Projects Performance Analysis Forecasting
Projects Performance Analysis Forecasting
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Session Agenda:-
• Introduction
• Overview of Key Performance Indicators ( KPI )
• What Is The Earned Value Management ?
• Why Project Managers Use EVM ?
• Earned Value Management Terms and Formulas
• Planned value (PV)
• Earned value (EV)
• Actual cost (AC)
• Variance
• Schedule Variance ( SV ) • Project Forecasting
• Cost Variance ( CV ) • Budget at Completion (BAC)
• Performance Index • Estimate at Completion (EAC)
• Schedule Performance Index (SPI) • Estimate to Complete (ETC).
• Cost Performance Index (CPI) • Variance at Completion (VAC)
• Example ( Case Study ) • To Complete Performance Index (TCPI)
1.1 Introduction
1.1 Introduction
• These Metrics Are Used To Determine a Company's Progress In Achieving Its Strategic and Operational Goals,
And Also To Compare A Company's Performance Against Other Businesses Within Its Industry.
1.1 Introduction
Any Project Manager Use Earned Value Management To Assess The Schedule and Cost
Performance Of a Project He Should Based On Three Terms.
PV PV Planned value
EV Earned value
EVM
AC EV AC Actual Cost
1.2 Earned Value Management Terms and Formulas
PV Planned value
Budgeted Cost For Work Scheduled (BCWS)
Scheduled (BCWS).
1.2 Earned Value Management Terms and Formulas
EV Earned value
Budgeted Cost For Work Performed (BCWP)
AC Actual Cost
Actual cost for work performed (ACWP)
Performed (ACWP).
1.3 Project Variance & Performance
Index
1.3 Project Variance & Performance Index
Project Variance
According To Earned Value Management Three Terms We Can Define The Project
Variance :-
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC) EV – AC
Schedule
Variance
Project
Variance Cost
SV CV
Variance
EV – PV
1.3 Project Variance & Performance Index
SV > 0
Ahead of Schedule
SV < 0
Behind Schedule SV = 0
On Schedule
1.3 Project Variance & Performance Index
CV > 0
Under Budget
CV < 0
Over Budget CV = 0
On Budget
1.3 Project Variance & Performance Index
Performance Index
According To Earned Value Management Three Terms We Can Define The Project
Performance Index :-
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC) EV / AC
Schedule
Performance
SPI CPI
Project Index
Performance
Index Cost
Performance
Index
EV / PV
1.3 Project Variance & Performance Index
SPI < 1
Behind Schedule
SPI > 1
SPI = 1
Ahead of Schedule
On Schedule
1.3 Project Variance & Performance Index
CPI < 1
Over Budget
CPI > 1
CPI = 1
Under Budget
On Budget
1.3 Project Variance & Performance Index
Project Forecasting
• Consists Of Taking The Project Status
Information And Extrapolating The Current
Project Performance To The End Of The
Project and How The Future Will Turn Out
Based On Evidence Or Assumptions.
Forecasting Terms :-
• Budget at Completion (BAC)
Considering CPI