Assignment 02 2020 Memo MGA40AT
Assignment 02 2020 Memo MGA40AT
QUESTION 1
Material A 1 104,000 1
Material B 2 180,000
Components 3 200,000
Direct labour 4 58,200 1
Machine hours 5 2,800 1
Fixed overhead 6 NIL
Production director – 7 NIL
meeting
Total relevant cost R545,000
Notes:
1. Material A is in regular use by POULUS LIMITED and consequently its relevant
value is its replacement cost. [1]
The historical cost is not relevant because it is a past cost and the resale value is not
relevant since POULUS LIMITED is not going to sell it since the material is in regular
use and therefore must be replaced. (400kgx 260)
4. Since 80 hours of spare capacity are available which have a zero relevant cost, the
relevant cost relates only to the other 180 hours [1]. POULUS LIMITED has two
choices: either use its existing employees and pay them overtime at R340 per hour
which is a total cost of R61,200;[1] or engage the temporary staff which incurs their
cost of R54,000[0.5] plus a supervision cost of R420 which equals R4,200. [0.5]The
relevant cost is the cheaper of these alternatives which is to use the temporary
employees.
5. The machine is currently being leased and it has spare capacity so it will either
stand idle or be used on this work. The lease cost will be incurred regardless so the
only relevant cost is the incremental running cost of R140 per hour. [1]
6. Fixed overhead costs are incurred whether the work goes ahead or not so it is not
a relevant cost.[1]
7. The production director has already had this meeting with the potential client,
therefore the relevant cost is NIL firstly because it is a past cost, and secondly because
even if it were future the director is paid an annual salary and therefore there is no
incremental cost to POULUS LIMITED. [1]
1
QUESTION 2
General factory
Harvesting Pressing overhead
QUESTION 3
Cost driver rate:
Cost R'000 Consumption ‘000 Rate
400 2000 0,20
1300 2500 0,52
1100 5000 0,22
160 1000 0,16
660 990 0,67
2
Customer profitability:
Personal
loans Cheque Platinum Savings Total
Contribution 500 000 2 000 000 600 000 320 000 3 420 000
QUESTION 4
QUESTION 5
(a) In order to ascertain the optimum price, you must use the formula P = a – bQ
Where P = price; Q = quantity; a = intersection (price at which quantity demanded will
be nil); b =gradient of the demand curve.
The approach is as follows:
(i) Establish the demand function i.e P = a – bQ
b = change in price/change in quantity = R5.6/70,000 = 0.00008. (1)
We know that if price = R72,60 quantity = 280,000 units.
We establish ‘a’ by substituting the values for P, Q and b into our demand function:
72,60 = a – 0.00008(280,000)
22,4 + 72,60 = a
Therefore a = 95. (1)
Demand function is therefore P = 95 – 0,00008Q
3
(ii) Establish marginal cost
The total marginal cost = R13. (1)
(iii) MR=MC
(1) Establish the marginal revenue function
MR = a – 2bQ
MR = 95– 2(0,00008)Q
MR = 95 – 0,00016Q (1)
QUESTION 6
Minimum required monthly contribution = R510 000/30 000 units =R17 per unit
(360 000/12 months)
Following is the list of all possible contributions exceeding R510 000(R17 per unit):
(VC)
per Contribution Total
SP (R) unit per unit contribution JP
30 12 18 30 000 540 000 0,3 0,2 0,060
4
The probability of earning contribution exceeding R510 000 is 76% [5]
• A risk-seeker is one who, given a choice between more or less risky
alternatives with identical expected values, prefers the riskier alternative. He
will use a maximx decision rule.
• A risk averse decision-maker will seek to avoid high levels of risk and will focus
on the less risky alternative. He will use the maximin decision rule.
• A risk neutral decision maker will tend to ignore risk and use the expected value
for decision-making.
[1 mark each =3marks]
Reasonable
comply
Company C R5500 x 40%
EV=R4550 Fully comply
R3500 x 10%
Not comply (.2)
R4000 x 50%
Reasonable
comply
R6000 x 40%
Company D
Fully comply
EV=R5200 R3000 x 10%
Not comply (.2)
R5000 x 50%
[1 mark for EV]
Without perfect information Company A would be chosen since it has the lowest
expected value of R4 160 000.
If the additional information is obtained from Zindlo Limited, then this will give a perfect
prediction of the costs, and the bidder choice can be matched with the type of bidder’s
law compliance. Therefore, if the action is predicted to be reasonably comply
Company B will be selected, if the action is predicted to be fully comply Company D
5
will be selected, and if the action is predicted to be not comply Company C will be
selected. The revised expected value is (R4800 x 40%) + (R3000 x 10%) + (R4000 x
50%) =R4 220 000 [2]
Value of perfect information =R4 220 000-R4 160 000= R60 000 [1]
The additional information from Zindlo Limited is not worth obtaining, as it will not
change the decision of selecting Company A. [1]