0% found this document useful (0 votes)
99 views8 pages

Installation Instruction Sheet - 36kV 630A T

MV terminations

Uploaded by

untoopravin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views8 pages

Installation Instruction Sheet - 36kV 630A T

MV terminations

Uploaded by

untoopravin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 8

36 kV 630A IEC Front / Coupling (Rear) T-Body

Connector
INSTALLATION & OPERATING INSTRUCTIONS
DESCRIPTION
The CHARDON 36 kV 630A IEC front / coupling (rear) T-body
connectors are used to terminate polymeric cable to equipment,
such as transformers, switchgear, motors etc. equipped with
bushings meeting type C interface per CENELEC EN 50180 and
50181. They are fully screened and fully submersible when mated
with the proper bushing or plug and they meet the requirements
of CENELEC HD 629.1 S2.

· 36kV 630A Class (18/30 kV)

Front T-body Kit Content: Coupling T-body Kit Content:


◎ - Front T-body ◎ - Coupling (rear) T-body
◎ – Connector ◎ - Connector
◎ - Cable Adapter ◎ - Cable Adapter
◎ - Stud ◎ - Stud
◎ - Washer ◎ - Connecting rod
◎ - Hex nut ◎ - Silicone Lubricant
◎ - Insulating Plug ◎ - Paper Towel
◎ - Conductive Cap ◎ - Installation Instructions
◎ - Silicone Lubricant
◎ - Paper Towel
◎ - Installation Instructions

All associated apparatus must be de-energized during installation and/or maintenance.


CAUTION: Indicates a hazardous situation which, if not avoided, could result in minor
or moderate injury.

Do not touch or move energized product by hand. Otherwise it will result in death or
DANGER:
serious injury.

SAFETY INFORMATION

The instructions in this manual are not intended as a substitute for proper training or adequate experience in
the safe operation of the equipment described. Only competent technicians, who are familiar with this
equipment should install, operate and service it.

Part No: 138404P000 1 REV:A


INSTALLATION PROCEDURE

STEP 1 STEP 3
For Tape Shielded Cable
Check kit components to insure proper fit with
the cable diameter dimensions, conductor size,
and mating products.

STEP 2

 Use sandpaper to grind the cable jacket to


rough the surface and clean cable jacket
and Semi-conductive shield.
 Wrap the sealing tape onto the cable jacket.
Sheal bol t range A B Compressi on Lug A B  Use constant-force spring to fix ground braid
SBC- B- 25- 50/ 1 200 50 25- 35 190 50
SBC- B- 70- 95/ 1 200 50 50- 70 190 60 into Semi-conductive shield.
SBC- B- 70- 120/ 2 197 70 95- 150 190 65
SBC- B- 150- 240/ 2 197 70 185- 240 190 70  Wrap the sealing tape onto the ground braid.
42kV
SBC- B- 300- 400/ 3 190 80 300- 400 190 80
630A as shown in Fig. 2-1.

For Wire Shielded Cable / JNC Cable

Prepare the cable to the desired finished


position and cut the cable. (See Fig. 1)
1) Remove the cable jacket for a distance of
“A”+80 mm from the end of the cable. Do not
damage the copper conductive shield or
copper wire.(See step 3 to deal with the
copper conductive shield or copper wire.)
 Use tinned copper wire to lash the neutral
2) Remove “A” +40(mm) of copper conductive
wires
shield. Do not damage the semi-conductive
 Use sandpaper to grind the cable jacket to
shield.
rough the surface, clean the grinded surface
3) Remove “A” (mm) of insulation screen. Do
then bind the sealing tape on.
not damage the cable insulation.
 Bend neutral wires down and parallel to
4) Remove ”B” mm of cable insulation. Use
cable.
PVC tape to secure the exposed ends of the
 Use tinned copper wire to secure neutral
cable conductors.
wires to cable jacket
5) At the end of the insulation and semi-
 Wrap the sealing tape onto the neutral wires.
Part No: 138404P000 2 REV:A
conductive shield chamfer the sharp end at a
45° angle.

Part No: 138404P000 3 REV:A


STEP 4 Then remove the marker. Wipe off grease from
end of cable adapter, preparing the surface for
application of tape.

STEP 7

Wrap 2 layers a distance of 60mm of the semi-


conductive tape for a distance of “A” +90mm
from the end of cable, copper conductive shield
and semi-conductive shield as shown in Fig. 3.
Wrap 2 layers of sealing mastic tape “A” +95mm
STEP 5 from the end of cable (wide 105mm). Wrap 2
layers of PVC tape on the sealing mastic tapes.
(See Fig. 6)
STEP 8

Polish and thoroughly clean the cable insulation,


using sand paper and paper towel.
Wrap two turns of PVC tape to serve as a
marker at a position of 20 mm from end of the
insulation screen (a distance of “A”+20 mm from
the end of the cable, See Fig. 4).
STEP 6

Remove the PVC tape and clean conductor from


the end of the conductor.

Immediately insert the conductor into the


Lubricate the exposed cable insulation and crimping barrel as far as it will go. Ensure that
adapter inside interface. Slide the cable adapter the flat of the lug spade is parallel to the face of
onto the cable, black end first, until the black the bushing. Stress from the tail cone to the
end is flush with tape marker. Check the Critical terminals 145 ~ 155mm at the top of the
Dimension as shown in Fig. 5 below. terminals , installed as shown in Fig. 7.

Part No: 138404P000 4 REV:A


STEP 9 STEP 11

Clean the outer surface of the cable adapter and


the interior of the cable entrance of the front T-
body with a lint-free cloth. Apply a thin layer of
lubricant to both surfaces. Push the front T-body
over the cable adapter as far as it will go.
Ensure that the hole in the top of the crimp
connector is visible through the interface end of Push the front T-body onto the equipment
the T-body. (See Fig. 8) bushing. Make sure the stud passes through the
hole in spade of lug. (See Fig.10)
STEP 10
STEP 12

Put washer and hex nut on the stud, and tighten


the nut to 50-55 Nm, using a torque wrench and
Tighten the stud to 55 Nm, using a 14 mm open
a 24 mm socket. Clean the insulating plug and
end wrench. (Slotted outwards) Clean
front T-body interfaces with cleaning wipes. Wait
equipment bushing and front T-body interface.
for the cleaning solvent to evaporate. Apply a
Wait for cleaning solvent to evaporate.
thin layer of lubricant to both surfaces. Insert the
Lubricate both interfaces. (See Fig. 9) insulating plug into the front T-body and engage
the threads of the threaded stud. Tighten the
insulating plug to 35-40 Nm, using a torque
wrench and 19 mm socket. (See Fig.11)

STEP 13 Step 2. Install the rod and stud assembly by


hand in the front T-body. Make sure the
stud in the equipment bushing passes
through the hole in spade of the
connector.
Part No: 138404P000 5 REV:A
Step 3. Tighten the rod and stud assembly to
approximately 50-55 Nm, using a 22
mm open end wrench. (See Fig. 13)
(Slotted outwards)

Step 4. Repeat Step 1 to Step 8, prepare cable


and install bolted companion coupling
(rear) T-body connector. (See Fig. 14)

Step 1. Before install coupling (rear) T-body,


complete step 1 to step 11 of front T-body
instructions. If front T-body was installed
completely, remove insulating plug, nut and
washer. Step 5. Clean the interface of companion front
T-body connector and coupling (rear) T-
body connector with an ISO wipe. Wait
for the cleaning solvent to evaporate.
Apply a thin layer of lubricant to both
interfaces. Slide the bolted companion
coupling (rear) T-body connector over
the rod and stud assembly and into the
front T-body connector.

Step 6. Put the hex nut onto the rod and stud
assembly and tighten to 50-55 Nm using
a 24 mm socket and a torque wrench.

Step 7. Clean the insulating plug and the


companion coupling (rear) T-body
interfaces with an ISO wipe. Wait for the
cleaning solvent to evaporate. Apply a
thin layer of lubricant to both surfaces.

Step 8. Insert the insulating plug into the back of


the companion coupling (rear) T-body
and engage the threads of the threaded
stud.

Tighten the insulating plug to 35-40 Nm, using a 19 mm socket and a torque wrench.

Step 9. Clean the interior surface of the rubber cap. Place it over the insulating plug and push it until
it snaps into place.
Step 10. Connect drain wire on front
Part No: 138404P000 6
T-body /companion
REV:A
coupling (rear) T-body to grounding
Inasmuch as CHARDON GROUP, Inc. has no control over the use which others may put the
material, it does not guarantee that the same results as those described herein will be obtained,
Each user of the material should make his own tests to determine the material’s suitability for his
own particular use. Statements concerning possible uses of the materials described herein are not
to be construed as constituting a license under any CHARDON GROUP, inc. patent covering such
use or as recommendations for use of such materials in the infringement of any patent.

FOR FURTHER INFORMATION WRITE TO

[email protected]

Part No: 138404P000 7 REV:A

[email protected]

You might also like