NEC4 ECC Contractor Submission Workflow
NEC4 ECC Contractor Submission Workflow
Template
Use this free downloadable template to help you create a Contractor Submission under the
NEC4 Engineering and Construction Contract (ECC).
The ECC requires the Contractor to make submissions to the Project Manager on various
matters that arise during the course of a construction project some of which require
acceptance. The ECC goes a step further than most traditional contracts by requiring the
Project Manager to not only respond to a submission, but to respond with reasons. A reason
outside those listed in the contract will be a compensation event.
You can use this NEC4 ECC template for a Contractor’s submission of the following:
Submit under clause 16.1 a proposal to change the Scope to reduce the amount the
Client pays to the Contractor (period for reply is 4 weeks)
Submit under clause 16.3 for acceptance a proposal to add an area to the Working
Area (period for reply is period for reply)
Submit under clause 20.4 forecasts of the total Defined Cost for the whole of the
works (main Options C, D, E and F) (no reply)
Submit under clause 21.2 for acceptance of particulars of design (period for reply is
period for reply)
Submit under clause 23.1 for acceptance of particulars of design for an item of
Equipment (period for reply is period for reply)
Submit under clause 24.1 for acceptance of details of a replacement person (period
for reply is period for reply)
Submit under clause 25.1 information to Others (no reply)
Submit under clause 26.2 for acceptance of the name of a proposed Subcontractor
(period for reply is period for reply)
Submit under clause 26.3 for acceptance of proposed subcontract documents
(period for reply is period for reply)
Submit under clause 26.4 of pricing information for each subcontract (main Options
C, D E and F) (no reply)
Submit under clause 27.1 design for approval (no reply)
Submit under clause 29.2 to publicise the works (no reply)
Submit under clause 36.1 to propose an acceleration to achieve Completion before
the Completion Date (period for reply is period for reply)
Submit under clause 36.1 a quotation for acceleration (period for reply is 3 weeks)
Submit under clause 50.9 for acceptance of records demonstrating Defined Cost has
been correctly assessed (main Options C, D, E and F) (period for reply is 13 weeks)
Submit under clause 50.9 a reply to a submission of records demonstrating Defined
Cost has been correctly assessed (main Options C, D, E and F) (period for reply is 4
weeks)
Submit under clause 50.9 for acceptance of further records in connection with
Defined Cost (main Options C, D, E and F) (period for reply is 4 weeks)
For simplicity, you can use this template for a ‘request’ under clause 26.2 and X22.3(6),
‘report’ under clause X20.2, ‘gives’ under X4.1, X13.1, X14.4 and X16.3, and a ‘provision’
under clauses 25.1, X8.5, X9.1, X10.6, Y1.4 and Y1.9.
You can also use this NEC4 ECC template for the Project Manager’s reply.
50.9 of further records in connection with Defined Cost (main Options C, D, E and F)
Accepted
Not Accepted as:
Further records are needed
The Project Managers assessment is notified
Other reason
X22.2(1) of detailed forecasts of the total Defined Cost for Stage One
Accepted
Not Accepted as:
More information is needed
It does not comply with the Scope
It includes work which is not necessary for Stage One
Other reason
Y1.4 of details of the banking arrangement for the Project Bank Account
Accepted
Not Accepted as:
More information is needed
The banking arrangements do not provide for payments to be made in accordance
with the contract
Other reason
Project Name: …
Contract No: …
Date: …
Submission No : …
Subject: …
Details:
…
[here is some suggested wording]
16.1 to change the Scope to reduce the amount the Client pays to the Contractor
16.3 of a proposal to add an area to the Working Area
20.4 of forecasts of the total Defined Cost for the whole of the works (main Options C, D, E and F)
21.2 of particulars of design
23.1 of particulars of design for an item of Equipment
24.1 of details of a replacement person
25.1 of information to Others
26.2 of the name of a proposed Subcontractor
26.3 of proposed subcontract documents
26.4 of pricing information for each subcontract (main Options C, D E and F)
27.1 of design for approval
29.2 to publicise the works
36.1 of an acceleration to achieve Completion before the Completion Date
36.1 of a quotation for acceleration
50.9 of records demonstrating Defined Cost has been correctly assessed (main Options C, D, E and
F)
50.9 of a reply to a submission of records demonstrating Defined Cost has been correctly assessed
(main Options C, D, E and F)
50.9 of further records in connection with Defined Cost (main Options C, D, E and F)
50.9 of a reply to a submission of further records in connection with Defined Cost (main Options C,
D, E and F)
55.3 a revised Activity Schedule (main Option A)
84.1 of certificates of insurance
X4.1 an ultimate holding company guarantee
X4.2 of an alternative guarantor
X8.5 of signed copies of the undertakings
X9.1 of documents transferring rights
X10.4(1) of a first Information Execution Plan
All rights reserved BuiltIntelligence 2022
X10.4(2) of a reply to a submission of a first Information Execution Plan for acceptance
X10.4(2) of a reply to a submission of a revised Information Execution Plan for acceptance
X10.4(3) of a revised Information Execution Plan
X10.6 of information transferring rights
X13.1 of a bank or insurer to provide a performance bond
X13.1 a performance bond
X14.2 of a bank or insurer to provide an advanced payment bond
X14.2 an advance payment bond
X15.6 certificates of insurance
X16.3 a retention bond
X16.3 of a bank or insurer to provide a retention bond
X20.2 of performance
X20.3 of proposals for improving performance
X21.1 of a proposal that the Scope is changed in order to reduce the cost of operating and
maintaining an asset
X21.2 of a quotation to reduce the cost of operating and maintaining an asset
X22.2(1) of detailed forecasts of the total Defined Cost for Stage One
X22.2(2) of a reply to a submission of the total Defined Cost for Stage One for acceptance
X22.2(5) of forecasts of the Project Cost
X22.3(1) of proposals for Stage Two
X22.3(2) of proposals for Stage Two
X22.3(6) for approval or consent
Y1.4 of details of the banking arrangement for the Project Bank Account
Y1.4 of copies of communications with the Project Bank
Y1.5 the details of the Project Bank Account
Y1.6 of a proposal to add a Supplier to the Named Suppliers
Y1.9 of a copy of the Payment Schedule
Y1.9 information in the Payment Schedule
Y1.14 of the Project Bank Account Tracker
Attachments: …
Distribution: …
Project Name: …
Contract No: …
Date: …
Submission No : …
Subject: …
If applicable the changes to the Prices, Completion Date and Key Date are as follows:
Change to the Prices: …
Programme Details: …
Attachments: …
Distribution: …