ERCOT EHV Infrastructure Initiative Update October 2024
ERCOT EHV Infrastructure Initiative Update October 2024
Infrastructure Initiative
Update
PUBLIC 2
September RPG – Recap
PUBLIC 3
2024 RTP – 765-kV Scope
• Two RTP assessments will be performed
– Standard RTP assessment (without 765-kV Core plan)
• Corrective Action Plans (CAPs) will be developed for
– N-1, G-1+N-1, X-1+N-1
» Will include 69-kV, 138-kV, and 345-kV
– N-1-1 maintenance outage scenario
» Will include 69-kV, 138-kV, and 345-kV
– Minimum Deliverability
» Will include 69-kV, 138-kV, and 345-kV
PUBLIC 4
2024 RTP – 765-kV Deliverables
PUBLIC 5
Additional – 765-kV vs Standard RTP Plan
PUBLIC 6
Questions/Comments
PUBLIC 7