Column Analysis
Column Analysis
Column design
Roof beam= 1.5*1.5 = 2.25KN/m2
6225mm Beam A (4-5)
External
Roof Load = 2.25*6.225*1/2
1
1- = 4.67 KN|m
3 6.223 2
6.225
Beam = 0.23*0.45*24*1.4
= 4.54KN|m
Finishes = 0.6*1-4 = 0.8
0.8KN|m
Total UDL = 10.05KN|m
Fixed End Moment
=10.05*6.2252
12
= 12.0KNM
6.225m Beam A(4-5)
External
Same as Beam A(3-4)
Extenal
Total UDL = 10.05KN|m
FEM = 12.0 KNm
8225 Beam Grid 5(A-E) (Internal)
Roof load = 2.25*8.225*
½ 1- 1
3 8.225 2
8.225
=6.17kn|m
Roof load = 6.17*2 = 17-34
12.34KN|m
Fixed End Moment
17.72*8.2252
12
= 99.9KNm
6.225 Beam Grid E(4-5)
Internal
Roof load 1= 2.25*6.225*1/2
1- 1
3 6.225
1.145
= 4.67KN|m
= 16.47*6.2252
12
= 18.297KNm
6.225 Beam Grid E (3-4)
FEM = 18.297KNm
1- 1
3 2.252
2.252
1.67KN|m
Beam finishes = 5.38KN|m
Total UDL = 7.071*2.252
12
= 2.99KN|m
Floor Beam
6225mm Beam A (4-5) External
slap load =10.52*6.225*1/2*( 1-0.333 )
= 21.84KN|m
Beam & finishes = 5.38 KN|m
Wall load = 3.47*3.5*1.4
= 17.003KN|m
Total UDL = 44.22KN|m
Fixed End moment
= 44.22*6.2252
12
= 142.796KN|m
8225mm Beam Grid 5
(A-E) Internal
Slap load = 10.52 * 8.225*1/2 * ( 1-0.333)
= 28.84KN|m
LOADING ON COLUMN
CT2 & CT1 & CT3
Roof live load = 1.5KN|m2
Roof dead load = 1.5KN|m2
Column -CT2
Floor area = ( 6.225 )*( 8.225)
2 2
= 3.113*4.113
= 12.80m2
Floor leangth = 3.113+4.113
= 7.226m
Column CT3
CT3 (Column type3)300
360
Floor area= 8.225 + 6.225
2
7.225 * 7.225 = 52.20m2
K external = 0.155
K internal = 0.298
Column CT1
Roof level