Pit Optimization Pro Slide
Pit Optimization Pro Slide
MineScape 2021
Materi
• Pit Optimization Concept
• Pit Optimization Setup (Basic)
• Pit Optimization Setup (Study Case)
Pit Optimization Concept
New pit optimization is an import step in the mine planning process. It is used to define the
most profitable pit shell (ultimate pit limit) from a set of geological model and economical
parameters applied. These pit shell is used as a guide to make a detailed pit design.
Pit Optimization will use input parameter such as geological model (schema) and economic
model ( cost of OB and Coal, also other additional cost). Pit optimization also can accept
variable parameter such as pit slope wall and cost haul parameter.
New MineScape Pit Optimization Pro used Push Relable algorithm that can generate ultimate
pit limit in shorter period of time. Push Relable algorithm also available for 3D model.
Pit Optimization Concept
TOPO
COAL
Pit Optimization Concept
Pit Optimization Concept
Example of Cost Variable for Pit Optimization:
Item Cost Mining $/Tonnes
1. Stripping cost 2
2. Equipment cost 2
3. Maintenance Cost 1
4. Hauling Cost 2
TOTAL 7
For cost-based unit will be setup specifically for OB in volume based (BCM,
1000 BCM) and COAL in mass based (Tonnes, 1000 Tonnes)
Pit Optimization Concept
+ 20
+ 30 + 25
Optimum pit
Pit Optimization Concept
Optimum Pit
Noted : masih dalam bentuk pit shell, belum detail engineering design (DED)
Setup Pit Optimisasi (Basic)
• New MineScape pit optimization pro tool is fully integrated
with Stratmodel schema.
• MineScape Pit Optimization pro accept basic input of economic
model such as coal and OB cost mining, sell price, coal
processing cost included complex setup for additional variable
cost (lifting cost, hauling cost, etc), optimization by quality and
various pit slope wall setup.
Setup Pit Optimisasi (Basic)
✓ On Start Page –
Select MineScape
Product Engineering
Optimization- Load
✓ Select Pit
Optimization on
Install Apps
• With the coal price of $15/tonnes it proves that pit shell number 3 is the optimum pit shell with SR 3.32
Setup Pit Optimisasi (Study Case)
• Additional Cost Lifting
• Additional Cost Processing
• Optimization By Quality
• Additional Cost by Polygon
Setup Pit Optimisasi (Cost Lifting)
• The increase in the cost lifting parameter is related to the additional costs that occur from the mining
progress that getting deeper to the pit floor.
• MineScape Pit Optimization pro calculates this formula based on the decrease in elevation that occurs
following to the mining progress and adjusted to the 3D model used.
• User can simply add the formula to form to calculate the cost lifting automatically.
• The calculation can be done in one input process with the basic setup.
Setup Pit Optimisasi (Cost Lifting)
• The implementation of cost lifting formula can be visualized using Blockmodel section.
• The detail valued of block_MCAF will show the cost applied in each block 3D based on the calculation
16
Additional Cost by Polygon
• Additional Cost by Polygon will help user to setup specific cost that applied in specific area. It can handle
additional cost for mud cases, additional hauling cost, etc.
• User can simply add the formula to form to calculate the cost by polygon automatically.
Additional Cost by Polygon
• Run the pit optimization process