft Per% cft
13 Concrete works. Cu. m Per cu. m cft Per% cft
Lime or Cement concrete in foundation
14 Reinforced cement concrete. Cu. m Per cu. m cft Per% cft
15 Form work Sq. m Per sq. m Sft Per% sft
P a g e 44
CHAPTER # 03 BUILDING ESTIMATE
P a g e 45
CHAPTER # 03 BUILDING ESTIMATE
P a g e 46
CHAPTER # 03 BUILDING ESTIMATE
P a g e 47
CHAPTER # 03 BUILDING ESTIMATE
Note: Any work done by the contractor extra over the specified dimensions
shall not be paid.
RULES OF DEDUCTION
While preparing the estimate of the building, measurement of various Items
of work is done according to the principles laid down. Deduction is made in it
according to the rules for doors and windows etc. as required. The following
are the rules for different type of items.
Brick work
In the case of brick masonry, the measurement for doors, windows, skylights
and shell beams etc. is deducted while taking the measurement of the
completed work. However, if their size is less than 0.1 square meter (one
square foot), it is not included in the deduction. Similarly, the area of
masonry attached to beams, etc., is ignored if it is less than 500 square
centimetres (100 square inch).
Concrete work
When making the measurements for concrete work, the actual size of the
prepared structure is considered and if it contains holes, etc., their size is
deducted, but if the size of these holes is less than 0.1 square meters (one
square foot), it is ignored. Similarly, if the work of concrete is done with any
P a g e 48
CHAPTER # 03 BUILDING ESTIMATE
other material, the area of less than 500 square centimetres (100 square
inches) is ignored. There is no deduction in case of a pipe or steel in the
concrete.
D.P.C.
If D.P.C. is provided at plinth level, it’s measurement is taken to be equal to
length and width of wall above it and for doors and veranda opening,
deduction is made.
i. Trade System
ii. Group System
Trade System
In this system, after registering the measurement of one type of items (items
of work), the measurement of other items is started and the same order and
form is adopted for it in which the bill of Quantity (B. O. Q) is prepared. For
example, first of all, earth work is measured, which includes all kinds of
excavation and filling work. After this, all kind of masonry work under brick
work is completed, then another work is started. Since the ordering of items
in this method is the same as that required for Bill of Quantity (B. O. Q.), So
P a g e 49
CHAPTER # 03 BUILDING ESTIMATE
separate entry is not required. Chances for mistake are high in that system
so, you have to look at the whole drawing again and again.
Group System
In this system, the measurement work is divided into different groups. For
example
i. PWD method
ii. English Method
iii. M. E. S. Method
P. W. D. Method
This is the usual method of recording measurements in government
departments. The table format used in this system is as follows.
Sr. Description of No. Measurements Quantity Remarks
No. work Length Breadth Height or
Depth
P a g e 50
CHAPTER # 03 BUILDING ESTIMATE
The Serial Number of the items is entered in the first column of the Table
made for the entry of measurements according to the P, W.D. Method.
Description of item is written down in second column. The column of
measurements is then filled. If a measurement consists only of length, it is
entered in the length column (L) and the other two columns (B) and (H) are
left blank. If a measurement is of area, it is entered in the first two columns
of measurement (L) and (B) and if any measurement is of volume, it is
recorded in all three columns of measurement. Then the next (Content /
Quantity column) is recorded which is the product of the previous four
columns, which can be only a length, area or volume. Detail about any
measurement is written in last column named as Remarks.
ENGLISH METHOD
This is a common practice in private firms and foreign countries. It uses lined
paper called Dimension Paper. An example of this is as follows.
1 2 3 4 1 2 3 4
Column No. 1
This is called the Timesing Column. If the number of items to be measured is
more than one, the number is written in this column
Column number 2
This is called (Dimension Column). It contains measurements of drawings or
measurements taken on the spot, which can be one, two or three, such as
length, width and height or depth. If only the length of an item is to be
entered, one measurement will be written and if the area is to be measured,
two dimensions will be written in case of volume and all three dimensions
will be written. The top dimensions will represent the length, next the
second one will represent the width, and the bottom dimensions will indicate
the height or depth. A line is drawn after the set of measurements.
P a g e 51
CHAPTER # 03 BUILDING ESTIMATE
Column No. 3
This is called a squaring column. In it, the product of the number and
dimensions is entered, in shape of length, area or volume.
Column No. 4
This is called the Description Column. The detailed descriptions of the items
are written in it. To the right of this column is a redundancy process called
Waste is entered. Waste contains the following information.
i. Rough process required for the measurements written in column 1
and column 2, i.e. initial addition and subtraction.
ii. The place where the said work will be done. This place is marked and
so on.
M.E.S. Method
This method is used in the Department of Military Engineering Services
(M.E.S) for measuring construction work or for supplying construction
materials. In terms of entry this method is similar to the English method.
The following table is used to record the measurements according to this
method. In the first column of this sheet, the number of items is written. If
there is only one item, it is not necessary to write one. Measurements of
items are written in second column. The number of measurements may be
one, two or three measurements such as width, height or depth. If an item is
intended to enter only the length, one dimension is written, and if the area is
to be entered, two and in the case of volume three values are written. The
top measurement will show the length, the next measurement will show the
width and the lowest measurement will show the height or depth. After each
set of measurements, a line will be drawn below it. In the next column, the
product of the entries of the first two columns is entered which shows the
total product of the items. The last column contains the description about
the item.
No. Dimensions Contents Particulars
P a g e 52
CHAPTER # 03 BUILDING ESTIMATE
With these methods the lengths and widths of various items are mainly
found out which helps in calculations.
Here, the external wall length in the longitudinal direction and the internal
wall length running in transverse direction are found out and quantities are
calculated by multiplying the length, breadth and height of wall. Similarly, in
excavation of foundation to concrete in foundation and to masonry, this
method is carried out. Special care is taken to note the difference in
dimensions at different heights due to footings or due to offsets. The length
of wall in longitudinal direction is normally reduced from earth work to brick
work in case of super structure whereas the wall in transverse direction is
raised. Also, the wall along the length of room is taken as long wall whereas
the wall perpendicular to long wall is treated as short wall.
Following formulas are used
Long wall length out-to-out = centre to centre length + half breadth on one
side + half breadth on the other side = centre to centre length + one breadth
Short wall length in-to-in = centre to centre length – one breadth
This method is simple and accurate and is also termed as Long wall and short
wall method or general method.
P a g e 53
CHAPTER # 03 BUILDING ESTIMATE
P a g e 54
CHAPTER # 03 BUILDING ESTIMATE
P a g e 55
CHAPTER # 03 BUILDING ESTIMATE
P a g e 56