Analysis 3.11.32

Uploaded by

shahed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Unit Cost Analysis for Schedule of Rates

Schedule of Rates, LGED, February 2023

Zone-C (Rajshahi, Rangpur Division)

Detailed Analysis
Item
Code Brief Description of Item Unit Sub-Item Quantity Unit Rate Amount
1 2 3 4 5 6 7 8

Chapter - 3 : Road Works

3.11.32 RCC(TW-600): Construction and Installation in position RCC toe wall as m


per standard drawing enumerated in Appendix-6 (type design for
protective work) with 3.5m long 200mmX200mm RCC Pre-cast Post,
300mmX500mm Capping Beam and 600mm RCC wall having thickness
150mm using 20mm down graded crushed stone chips (LAA value not
exceeding 30), sand (minimum FM 2.5) and cement conforming to BDS
EN 197-1 : 2003 CEM-II/A-M 42.5N to attain a minimum 28 days
cylinder crushing compressive strength 25.00 Mpa (mixing ratio 1:1.5:3
& maximum water cement ratio 0.4) as per standard practice of code
AASHTO/ASTM including supplying, fabricating and binding of 400/420
Grade MS deformed bar of required size, length and spacing, excavating
minimum 600mm depth foundation trenches for capping beam and
laying one layer polythene sheet, casting 75mm thick cement concrete
(1:3:6) below the capping beam. Pre-cast Post must be driven by
suitable monkey/drop hammer in full length of the post @ 1.0 meter c/c
into the ground laying on proper alignment as per design, breaking head
(400mm length) of all post carefully, scrapping and removing concrete
from Steel/MS rod including all types of form work etc by means
approved designed all complete in all respect as per approved drawing,
specification and direction of the Engineer-in-charge. (Unit cost includes
all casting work, reinforcement, its fabrication, shuttering, curing for 28
days, driving of the post, pile shoe, lab testing charges as per design,
and all other incidental charges, etc.)
Earthwork in excavation of foundation trenches, including 0.3000 cum 192.54 57.76
layout, ……. (2.04.1.1)
RCC-25SCCM: Reinforced cement concrete work for pre-cast 0.1517 cum 13784.10 2091.05
pile with cement content relates to mix ratio
1:1.5:3....(4.07.10)
RCC-30SCCM: Reinforced cement concrete work for pre-cast 3.2500 m 242.12 786.89
driven micro pile with minimum cement
content....(4.07.21.02.02)
Labour for breaking head of hardened cast-in-situ bored pile/ 0.0173 cum 2669.42 46.18
pre-cast piles to the correct lines and levels from the top of
the piles to the cut-off level ....(4.07.08)
PCC-10: Plain cement concrete work in foundation with 0.0268 cum 8282.96 221.98

Note : Rates of all items should be inclusive of all supply and carriage. Page: 2 of 13
Unit Cost Analysis for Schedule of Rates
Schedule of Rates, LGED, February 2023

Zone-C (Rajshahi, Rangpur Division)

Detailed Analysis
Item
Code Brief Description of Item Unit Sub-Item Quantity Unit Rate Amount
1 2 3 4 5 6 7 8

minimum compressive strength of 10 MPa at 28 days


(sugessted mix proportion 1:3:6) on standard
cylinder...(4.06.03)
RCC-25SCCM: Reinforced cement concrete work with 0.1500 cum 13374.23 2006.13
minimum cement content relates to mix ratio 1:1.5:3...For
pile caps, abutment base....(4.09.03.01)
RCC-25SCCM: Reinforced cement concrete work with 0.0900 cum 13987.73 1258.90
minimum cement content relates to mix ratio 1:1.5:3...For
diaphragm walls, wing walls..(4.09.03.02.01)
WH: Providing weep holes in Brick masonry/ Plain/ Reinforced 0.6666 each 432.02 287.98
concrete retaining wall, abutment, wing/ return wall, with
50 - 100 mm dia uPVC pipe....(4.13.04.01)
Supplying and fabrication of Ribbed or deformed bar 49.3620 kg 92.11 4546.49
reinforcement for all types of RCC work including
straightening, removing ruts, cleaning, cutting, hooking,
....(4.11.01.01.01)
Pre-cast pile shoe making & supplying pre-fabricated frustum 1.0833 each 2710.61 2936.41
of square cone having four sides and a toe made of 6 mm
thick ASTM A36 complied MS steel plate join....(4.07.20)

Subtotal-A: 14239.78

Overhead (3.5% on Subtotal-A/ A1) 498.39


Profit (10% on Subtotal-A/ A1) : 1423.98

VAT (7.5% of Total) : 1310.44

Total: 17472.59

Note : Rates of all items should be inclusive of all supply and carriage. Page: 3 of 13