Test, MS Project
Test, MS Project
Create, name and save a new project file for each task.
Task 1A – Determine the Earliest Start Time (EST) for each activity A-E
B C
30
12 8
A D E
0
10 20 40 50
10 25 6
Task 1B – From the data in Table 1 regarding the refurbishment of a small workshop:
produce a Gantt Chart;
produce a Network diagram;
identify the Critical Path, and
determine the project duration and earliest date by which the workshop can be
expected to begin operations.
Assume infinite resources (i.e. don’t allocate any). Take all durations to be in weeks,
and assume MS-Project’s default working calendar.
Use “Network diagram” view to verify the dependencies, and alter them if necessary.
* Key: FS - Finish-to-Start: Activity can only start when predecessor has finished
regardless of resource availability
*** re-sequence your activities to give a better presentation layout on the Gantt
chart view.