Contents
Contents
A feeder canal feeds one or more canals. A link canal links the two canals
so that, if required, water of one canal can be diverted to the other canal
through the link canal. A given canal can serve more than one function.
An inundation canal (or non-perennial canal) draws its supply from a river
only during the high stages of the river. Such canals do not have any head-
works for diversion of river water to the canal, but are provided with a canal
head regulator. An irrigation canal system consists of canals of different
sizes and capacities.
Accordingly, the irrigation canals are further classified as:
The main canal takes its supplies directly from the river through the head
regulator and acts as a feeder canal supplying water to branch canals and
major distributaries. Usually, direct irrigation is not carried out from the
main canal.
Branch canal (also called ‘branches’) takes its supplies from the main canal.
Branch canals generally carry a discharge higher than 5 m3/s and act as
feeder canals for major and minor distributaries. Large branches are rarely
used for direct irrigation. However, outlets are provided on smaller branches
for direct irrigation.
Major distributaries (also called distributaries or rajbaha) carry 0.25 to 5
m3/s of discharge. These distributaries take their supplies generally from the
branch canal and sometimes from the main canal. The major distributaries
feed either watercourses through outlets or minor distributaries.
Minor distributaries (also called ‘minors’) are small canals which carry a
discharge less than 0.25 m3/s, and feed the watercourses for irrigation. They
generally take their supplies from major distributaries or branch canals and
rarely from the main canals. A watercourse is a small canal which takes its
Project Report # 2. Design of Stable Irrigation Canals:
Irrigation canals generally have alluvial boundaries and carry sediment-
laden water. A hydraulic engineer is concerned with the design,
construction, operation, maintenance and improvement of irrigation canals.
Irrigation canals should be stable over a period of their life span.
(b) The bed and banks of which are not scoured objectionably by the flowing
water, and
This means that silting and scouring in a stable channel should balance each
other over a reasonable period so that the bed and banks of the channel
remain unaltered. The cross-section of a stable alluvial channel would
depend on the flow rate, sediment transport rate and the sediment size.
Regime methods are commonly used for the design of alluvial channels
carrying sediment-laden water.
(i) Regime Methods:
Regime methods for the design of stable channels were first developed by
the British engineers working for canal irrigation in India in the 19th
century. At that time, the problem of sediment deposition was one of the
major problems of channel design in India.
In order to find a solution for this problem, some of the British engineers
studied the behaviour of such stretches of the existing canals where the bed
was in a state of stable equilibrium. These stable reaches had not required
any sediment clearance for several years of the canal operation. Such
channels were called regime channels.
.
(ii) Kennedy’s Method:
Kennedy collected data from 22 channels of the Upper Bari Doab canal
system in Punjab. His observations on this canal system led him to conclude
that the sediment supporting power of a channel is proportional to its width
(and not wetted perimeter).
The FSL of an off-taking canal at its head should always be kept at least 15
cm lower than the water level of the parent (i.e., supply) channel so as to
account for
(ii) The possibility of the off-taking canal bed getting silted up in its head
reaches, and
If the designed slope of a canal is steeper than the available ground slope,
the canal is laid at a slope equal to the ground slope, and adequate measures
are taken at the head regulator to prevent or minimise the entry of coarse
sediment into the canal so that there would not occur any silting problem in
the canal due to its flatter slope.
On the other hand, if the designed slope of a canal is flatter than the available
ground slope, the canal is laid at the designed slope. Such a canal would
soon have its entire section above the ground surface and its FSL would also
be at too high level above the ground. Therefore, vertical fails (or drops) are
provided at intervals in the canal. For economic reasons, a fall can be
combined with a regulator or a bridge.
Such falls can also be used for generation of power. One may provide either
a larger number of smaller falls (i.e., falls with smaller drop in the channel
bed elevation) or smaller number of larger falls.
If the amount of earth required for filling exceeds the amount of the
excavated earth, this excess requirement of filling is met by digging earth
material from suitable places known as borrow pits. These borrow pits can
be made in the bed of the channel; Fig. 5.5.
These service roads are about 6 m wide and may or may not be metalled. If
these service roads are likely to meet the communication needs of the local
people, they will be much wider and also metalled. Between the canal road
and the canal, a ‘dowla’ of height 0.5 m and top width 0.5 m is also provided.
The calculations for the design of an irrigation canal are carried out in a
tabular form and the table of these computations is referred to as the
‘schedule of area statistics and channel dimensions’. The computations start