Instrumentation Spec.
Instrumentation Spec.
CONTENTS PAGE
1.0 SCOPE
30. IEC 60332: Test for electric cables under fire conditions. (Flame
retardant)
31. IEC 60364: Electrical Installation of Buildings.
32. IEC 60391: Marking of Insulated Conductors
33. IEC 60423 : Conduits for Electrical Purposes: Outside Diameters of
Conduits for Electrical Installations and Threads for Conduits and
Fittings
34. IEC 60529 : Degrees of Protection Provided by Enclosures (IP
Code
35. EC 60534 Industrial Process Control Valves:
36. Part 1: Control Valve Terminology and General Considerations
37. Part 2: Flow Capacity: Section 1: Sizing Equations for
Incompressible Fluid Flow under Installed Conditions.
38. Part 2: Flow Capacity: Section 2: Sizing Equations for Compressible
Fluid Flow under Installed Conditions.
39. Part 8: Noise Considerations:
40. Section 1: Laboratory Measurement of Noise Generated by
Aerodynamic Flow through Control Valves.
41. IEC 60584 Thermocouples -Part 2: Tolerances. Thermocouples -
Part 3: Extension and Compensating Cables Tolerances and
Identification System.
42. IEC 60654 Operating Conditions for Industrial Process
Measurement and Control Equipment.
43. IEC 60751 Industrial Platinum Resistance Thermometer Sensors.
44. IEC 60757 Code for Designation of Colors
45. IEC 60902 Industrial Process Measurement and Control Terms and
Definitions.
46. IEC 61000 Electromagnetic Compatibility for Industrial Process
Measurement and Control Equipment.
47. IEC 61508 Functional safety of electrical/electronic/programmable
electronic safety related systems.
48. ISO 5167 Measurement of Fluid Flow by Means of Pressure
Differential Devices.
R2 49. NACE MR0103 (95) Standard Material Requirements -Sulfide
Stress Cracking-resistant Metallic Materials for Oil field Equipment.
50. IEC 62086-1 Electrical apparatus for explosive gas
atmospheres_Electrical resistance trace heating_Part 1: General
and Testing requirements
51. ANSI/API RP 552 (1994) “Transmission System”
R2 52. ANSI/API RP 553 “Refinery Control Valves”
53. ANSI/API RP 554 “Process Instrument and Control”
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 5 / 379
Revision : 2
RESID UPGRADING PROJECT
2.2 Should any conflict arise among this specification set, licensor standard
specifications, project specifications and any other referenced standards they
will be resolved by TÜPRAŞ after obtaining CONTRACTOR comments.
3.0 GENERAL
3.2 Engineering flow diagrams will identify all instrumentation according to legend
on flow diagrams . The instrumentations symbols will be based on ISA standard
R2 RP 5.1. The installation of instruments and control shall generally be in
accordance with API-551/552/553/554 (latest edition), unless otherwise
required by these specifications, the PROJECT SPECIFICATIONS, or local
regulations.
3.3 Instrument schedule and drawings will prescribe the installation of instruments.
3.4 Units will be operated mainly from a digital distributed control system using
digital data storage and retrieval techniques and associated peripheral and
interconnecting equipment.
3.5 Transmission of measurement and control signals will be 3-15 psig for
pneumatic instruments and two wire 4-20 ma (HART) 24 V DC signal system
for electronic instruments.
3.6 One manufacturer shall be selected for each type of instrument including
instrument supplied by Vendors in packaged units for standardization purposes
unless otherwise approved by OWNER.
involved.
3.8 Generally the parts in contact with the process fluid will be similar to that used
in the related process vessel and lines. Where the instrument design prohibits
the use of these materials or where suitable material cannot reasonably be
procured the instrument shall be isolated from the process by seals or purges.
3.9 Pressure and temperature rating of instruments components will conform to the
rating of the process system to which they are connected. Consideration being
given to the reduced temperature at the instrument.
3.13 Instrument leads and outdoor instruments shall be protected from freezing. All
instrument handling high poor point or viscous oils shall be provided with
temperature controlled steam tracing system and easily installed/removed
instrument insulating enclosures with weather and corrosion resistance.
3.15 Intrinsically safe type protection for all electronic instruments in field shall be
provided with the barriers to be installed the cabinets in the technical
rooms.Irrespective of plant’s hazardous area classifications, all the electronic
instruments (transmitters etc.) shall be intrinsically safe EExia IIC T6 complying
to CENELEC 50020 codes and flame proof EEx d IIC T6 certification
R2 weatherproof to IP66 as per IEC529 (Both certification as EExi and EEx d).
All Signals associated to Motorized valve are Non Intrisically Safe. (TTAB-
02030-1041)
All I.S type instrumentation system documents related to I.S loops / circuits
shall be certified by official certification organization. Intrinsically safe wiring
shall terminate directly on barriers for incoming and outgoing to field.
Compliance with ATEX Directive:
The “Instruments” and the associated accessories shall be certified according
to the ATEX Directives.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 7 / 379
Revision : 2
RESID UPGRADING PROJECT
Field mounted electrical equipment and wiring shall be suitable for Class I,
Group B, Division 1 and Control room equipment and wiring shall be suitable for
non hazardous area only if ;
a) the control room is located within an area in which the nearest process unit
battery limit is minimum 30 meters; or
b) the control room floor is 0.7 meter above the grade of surrounding area and
the nearest process unit battery limit is minimum 15 meters. Regardless of
classification, enclosures for field mounted equipment shall be of heavy duty
construction, wiring shall be fully protected against physical damage, and
non-self cleaning electrical contacts shall be hermetically sealed to insure
operation in refinery atmospheres. The control room will be pressurized as
per API RP 554 section 5, point 5.4, item 5.4.4. Air purification will be
provided as per API RP 554 section 5, point 5.4, Item 5.4.3 and 5.4.5
3.16 Where applicable the “Instruments” and the associated accessories shall meet
the PED Requirements.
3.18 Piped and mounted filter regulator assemblies complete with a regulator output
pressure gage shall be provided for all instruments, control valves, etc.,
requiring individual air supplies and shall be designed for 6-8 kg/cm2 air supply
pressure.
3.19 All instruments shall be tagged for identification. The tags shall be substantial,
of stainless steel, stamped with the tag number, and permanently attached to
the instrument with stainless steel screws or drive pins.
3.21 All process connection of instruments (including pressure gauges) shall have
block and drain/vent valves as a minimum located near instruments.
3.23 Connection of field mounted instruments to piping and bulky equipment shall
have the following features:
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 8 / 379
Revision : 2
RESID UPGRADING PROJECT
3.23.1 As far as possible, support large case and bulky instruments from
rigid vibration-free basis and not from piping or walkways.
3.23.4 All process connections of instruments shall have block and drain
vent valves located near instruments.
3.23.7 All instruments will be of the latest but proven design of the
manufacturer.
3.24. All alarms related to instruments connected to safety system (ESD) will also be
sent to DCS via redundant-serial link with time stamp.
A dedicated DCS critical alarm to be provided when the emergency shut-down
system is activated by push buttons (local/on board).
Vibration monitoring system shall be Bently Nevada make 3500 series only.
Bently Nevada vibration and displacement monitoring systems shall be
integrated into DCS System via serial or ethernet communication interface to
observe and trend all displacement, velocity and vibration data. The latest
proven technology and models of Bently Nevada vibration and monitoring
systems (hardware/software) shall be used.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 9 / 379
Revision : 2
RESID UPGRADING PROJECT
R2 The trip from vibration monitoring system shall be via Series 3500 system with
hardwired relay outputs connected to central ESD system.
All the monitored variables of each module shall be connected with DCS via
MODBUS signals for continuous monitoring/trending purposes.
The power supply module in the vibration monitoring cabinets shall be 100%
redundant. Power to redundant modules shall be fed from two diff. 220 V AC
UPS feeders.
The BN 3500 for each machine shall consist of a rack, redundant power
supplies, rack interface module, any combinations of monitor modules
necessary for the relevant I/Os (e.g. radial vibration, thrust position, keyphasor,
etc.) and redundant Communication gateway.
Redundant power supplies in the monitor rack shall convert the incoming power
supply into the voltage levels required by the system. Each power supply
module shall be powered from the external redundant UPS power source with a
dedicated circuit breaker. The removal or failure of one power supply in the rack
shall not cause any disruption or machine to trip. Each power supply shall have
the capacity to power the fully loaded rack.
R2
DELETED
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 10 / 379
Revision : 2
RESID UPGRADING PROJECT
All signals coming from BN probes in field will be wired directly to the BN
system (through dedicated FJB and multicables).
R2 The trip logics in the Bently Nevada shall send hardwired signals from relay
output cards towards the ESD.
The monitoring system shall have the self-diagnostic capability and it shall be
required to provide the advance diagnostics in all machinery problems. The
system fault alarms shall be provided for:
A common system fault alarm contact output from each rack shall be hardwired
to DCS for annunciation.
The Bently Nevada system shall be maintained and configured via 3500 Rack
R2 Configuration software, installed on a PC with an interface to the programming
ports of the MMS.
The Bently Nevada System 1 shall continuously evaluate both mechanical and
process parameters (including performance) and provide timely advisories to
operators, in order to avoid or mitigate catastrophic failures. This results in
improved site profitability from higher unit on-stream factors, lower maintenance
costs and more effective preventative and predictive maintenance.
For machinery with sleeve type radial bearings of any design, (tilting
pad, cylindrical, elliptical, lobed, etc.) the Contractor shall supply to
orthogonally mounted (90 degrees separation) proximity probes to
measure radial vibration using the Bently Nevada XY & Gap
Monitor or the 3500 equivalent Monitoring System. The probes
should be mounted directly to the bearing cap.
The thin fluid film that supports the shaft, in a fluid film bearing,
permits shaft movement relative to the bearing. Two orthogonally
mounted proximity transducers are required to observe this motion
directly.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 11 / 379
Revision : 2
RESID UPGRADING PROJECT
· For Gas Turbines with spooled shafts, the High Speed shaft
speed is typically only accessible via the Auxilliary Gearbox. In
this case, a keyphasor transducer shall be mounted to observe
the gear teeth on the high speed gear wheel. The TÜPRAŞ
Engineering Manager shall approve any deviation from this
requirement. If the gear profile is not suitable for a standard 8mm
sensor, a specialty “Narrow Side View” transducer may be
substituted. All other keyphasor locations must be designed to
observe a once-per-revolution target.
· For Gearboxes and Integrally Geared Compressors, one
Keyphasor® sensor must be installed on each shaft for once-per-
rev phase reference measurements (unless already installed on
the driver or driven machine on the same shaft).
R2 3.25.5 DELETED.
R2 · DELETED.
3.25.7 All communication links between the systems such as DCS, ESD,
PLC, F&G, B/N monitoring systems, PHD, anti surge control
system. , control panels , etc. shall be provided as redundant.
Moreover , the connection of each system ( device ) to other system
will be provided with separate and redundant communication ports .
Each redundant communication bus port will be included only one
system.
3.25.8 All screens / monitors will be LCD type instead of CRT monitors .
3.26 The use of Foundation Field Bus/ PROFIBUS or any other cluster/Multiplexer
type I/O philosophy shall not be allowed in project and any part thereof.
3.27 Minimum contact rating for disconnecting inductive loads shall be:
3.29 Instrument ranges for trip functions and control functions in the same service
shall be equal.
3.30 Ranges used for measurement and control instrumentation shall overlap alarm
and trip settings by minimum 5% of the span.
3.32 All field instruments, junction boxes, cabinets, panels etc. shall be provided
screwed SS tag plate with tag no. engraved or embossed on it.
3.33 Weights and measured approved Mass Flow meter shall be provided for all
type for fluids/material (input/output ), raw materials, finished product or by-
product, which is considered as custody transfer.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 16 / 379
Revision : 2
RESID UPGRADING PROJECT
3.34 All interlock shall also be realized from 4-20 ma analog input transmitters in the
ESD. No field switches shall be used for interlock purpose, except NAMUR type
proximity sensors for valve positions switches.
3.35 All signal exchange between field and central cabinet room shall be via
individual hardwire pair of cable as specified in detailed cable specifications.
From the field, all field transmitters shall be routed to field mounted junction
R2
boxes, from where these shall be taken to central cabinet room via multi pair
cables. Use of 6 pair or 12 core cable shall be used in special cases. All analog
multi pair cable shall be up to 24 pair. All Digital input/output multi pair cables
shall be either 24 core or up to 24 pair. All T/C multi pair cable shall be 12 pair
and RTD multi pair cable shall be 6/8/12 Triad only.
Multicables shall be named with the same tag of the Junction Box adding a “M”
instead of a “JB”, and an “I” in the cases of intrinsically safety.
Example: Example: 147-JA(I)-M-0015-DCS
3.36 To the extent possible, direct run cable from field instrument to central cabinet
room shall not be employed. All the signals to the central cabinet room shall be
routed through multi pair cables via field mounted junction boxes only.
3.37 Usage of Foundation Field bus / Profibus type clustered I/O wiring philosophy is
not allowed at any locatıon in the whole plant.
3.38 Few dedicated, special type of cables from special control system may be
directly routed to cabinet room in place of multi pair cables.
3.39 All the fiber optic cables / system cables, special cables must be armoured type
laid preferably in overhead trays/duct only. All system cables outside control
room should be armoured.
3.40 All type of single and multi pair power, control and signal cables in the field shall
be with steel armoured only for mechanical protection.
3.41 In the whole plant area, where there are chances of fluid leakages/spillage in
normal operating conditions, all cable trays/cable ducts shall be provided with
closed covers made of 2 mm thick SS304 sheets.
- Electrical certificates;
R2 - DELETED.
3.45 The material components, which come into contact with the fluids to be
measured, shall be resistant to corrosion caused by said fluids. It shall be
compatible with the piping material when being clamped, welded or connected
by other methods.
3.46 All instruments and equipments shall be suitable for use in specified site
climatic conditions and industrial environment in which corrosive gases and / or
chemicals may be present. All external surfaces shall be suitably treated to
provide protection against corrosive plant atmosphere with epoxy painting /
powder coating.
3.48 All in-line instruments shall be with flanged connection. Sandwich type
connections shall not be used. Pressure rating for all instrument items shall be
R2 ANSI 300 # minimum. For pipe classes with higher pressure rating the same
shall be as per pipe class. For pressure class 600 # and above RTJ type
connections shall be used if it is required by piping specifications.
3.49 Flange ratings for instruments may differ when instrument flanges and the
mating flanges on piping / equipment are of different materials (e.g. SS-316
thermowell on CS pipes). The contractor shall in such cases, ensure that the
rating of flange is chosen for the instrument and the corresponding flange on
piping / equipment.
3.50 Material of process wetted parts shall be SS-316 minimum. Superior material
shall be considered, if required, as per the process medium. This is a common
requirement for all Instruments and hence applicable even if not explicitly
specified against each type of instrument in the succeeding pages of this
specification.
3.51 Piping/Instrument scope change for instrumentation shall always be after first
isolation/drain valve for all types of instruments, including local Pressure
gauges.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 18 / 379
Revision : 2
RESID UPGRADING PROJECT
3.52 Transmitters shall be mounted on nearest platform / grade level keeping in view
requirements of readability and accessibility.
3.53 All remote seal diaphragm type Flow, Pressure and Level transmitters shall be
designed with 2” flange size except for low range pressure (vacuum 0.5
R2 kg/cm2) shall be 3” flange size. Also, irrespective of the pressure rating, the
minimum pressure rating for all the flanged instruments shall be ANSI CL 300.
3.54 Irrespective of the pressure rating, the minimum pressure rating of all
instruments nozzles, flange size shall be ANSI 300# ratings only. This includes
orifice flange assembly, thermowell flanges, RADAR type level transmitters,
Ultrasonic type level transmitters, Diaphragm type remote seal
Pressure/Flow/Level transmitters, Magnetic and mass flow meters and any
other flanged connection type instruments. Control valves and ON-OFF valves
R2 shall be rated in accordance with the line spec. unless otherwise specified
except that carbon flanged valve up to and including 6” shall not be less than
300 L.b (TRM-TQ-INS-0039)
3.55 At few places, for improving reliability and safety of operation and control, “2
Out Of 3” philosophy for Interlock shall be followed. The general guide line for
selecting such loops may be a trip/interlock, which is causing complete plant
shutdown, either directly or indirectly. This necessitates installing and
connecting 3 transmitters for interlock purpose with PLC on the same
parameter. If there is a closed loop control in DCS on the same parameter,
there shall be fourth transmitter, dedicated for connecting with DCS.
3.56 All temperature measurement in the plant shall be carried out using only
Thermocouple or RTD elements. Local temperature gauges may be used only
R2 where essentially required. All temperature points shall be provided with either
direct thermocouple (generally “E” type or “K” type) or RTD (generally 3 wires,
PT100) sensors with flanged thermowell assemblies. 2 wire, 24 V DC, SMART
transmitter shall be used for all temperature measurement.
3.57 All thermocouple/RTD sensors shall be duplex type with Flanged thermowell
along with nipple-union-nipple assembly along with thermocouple head,
certified as per EExia, IIC/T6 and weatherproof to IP65 as a minimum.
R2
Thermowell shall be manufactured from drilled bar stock, tapered. The cable
entry shall be ½” NPT(F) and complete assembly shall be provided with SS
MOC, double compression cable glands certified as per EEx “e”/”d”, IIC/T6 and
weatherproof to IP65 with PVC hood. EExia will not be considered.
3.61 Systems enclosures shall have a degree of protection in accordance with IEC
60529, protection code IP 65 as a minimum. Preference to IP-65 due to heavy
rains/storms. Cable glands to be IP-66 to avoid ingress of local present
electrical conductive dust.
All field instruments shall be damp-proof and dust-proof, minimum protection
class as per IEC 529 shall be as follows:
Electrical / Electronic instruments : IP 67 Sensors; RTD, T/C, etc. : IP 65
Solenoid valves : IP 67 etc.
3.63 The quality of the instrument air and the air supply pressure range for
transmission devices shall be in accordance with IEC 60654.
3.64 Instrument air shall be used for the pneumatic operated actuators (e.g. control,
on/off valves).
3.65 All central cabinet room located instrument systems including DCS/ESD
systems, stations, printers, etc., Fire and Gas detector monitoring systems,
CCTV System and cameras, Bently Nevada Vibration Monitoring system and
MMS, Local Control Panels, Pilot Ignition and Panels, Flare Local Panels,
Woodward Digital governor system, PA System, Analyzers, critical instrument,
mass flowmeters, Tank gauging systems, nuclear level instruments,critical
loads etc. shall be feeded 220 V AC UPS Power only.The instrument earthing
system consists of one or more earthing electrodes close to the control building
at a safe distance from any plant-earthing electrode. The resistance to earth is
to be less than 1 ohms. To achieve this an array of parallel electrodes
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 20 / 379
Revision : 2
RESID UPGRADING PROJECT
may be used. The instrument earthing shall terminate in a copper bus, mounted
centrally to all instrument equipment, but electrically isolated from any other
equipment or structure. The cable connections shall be easily accessible for
testing facilities. All connections between the copper bus bars and to the central
earth bar shall be individually connected via a separate, insulated, stranded
wire conductor of at least 6 mm². To avoid undesired ground loops due to
differences in earth potential or influence of surface currents, the shield of
signal wires shall be connected to the instrument earth system only at one side
(in the control room/satellite building). The shielding shall be kept isolated from
cable armoring and instrument enclosures.
The model / type of probe/sensors and all primary devices, which are to be
installed in the field shall be suitable for plant hazardous area classifications
and suitable to the application.
The over-speed trip mechanism/interlock for all the machines shall be equipped
R2 with Woodward make Protech Trip systems only. The secondary hardware of
these system shall be installed in cabinet rooms in a standard RITTAL panel of
1200mm (W) x800mm (D) x 2100mm (H) or 600mm (W)x 800mm(D) x
2100mm(H) with RAL7035 color shed. CONTRACTOR to supply suitable
armoured, pair/overall shielded, cooper conductor PVC cables between field
sensors and control room.
The system shall provide additional 4-20 ma isolated dc output to be connected
with central DCS for real time trend/historical analysis of various measured
parameters. Also system shall provide dry contacts for additional trips/alarms to
connecting these to central DCS/ESD system.
All field sensors, input/output cables shall be laid between final control element
in the field and secondary electronic unit panel at cabinet rooms
WOODWARD digital governor shall provide necessary speed, controller
inputs/outputs (isolated 4-20 ma dc) and trip/alarms’ signals (Isolated DI & Dry
DO contacts) in hardwired form for connecting it with central ESD/DCS.
Apart from these hardwire signal exchange between Woodward digital governor
R2 and central DCS / ESD; Woodward governor have a communication
(redundant) link with MODBUS protocol for information exchange to central
DCS.
The power supply to the secondary unit installed in central cabinet room shall
be from UPS 220 V AC only. This shall be fed from PDB located at cabinet
rooms. All field sensors, input/output cables shall be laid between final control
element in the field and secondary electronic unit panel at cabinet rooms.
Anti-surge control system shall provide necessary process parameters
indication, controller inputs/outputs (isolated 4-20 ma dc) and trip/alarms’
signals (Isolated DI & Dry DO contacts) in hardwired form for connecting it with
ESD/DCS.
Apart from these hardwire signal exchange between anti-surge control system
for turbo machinery and DCS / ESD; Anti-surge control system shall have a
facility for 2 wire RS485 communication (redundant) link with MODBUS
protocol for information exchange to central DCS.
R2 XXX-JY(I)JB-YZZZ-SYSTEM
Example: 147-JAIJB-0015-DCS
The naming philosophy for junction box shall be adopted in such a way that
from the tag number of the particular junction box, it shall be evident to decide
type of signal and destination
All junction box shall be die-cast aluminium and it shall be epoxy painted
according to the type of hazardous area protectıon type (example; blue for IS
signals). Based on requirement, there shall be diff. insulated shield and earth
bus bars are to be provided in the junction box. The individual branch cable
shall be brought to central cabinet room panel instrument shield bus bar via
insulated shield bus bars and multi pair shields from junction boxes.
All junction boxes shall have branch from side entries and multi pair cable
entries from bottom only.
R2 All junction boxes shall be weather proof to IP65 as a minimum. Generally 12
branch entries and 1 no. of main multi pair cable entry type junction boxes shall
be used in the total project.
The color code shall be based on type of signals. The qty. shall be as required.
Each junction box shall have engraved/embossed SS tag plate with tag
number. This tag plate shall be screwed on the junction box.
3.70 Instruments shall be mounted on a vibration free place. Special care shall be
taken for heat expansion.
3.71 All pressure instruments, except for those fitted with diaphragm seals, shall
have a block valve and a drain/vent facility, to provide the capability of
depressurizing the impulse line.
3.72 Differential pressure instruments shall be located above the taps for gas and
non-condensable fluids, and below the taps for liquids and condensable liquids.
For steam service, pressure instruments shall be mounted with a steam siphon
or condence pot.
3.73 When instrument supports have to be fixed to fireproofed plant structures, these
supports shall be welded to the steel structure before the fireproofing is applied.
shall be taken that selected fittings are compatible with the tubing size and its
specifications.
3.75 Where the above tubing and fittings are not suitable for the process fluid or the
process conditions and/or specific project requirements, other materials
conforming to the piping specification shall be used.
Tubing shall be supported and protected from vibration and physical damage.
3.76 No mechanical stress shall be induced upon an instrument that will cause a
malfunction or error in the readout. Tubing shall not be secured directly to
machinery or pipes. Tubing clamps and miscellaneous hardware shall be 316
stainless steel.
3.77 Individual instrument air supply and pneumatic transmission lines to and from
instruments shall be SS 316 tubing. Tubing shall be 6 mm x 1 mm wall thickness
soft annealed, seamless. High-volume pneumatic actuators may require 12 mm
R2 OD x 1 mm tubing. Fittings shall be SS double compression, Swagelok or Parker
only. Care shall be taken that selected fittings are compatible with the tubing
size and its specifications. Individual tube runs shall be supported by existing
structures and steelwork.
3.78 Nameplates of a permanent type, firmly fastened, showing tag number (and
service) shall be used.
3.79 Local indicating instruments shall be readable from where the related
equipments are operated or from where the primary instruments are to be tested
or calibrated.
3.80 Wherever possible, the centerline of instruments shall be 4'-6" above grade or
platform, with the exception of d/p flow transmitters which shall (in most cases)
be line mounted, close to the flow element. The closed coupled mounted
instruments shall be installed on the process pipe through a pipe strap
installation only when it is required as mandatory by the licensor. (TRM-TQ-INS-
0101 Rev01)
3.81 All instrument supports, cable ladders/trays, conduits and other iron supporting
materials shall be hot dip galvanized.
The INtools database will include all the Input / Output signals with a physical
connection with systems (AIs from transmitters, contacts from switches, AOs to
valves, alarms to local panels etc.) and all the local instruments (thermometers,
pressure gauges…).
INtools shall also include all instruments that are part of package Vendors
scope of supply.
INtools shall also include all new instruments specification sheets that will be
completed after purchase order.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 26 / 379
Revision : 2
RESID UPGRADING PROJECT
The INtools modules and database will include, as a minimum, the following
information:
. Instrument List and index modules
. Instrument Specifications modules
. Process data modules-process sheets
. Database
. Inst. Type
. Administration modules
. Process Function
. Gen. Pr. Function Subcategory
. Spec. Sheet Form No
. Wiring and connection modules-panels, cables, connections, automatic
cross wiring, auto-wiring, intrinsic safe calculations, cable routing etc.
. Panel
. Cable
. Connection type
. Control system
. Hook-ups- AutomaticHOOKUP generation
. Panel Layouts
. Locations
. System I/O Type
. Skip loop creation
· Loops modules- Automatic LOOP generation(multiple sheets supported),
Enhancedsmart loop, Customizedsymbols, Revisioncontrol and instrument
tag number (field tag and system tag),
· Reference P&Id number,
· Line number or equipment number,
· Measuring range and engineering unit,
· Service description,
. Junction Boxes
. Marshalling racks
. Installation details modules
. Cabinets
. DCS&SIS
. DCS&SIS interfaces
. Control valve
. Calculations modules-flowmeter, valve, orifice, control valves, flow
elements, thermowell (vibration) etc.
. Procurement modules-order lists,reports,manufacture product
. DCS&ESD loop drawings
· Wiring information (RIE no., cabinet no, terminal strip reference no, etc.).
Specific procedures shall be issued covering the split of responsibilities for the
database maintenance and updating during the various phases of the project
All necessary Hookup drawings must be generated from smart plant
instrumentation in ESL format.
3.84 The instrumentation loads such as DCS/ESD Systems (CPU and I/O cards,
cabinets, operator consoles and stations, engineering consoles/PC’s,
printers/hard copies etc.), CCTV system and cameras, Bently Nevada
Monitoring Systems, local control panels, pilot ignition and flame panels, flare
local panels, Fire & Gas Detection Panels, analyzers, special instruments
nuclear level instruments, positive displacement meter, capacitance level
instruments, ultrasonic level transmitter, tank gauging system, selling system
critical loads etc. will be feeded from UPS.
- All type of limit switches shall be 2 wire, proximity type, and NAMUR
sensors only.
- The make shall be P+F only. The sensor shall be generally cylindrical
NAMUR sensor type proximity switch. The diameter and sensing range
shall be selected based on application.
- The material of the sensor shall be SS316. Krastin type probes shall not be
used, unless surrounding atmosphere heat permits the use of the same
under worst condition.
- All limit switches sensor shall be adjustable with the threaded length and
check nut arrangement.
- Flying lead type loose connections for NAMUR sensors are not acceptable.
All these NAMUR sensors installed on any instruments to sense the
position shall be housed in a closed box certified for weatherproof to IP67.
The gland size shall be ½” NPT(F).
- All ON-OFF type application valves taking in part in interlock/shutdown
shall be provided with Open and Close type NAMUR sensor as limit
switches. The sensors along with enclosure shall be installed in control
valve in such a way that it can be removed with ease for maintenance.
R2
- Limit switches shall not be used for Control Valves unless it is indicated in
pids. All controls valves shall be equipped with SMART positioner, from
where the analog output for continuous position is available, which shall be
used for interlock/control purpose.
- Limit switches shall be certified as intrinsically safe to Eexia-IIC-T6.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 28 / 379
Revision : 2
RESID UPGRADING PROJECT
3.86 For process Hook-ups, tubing compression fitting and manifolds shall be used
up to class 600. For class 900 and above and Hydrogen service shall be used
pipe and individual valves. Installation shall also be done as close couple when
R2
licensors required as mandatory (FW and UOP). For the rest of the units API
551 standard can be applied. Contractor must follow and apply the
requirements and comments of Tüpraş for the process Hook-ups without
charging any change order.
3.87 Intrinsically safe wiring shall terminate directly on barriers for incoming and
outgoing to field for DCS and SIS I/O signals-all. Barriers shall be ATEX
certified.
3.88 Vendors for the electronic transmitters (flow, temperature, pressure, diff.
pressure and diff. pressure for level ) shall be EMERSON, YOKOGAWA or
HONEYWELL.If the vendor is EMERSON, 3051S and 3144P series
transmitters of EMERSON must be selected and installed. If the vendor are
YOKOGAWA or HONEYWELL , the equal series and models transmitters which
have the same and or equal characteristics, features, standards, hardware and
software properties, functional and performance specifications etc. of the these
vendors must be selected and installed with the approval of Tüpraş.If the
transmitters properties of YOKOGAWA or HONEYWELL does not have same
or more proper and advanced specifications , 3051S and 3144P series
transmitters of EMERSON must be selected
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 29 / 379
Revision : 2
RESID UPGRADING PROJECT
Temperature(1) : Degrees C
Pressure (near atmospheric) : MM H2O
Pressure (above atmos) : KG/CM2 gage or absolute
Vacuum : MM H2O
Level (2) : % of range for process.
Flowrate-Liquids :( 1 M3/H) : M3/H at 15C Refer to 5.332 & 5.333 utilty and
process metering (TRM-TQ-INS-0020)
- Gas and vapors : NM3/H
- Steam : KG/H
Mass Flow : KG/H
2.1 Scales
Scales shall be direct reading for all variables except level, which will be
displayed as "0-100%”. The square root implementation shall be made on the
differential pressure flow transmitters and the 4-20mA output of the transmitters
will be linear to the DCS or ESD systems.
2.2 Charts
R2 In general, chart ranges shall be 0-100 uniform for all variables. Flow
transmitters shall include the square root.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 30 / 379
Revision : 2
RESID UPGRADING PROJECT
3.1 Scales
Scales shall be direct reading for all variables except level, which shall be
displayed as 0-100%. Units shall be as above.
Charts shall be direct reading for all variables except level, which shall be 0-
100%
3.4 All recorders shall be supplied with one year of charts and ink sets. Chart types
and ranges shall be standardized as much as possible.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 31 / 379
Revision : 2
RESID UPGRADING PROJECT
Diff. Press.
Level: 1”SW As Piping spec.(1) 1”SW As Piping spec.(1) 1”SW As Piping
- General spec.(1)
2”(3)RF MNFR.STD 2”(3)RF
- Remote Seal MNFR.
STD
Displacer/Radar
Level:
- Ext. Cage --- --- 2”RF 2”RF 300# as a
- Internal --- --- 300# as a 4”RF minimum
R2 minimum and and
Level Switch:
according to according
- Ext. Cage --- --- 1”RF 1”RF
piping to piping
- Internal Float --- --- --- 4”RF
specification specificati
Level on
Gauge/Magnetic: 1”RF 1”RF
Pressure
Instrument:
- General 1” SW As Piping spec. 1” SW As Piping spec. 1” SW As Piping
- Remote Seal 2”(3)RF As Piping spec. (1) 2”(3)RF As Piping spec.(1) 2”(3)RF spec.
- Draught --- --- --- ¾”SCRW As Piping
Gauge spec.(1)
Flow element
(tapping):
- Below 900# ½”(2) As Piping spec.(1) --- --- --- ---
- 900# and ¾”(2) As Piping spec.
above
(IV) FLOWMETERS
Orifice plate shall be the standard flow measurement device except for following
conditions:
2.1 Flow of fluids shall normally be measured by sharp-edge concentric plates with
differential pressure actuated meters. Quarter circle-edge concentric orifice
plates with differential pressure actuated meters will normally be used for
viscous fluids having a Reynolds number below 20,000.
2.3 Eccentric type orifice plates shall be used for fluids containing two phases. The
eccentric orifice plates shall have the bottom of the orifice bore flush with the
bottom I.D. of the pipe. Eccentric orifice plates shall be used in horizontal runs
only.
2.4 Flow elements such as flow nozzle, venturi, rectractable multihole averaging
pitot tube (annubar type) will be used where high capacity and good pressure
recovery is required.
R2 2.5 All “V-cone” or balanced type flowmeter transmitters shall be multivariable and
flanged capillary type.
2.5 Multihole averaging pitot tube(Annubar type) shall be used for larger pipe sizes
and clean fluids. It shall be multiple averaging type, retractable type allowing it
to be removed for maintenance during operation and purging accessories are to
be taken into consideration during selection.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 33 / 379
Revision : 2
RESID UPGRADING PROJECT
2.6 Flow measurement shall generally be made using differential pressure type
primary sensors of advanced capacitance type with digital information
processing unless otherwise specified by OWNER.
2.7 Rotameters of the metal tube type will be used where applicable in process
service. Where streams cannot be easily interrupted in line, in toxic services
R2 and critical lines, block valves and by passes shall be provided under client
approval.
For venturi meter, V-cone meter, orifice plate, annubars and ultrasonic meter
independently of the size bypass and block valves shall not be considered.
2.8 Orifice plate dimensions shall be in accordance with Licensor standards (latest
edition) and for non licensor units primary elements shall be calculated,
R2 manufactured and installed in accordance with ISO 5167. For quarter circle
and conical entrance BS-1042 shall be used.
Orifice plate material is stainless steel 316 SS minimum (higher grade material
as per Piping Spec.).
The minimum thickness for orifice plate based on shall be in accordance with
ISO-5167 shall be:
The Thickness shown is for service under 650 oF (343 oC). For services above
this temperature the thickness shall be increase 1/8” (3 mm)
2.9 The minimum orifice run shall be 2 inch diameter. If the process lines are
smaller than 2 inch, the line size shall be increased to 2 inch for the meter run,
provided that the requirements of flow can be met. If a line size smaller than 2
R2 inch and it is not possible to increase the line to 2 inch diameter, it must be
used an integral orifice meter (½ and ¾ inch) or precalibrated orifice meter run
(1 and 1 ½ inch) with corner taps shall be used. In conjuction with integral
orifice meter, a suitable strainer and flow conditioner shall be installed
preceding the meter. If service is continuous block and by-pass valves shall be
considered for integral orifice and meter run up to1 ½ inch.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 34 / 379
Revision : 2
RESID UPGRADING PROJECT
2.10 Drain and wheep holes shall be provided for orifice plates which have a bore 1
inch and larger. Drain or weep holes shall be included in the orifice bore
calculations.
2.11 Flowrate measurements of process charge, product and utility streams involved
in material, utilities balance, boiler efficiency and process calculations requiring
compensated flowrate computations(i.e. corrected with actual temperature,
pressure and specific gravity) and totalization shall be performed by corriolis
type mass flowmeters as far as mass flowmeters sizes and measuring
capacities are applicable.
For pipe sizes bellow 18” orifice plate with tap flanges shall be used. For sizes
18” and larger radius tap shall be used, and taps shall be located one pipe
diameter upstream and one half pipe downstream.
Venturi meter & flow nozzles may be considered for gas/air flow measurement
in large size pipes / ducts, where high accuracy is required with less permanent
pressure loss For high velocity steam or similar fluid, flow nozzles may be used
in place of orifice plates to avoid problems due to erosion.
Irrespective of pressure, the minimum flange rating shall be ANSI 300#.
Averaging pilot tubes shall be considered for low pressure loss, high velocity,
large diameter lines and air ducts. This shall be installed on 1 ½” size nozzle for
small lines and 3” for large lines or lines with large velocity. Small lines are lines
up to 12”, large lines are lines above bigger and equal to 12”, vendor
recommendation shall be used. The averaging pitot tube shall be of SS316
MOC as a minimum. It shall be retractable with ball valve arrangement and
shall be provided with end supports. Irrespective of pressure, the minimum
flange rating shall be ANSI 300#. Vendor recommendation for isolation valve
type shall be followed with client approval. All wetted parts (pitot utbe, flanges,
isolation valves shall be 316 SS as minimum, higher material as per piping
specification.
Mounting flanged and accesories for the installation to the pipe shall be
supplied by vendor.
Variable Area Flow meters or Rota meters shall be as per ISA-RP 16.1. 16.2,
16.3 16.5 and 16.6 and shall be used for viscous or corrosive services or where
rangeability of required flow precludes the use of an orifice.
Metal tube rota meters shall be used for all fluids. The devices for indicating or
transmitting shall be magnetically coupled with float or extension. Magnetic
coupling shall be glandless type.
Rota transmitter shall be 24 V DC, 2 wire, 4-20 ma, SMART with local display
type. Irrespective of plant’s hazardous area classifications, all the Rota
transmitter shall be EExiaIIC/T6 as per CENELEC and Weather proof to IP67.
Variable Area Flow meters (purge rotameters) fitted with a constant flow
regulators shall only be used for fixed rate flows such as flushing or purging.
Where high accuracy is required like for input/output fluids in the plant, where
mass balance is important, where custody transfer is involved, or where liquid
physical property is varying, the Coriolis principle based mass flow meters shall
be used.
The Coriolis mass flow meters shall be used for all density measurement, fuel
oil consumption of heaters and boilers, unit feed and liquid and gas products.
Mass flow meters end connections shall be flanged and the minimum flange
rating shall be ANSI 300#.
Mass flow meters shall be 4 wire transmitters and supply shall be 220V AC
only. Mass flow meters shall be supplied with SMART
(Hart) transmitter with 4-20 ma output and pulse output. All mass flow meters
shall be supplied with Local LCD type display. All mounting bracket shall be
SS304.
All mass flow meters shall have accuracy of +/- 0.1% for both analog and pulse
output. It shall be possible to freely configure density or flow output over any of
these two available output options.
R2 DELETED.
Electrical certification for the meters shall be EExib IIB/IIC T1-T6 and for the
transmitters shall be EExde ia/ib IIC T5
While selecting mass flow meters, consideration shall be given to fluid velocity
max. limit ( 2 meter /second for liquids), permanent pressure loss, etc.
Accuracy compliance (+/- 0,1%) will be the criteria to be followed for the
selection, even if velocity is higher than 2meter/sec. When pressure loss is
higher than the process requierement it must be submitted to process
approval.Vendor shall confirm the longest meter life by selecting the design
with the thickness wall and the slowest velocity that can provide the required
accuracy and range.
Magnetic type flow meters shall be used for electrically conductive slurry,
cooling water or corrosive services and shall be installed with line size bypass,
with block and cleaning valves, at the lowest point in piping to ensure that
meter run is always liquid filled.
Grounding ring or ground electrode shall be used in all the magnetic flow
meters.
R2 In battery limits block and bypass valves for big lines shall not be considered.
Magnetic flow meter shall be used with a full pipe size so that the measurement
is accurate.
All magnetic flow meters shall be 4 wire transmitters. The power supply shall be
220 V AC.
All Magnetic flow meters shall be supplied withSMART transmitter with 4-20 ma
output and pulse output with hart communication .All magnetic flow meters shall
be suitable for 2” pipe mounting and shall be supplied with Local LCD type
display.
All magnetic flow meters assembly shall be EExia IIC/T6 as per CENELEC,
irrespective of the plant’s hazardous area classifications.
All the magnetic flow meters assembly shall be weather proof to IP67.
All mounting bracket shall be SS304.
The end connections shall be flanged type and min. pressure rating for flanges
shall be 300#.
Size the meter so that its maximum permitted flow rate is as close as possible
application maximum flow rate.
Vortex flow meter shall be used for steam mass balance of units.
Vortex flow meter shall not be used for the following services:
- Liquids having large concentration of solids and two phase flow service.
Vortex flow meters shall be installed with required straight lengths. Vortex flow
meters shall be supplied with (Hart) SMART transmitter with 4-20 ma output
and pulse output. All vortex flow meters shall be be supplied with Local LCD
type display.The end connections shall be flanged type and min. pressure
rating for flanges shall be 300#. All Vortex flow meters assembly shall be EExia
IIC/T6 as per CENELEC, irrespective of the plant’s hazardous area
classifications. All the Vortex flow meters assembly shall be weather proof to
IP66. All mounting bracket shall be SS304.
For gas and steam applications Multivariable flow transmitter with integral
R2
temperature sensor shall be used.
The sensors shall be isolated from the process and can be replaced without
shutting down the process, so bypass and block valves for maintenance are not
required.
Temperature compensation is done by vortex flow meter and pressure
compensation is done by DCS.
For simple restriction orifice, the orifice diameter shall be calculated in the same
manner as a square-edge concentric orifice plate in accordance with ISO 5167,
considering relationship between differential pressure an permanent pressure
loss.
Multiple restriction orifices consist on two or more steps of pressure loss joined
one common mechanical device. These devices shall be used the following
applications:
For multiple restricition orificies flanges must be welded. The rating must follow
piping specification.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 39 / 379
Revision : 2
RESID UPGRADING PROJECT
Ultrasonic flowmeters may be used for all liquid and gas applications where
there is a requieremente for the meter to present a minimum obstruction to the
flow an a magnetic flow meter is unsuitable.
3.1 The ratio of orifice bore to inside pipe diameter (d/D) shall be between the limits
0.20 to 0.70. If d/D ratio exceeds 0.70 for 5000 mm WC differential range, the
process line shall be increased for the meter run.
3.2 Differential range of orifice meters shall be selected 2500 mm WC for purpose
of standardization. In addition 1250 and 5000 mm WC can be used to obtain
the ratio d/D within the limits of 0.2 to 0.7.
3.3 Normal flowrate shall be approximately 70% of maximum flow meter capacity,
provided anticipated minimum and maximum flow rates will be between 30%
and 95% of capacity.
3.5 Where two or more disturbances exist, the distance between any disturbance
and primary element shall not be less than the limits given on Licensor
Standards. Therefore, it is required to consider also those disturbances more
upstream, and not only the one closest to the orifice.
3.7 Vertical orifice runs are often preferred for gas or steam flows which contain
appreciable amounts of condensates and for liquids which contain vapor. If
vertical runs are used, flow shall be downward for wet gases and steam an
upward for liquids. The potential error in vertical lines can be minimized by
R2
proper manifolding. DELETED.
3.8 DELETED.
R2
3.9 Orifice or venturi flowmeter calculations shall be supplied on OWNER approved
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 40 / 379
Revision : 2
RESID UPGRADING PROJECT
3.10 Orifice flanges shall be of weld neck type having flange tappings conforming to
3.11 Orifice flange taps shall have at least 500 mm. clearance accros them for
reaming purposes.
3.12 For pulsating services the DP measuring instrument shall have an internal
damping adjustment. Individual pulsation dampeners installed in the high or low
impulse piping is not acceptable.
3.13 Orifice taps at angles other than horizontal or vertically upward are not
acceptable.
R2 3.15 Eccentric orifices, quadrant/conical edge orifices and segmental orifices should
be used in horizontal runs.
4.1 All flow elements shall be checked concerning dimensions, marking and name
plate according to the individual specification. Hardness test as per NACE MR
R2
0103 shall be provided where required in individual specification. The following
certificates shall be produced.
5.1 Instruments, except for orifice plates shall have the following information on a
nameplate permanently fastened to the instrument.
5.1.1 Instrument identification number.
5.1.2 Pressure rating of pressure holding parts.
5.1.3 Manufacturer's name, model, serial number, operating range and
materials of parts exposed to process fluid.
As applicable, nameplates shall also carry information relating to voltage and
frequency.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 41 / 379
Revision : 2
RESID UPGRADING PROJECT
5.2 Orifice plates shall have, in addition to the requirement of API RP 551 process
measurement instrumentation, API RP 554 process instrument and control. The
equipment identification number and material stamped on the upstream side of
the plate.
1.0 REFERENCES
2.0 GENERAL
2.1 The range of pressure instruments shall be selected so that the normal pressure
will be in the middle third of the span.
2.2 Pressure instruments shall have over-range protection to the 1.3 times the
maximum range of the instrument.
2.3 Pressure ranges shall be standardized so that only one reasonable number of
different ranges need to be supplied to cover all probable refinery service.
2.7 Wherever used, bourdon tubes and bellows shall be AISI type 316 as a
minimum unless special conditions require otherwise. An exception may be
made in case of small size instrument air gauges.
2.8 Pressure instruments on steam and other hot condensable services shall be
fitted with syphons as necessary.
2.9 Pressure instruments shall be sealed or fitted with chemical protectors where
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 42 / 379
Revision : 2
RESID UPGRADING PROJECT
necessary.
3.1 Pressure gage measuring element shall generally be bourdon tube type. For
measurement of viscous, corrosive fluids and slurries, diaphragm seals shall be
used.
3.2 Direct indicating process pressure gauges shall be bourdon tube actuated with
160 mm diameter dials, bezel with a back flange and white with black figures.
On local panels 100 mm dial size gauges may be used. Pressure gauges shall
conform to OCMA specification 1N-1 or OWNER approved equal. All process
pressure gauges will be of “solid front” safety type.
3.3 Bourdon tube material for all pressure gauges shall be type 316 stainless steel
as a minimum unless otherwise required by special process conditions.
3.5 Gage connections shall have cases with bottom connections ½ " NPT-M ANSI
B 2.1 (except for diaphragm seal where 2” flanged connection shall be used in
general. Irrespective of design pressure, the minimum pressure rating for the
flange shall be ANSI 300#.) and ¼" NPT-M ANSI B 2.1 for pressure receiver
gauges and provided with wrench flats. Connection shall normally be 316SS
unless otherwise the special material is required.
3.6 All process pressure gauges shall be with "solid front" cases and be provided
with blow-out backs or disc inserts for safety.
3.7 Receiver pressure gauges shall have phosphor bronze measuring elements.
R2 3.10 DELETED.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 43 / 379
Revision : 2
RESID UPGRADING PROJECT
3.11 Excess flow check valve on inlet of any gauge operating above 70 kg/cm²(g)
shall be provided.
3.12 Compound gauge shall be provided with appropriate upper range value at any
ejector inlet or on discharge of any pump taking suction from a vessel operating
under a vacuum.
3.13 Where diaphragm seals are used they shall be of a type which permits
separation of the "bottom bowl" without loss of fill. This permits removal of the
gage/seal assembly from the bottom bowl for the purpose of cleaning,
calibration servicing of the seal, etc. The gauge and seal shall be furnished
(filled and calibrated) as a complete assembly, with the gauge directly mounted
on the seal.
3.14 Pressure indicators shall be provided upstream and downstream of the draft
control dampers.
3.15 A suitable draft gauge system including connections at the inlet of convection
section, in the stack before and after the damper and at above heater floor shall
be provided. If the convection section of the heater has two or more flue gas
outlet connections to the sack the above group of draft connections, except the
ones in the stack, shall be provided for each convection section flue gas outlet.
3.16 Dial cover shall be of shatterproof glass. The dial face shall be marked with
pressure element material. Pointers shall have micrometer adjustment.
3.17 For low pressure and vacuum services pressure gauges with capsule sensing
element to be used.
3.18 All pressure gauges and diff. pressure gauges’ Cases shall normally be of
304SS and weatherproof to IP-65 as per IEC-529 / IS-2147.
3.19 Ranges shall be so specified that the gauge normally operates in the middle
third of the scale.
3.20 Diaphragm seals, filled type shall be furnished where plugging or congealing of
the element may occur. When chemical seals are required, they shall be
R2 provided with fabricated vent and drain arrangement. Diaphragm seal device
shall be furnished completely assembled with the pressure gauge.
3.21 Remote seal Diaphragm type pressure gauges with capillary shall be used
wherever required for access and visibility. Use of Schaffer diaphragm type
gauges will be avoided as far as possible.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 44 / 379
Revision : 2
RESID UPGRADING PROJECT
3.22 The diaphragm seal devices shall be stainless steel SS316. The flange and
Diaphragm rings and top housings shall be of SS304, unless a special material
is required.
3.23 Liquid filled gauge shall be used where extreme vibration of the gauge is
expected. Glycerin or other suitable case filling liquid with non coloring property
shall be used.
3.26 Oxygen service pressure/diff. pressure gauges shall be supplied with special
inert fluids and shall be free from grease/oil. These shall be clearly marked with
“For use in Oxygen services”.
3.25 Over range protector and pulsation dampener, whenever used, shall be of SS
316 as a minimum. Pulsation dampener shall be used for all pulsating services.
It shall be floating pin type, externally mounted and externally adjustable.
3.26 Design materials, connections and accessories not specified herein shall be in
accordance with the standards, suitable for the specified service conditions.
4.1 Pressure switches connected to the process shall have stainless steel
measuring elements (helical bourdon or spiral or bellows, etc.) as a minimum,
except where other (higher) alloys are required for the application.
4.2 Pressure switches for pneumatic signals shall have bronze elements
(preferably bellows). Alternatively Buna N diaphragm elements shall be used.
4.3 Instrument process connection shall be ½" NPT-M B 2.1 for direct pressure
switches and ¼" NPT-M ANSI B 2.1 for receiver pressure switches used on air
transmission signals.
4.4 Electrical connection for cable entry shall be ½" NPT-F ANSI B 2.1.
4.5 All Switch function shall be snap acting, Single-pole Double Throw (SPDT),
hermetically sealed and potential-free contacts.
4.7 All interlocks/logic and alarms shall be realized via 2 wire, 24 V DC,
SMART,HART pressure/diff. pressure transmitters connected to ESD for
pressure, diff. pressure and level application.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 45 / 379
Revision : 2
RESID UPGRADING PROJECT
4.8 However, in special case, when required by machine vendors for machine
safety, for few critical applications, use of pressure and diff. pressure switches
shall be allowed.
4.11 Pressure switches shall be provided with a positive means of protection against
process fluids entering the electrical housing in the event of element failure.
4.12 Pressure switches shall be operative in full specified range. The switch
differential shall be selected as per operating conditions; it shall be less than
60% of difference between set value and operating value.
4.13 Diaphragm seal type pressure switches with flanged end connections shall be
specified for applications on plugging / congealing services. In all these case,
R2
the diaphragm flange size shall be min. 2” x 300 # ANSI ratings and Material
shall be SS316 for flange. Better material shall be opted based on process
requirement.
4.14 All diaphragm type pressure / diff. pressure switches with flushing connection.
Diaphragm seal device shall be furnished completely assembled with the
pressure switch.
4.15 Pressure switches shall have repeatability of ± 0.5% of full scale as a minimum.
4.16 The switching set point shall be adjustable over the whole range, with an
internally calibrated scale.
4.17 Switches shall be specified such that the on/off differential does not prevent the
switch resetting inside normal operating pressure ranges.
4.18 Over range protection and pulsation dampener requirements and design shall
be as per as specified above.
4.19 Design materials, connections and accessories not specified herein shall be in
accordance with the vendor's standards, suitable for the specified service
conditions.
2.1 Level transmitters and local controllers shall normally be of the external float
displacer type. For level control on hot columns where steam is present, the
vapor space of the displacer chamber shall be gas purged to prevent
condensation and flashing of accumulated water. However they will not be used
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 47 / 379
Revision : 2
RESID UPGRADING PROJECT
2.2 GWR (Guided Wave Radar) type will be used for interface level measurement
instead of displacement type for a better accuracy in the measurement unless
Licensor specifies another type. Displacer types may be used unless radar is
R2 not suitable to the process.
2.3 Differential instruments with static or flowing seals shall be used for extra high
pressure or temperature applications or where the service makes their use
particularly appropriate (e.g. interface between liquids. For ranges greater than
48" differential type instruments shall be used, directly piped, with either a
condensing or a filled reference leg.
2.4 External displacer type instruments shall have rotatable heads. External
R2
displacer type instruments with side-side connections shall be normally used for
level measurement upto 1524 mm. The standard ranges of 356, 813, 1219 and
1524 mm. Internal displacer type of level transmitter shall not be used.
2.5 Internal displacers without float cages may be used on open tanks and sumps.
In special services, such as extreme temperatures, high viscosity, with liquids
which could boil in an external cage, or where corrosion or other process
conditions dictate their use, internal displacers may be used in closed process
vessels. The design selected shall permit removal of the instrument without
entering or draining the vessel. Stilling wells shall be provided where required
by liquid turbulence.
2.6 Where necessary, to exclude process fluid from either or both connections or
from the instrument itself, the installation may be purged with gas or liquid
compatible with the process fluid.
2.7 Level transmitters with capillary connected diaphragm seals shall be applied.
2.8 When the above instruments do not satisfy the job requirements and process
conditions dictate, capacitance, ultrasonic, radioactive and other type of level
instruments shall be considered, e.g. de-asphalting solvent extraction interface.
Use of such instruments shall be subject to OWNER's approval.
2.9 Three pyrometer type liquid level indicators (rams horn temperature points)
shall be provided as a secondary indication for high temperature residual oil
services.
R2 2.10 All level transmitters shall be equipped with digital built in output indicator in
addition to the separate local indicator mounted near the final control element if
if they are indicated in pids.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 48 / 379
Revision : 2
RESID UPGRADING PROJECT
2.12 Displacer type level transmitter shall be 2-wire, 24 VDC, 4-20 mA output with
LCD type local display.(hart) Irrespective of plant’s hazardous area
classification, the displacer type level transmitter shall be intrinsically safe and
weatherproof to IP67. Transmitters shall have ½” NPT(F) electrical cable entry.
2.13 The standard materials for Displacer and displacer chamber shall be SS316
and Torque tube shall be Inconel, as a minimum. Based on process fluid better
options shall be selected.
2.14 Finned torque tube extensions shall be provided as necessary for temperature
service conditions.
2.15 Differential pressure transmitter shall be used for level measurement above
1500 mm for services requiring purge or where liquid might boil in external
portion.
R2 2.16 Differential pressure transmitters for use on corrosive or fouling service shall
be diaphragm wafer with extended filled capillary type. The length of capillary
shall be 5 mtr. with SS armoured. DELETED.
2.17 The process connection size shall be 2” Flanged for remote seal diaphragm
type Level Transmitters. Irrespective of design pressure, the min. pressure
rating shall be 300# .
2.20 Dip Tube type level transmitters may be used on corrosive, congealing, slurry
services, where suitable diaphragm seal type transmitter is difficult to obtain or
where accuracy is not of prime importance.
R2 2.21 For design temperatures equal or higher than 300°C, toxic products only
magnetic level gauges shall be used. For other cases, licensor design can be
followed.
3.1 Gauge glasses shall be provided for all levels requiring automatic or manual
control or monitoring. Gauge glasses shall have at least the pressure and
temperature rating of the equipment to which they are attached.
The Level gauge shall provide visible coverage of complete level transmitter /
controller range and the alarm/ trip level switches
3.2 Armored transparent type gauge glasses with integral illuminators shall be
provided for:
3.3 Armored type reflex gauge shall generally be used for light clean liquid level
indication.
3.4 The visible portion of gauge glasses shall cover the range end points of the
associated level transmitters or controllers.
3.5 Gauge glasses shall be standardized for individual glass section length and
R2 overall length achieved by multiple sections in a single casing. Overall length
shall not be achieved by screwing together short casings. Gauge glasses shall
be properly supported and valves shall be gate valve. Gauge glass shall
conform to size 7 and 9.
3.6 Protective shields shall be used where process fluid will attack glass.
3.7 Frost shields shall be used for process temperature below 32° F.
R2
3.8 For ranges in excess of 1399 mm (visible length) multiple gauges shall be applied
When two or more level gauge columns are required to cover a longer range,
the visible portion of the gauges shall overlap at least 1 in. No more than four
gauge units shall be used in one column.
3.9 Off-set type gauge valves shall be forged steel with horizontal ball checks.
3.10 Gauge glass lighting shall be provided by the gauge glass manufacturer and be
suitable for the area classification.
3.11 Consideration shall be given to the use of steam jacketed gauge glasses for
viscous stocks and to magnetic type level gauges where stocks are liable to
boil, e.g. propane, propylene etc.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 50 / 379
Revision : 2
RESID UPGRADING PROJECT
3.12 Gauge glass connections on all vessels shall be so located and arranged that
the gauge glass piping will be self-draining and cannot form a pocket for
retention of water.
3.13 In case where several connections for level instruments are located on one
vessel, a 3 in pipe column may be installed to reduce the number of
connections on vessel. The standpipe will be separated from the vessel by
block valves. All connections from this standpipe to instruments will be fitted
with block valves.
3.14 For application of gauge glasses to boilers and waste heat steam generators
refer to TGPS-F2 and TGPS-F3.
3.15 Gauge glasses for low pressure vessels containing low temperature non-
flammable, non-toxic fluids, such as water, or phosphate solutions may be
tubular glass type in lengths not exceeding 30" , with specific OWNER
approval.
3.16 Level gauge connections shall be min. 1 inch flanged 300 RF.
3.17 Magnetic type level gauges shall be used for the measurement of all liquids,
including dangerous, toxic or flammable fluids where glass breakage would
R2 cause a hazard. Centre to centre nozzle distances shall be as 300, 500, 800,
1000, 1500, 2000 and 2500mm, except for magnetic level indicator with
transmitter that center to center nozzle shall cover the total leght to be
measured.
Thermal expansion forces should be checked.
Body material for magnetic level gauge shall be as minimum SS304L, and follow
the associated vessel material specification.
The instrument connection shall be 1” for stand pipe and 1” for direct vessel
connections. Vent and drain connection shall be ¾”RF connection.
Where NACE is specified the magnetic level gauge shall be in accordance with
NACE MR0103. Hardness test and test certificates shall be provided.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 51 / 379
Revision : 2
RESID UPGRADING PROJECT
4.1 Level switches operating interlocks, shutdown or process alarms which are
related to personnel or equipment safety shall be directly "process actuated",
and shall utilize separate connections to the vessels.
4.2 External cage float switches (with flanged end) of the welded cage type shall be
used where separate switches are required. Materials of construction and
pressure/temperature ratings shall be in accordance with the requirements of
the process piping specification.
4.3 Other type of switches, using the principles noted in para. 2.8 (transmitters)
may be used where process conditions dictate.
4.4 For alarm application magnetically coupled level switches with switch mount rad
attached to the out side of the float chamber will be utilised.
4.5 All externally mounted float/displacer type level switches, the process
connection size shall be1”. Irrespective of design pressure, the minimum
pressure rating for this diaphragm flange shall be ANSI 300#.
4.6 The low-level switch shall be mounted directly on the column when the set point
is not less than 630mm. When level gauge and level switch are on the same
stand pipe, minimum allowable low level set point shall be 480mm on the
column.
4.7 External displacer type level switches can be considered for lighter fluids where
specific gravity is less than 0.5. Internal float / displacer type level switches shall
only be used if external type is not possible, like in viscous services and in
underground tanks / vessels.
4.8 For all type of level switches, the micro-switches shall be hermetically sealed,
snap acting, with 230 V AC/5 Amps contact ratings.
4.9 For all type of Level switches, there shall be a DPDT with 2 NO/NC contacts
with adjustable differential.
4.10 For all type of level switches as specified above, the process connection shall
be flanged type and the flange size shall be 1”and irrespective of design
pressure, the minimum pressure rating for flange shall be 300#.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 52 / 379
Revision : 2
RESID UPGRADING PROJECT
Irrespective of pressure rating, the minimum pressure rating for RADAR flange
shall be 300#.
RADAR type transmitter shall be standard SMART with HART protocol type
with Local LCD display.
Flange and wetted part for RADAR shall be min. SS316.
Irrespective of plants hazardous area classification, the RADAR type level
transmitters shall be intrinsically safe and weatherproof to IP67.
RADAR shall be with various software features like empty tank spectrum,
dynamic error corrections, false echo filtering, Programmable range from 0-
100%, throughout out the tank height, SPAN/ZERO elevation/suppression,
programmable blocking window distance, etc.
Trip level switches should be directly mounted on vessel/column and not with
the standpipes.
Connection of standpipe from the bottom of vessel must be avoided.
On horizontal vessels with boot, a separate standpipe shall be used for boot
interface level measurement in addition to standpipe used for horizontal vessel.
Level co-ordination sketches shall be produced showing all pertinent details
including nozzle locations, alarm levels, controlled level zones, shutdown level,
etc.
The type of tank gauging used shall be certified by local authority. Reference is
R2 made on to the API MPMS, Chapter 3.
Tank gauges for custody and transfer shall have an approval certificate from an
institute for weight and measures,
High level trip functions shall not be combined with tank gauge.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 53 / 379
Revision : 2
RESID UPGRADING PROJECT
5.1 All level instruments, switches and level gauges shall be submitted by
manufacturer to internal test procedure which vendor will indicate during the bid
phase.
5.2 All level instruments, switches and level gauges shall be checked concerning
dimensions, marking and nameplate according to the individual specification;
certified drawings and codes.
R2 Hardness test as per NACE MR 0103 shall be provided where required in
individual specification.
6.3 Manufacturer's name, model, serial number, operating range, set value (if
applicable) and materials of parts exposed to process fluids.
1.0 REFERENCES
2.0 THERMOWELLS
Temperature measuring devices which penetrate the wall of piping or vessels shall be
located in thermowells except for those used in skin point measurement.
R2 2.1 Thermowells (well and flanges) shall generally be of minimum AISI 316 material
unless otherwise required in project specification or special process conditions
require other special materials.
Test thermowells shall be provided with stainless steel plug and chain.
2.3 Minimum flanged rating specified for flanged thermowell shall be 300 lbs.
Minimum connection for all temperature measurements as 1 ½ “for rating up to
600#. For ratings 900#, 1500#, 2500# minimum connection size shall be 2”.
Irrespective of design pressure, the minimum pressure rating for this thermowell
flange shall be ANSI 300#. Thermowells shall be installed with proper “Long
R2 Welding Neck Nozzle.
2.4 Flange material shall be of the same material as the well. Thermowell material
shall be clearly stamped on the flange or on the body. When NACE is specified
R2 process wetted parts shall be in accordance with NACE MR0103. Hardness
test and test certificates are required for NACE Thermowells
2.5 In applications where fluid velocity, pressure and temperature indicate the
necessity, velocity (Von Karman) and pressure rating calculations shall be
performed, to determine thermal well dimensions and installation configuration.
2.6 All temperature sensing devices except for those used in skin point
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 55 / 379
Revision : 2
RESID UPGRADING PROJECT
2.7.2 For lines smaller than 3" any elbow installation must be in vertical.
2.7.3 Lines 2" and smaller shall be increased to 3" at the bend or 6" in the
pipe section where the thermowell is installed. When installing reducers
in horizontal the eccentric type shall be used to avoid pockets.
2.8.1 For pipe lines the well shall be sized to reach the center line of the pipe
when the bore is 12" or less. On pipes larger than 12" the tip should
extend at least 6" into the pipe.
2.8.2 For column tray measurement the well tip shall extend approx. 3" into
the column.
2.8.3 For column bases and vessels the well shall project 12" into the vessel.
Care must be taken to ensure that there is no conflict with any internal
parts that may be installed.
2.8.4 For the tank a 12 to 18 inch extension into the tank is necessary to place
the thermowell tip into the well mixed portion of the tank.
R2 2.9 DELETED.
2.10 The inside diameter of the finished thermowell shall be concentric with all other
diameters with a tolerance of 0.2 mm.
2.11 In case the thermowell design fails vibration analysis, alternate design may be
used by the contractor. All such design along with calculations shall be
submitted for purchaser's review and approval.
3.0 THERMOCOUPLES
3.2 Thermocouple element shall be generally "E" type of the metallic sheated
mineral insulated style, ¼" diameter (chromel-costantan). For special uses and
high temperature measurement range "K" (Chromel-Alumel) element shall be
used. They shall be fabricated from # 14 AWG wire which is 1.63 mm in
diameter.
a. Easy removal,
b. Heat dissipation.
If such combination is not enough for adequate cooling, length of the pipe
nipple shall be arranged accordingly.
3.9 Minimum of 24 inch clearance shall be allowed beyond well for thermocouple
head, to permit removal of thermocouple.
3.10 A single well and thermocouple shall be used for each point on the control room
multipoint temperature indicator.
3.11 When digital distributed control system are used, multipoint temperature
indicator points shall be function of the distributed control system and
incorporated into the data acquisition facilities of the control system. Minimum
overall accuracy at reference conditions shall be ±1 percent of full scale and
minimum resolution shall be one degree.
3.12 Points on the panel multipoint temperature recorder shall be operated from
duplex type temperature elements, the second element being connected
directly to the multipoint indicator or its equivalent incorporated into DCS.
3.14 Thermocouple actuated instruments shall drive the output (or contact) to a safe
condition in the event of T/C failure (open circuit).
3.15 T/C's used as sensors for interlocks, important process alarms on solid state
annunciator and shutdown circuits shall be of duplex type and installed in wells
separate from control circuit T/C's.
thermocouples.)
3.17 Deleted.
3.19 Deleted.
3.20 Multipoint strip chart recorders, where used, shall be directly wired to the field
sensor and shall be digital data recorder type.
3.21 Deleted.
3.22 Hysteresis and dead band in temperature transmitters shall be less than 0.01%.
Input resolution for digital systems shall be at least 10,000 steps for the
temperature range specified.
R2 3.23.1 All temperature measurements shall be carried out with the help of
Thermocouple / RTD elements along with remote field mounted ,2
wire, 24 V DC, 4-20 ma, SMART, HART temperature transmitters.
No head mounted transmitters shall be used throughout the project
or any part thereof, including package unit instruments. Multiplexers
are not used and all temperature transmitters shall be connected to
systems.
R2
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 59 / 379
Revision : 2
RESID UPGRADING PROJECT
3.29 For Reformer / heater tube skin thermocouple, wherever applicable, assembly
shall meet the equipment design requirements and shall be provided with
expansion loops. The sheath material shall be selected based temperature and
sulphur shall be selected based on temperature and sulphur content.
3.30 Class 'A' / Class '1’ tolerance as per IEC 751 / 584-2 shall be specified for all
RTD and thermocouple sensors in complete temperature measurements for all
open/closed loops and interlocks.
3.31 Head mounted temperature transmitters are not allowed at any location,
through out the project or part thereof. Field mounted remote temperature
transmitters shall be used for all temperature transmitters.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 60 / 379
Revision : 2
RESID UPGRADING PROJECT
4.0 THERMORESISTANCES
4.2 Mineral oxide insulation shall be of pure (> 99.4%) compacted oxide with
resistivity 1012 ohm/cm at 538°C. The insulation resistance shall be >100 Mega
Ohm.
4.7 RTD shall be used for a temperature range of -200 to 650°C. Three-wire
system shall be the element.
4.8 RTD shall generally be selected for applications requiring low temp with
comparatively shorter temperature span requiring accuracies of better than
+/-0.25%.
4.10 The design of RTD assemblies shall be such that replacement of elements shall
be possible on-line. It shall be equipped with SS304 material Nipple-Union-
Nipple Joints. Assembly shall include nipple-union-nipple (1/2" NPT threaded)
to allow approximately 150 mm between top of well and bottom of head, when
made up.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 61 / 379
Revision : 2
RESID UPGRADING PROJECT
4.11 RTD bulb sheathing material shall be 316 stainless steel as a minimum and are
constructed from a seamless tube with a wall thickness of at least 1 mm. Bulb/
Sheath diameter shall be 8 mm and the overall diameter of the sheathed
element shall not deviate by more than 2%.
5.0 THERMOMETERS
5.1 Bi-metallic, stainless steel, dial 150 mm, "every-angle" type thermometer shall
generally be used unless otherwise required in individual specification for local
temperature indication.
5.3 Thermometer connection to the well shall be sliding ½" NPT ANSI B2.1
5.5 Range shall be so selected that the normal operating temperature indication is
approximately midscale.
6.0 OTHERS
6.1 Local temperature switches utilizing filled bulb or bimetallic sensing elements
may be used where appropriate. DPDT switch contacts shall be provided.
6.2 Filled system type instruments may be used for local control, within the
manufacturer's recommended temperature limits, provided that failure of the
capillary system does not result in a hazardous control situation.
7.3 For special use thermocouples the Vendor shall carry out all inspection and
testing, and shall provide all the certifications indicated below.
1.0 REFERENCES
2.1.3 Transmitters power supply shall be 24V DC. The maximum allowable
loop resistance and minimum required supply voltage at 20 mA and
max. load value of the output module/card of the control system shall
be advised by Vendor. 4 - 20 mA - 24 V DC output will be used for
tranmission unless the world ındustry digital field to board
communıcation standards have been finalized.
2.1.8 All transmitters shall be equipped with easily accessible external zero
and span adjustments. Transmitters shall have integral vent/drain.
2.1.11 All transmitters for level measurement shall have suppressed and
elevated-zero features.
2.1.12 All transmitters for flow measurement shall have square rooting feature
of 4-20 mA DC signal.
2.1.13 For all transmitters minimum span rangebility (turn-down ratio) shall be
200:1. Total response time (Td+Tc) shall be or less than 100 msec
(dynamic performance). Stability of the electronic transmitters shall be
or better than +/- 0.2 % of URL for 10 years. Minimum 12 year
warranty. The pressure (p, dp, absolute) transmitters in the emergency
shut down system shall be SIL2 compliant.
2.1.14 Operating temperature upper limit for the transmitters measuring cell
(sensor) shall be or greater than 120°C .
2.1.19 Material of construction for wetted portion (body, capsule, oval flanges,
process connections, drain, vents flange adapters material etc.) of the
transmitters including sensing element shall be Hastelloy C-276 as a
minimum and shall be able to withstand over pressure of at least 1.5
times the maximum working pressure . Other special materials may be
used as required by process fluid conditions. Conforming to the
corrosion requirements of the application shall also be taken into
consideration during material selection.
2.1.20 All instruments shall be equipped with supporting materials suitable for
2" pipe support and mounting.The transmitters shall be supplied with
SS304 mounting brackets, hardware, nut/bolts, etc.
All transmitters are supplied with ATEX certificates and with double
certification EExd/EExi.
2.1.25 The min. loop load shall be 600 ohm for 4-20 ma output circuit of
transmitters. Transmitters shall be able to work between 12 to 35 V DC
with 600 ohm loop impedance.
2.1.28 All remote seal diaphragm type pressure/diff. pressure transmitters for
pressure, diff. pressure, and flow and level application shall have 2”
Flanged diaphragm as process connection. Irrespective of design
pressure, the minimum pressure rating for the flange shall be 300#.
2.1.31 Care shall be taken while selecting the transmitter models that there
shall be minimum type of diff. models of the same category of
transmitters to reduce spare/inventory.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 67 / 379
Revision : 2
RESID UPGRADING PROJECT
2.1.34 HART protocol of latest version shall be used and shall be suitable for
HART maintenance system with corner stone or AMS like software
with the following features as minimum:
2.1.36 The model selected shall be the latest from the vendors product range
and proven in the field for minimum of 1 year of operation.
2.1.37 For hydrogen gas service transmitters, Hastelloy wetted parts shall not
used to avoid damage due to hydrogen ion permeability. It shall be
R2 SS316L gold plated.
2.1.38 Diaphragm seal element with capillary shall be used for congealing,
corrosive and highly viscous services (higher than 200 cSt) at high
R2 operating temperatures. Filled fluid shall be capable of withstanding
the process temperature/pressure/fluid.Capillary shall be SS armoured
DELETED.
R2 2.1.43 All remote seal diaphragm type PT/DPT shall be supplied with min. 5
mtr. of capillary with SS armoured. DELETED.
2.1.47 All the Temperature transmitters shall be 24 V DC, 2 Wire, 4-20 m amp
dc output with SMART HART with HART protocol.
2.1.49 All temperature transmitters shall be equipped with local, LCD type
digital indication which shall be configurable in engineering unit.
2.1.53 All the transmitters shall be provided with min. two cable entries with
½” NPT(F) size. One entry shall be used for sensor cable input and
other shall be for 24 V DC/2 wire output cable.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 70 / 379
Revision : 2
RESID UPGRADING PROJECT
2.1.54 Deleted.
2.1.55 Each temperature transmitters shall be supplied with min. of two nos.
of double compression type, brass with nickel cadmium plated cable
gland. Cable glands shall be intrinsically safe to Eexia-IIC-T6 and
Weatherproof to IP65 as per IEC529.
2.1.56 Differential pressure transmitter shall be fitted with 5 valve manifolds,
R2
consisting of two for isolation valves an one for bypass valves and two
for drain valves for flow applications.
Pressure transmitter shall be fitted with two valve manifolds one for
isolation and one for drain
For the pressure ranting of class 900 and above, manifolds and tubing
shall not be used; pipe and valves shall be installed.
Transmitters tag details shall be clearly stamped on the external part of the housing by
means of stainless steel label and shall have minimum the following identifying
information.
1.0 REFERENCES
1.4 ANSI/FCI 70−2 and IEC 60534-4 Control Valve Seat Leakage Classifications
1.5 ASTM A 193 Alloy steel bolting for high temperature service.
1.6 ASTM A 194 Carbon and alloy steel nuts for bolts for high
pressure and high temperature service.
1.7 ANSI B 16.5 Steel pipe flanges, flanged valves and fittings.
1.8 ASTM A 320 Alloy steel bolting materials for low temperature
service.
1.16 ASME B16.42 Ductile Iron Pipe Flanges and Flanged Fittings,
Classes 150 and 300
1.17 ASME B16.47 Large Diameter Steel Flanges NPS 26 through NPS
60
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 72 / 379
Revision : 2
RESID UPGRADING PROJECT
1.24 MSS SP-55 Quality Standard for Steel Castings for Valves,
Flanges, and fittings and Other Piping’s Components -
Visual Method
2.1 GENERAL:
Smart control valves shall be used. Smart control valves shall have a
microprocessor based (controlled), HART digital positioner accepting
2 wire, 4-20 m amp input signals from central DCS system and are
capable of bidirectional communication with external electronic
devices, such as computers or operator’s console within the control
room and hand held terminals. The microprocessor is capable of
receiving signals and implementing changes in both settings and
diagnostic test instructions, and transmitting test outputs and
diagnostic trends collected automatically by the microprocessor.
Microprocessor technology shall be used to improve valve response
time and positioning accuracy in order to reduce process variability.
2.1.2 Block valves, bleeders and by-pass valves are required for all control
valves unless otherwise specified except that a bypass valve shall not
be provided in safety shutoff or depressurizing service or in applications
where solids suspended in the stream may collect and block the bypass
valve. Control valve piping assemblies shall be designed accordingly.
Block valves, bleeders and by-pass valves shall be provided where are
R2
shown on P&ID’s.
Outside these limits control valves with handoperator may be used,
except that in cases where removal for maintenance will cause
extensive plant shut-down, e.g. in integrated refineries. Hand operations
shall be side mounted type capable of full valve operation regardless of
spring or diaphragm failure.
2.1.3 Valve action shall be specified to minimize upsets and hazards upon
air or other motivation failure and shall be indicated on the Piping and
Instrument Diagram, i.e. FO (fail open) or FC (fail closed). Piston
operated valves shall have an air buffer storage cylinder to stroke them
to a safe position on air failure. Lock-up valves for maintaining last
valve position shall be used as necessary for equipment protection. A
separate air reservoir only to be used if the required action is
unobtainable by any other means.
2.1.4 For each valve the manufacturer, on the base of the data given in the
individual specification and the Cf of his standard valves shall
calculate the proper Cv and shall give in the bid the relevant noise
level, velocity, cavitation or flashing (if any) and percentage of opening
for the operating conditions. Calculations shall be made using a
computer program, and shall be made for each process case (normal,
max. and min. flow) and in accordance with IEC 60534-2-1 Preliminary
R2 Calculations shall be done in INTOOLS following ISA S 75.01
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 74 / 379
Revision : 2
RESID UPGRADING PROJECT
Satndard and after that, the final calculation shall be done by Vendor
with his software program.
2.1.5 Control valves shall be sized in accordance with ISA S 75.01 and
generally, valves shall be selected to have twice the Cv required for
the normal design flow at specified conditions. Butterfly valves shall be
sized for maximum flow at 60 degree opening; characterized vane
valves such us "fishtail disc" may be sized at 90 degree opening.
Three way valves shall be sized to pass max. flow at min. available
pressure drop through either part.
2.1.6 The manufacturer shall check and notify that the valve type and the
required materials are suitable to the operating conditions indicated in
the individual specification, with particular reference to the pressure,
temperature, flash, cavitation, possible suspended solids,
crystallization phenomena, speed, noise and type of fluid.
2.1.7 Fluids speed measured at the outlet flange of valves must be kept
within the manufacturer's safety limits, for the valve body material. If
the speed limits would not be respected a material proper to the body
shall be chosen or the valve diameter shall be increased using a
reduced passage.
2.1.8 Liquid volume flow rate at flowing temperature. Gas volume flow rate
base temperature is 0°C, and base pressure is 1.033 kg/cm² abs.
2.1.9 Block and by-pass valves shall be sized in accordance with piping
specification.
2.1.10 Where block and by-pass valves are required these will be indicated
on engineering flow sheet.
2.1.11 Regulators for flow, pressure and temperature with integral actuators
shall be used where loads remain reasonably constant and for
application where accuracy is less demanding.
2.1.15 The available instrumentation air pressure will be: min. 4 max.
7,5kg/cm².
2.1.16 All valves except self operated types, shall have position indicators.
Indicators shall also be provided on self operated wherever design
permits. Indicators shall be reversable where valve action can be
changed.
2.1.17 Valve shall be complete with set of packing lubrıcators charged with
correct lubricant and bearings correctly lubrıcated.
2.1.18 The manufacturer shall paint the valves as per painting specification
R2
TPS-N1 and shall supply all the accessories installed on the valve,
suitable for indicated climate conditions. DELETED
2.2 TYPES
2.2.2 Single seat globe valves shall be used in services requiring tight shut-
off and where effective control can be achieved using a standard size
actuator. Single seat globe valves shall be heavy duty top (stem, port
or post) guiding type. For special applications on high pressure drop
and flashing services with low pressure recovery , may offer his cage
design with appropriate guiding.
2.2.3 High lift top and bottom guided globe valve with removable seat rings
and interchangeable bolted bonnet and blind. Capable of action
reversal without extra parts.
2.2.4 Angle type valves shall be used where pressure drop exceeds 300 PSI
and in erosive and coking services and shall be of heavy duty full
venturi type angle, with full guiding and removable seat.
2.2.5 Butterfly valves shall be considered for large flows with low pressure
drops e.g. draw-off lines to side stream strippers and shall be sized for
R2
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 76 / 379
Revision : 2
RESID UPGRADING PROJECT
full flow at 60 degrees open. Butterfly valves shall be heavy duty wafer
type.
The wafer or lug type butterfly valves shall not be used in hydrocarbon
service however they should be used in systems which non-flammable
products unless specified by licensors.
2.2.6 Three way globe valves for combining or splitting services, with linear
plugs. Generally to requirements for globe valves.
2.2.7 1" valves with top guided reduced trim. Plugs for these valves shall be
of fluted design where the equivalent contour plug would be a needle
of diameter less than ¼ inch.
2.2.8 Self operated valves. Generally to requirements for globe valves. Self
operated valves with top or skirt guiding will be acceptable on low
pressure clean gas or air service only.
2.2.9 The Minimum control valve body size shall be 1" in general. Body size
shall be limited to 1", 1-1/2". 2", 3", 4", 6", 8'”, and 12”. Higher size may
be used if required. The flanged connection dimensions and pressure
temperature ratings shall be as per ANSI B16.5.
2.2.10 The accessories like Air Filter Regulator, Solenoid Valve, Limit
switches, Positioners, etc. shall be pre-tubed with actuator so that they
can be removed easily for maintenance purpose.
2.2.11 The max. allowable noise shall not exceed 85 dBA SPL ( Sound
Pressure Level). Control valves, exceeding this limit will be provided
with special precautions.TRM-TQ-INS-0099
2.2.13 For all interlock/shutdown valves, the minimum leakage class shall be
Class VI as per ANSI/FCI 70−2 and IEC 60534-4.
2.2.14 Control valve sizing shall be carried out as per ISA S75.01. The
selected CV shall permit up to 150% of normal flow or 110 % of
maximum flow, whichever is higher. In general, control valves shall be
sized so that the valve opening is as mentioned below.
- At Max. Flow :-80% Open
- At Normal Flow :-70% open
- At Min. Flow :-20% open
2.2.15 Equal% control valve shall be sized for 60% to 80% opening for normal
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 77 / 379
Revision : 2
RESID UPGRADING PROJECT
2.2.16 Flanged bolted type gland packing boxes shall be used, unless other
specified. Gland packing shall normally be self-lubricating type.
Packing shall be PTFE type up to 200”C. For temperature above 200 “
C, grafoil is to be used. Usage of asbestos is not allowed in any part.
2.2.17 Bellows seals shall be used for lethal services. Low emission packing (
TA-Luft or ISO 15848) shall be used for toxic / hazardous product. Low
R2 emission packing ( TA-Luft or ISO 15848) shall also apply for all
services except air, steam, water and Nitrogen
2.2.19 Where tight shutoff is required, fire safe type soft seat trims shall be
used, provided pressure/temperature of service permits the use of this.
For temperature above 300°C stellited facing shall be used for guide
and guide bushing shall always be harder by a minimum of 125 Brinnel
than that of the guide.
The below detailed philosophy for the stroking time of the shut-off
R2 valves shall be followed unless otherwise specified on the licensor
documents. Durign the fail position, the valve shall reach a fully closed
or fully open position within the time specified
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 78 / 379
Revision : 2
RESID UPGRADING PROJECT
Notes:
1. Stroking time of non-critical shut off valves for each valve shall
be checked/confirmed by CONTRACTOR Process Department
and specified on data sheets. These valves shall be noted as
non-critical valves on data sheets.
5. Stroking times of the heater valves (fuel gas, pilot gas, etc.) shall
be specified according to the requirements of heater vendor
and NFPA-85.
2.2.22 PCV shall be used only when load is constant and precise control is
not required.
2.2.23 All shutdown valves shall be floating ball design with full bore design,
unless otherwise specified.
2.2.25 Oxygen service valves shall be de-greased completely and certified for oxygen
R2
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 79 / 379
Revision : 2
RESID UPGRADING PROJECT
service use. Body shall be Monel and trim shall be Inconel 600 only.
2.2.26 DELETED
R2
2.2.27 For all shutdown valves when it is indicated in P&ID or in Process, air
volume tank shall be supplied for the storage of air volume for
minimum 3 stroke operation.
2.2.28 Each valve shall be provided with SS material tag plate indicating the
following details as a minimum:
- Instrument Tag Number
- Vendor's Name -Valve Model Number
- Order/Requisition Number
- Body & Trim Material
- Stem Packing
- Material Body Size and Rating -Design CV (For
- Trim Characteristic or Cam Code/type as necessary
- Air-Fail Action
- Hazardous Area Class
- Actuator size
- spring range -air supply pressure
2.3.1 Body
2.3.1.3
Unless otherwise indicated on the individual specifications,
valve body materials shall be choosen according to ANSI B
16-5 table 1, and shall meet the pressure temperature
ratings of table 2 to 8 of that standard. Vendor is free to
use higher grade materials than are strictly necessary to
meet pressure and temperature ratings, but materials must
be according to specifications listed in table 1 and agreed
with Owner. Body material shall conform to piping class requirements.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 80 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.1.4 Globe valve bonnet and blind shall be of the same material
as body and shall have retained gaskets suitable for
maximum pressure temperature and corrosion rating of the
body.
2.3.1.7 Valve body shall have direction of flow stamped or cast on.
Threeway valve shall have "COMMON" stamped on the
periphery of the flange of the combined stream connection.
2.3.1.8 Globe valves shall be of flanged bonnet and bottom (if any)
design with a confined gasket; gasket material shall be of
"non asbestos" type and be Vendor's standard, unless
otherwise specified.
2.3.1.9 The quality of and repair of body castings must follow the
requirements of the reference ASTM material specification.
Wall thickness shall meet or exceed min. of applicable
codes.
2.3.1.10 Valve body and pressure parts shall have pressure and
temperature rating equal to, or greater than flange rating.
2.3.1.12 The globe control valve bodies with top and bottom spindle
entries and butterfly valves shall have an easily reversable
action.
2.3.1.14 Body sizes 1¼, 2½, and 5 in. shall not be used.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 81 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.1.16 Castings can be replaced with forged pieces but not vice
versa without any previous Owner approval.
2.3.1.18 Tights shut off valves shall have seals as specified on the
data sheets. Where grease seals are specified, supply
grease fittings, gun and IO LBS of correct grade of grease.
2.3.2 Trim
2.3.2.3 Plugs with a low torque are required for butterfly valves.
For throttling service, butterfly valve travel shall be limited
to 60° providing positive stops or other devices to prevent
overtravel in either direction.
2.3.2.11 Except where tight shut off is required, butterfly valves shall
be swing through type, arranged for simple reversal of
action without extra parts. Discs may be plane, or
contoured to give enhanced operation characteristics. Tight
shut off valve shall have seals as specified in individual
specification.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 83 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.2.16 Valves with screwed seat rings shall not be used on steam
service.
2.3.3 Actuators
2.3.3.11 Actuator for three way valves shall be direct acting unless
otherwise indicated on the individual specifications.
2.3.4 Accessories
2.3.4.1 The manufacturer shall install and connect on the valves all
the accessories requested in the individual specification.
Unless otherwise specified the filters regulator and the
positioners, shall have ¼" NPT female couplings; the
pneumatic connection shall be carried out, 316 SS tubing
with 6 mm outside diameter and 1 mm wall thickness, with
R2 exception for the connection between the valve and
positioner which will be 12 mm and have a 1 mm wall
thickness. Where expressly required in the individual
specification, stainless steel AISI 304/316 tubing and
compression fittings in AISI 316 shall be used.
2.3.4.5 The connecting links between the positioner and the valve
stem outside the positioner case shall be in austenitic
stainless steel.
2.3.4.9 Where one controller output adjust more than one actuator
- except split range application- (e.g. louvers and
variablepitch fans) positioners, boosters or transducers
shall be installed at each actuator. Isolation valves shall
be provided for each actuator.
- PWB protection.
- Valve customization.
- Talk terminals.
- Local keypad/display.
- Predictive maintenance.
- Local security.
- Single/double acting.
- Direct/Reverse action
- IP 65 enclosure rating.
Firmware capable of :
3.1 The manufacturer shall carry out the guarantee on the requirements of Licensor
Control Valves STD SPC.
3.2 The manufacturer shall guarantee that the performance listed hereinunder must
come within the following limits.
3.2.2.1 Double seat (metal-metal seal): 0.5% of the rated design flow
rate.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 93 / 379
Revision : 2
RESID UPGRADING PROJECT
3.3 The manufacturer shall provide below inspecting, testing a and certificates for
each control valve.
4.0 NAMEPLATE
Each valve shall be fitted with a corrosion resisting nameplate including the following
information.
4.4 Valve body material nominal pipe size and body sıze
5.0 PACKING
5.1 Exposed machıned parts shall be coated with easily removable rust
preventative.
(X) ANALYSERS
1.0 REFERENCES
PARTICULATES
ISO 10155/1995 Stationary source emissions – Automated monitoring of
mass concentrations of particles – Performance characteristics, test
methods and specifications.
ISO 9096/2003 Stationary source emissions – Manual determination of
the mass concentration of particulate matter.
EN 13284-2/2004 Stationary source emissions – Determination of the
low range mass concentration of dust – Part 2: Automated measuring
systems.
EN 13284-1/2001 Stationary source emissions – Determination of low
range mass concentration of dust – Part 1: Manual gravimetric method.
GAS
ISO 10396/2007 Stationary source emissions – Sampling for the
automated determination of gas emission concentrations for
permanently – installed monitoring systems.
ISO 7935/1992 Stationary source emissions – Determination of the
mass concentration of sulfur dioxide – Performance characteristics of
automated measuring methods.
EN 14791/2005 Stationary source emissions – Determination of mass
concentration of sulphur dioxide – Reference method.
ISO 10849/1996 Stationary source emissions – Determination of the
mass concentration of nitrogen oxides – Performance characteristics of
automated measuring systems.
EN 14792/2005 Stationary source emissions – Determination of the
mass concentration of nitrogen oxides (NOx) – Reference method:
Chemiluminescence.
ISO 12039/2001 Stationary source emissions – Determination of the
mass concentration of carbon monoxide, carbon dioxide and oxygen –
Performance characteristics and calibration of automated measuring
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 98 / 379
Revision : 2
RESID UPGRADING PROJECT
systems.
EN 15058/2006 Stationary source emissions – Determination of the
mass concentration of carbon monoxide (CO) – Reference method:
Non-dispersive infrared spectrometry.
EN 14789/2005 Stationary source emissions – Determination of the
volume concentration of oxygen (O2) – Reference method –
Paramagnetism.
Environment Agency Technical Guidance, Note 13 Monitoring hydrogen
sulphide and total reduced sulphur in atmospheric releases and ambient
air.
2.0 GENERAL
2.1 Where possible "Insitu" analysers will be used to avoid the necessity for an
extractive sampling system.
2.2 Where extractive sampling systems and/or sample conditioning systems are
necessary, they shall be designed and provided by the manufacturer of the
analyser or analyser system. ASTM type sample probes shall be used where
samples must be taken from flowing lines.
2.3 Analysers shall also be protecteds with shelters meeting the recommendations
of the analyser manufacturer.
2.4.3 Walk-in type enclosures and rooms housing two or more analysers
located in ZONE 2 area, and enclosing two or more analysers located
in nonhazardous areas which enclose sample lines containing
flammable and toxic gases shall be provided with a continuous
explosivity and toxic gas detecting analyser which will provide visual
and audible alarm in case toxic and explosive gases exceed certain
level.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 99 / 379
Revision : 2
RESID UPGRADING PROJECT
2.4.4 The manufacturer shall design and furnish the analysers, sampling
systems, sample return pump (if required), etc., to provide a complete
operating system.
2.4.5 Redundant forced ventilation system with "clean" air intake, (physically
and chemically filtered to assure corrosive/acidic component free air)
shall be provided for shelters/houses to maintain 5 mm WC internal
R2
overpressure with at least 10 changes/hour of internal air changing
capacity. A "U" tube type pressure indicator shall be provided. An
audible and visual alarm shall be provided in case of internal pressure
drops down 2,5 mm WC, common gas detectors malfunction and when
standby fan automatically starts running. Each alarm shall be repeated
also in the main control room.
2.4.6 Gas cylinders for calibration or carrier gas shall be rigidly mounted
outside the walk-in enclosure. All regulators, gauges, cylinder gas
piping manifolds and driers (if required) shall be provided by the
manufacturer. All calibration gases shall be provided with contractor for
one year operation.
Approved analyzers and equipment which are required for hazardous areas
shall be labelled, listed or certified by an internationally recognized testing
organization such as ATEX, Underwriters Laboratory (U.S.A.), BASEEFA (U.K.)
OR P.T.B. (Germany). Where such equipment is not available, its design shall
conform to standards of a nationally recognized testing organization. Purging of
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 100 / 379
Revision : 2
RESID UPGRADING PROJECT
cabinets, analyzer systems etc shall be avoided as far as possible. Where there
is no other option but purging to meet area classification, purging shall be
carried out as per NFPA-496 " Purged Enclosures for Electrical equipment"
2.10 For analysers requiring cooling water, closed loop cooling water system with
pressure and flow measuring provisions shall be provided.
2.11 All components in contact with the sample shall be 316 stainless steel (as a
minimum.)
2.12 The sample conditioning system and the analysis section shall be located at
grade as close as possible to the sample tap.
2.13 Analyser enclosures shall be heated if the ambient temperature can drop below
50F.
R2 2.15 Other auxiliary equipment shall be located in the control house. (Recorders are
not used due to discontinued for analyzers).
2.15 Sample taps shall be made on the top of pipes. For pipe sizes up to and
including 20 inch, sample taps shall extend into the midpoint of the pipe with a
R2 45 degree beveled edge on the down stream side. In lines above 20 inch, the
immersion shall be 10 inch, minimum. (See API RP 555, Section A Part 4).
2.16 Sample taps shall be located at least 12 pipe diameters from the junction of two
streams, or at least 12 pipe diameters downstream of a pressure reducer,
where two phase can exist.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 101 / 379
Revision : 2
RESID UPGRADING PROJECT
2.18 All connected piping to the instrument and its sample conditioning system shall
be identified by permanently attached labels, marked with the same
designations as used on the drawings for the analyser.
2.19 A suitable system shall be provided to return the spent liquid sample to the
process line.
2.20 Self cleaning filters with 100 mesh stainless steel, filtering flow to the sample
conditioning system shall be provided.
2.21 Rotameters shall be armored type and shall be provided with block and by-pass
valves permitting rotameters to be removed for maintenance.
2.22 Where reverse flow is possible, a check valve in return line shall be provided.
2.23 To verify proper operation and calibration, provisions shall be made for
introducing a standard sample of known composition into the analyser.
Introduction of the sample shall be by manually operated valves at the analyser
location. It shall not be necessary to disconnect any tubing or piping to
accomplish this operation.
2.26 Multistream analysis using one analyser shall not be used unless approved by
the OWNER.
2.28 A calibration curve for each analyser shall be furnished by the manufacturer.
Demonstrated deviation from the calibration curve shall be maximum of 1% of
span.
2.29 The power for all devices associated with a given analyser system shall be
supplied from the same source and each system shall have a single disconnect
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 102 / 379
Revision : 2
RESID UPGRADING PROJECT
switch for the entire system. In addition, disconnect switches shall be installed
to permit isolation of each device in the analyser system.
Beyond this requirement OWNER shall have the right within the scope of
purchase order to call for inspection of each analyser once within the defect
liability period by Manufacturer service engineer. Site visits after the defect
liability period will be executed by Manufacturer service engineer on basis of
Owner request and at Owner charge. The number of visits shall be up to three
in five years.
2.31 Automatic periodic flushing facilities with cleaning agent shall be provided for
PH meters. Only in case of coating, slurry and highly polluting fluid applications
R2
like waste water shall be used.
2.32 Metallic type filter instead of ceramic for measuring probe of O2 analyser shall
be used.
2.33 Oxygen analyzer shall be provided below convection section, one for each flue
gas outlet from the convection section when convection section flue gas outlet
is more than one.
2.34 All parts exposed to the process shall be resistant to the specified process fluid.
All parts exposed to the atmosphere shall be resistant to the atmospherıc
conditions.
2.35 Where feasible, a local indicator showing measured value of sample shall be
provided for calibration purpose.
2.36 Vendor shall specify certified gases which are necessary for operation of
analyzers ( zero and span calibration gases, etc.)
system and sample line to the analyzer inside shelter will be used tubing
321/347 Stainless steel.
2.41 During transportatıon, threaded end connections shall be protecded with plastic
plugs or caps.
2.42 Where applicable, all the electrical connections on the analyzers shall be
provided by means of terminal block.
2.43 Required special devices for calibration and maintenance purposes shall be
provided.
2.46 As a rule, no single analyzer (detection system) shall be used for measurement
of more than one component except chromatographs which can be multi
stream multi component type based on requirement. Process Stream sampling
shall be continuous. As a minimum, all analyzers shall provide one isolated 4-
20ma signal along with 2 potential free contacts to the control system. In
addition to the above, Chromatographs and IR analyzers shall be provided with
2 wire RS485 serial link with MODBUS protocol for communication with central
DCS.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 104 / 379
Revision : 2
RESID UPGRADING PROJECT
2.47 In the case of Analyzer houses, the electrical power supply distribution shall be
as follows:
- 3 phase, 4 wire, 380 Volts, 50 Hz power supply from Emergency Panel will be
used to feed motors <150 kW, ventilation fans, HVAC compressor, pumps, etc.
R2 A distribution board shall be mounted outside the analyzer House.
- All 220 VAC power supply, except the Analyzers and Safeguarding Systems,
shall be derived from the 380 VAC 3 phase feed from Emergency Panel. 220
volt, 50 Hz power supply will be used to feed house single users and house
lighting. A distribution board shall be mounted inside the analyzer house.
- Analyzers and Safeguarding System shall be powered with 220 VAC from the
plant UPS.
2.48 Analyzer enclosures and accessories shall be suitable for the specified
electrical area classification. As a minimum, the electronic unit of all the
analyzers shall be to the following standards :
- Weather proof housing IP65 as per IEC-529 / IS-2147
- Flame proof housing Flameproof Ex (d) as per IEC-79 / IS-2148
(Flameproof equipment shall also be made weatherproof)
2.49 All interconnecting wiring shall be color coded / numbered and terminal blocks
clearly identified.
2.50 The design of analyzer system shall be in compliance with the electromagnetic
compatibility requirements as per IEC-801.
2.51.5 Sampling system design shall be such that the sample drawn for
analysis is truly representative of the process stream. Extra care shall
be exercised in the selection of the various components forming the
sampling system. Minimum material of construction for the sample
system components shall be SS 316.
2.51.6 Sampling system shall be designed to move the sample from the
process to the analyzer proper in the shortest possible time.
Transportation time for the sample from the process tapping point up to
the sampling system shall not exceed 30% of the cycle time specified
for the chromatograph. Sample tube material shall be selected based
on process fluid requirements and tube size shall be recommended by
vendor to suit process condition and avoid possible plugging. Any heat
tracing requirement of sample tubing such as condensible process
vapour shall be fulfilled using appropriate tracing with temperature
control. No sample shall be vented to atmosphere unless specifically
indicated otherwise. Sample disposal scheme shall be as per P&ID or
agreed upon before implementation.
2.51.8 Filters shall be always dual and it shall be possible to remove and
replace one of the filters without upsetting the operation of the
analyzer. Pressure reduction where required, shall be provided with a
safety valve downstream. Variable area flow meters shall be provided
for Fast Loops.
2.51.9 Process sample return point, if needed and utilities as required will be
made available near the analyzer at pressure and temperature
conditions specified in the data sheet for each analyzer as single point
supply and return. In general, all the offered items are to comply with
maximum pressure and temperature data specified. Multi-point
distribution of utilities and process sample as needed, is to be
arranged by CONTRACTOR following good engineering practices.
2.51.12 The sampling system shall contain at least one wire mesh strainer of
US standard sieve mesh size 100 or finer. Where purchaser's data
sheets indicate greater possibilities of plugging, vendor shall provide
more filters / separators as required. Where purchaser's data sheets
indicate possibilities of polymer formation of presence of excess
polymers, vendor shall offer suitable design features to minimize
plugging because of polymer residue.
2.51.6 Interconnecting wiring shall be color coded and numbered. All terminal
blocks shall be dearly identified, and all individual terminals shall be
clearly marked. Bigger size and fused type terminals with the same
specifications may be used based on the requirement. CONTRACTOR
shall take care for separation or shielding of power and signal lines, or
both.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 107 / 379
Revision : 2
RESID UPGRADING PROJECT
2.51.7 Sample probes shall be considered within 4” process line and bigger.
R2
2.51.8 Analyzer shelters and analyzer cabinets shall be built hot dipped
galvanized steel with the external walls in specific color code RAL
7035 and the internal shelters walls finished with white epoxy paint.
Shield Assembly:
Probe Assembly:
Control Unit:
2.53 CALIBRATION
Gas or liquid samples that deteriorate with time are not acceptable for field
calibration. Examples of samples having a composition that deteriorates with
time if stored in a cylinder include: hydrogen or gas mixtures, hydrogen
sulphide in gas mixtures, moisture in gas mixtures, and samples with
components present in amounts less than 20 ppm.
- For each gas Chromatograph, a dual cylinder carrier gas system shall be
dedicated one to each chromatograph providing automatic switchover to
standby cylinder when the first cylinder is exhausted. Number of cylinders
supplied by vendor shall be adequate for 2 years continuous operation. In
case of dual range of measurement, separate calibration standard for each
range shall be provided. Calibration standard supplied by vendor shall be
adequate to last six months. Also, Fuel gas cylinders for FID/FPD detector
for three months continuous operation. Each of the calibration gas and fuel
gas cylinders shall be provided with two stage pressure regulator. For carrier
gas manifolds, pressure regulator shall be provided on the manifold for each
cylinder.
- All analyzers shall be calibrated using a test sample showing 50% of scale
reading for the component of interest. Deviation of actual calibration from the
calibration curve supplied by vendor shall be within +/-1% of span.
- Programmer / Controller
- Gas Cylinders for calibration standards, carrier gas and fuel gas.
- Communication Interface
Pick detection mechanism shall be fully electronic and shall not use recorders.
It shall be available in front LCD display of analyzer in real time basis.
The carrier gas system shall be complete with the supply of carrier gas bottles
and instrumentation for flow control. The carrier gas system shall use minimum
of threaded connections and fittings. These shall not be lubricated. Whenever
hydrogen, gas is used as carrier gas, the associated fittings and enclosures
shall be made flameproof to IEC Zone 1 Group IIC requirements.
With each chromatograph, vendor shall provide a pressure switch to shut off power
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 114 / 379
Revision : 2
RESID UPGRADING PROJECT
supply to the detector during loss of carrier gas flow, so as to prevent any
damage to the detector.
Base line drift during one analysis cycle, without auto-zero, shall be less than
1% of auto-zero adjust span.
Column life shall be expected minimum of six months during normal operation.
One spare set of columns shall be provided with each chromatograph. For
calibration blends, stability will be 1 year from date of commissioning.
- Communicate the values for all measured process variables in the DCS in
a form (scaled variable or engineering units) consistent with the DCS data
highway. Each process variable will be designated by a unique point
identification or address. For multi stream analyzers, the same component
will have unique point identification or address for each stream.
- Communicate the sample point no./data being used currently to the DCS
for multi stream analyzers. This will facilitate multiplexing of various analog
inputs with a fixed set of analog input channels on DCS. Communicate
individual chromatograph diagnostic alarm to the DCS for display and use
in DCS control strategies. This alarm must include a maintenance
diagnostic i.e. technician working on a chromatograph. if not provided
separately.
The analyzer room shall be located as close to the analyzer sample points as
possible to reduce sample tubing lengths. Analyser room shall be provided with
a main door and an opposite door for emergency exit. Both doors shall be
openable outward with safety glass windows and automatic door closer.
Extension roof of @ 1000 mm shall be provided on both the doors.
Analyser rooms shall be able to house all the analyzers designated to that area,
including all sample conditioning accessories, etc. The calibration gas, carrier
gas and fuel gas cylinders shall be kept outside the analyzer room with a
structure provided at outside of the wall. Proper platforms shall be provided with
chain support to keep the cylinders with due care and safety.
Analyzer rooms shall be provided with air conditioners in such a way that the
inside temperature shall be 24’ C +/-1’C. The air conditioners shall provide once
– through A/C only and there shall be min. 10 nos. of single room volume
scavenges per hour. Air conditioners and all components shall be suitable to
plants hazardous area classifications and temperature class.
Analyser may be installed on self standing rack inside the room along with
sample handling system components, etc. There shall be flameproof power
supply junction box for powering up various analysers. Only 1 feeder to each
analyzer shall be fed from this junction box. Further distribution shall be done
by CONTRACTOR inside the analyzer cabinet/panels. There shall be analog
R2 and digital signal exchange junction box outside the analyzer room, preferably
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 117 / 379
Revision : 2
RESID UPGRADING PROJECT
mounted on the side walls, for various signal exchange between analysers and
central DCS. There shall be multi pair cable laid between central cabinet
room/DCS and individual analyzer room junction boxes.
Analyser room shall be provided with proper lighting supply and illuminations.
The analyzer house shall be provided with fluorescent lamps to provide an
R2 illumination of 500 lux inside the shelter and 400 lux outside the shelter at
working levels.
Fluorescent lamps shall also be provided outside of the analyzer room for
carrying out the repair / adjustments on the equipments mounted on outside of
the analyzer shelters e.g. sample conditioning systems etc.
It shall facilitate cable, sample tubing entry/exist through the various cutouts on
the side wall at a height inside the room. All the entries shall be sealed to
prevent the loss of air conditioners.
Analyser room shall be equipped with all safety measures like panic bar at the
doors. Emergency alarm push buttons, LEL gas (hydrocarbon) detectors, Fire
detection system, Fire extinguishers, wash basin etc.
All electrical equipments, fittings, fixtures shall be Flame proof suitable for
hazardous area classification.
All safety valve outlets from the analysers shall be terminated in a common
header of 2" NB schedule 808 SS 304 pipe and single outlet shall be provided
outside the shelter with one non-return valve and lock open type 2" ball
valve.Similarly all vents to atmosphere shall be terminated in a similar 2" NB
Sch 80 S SS 304 pipe and single outlet shall be provided with non-return valve
and Lock open type 2" ball valve.
All analyzer room shall also have utility tapings from main pipe headers form
the main plant with proper isolation valves outside the analyzer room. This shall
include instrument air, utility Nitrogen and service water as a minimum.
All type of cables /tubing entry in the analyzer rooms shall be through Multi
Cable Transit (MCT) blocks to ensure gas tightness of the analyzer rooms.
All tubing work shall be done by using ½” , ¼” or 1/8” OD, SS316, Swagelok,
R2 Parker or Hoke only, type of double compression fittings only.
All wiring / tubing and all other erection work shall be done in accordance to API
RP 552.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 118 / 379
Revision : 2
RESID UPGRADING PROJECT
All cable entries / outlets in the junction boxes / distribution boxes etc and to the
analyzer shall be provided with double compression type certified flame proof
SS cables glands.
For all the H2S/CO detectors, 2 No's of portable purge calibrators each
consisting of a volume bottle containing a known gas/air mixture, a
pressure regulator, a flexible hose and adaptor cap (to fit the sensing
head) shall be supplied to enable calibration of the sensors in the field
without dismantling them.
- Two Audible Alarm horns, one for Fire Alarm detection and one for
Gas detection.
- Three Beacon Lights, yellow for toxic gas detection, red for fire
detection and blue for flammable gas detection.
Apart from the Junction Boxes for analogue and digital signals to be
hardwired to DCS, in analyzer shelters shall be considered three
additional junction boxes for F&G signals, one for analogue outputs,
one for digital outputs and one for digital inputs
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 121 / 379
Revision : 2
RESID UPGRADING PROJECT
3.1 When the analyzer and associated sample conditioning equipment are
completely assembled, OWNER shall subject them to inspection a factory test .
For a factory test as follows:
The factory test shall be an operating test, and it is the manufacturer's
responsibility to provide all facilities required to demonstrate the analyser in
accordance with the individual specification and this standard. The Owner or his
representative shall witness and approve all factory tests and reserves the right
to approve the test procedure.
3.3 Calibration shall be demonstrated with a test sample giving approximately one
half scale reading for the component of interest. The concentration of the
component of interest in this test sample should be at least 25% of span
different from the concentration of the sample component in the standard
sample used for reproducibility test.
3.4 Accuracy and stability checks (Base line drift check on data sheet) shall be
performed.
3.5 Functional check comprising all the peripheral units such as printer, recorder,
etc. shall be performed.
3.6 Visual and dimensional check along with rated data check and marking check
shall be done.
3.7 A functional test using a radio set about 160 MHZ with a power of 5 WATT shall
be performed to check radio frequency immunity.
3.8 Ancillaries (i.e, sampling system and all other auxiliaries fit) shall be checked in
regard to for process fluid rating physical and chemical conditions with special
attention to seals (gaskets, O-rings etc.)
3.10 For all items above check certifications by the manufacturer shall be provided.
3.11 Prototype certification for mechanical protection (IP...) test (as per IEC 529
code), suitability to environmental test (according to MNF STD) and for safety
execution shall be provided.
3.13 Program print-out check and paragraph chart check shall be performed and
certified by manufacturer for chromatographies.
3.14 OWNER or OWNER representative (third party agency) shall have the right to
witness to all above mentioned checks and tests.
3.16 For infrared analyzers, the proportion of the components in the test sample
shall be varied to demonstrate freedom of interference from components other
than those of interest.
3.17 A leakage test shall be conducted on the entire system. Maximum permissible
leakage rates are as follows:
- Gas systems, 5% change per hour of the specified design pressure
- Liquid systems, no visible leakage.
5.0 DOCUMENTATION
Copies of all instruction manuals and drawings shall be supplied for all the analyzers.
These shall cover the following as a minimum:
(XI) ACCESSIBILITY
1.0 REFERENCES
2.0 GENERAL
Instrument installations shall be designed for safe and convenient access for the
purpose of operation, maintenance of seals, calibration, other routine maintenance, as
well as for ease of construction and instrument protection. Primary sketches and hook-
up drawings of ınstrument installations shall be prepared in accordance with their
accessibility.
3.0 General criteria for accessibility for instrument installations are as follows:
3.3 Control valves shall be located with sufficient clearance above the diaphragm to
allow for diaphragm case plug and stem removal (min. 300 mm between the top
of the diaphragm and the underside of the nearest obstruction above it). Valve
manufacturer's drawings are to be consulted to insure sufficient clearance and
sufficient access to valve positioners and handwheel operators.
3.5 Gauge glass and level instruments shall be located adjacent to each other and
the gauge glass shall be readable from any valve which controls the level in the
vessel.
3.7 All flow transmitters shall be accessible from platforms or grade unless
specifically approved by OWNER. The closed coupled arrangement is preferred
and impulse lines can be detoured at minor cost to gain accessibility to
transmitters from permanent platforms or grade. It is not intended to build
platforms solely for access to transmitters and where access from existing
platforms can not be easily obtained, transmitters shall be grade mounted
remote from orifice.
3.9 The location for the meter runh and meter installation shall be selected to
provide accessibility from platform or grade. ( Up to certain meters mobile
platform could be used unless specifially approved by owner.
3.10 Primary sketches and hook - up’ s will be prepared in accordance with
accesibility
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 126 / 379
Revision : 2
RESID UPGRADING PROJECT
TYPE OF ACCESS
Portable
Ladder or
Portable
Max. 7'-0" Above Platform Max
Grade or Permanent Permanent 22 Feet
Platform (Note 2) Ladder Above Grade
A. Instrument Process Connections
Instrument Tap on line or equip. X X X
Orifice flange X X X
1.0 REFERENCES
2.1 This specification gives directives for the design, selection criteria, methods,
instructions and examples of instrument design scope of work. This shall be
read in conjunction with the general specification specified and individual
instruments specifications given in other parts of this document.
Any conflict between the requirements of this specification and related codes,
standards, data sheets, drawings, requisition, etc., shall be referred to the
Tüpraş for clarification. The instrument design scope of work covered by this
specification shall be designed and constructed in accordance with the
requirements of this specification and the edition of the applicable National
and/or International Codes and Standards. In cases of conflict between
standards the most stringent requirements shall apply.( API : American
Petroleum Institute API 551 : Process Measurement Instrumentation etc. )
This instrument design specification provides the basis of design for instrument
drawings and documents, instrument subcontracts and instrument installation
material requisitions. Project requirements that differ from this specification will
be submitted as exceptions with requisitions and subcontracts.
The interface connection between piping and instruments is always after first
isolation valve provided by piping group. No instrument needle valves shall be
used as first isolation valve. The various piping / instrument connections details
are given in this document.
Instrument piping up to and including the first block valve and inline instrument
equipment shall conform to the line class or vessel rating concerned. The
specific requirements will be found in "Piping Specification". The first block
valves shall be minimum ¾" size (½" size at orifice flanges) and will be installed
as close as possible to the process tapping. Piping for instrument connections
to process shall meet the minimum requiredments of OWNER’ s piping
specifiications. ( TGPS - L )
2.2 Socket weld pipe, valves and fittings shall be used for dead ended instrument
installations, with pipe threads allowed at vent, drain, rod-out, and instrument
connections only.
2.3 Piping for level gauge glasses, float type level switches, and external displacer
type level instruments shall follow the applicable piping specification, threaded
connections in socket weld piping specifications allowed at vents, drains, and
instrument connections only.
2.4 All process connections of instruments (including pressure gauges) shall have
block and vent/drain valves located near instruments. Additional block valves
for remotely mounted instruments shall be installed near the instruments.
2.5 If vent/drain connection not available on displacer level transmitter, float type
level switches, flanged hold rings having vent/drain connections shall be used.
2.6 In case of use of 3" stand-pipe for multi connections of level instruments
separate vent and drain connections shall be provided for stand-pipe apart from
the level instruments.
2.7 All vent and drain connections shall be furnished with gate valves and threaded
end caps.
2.8 Materials of construction for piping, valve and fitting materials to be used for
instrument-process connection shall conform to the corrosion, temperature and
pressure requirements of the process systems to which they are connected.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 129 / 379
Revision : 2
RESID UPGRADING PROJECT
2.9 Screwed connections are used when piping specifications allow. Seal welding
shall be applied for all screw connections except end connections for
instrument, vent/drain, rod-out and manifold block (if any).
2.10 Generally breaking flanges shall be applied for instruments removal as close as
possible to instruments.
2.11 Drain piping to sewer for displacement/float type level instrument shall be
provided.
3.1 Instrument air piping material shall follow the piping specifications for main and
branch headers up to and including the block valve at the individual users.
Between the block valve and the instrument, 6mm and 12 mm ODx 1 mm
R2 thickness stainless steel tubing shall be used with stainless steel compression
type tube fittings. The same type tubing shall also used for instrument
pneumatic signal lines .Piping for instrument air shall meet the minimum
requirements of OWNER’ s piping specifications.
3.2 Air supplies to the block valves at individual air sets at local controllers, control
valves, etc.., shall be ½" galvanized carbon steel pipe. All air piping shall be
galvanized inside and outside.
3.3 Maximum number of air users for branch headers shall be as follow:
½ inch for 1 to 5 taps, ¾ inch for 6-10 taps, 1 inch for 11-15 taps, and 1½ inch
for 16 to 20 taps. Branch headers shall have shut-off valves at the main air
header.
3.4 All branch headers shall have minimum 1 valve spare of 1/2" size connected to
each branch header for future spare needs.
3.5 All main and branch headers shall have valves at the dead ends for blowdown.
For points related with instrument control philosophy and design of complete
R2 RUP Project refer to Technical Specification for Control Philosophy and
Instrumentation Design, Chapter 29000
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 130 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 REFERENCES
R2 2.1.1 Push button for trips will be hardwired from ESD matrix console to
remote ESD in CCB.
2.1.2 With an IBM compatible PC, printer and user interface software, which
are all in the scope of supply, it shall be possible to configure and
calibrate system even during operation. The software shall operate in a
MS - WINDOWS environmental making use of DDE capabilities, thus
allowing other windows application would make use of data for
additional processing and / or analysis. Events and alarms shall be
saved to a text file as well as immediate printing feature.
2.1.3 It shall be able to drive annunciator lamps, push - button inputs and
horns. It shall be possible to select any sequences and first - out
grouping shall be possible through program.
2.2 Alarm switches (trip-amp units) shall be dedicated hardware, operating directly
from remote ESD in CCB. When digital control systems are used, these alarms
R2 shall be repeated into the operator station alarm display and logging facilities in
DCS console graphics
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 131 / 379
Revision : 2
RESID UPGRADING PROJECT
2.4 The operating sequence for normal process alarm shall be as per below item
2.6.
2.5 The operating sequence for alarm annunciators which monitor shutdown of
process equipment such as fired heaters, compressors, incinerators, etc. , shall
include "first failure" facilities. This system will be of the triple flash type and will
have the following operating sequence.
2.6 Alarm switches shall be of the normally energized closed contacts which shall
open for alarm (fail-safe). They shall be supplied with 24 d.c. from alarm
system.
2.8 Alarm switches shall have DPDT (double pole double throw) contacts having
appropriate contact rating for interfacing to alarm system.
2.9 Alarm systems for installation in hazardous area such as local compressor
panels, pump house panels etc. shall be self contained (e.g. GEC lite-alarm)
explosion proof assemblies.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 132 / 379
Revision : 2
RESID UPGRADING PROJECT
2.10 All major pieces of processing equipment requiring a local operating panel shall
have all alarm and shut-down annunciator points on the local panel duplicated
on the main panel. The local panel is to be considered unattended during
normal operations.
2.11 Adequate isolation facilities shall be provided on alarm and control systems to
enable maintenance to be carried out on individual units without affecting the
operation of the other units, and also without affecting the safety of personnel or
the plant.
2.12 Alarm system shall be sectioned such that each process unit or process section
(each DCS console if distributed control systems are used) shall have its own
complete individual annunciator system.
2.14 Input/logic cards in the alarm logic system shall be grouped such that no card
shall include alarm point(s) from different process units. Even in the same
process unit, each major process equipment (i.e. compressors, heaters,
pumphouses, etc..) alarm points shall be grouped on a separate card(s).
2.16 Single large window annunciators will be installed on the panel above each
individual process section to act as a group alarm. This window will flash every
time an alarm occurs on the individual process section and is designed to assist
the operators in quick location of alarm conditions in busy multi process section
control rooms.
2.17 When an alarm unit is connected to equipment having its own power supply the
connection shall be made via an interposing relay to ensure complete
segregation. The interposing relay shall be certified barrier relay.
2.18 Alarm/annunciator systems (local and control room) shall be powered by the
control room UPS.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 133 / 379
Revision : 2
RESID UPGRADING PROJECT
2.19 The logic cabinet shall be so sized to ensure sufficient space to allow minimum
20% for future installation.
3.1 The shutdown system-SIS shall be functionally independent from all other
control systems such as DCS (monitoring and controlling system). All
components shall be of the latest generation, reliable and in current production.
Shutdown system shall be based on use of fail safe -fully triplicated architecture
( TMR) or quadruple architecture QMR (redundant architecture) thoughout
(approved for Safety Class-6 (AK6) as per TUV and IEC 61508 SIL 3 certified),
from the input modules, through the main processors, to the output modules, in
order to maximize reliability and process availability with system diagnostic
capability. There shall be 3 logic solvers ( microprocessors) running in parallel.
The I/ O and the logic solvers shall be voted 2 out of 3 or 2 out of 4D, and the I/
O or a single logic solver can be replaced while the system is online shall check
continuously for faults in the system hardware. During each cycle a full memory
test should be carried out.
The logics will be shown in the NORMAL OPERATING CONDITIONS (i.e in
absence of trips). In this condition all flows, pressures, levels, temperatures and
electrical power are at the respective normal operating values.
3.1.1 Functionalities:
3.1.2 The SIS system will be based on a PLC, with a fault tolerant (TMR -
triple modular redundant), fail safe architecture.A TMR (or QMR
redundant) PLC system is intended to be an equipment that utilises 3
(2x2) processors with identical logic, and duplicated or triplicated
input/output circuits. Different solutions to meet the fault tolerant
requirement shall be proposed by the VENDOR for TÜPRAS review
and approval. The SIS system shall be TÜV certified, according to
DIN-19250 AK6 (IEC 61508 SIL 3, 2oo3 or 2oo4D).
3.1.5 RAM memories shall be with battery backup; the system shall be
suitable to maintain the memories for two years.
The battery charge state shall be continuously monitored.
A special alarm shall be generated when the required maintenance
times cannot be ensured.
All batteries shall be replaced with no interruption of the functionality
of the
associated memories.
The system must process the analog I/O and loops within the
maximum times specified below:
- analog inputs 20 msec.
- thermocouple inputs 1 sec.
- control loops 250 msec.
3.1.7.1 Cabinets
Both the system and the marshalling cabinets of SIS shall
be VENDOR’s own production, Rittal or equivalent, of the
same model and dimensions and subject to approval. The
IP rating for the cabinets in the equipment room shall be
IP43. The cabinets shall have the following specifications.
R2 - free standing, enclosed type;
- RAL 7035
- designed for bottom cable entry;
- vent louvres backed by wire fly screen (with ventilation
fans if heat dissipating devices are enclosed);
- lamp with door switch;
- doors equipped with lockable handles and concealed
hinges with pull pins for easy door removal;
- clamping rails shall be provided for incoming cables;
- safety ground bar;
- isolated instrument (reference) ground;
- temperature and fan status;
- name plate of appropriate dimensions (white engrave
on black background).
DELETED.
3.2 Shutdown initiating contacts shall generally be closed when process conditions
are normal and open when abnormal conditions arise, the circuits being
designed to fail safe.
3.7 Trip systems in general are to be manually reset. Where local operator attention
is required (as on some burner light-off systems). the reset function shall be
local.
3.8 Each shutdown initiator shall be alarmed of "first-out" type (refer to item 2) and
shall be repeated into the operator station alarm display and logging facilities.
3.10 Circuits performing logic functions shall be organized such that, at power supply
failure, at module extraction, at module insertion, and at wiring cut-off shall
ensure that system will never generate active commands on the plants
(actuators); will leave the actuator in the previous state.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 140 / 379
Revision : 2
RESID UPGRADING PROJECT
3.11 Shutdown system shall be provided with facilities for start-up, test, or
maintenance of the system so that the initiating devices and the logic circuit
itself can be tested during operation and start-up accomplished. By pass
switches shall be provided for all input signals related to ESD and outputs for
actuating device. Process override switches ( POS ) with key and status lamp
(lamp will be powered by ESD once the relevant by pass is activated.) shall be
provided, in order to exclude some shutdown couses during process start up.
These pos will be installed on the DCS operator console. Emergency push
buttons shall be provided for installation DCS operator console. These shall be
secured against accidental activation. Vendor shall provide a test lamps push
button, in order to check lamps integrity.Reset push buttons shall be provided
for installation on DCS console.
3.12 Deleted
3.13 Output signals driving (DELETED explosion proof solenoid valves) electrical
motors shall require interposing relays with DPDT contact of 220V AC 2,5 A
R2
rating minimum. ( When shutdown unit is connected to equipment having its
own power supply the connection shall be made via an interpasing relay to
ensure complete segregation. The interpasing relay shall be certified barrier
relay.)
3.15 The power supply system including trip-amplifiers cabinet (if separate) shall be
redundant (each module can supply the related subsystem) and independent
for each main subsystem. The system shall operate on UPS at 220 V 50 Hz.
3.16 Explosion proof solenoid valves shall be driven by 24V DC supplied from
redundant DC uninterruptable power system.
3.17 The system shall be provided with 20% of installed and 20% space spare
capacity as a minimum.
3.18 All electronic circuits of the shutdown system shall be provided adequate radio
frequency filtering. 5W radio transmitter set about 160 MHZ shall be keyed
within close proximity with the door are open and a test report certified by the
manufacturer and showing that keying action does not affect the accuracy of
the electronic instrumentation shall be supplied.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 141 / 379
Revision : 2
RESID UPGRADING PROJECT
3.19 Galvanic isolation between field and the logic system shall be provided. For
basis of channel to channel and channel to field isolation, refer to RUP project
R2 Technical Specification for Control Philosophy and Instrumentation Design,
Chapter 29000, point 5.3.24
The PLC I/O modules will supply power to all loop powered 4÷20 mA devices.
The input modules shall be also suitable to accept input from externally
powered (4-20 mA on 1-5V active) transmitters. The modules will be
equipped with an electronic device for the short-circuit protection. External
labels shall be used to identify the tag signals belonging to each I/O card. All
the Analog I/O shall be continuously tested to verify that they are within the
fixed ranges and alarm signals are produced in case of malfunction (open loop
detection).
3.20 All the START output commands going to ELECTRICAL SUBSTATION shall be
performed with normally de-energized relays and output contacts open.
3.21 Most important input signals shall be performed in two out of three configuration
(i.e. recycle gas compressors) to avoid that any single fault generates a
shutdown condition. Instead of creating three strings constituted by one of the
three initiators related to one shutdown cause; each three initiators for one
shutdown cause shall constitute a string, in order to avoid two different initiators
of the same string to cause a shut-down when would exist together.
3.22 For TMR systems every Input and Output modules shall contain the circuitry for
three independent legs reading the process data and passing that information
R2 to its respective main processor. For each type I/O module, the system shall
support an additional hot - spare module which takes control if a fault is
detected on the primary module during operation. Additional hot - spare
modules shall be installed adjacent to primary modules and shall be included in
the scope of supply.
%20 hot spare module for each type existing I/O cards shall be provided on
ESD for TMR systems
3.23.1 DDE server for allowing Windows DDE client applications like Excel to
exchange data.
3.24 Necessary programming systems together with its relevant workstation shall be
provided to allow off - line configuration, programming, documentation and
R2 testing capabilities. It shall run under Windows7, Windows NT or Windows 98
operating system. It shall permit the user to develop and emulate functions,
function blocks, custom libraries and for testing applications off line. IEC
Standard Library shall also be provided. The user shall be able to write and
download control programs, monitor system status, program execution and
perform maintenance operations.
3.25.1 General
The codes, standards and specifications listed below form an integral
part of this requisition. Each publication shall be the latest revision or
R2 addendum in effect on the date of issue of the purchase order, unless
noted otherwise. PCS VENDOR under the responsibility of
CONTRACTOR shall confirm that he will comply with all applicable
requirements.
SIS equipment shall also bear the CE mark meeting the EN standards
relevant to EMC interferences and immunity. PCS VENDOR under the
R2
responsibility of CONTRACTOR shall confirm this system immunity
together with the specification for the equipment limitations, e.g.:
maximum wattage, minimum distance, and frequency band. All
components of the system shall be suitable for the refinery
environment. Immunity to radio frequency and electromagnetic
interference, such as generated by hand held walkie-talkie of 5 watt set
about 450-470 MHZ (UHF), within near proximity of system
components (doors of cabinets open and within 300 mm distance)
shall be provided.
Shock of 15G, 10 millisecond duration shall not result in any damage
or malfunction. Steady state vibration of 2.5G, 5-500 Hz shall not
cause any damage or malfunction.
QUALITY CONTROL
In case the PLC VENDOR owns a Quality Assurance Manual
according to ISO 9001/2/3 standards or, anyhow, has a well
established Quality Assurance System, he shall submit to TÜPRAS the
review of his standard working procedure to obtain the relevant
approval.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 144 / 379
Revision : 2
RESID UPGRADING PROJECT
3.26.1 General
The following requirements will be guaranteed and applied to the SIS
system:
a. The protective system will be based on a fail safe type PLC (or
TMR) architecture, safety level meeting SIL3 (certified) with 2oo4D
(QMR) voting logic.
b. The system will have a degradable mode of operation. Failure of
one channel will result in a single fail-safe mode of operation: a
failure of a second channel will result in a trip (3-2-0 mode).
Diagnostic will indicate each failure level.
c. There will be no common mode or single failure point that could
affect two or more channels.
d. Input and output signals will be voted independently.
e. Output signals will generally open to trip.
f. It will be possible to replace an I/O processor or CPU module on
line without degrading the safety of the system. Repair will not
require disruption of the scanning process or "freezing" of output
states.
g. The program is required to be resident in a RAM memory with
battery back up; therefore, in case of a power failure the program
has to restart without any "load" operation after power restore.
h. The system will be immune to electromagnetic interference and
surge currents .The SIS system shall not be susceptible to any sort
of damages resulting from electrical transients on power or signal
wiring generated by switching large electrical loads, power line
faults, lightning strikes and lightning induced surges on power or
signal cables, or other electrical noise radiated or conducted.
i. The system (including all relays) will be TUV certified, according to
DIN-19250 AK6 (IEC 61508 SIL 3, 2oo3)
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 145 / 379
Revision : 2
RESID UPGRADING PROJECT
3.27.1 General
a. The SIS will be powered at 220 VAC from UPS. Two independent
redundant 220V AC feeders will be made available for SIS. For
each voltage level there shall be a redundant power supply system,
based on two DC supply units; each one shall be sized for the
125 % of the full load.
Failure of one power supply unit shall be alarmed. Each power
supply unit shall be removable for maintenance without disturbing
the system operation.
b. The supply shall include redundant power supply systems like 220
VAC/24 VDC or any other voltage level to power all the I/O modules
and other circuits. Such systems will have on-line replaceable parts
in case of failures and will have fault-alarm contacts available for
monitoring.
c. The power supply system of the whole SIS system will be
redundant.
d. The SIS system will have internal power supplies arranged for
maximizing reliability. Therefore, if one of the feeder fails the other
one shall have sufficient capacity to operate the whole system.
e. The main electrical protections will be arranged so that no single
fuse failure can affect the availability of the entire protective system.
f. Dimensioning, arrangement and fuses coordination (selectivity) is
R2 as well included in PCS VENDOR scope under the responsibility of
CONTRACTOR.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 146 / 379
Revision : 2
RESID UPGRADING PROJECT
g. The SIS system DC power supply shall be floating 24 VDC. The SIS
system shall be capable of providing means to detect ground fault in
individual input field circuit.
j. Power supply to not removable components shall be fused.
k. Each user shall be individually fused. Power supply distribution
structure shall be arranged so that no single fuse failure can affect
the availability of the entire protective system.
3.27.3. Earthing
SIS system safety ground shall be connected to grounding system with
min. 25 mm2 copper cable having green and yellow colored insulation.
3.28. All the spare channels of the I/O modules will be properly configured and
wired to dedicated terminal boards in the marshalling cabinet. The SIS cabinet
R2 shall have minimum 15% spare space.20% spare terminals(included in 20% of
wired spare) and 20% spare space on marshalling cabinets shall be provided.
3.30 No system device shall be loaded more than 50% of its maximum capacity
under any normal/abnormal case, this shall include, networks, gateways,
resident memory and disk media etc. The system design shall be such that
system availability shall be 99.9%.
3.31 The communication system will have enough capacity for the load envisaged
from the start, plus the load deriving from expansion of functions. Such capacity
will exist at every condition of the plant: at start-up, when running, during shut
down, etc.
3.32 There will not be a dedicated operator workstation for SIS system. The DCS
operator workstations shall be used for this purpose.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 147 / 379
Revision : 2
RESID UPGRADING PROJECT
R2 3.34 All the AI and AO (DELETED “cards” )shall support SMART HART protocol.
3.35 Each module of the system (eg. CPU, I/O modules) is interconnected by means
of a system bus/network to the other modules to exchange data. The network
interface modules and the system network shall be both redundant.
3.36 Interface
The interconnections between the SIS and the DCS will be through
redundant process control network. As a general principle, PCS
R2 VENDOR scope under the responsibility of CONTRACTOR will supply
all the components (e.g. cables, connectors, terminators) needed to
connect properly all the modules of the system to the network. This link
will be used for a bidirectional data transmission (i.e. monitoring /
reporting, data flow SIS DCS ,or MOS enabling, interlock consents,
data flow: DCS, SIS).
The POS (process override switch) shall be utilised to override the shut-down
input during well defined operation conditions. Operating by-passes will be
activated by means of key operated switches with relevant lamps installed on
the push button bay.
The MOS (maintanence override switch) are needed to exclude the effects that
could be caused during the necessary maintanence operations on the field
instruments connected to the SIS system.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 149 / 379
Revision : 2
RESID UPGRADING PROJECT
Maintenance bypasses are provided for all the digital and analogue inputs that
may cause the shut-down of critical equipment. For each process unit a key
selector switch shall be provided on the DCS pushbutton bay and hardwired to
SIS for MOS enabling.When MOS enable is activated a white lamp on the bay
will be activated and an alarm shall be sent to the DCS operator station by SIS
system.Insertion and removal of maintanence override will be managed by
DCS operators through dedicated DCS custom graphics. Only when the MOS
enable is activated one bypass at a time will be accepted by SIS system. When
SIS accepts a MOS a flashing orange lamp on the bay will be activated and an
alarm shall be sent to the DCS operator station indicating that one by-pass is
inserted for the corresponding unit.
Maintenance By-pass
Maintenance by-passes, where required, can be either a physical input to the
system (generated by a selector switch) or a software input generated by the
engineering workstation.
The hardware by-pass selectors switch shall be key operated and installed on
the push button bay on operator console. Software by-passes shall be
accessible only through keyword and shall be enable through cumulative
enable switches (one by process unit) hardwired to SIS.
The condition of "By-pass on" shall be alarmed at DCS (one common by pass
and alarm for three inputs in case of triplicate sensors).
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 150 / 379
Revision : 2
RESID UPGRADING PROJECT
Operating By-pass
- Operating by-passes shall be activated by means of key operated switches
installed at operator console.
- If allowed by the application, the use of automatic by-pass reset shall be
considered in order to automatically insert the initiator once the plant has
reached as condition where the by-pass is not needed anymore.
Again, the by-pass will be automatically reset if the plant is not started in a
reasonable time. In case automatic by-pass is provided, key-switches are no
longer required.
3.39 All the cabinets (system and marshalling) supplied by the CONTRACTOR will
have the same height and colour. It is mandatory to have all the cabinets of a
unit mounted together in the factory.The system cabinets and marshalling
cabinets shall be designed and manufactured according to the requirements
and specifications.
- The application software shall not utilise more than 50% of the available
system memory. The central processing unit shall, under normal working
conditions, be less than 50% loaded. This loading shall be demonstrated
during the factory acceptance test.
- Worst case conditions shall also be simulated to determine if degradation
of loading is within acceptable limits. These include multiple alarms,
automatic shut-downs, and so forth.
- The system shall allow application software to be developed and tested
off-line by means of a SIS engineering workstation.
- It shall be possible to download at least minor changes in software from the
engineering workstation to the SIS while it is on-line without disturbing plant
operation. Adequate testing procedures shall be available to verify the new
logic prior to activating it in the on line program.
The method of storing the application program in the protective system
shall ensure that the program is not lost in the event of a power supply
failure.
The software for the system configuration and by-pass management is included
in the supply. The software will be, as minimum, relevant to:
a. sensor input voting logic
b. input / output error checking (out of range input limits, health of output
devices, etc.)
c. SIS self diagnostics and alarming
d. continuous alarm & shutdown supervision
e. interlocks and activation of sequences
f. management of maintenance by-passes
g. SOE software
h. communication with DCS: (alarms, graphics, diagnostics, indication of
analog and digital variables, management of operating by passes; consider
that all input to SIS will be repeated to DCS)
i. Any software package (Advanced version of Hart Device Manager, Field
Device Manager, etc.) allowing user to provide a communication
environment, diagnostic and configure, tune or monitor all smart HART field
equipments located at the field shall be provided.
All this will be accomplished on the basis of the following documents prepared
by others:
a. I/O list with: point tag, engineering units, alarm limits, point description;
b. interlock logic diagrams of shutdown sequences and alarms (ISA
directions) and/or cause & effect tables.
The database configuration will include smart HART field devices’ configuration
as well as the hardwired and software linked signals. The assignment of a
signal to an I/O module (tag assignment) is included in PCS VENDOR scope of
R2 work under the responsibility of CONTRACTOR.
The software programming tool will be:
a. designed in order to allow modifications of the various shut-down logics
and will be protected from unauthorized changes
b. in accordance with IEC-61131 norm (Sequential Function Chart (SFC),
Function Block Diagram (FBD) or the Ladder Diagram(LD) programming
languages, or a combination of the three
c. self documented
The maintenance bypass functionality shall be as per TÜV guideline for
actuation from the DCS operator station or from the SIS workstation.
3.41 DOCUMENTATION
3.41.1. General
The documentation has to satisfy in quality and quantity. The whole of
the documentation is comprehensive of the following:
a. hardware documentation
b. software documentation
c. instruction manuals
d. certificates
- Feeding System
A drawing detailing the whole electrical network from the distribution
board up to the users (included those supplied by others, if integral
part of the system).
- Cable List
A detailed list of system cables included in the supply, with the
following information:
- cable item;
- cable type (identification code) and length;
- starting and terminal points.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 154 / 379
Revision : 2
RESID UPGRADING PROJECT
- Dimensional Drawings
Drawings of every SIS device included into the provision.
- Cabinet Layouts
One drawing for each cabinet shall show all the positions of the
devices into the panels (plan and front views).
- Ground System
Drawing showing how and where the system has to be connected to
the ground system. In particular, ground conductors sections and
connection points will be indicated.
- Database
A document produced on a magnetic/paper support, holding all the
information on system entities.
- Functional Specifications
On the base of description of software (for sequences), the
VENDOR shall issue a proposal for a solution. After Tüpraş
comments and approval, the VENDOR can start with the actual
development of software.
- Detailed Functional Specifications
It shall be issued by the VENDOR at the end of software
development and shall cover in details all the software activities
done to comply with Tüpraş requirements.The Detailed Functional
Specification shall be issued at least one month before the
beginning of the FAT and shall be approved by Tüpraş.
- Operator Manuals
R2 Scope of these manuals, written in English and Turkish languages,
is to give operators a guide to use of the System. The Operator
Manual must have a "Quick Reference" Section, suitable for a
prompt consultation.
- Control and Sequence Flow Chart
- Interlock Logic Diagrams
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 156 / 379
Revision : 2
RESID UPGRADING PROJECT
On the basis of this specification, CONTRACTOR will submit their own testing,
installation, commissioning and acceptance procedures for approval.
For hardware, the procedure will include: purpose of test, test definition of input,
procedure, results expected and acceptance criteria) For software it will
include: details of the method, list of tests, sequence of execution, results
expected and acceptance criteria.
3.44 Any shutdown reset push buttons shall however be mounted on the control
panel together with any required indicating light or annunciation.
3.45 The main objective of the SIS system is to protect personnel, environment and
the installation. The SIS system shall perform safe automatic shut-down of the
plant, equipment or machineries upon detection of a potentially dangerous
abnormal process condition.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 157 / 379
Revision : 2
RESID UPGRADING PROJECT
Below specified test and checks shall be performed as a minimum and all will be
certified by manufacturer. The owner reserves the right to witness each test and check
stated below and satisfy himself.
The system shall not be shipped before the tests mentioned in this document
and its attachments are successfully completed.
Tests will be organised in two phases: first, tests during manufacturing of the
system;
Second and the final factory acceptance test PCS VENDOR, under the
R2 responsibility of CONTRACTOR shall test and demonstrate the functional
integrity of the system hardware and Software with Tüpraş engineers. No
material or equipment shall be transported until all required tests are
successfully completed and certified. TÜPRAS reserves the right to be involved
and satisfy himself at each and every stage of inspection. TÜPRAS shall be
free to request any specific test on any equipment considered necessary for
him although not listed in this specification.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 158 / 379
Revision : 2
RESID UPGRADING PROJECT
Phase – 1
System Pre-test:
VENDOR shall check physically the workmanship including the system
hardware prior to powering up the system of the consoles, racks and all other
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 159 / 379
Revision : 2
RESID UPGRADING PROJECT
accessories.
These shall be inspected externally and internally.
VENDOR as a minimum shall check the functions of all the system hardware
and software including diagnostic software at sub-system level by simulating
the inputs.
Testing Record
The test log book with the following information shall be sent to the TÜPRAS for
approval before FAT Phase-2 starts:
- date/time;
- assembly designation/loop tag number;
- test input;
- test result and sign off with personnel name;
- action required (if deficiency is detected);
- action taken, date of completion and sign off;
- special test methods (including special equipment requirement, bypasses
used etc.).
Phase –2
This test shall systematically, fully and functionally test all the hardware and
software in the presence of TÜPRAS representatives. Its purpose is to prove
the correct operation and performance of both hardware and software.System
shall be shipped to site only after this testing and certified ready for shipment by
TÜPRAS.
For the most complex parts of the plant, PCS VENDOR under the responsibility
R2 of CONTRACTOR will prepare dedicated software routines to allow the
functional test of the application software. This will complement the normal
testing that will be done by use simulation panels of switches, potentiometers
and lamps wired to the system (ie. marshalling cabinets).
This test shall start after the approval of Phase-1 log books and test reports and
if all the involved contractual documentation is completed.
- flow charts;
- logic diagrams;
Prior the starting of the test activities the system shall be installed in an area of
adequate dimensions, connected and powered.
Functional Tests
Once the visual checking activities have been completed with satisfactory result
the functional tests shall start.
- Hardware Functional Tests
The software test shall be carried out on all the configured points.
Activities relevant the software test shall include but shall not limited to:
The test of DCS application software relevant to signal coming from the SIS
shall be carried out (e.g. custom displays).
The test shall be performed in accordance with an agreed test procedure and
shall be carried out in parallel with the SIS software test (parallel test is
mandatory as the DCS need to be physically connected to the SIS equipment
to demonstrate the full hardware and software functionality).
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 162 / 379
Revision : 2
RESID UPGRADING PROJECT
Testing Record
During testing of Phase II, each test carried out shall be recorded. Any
deficiency or problem shall be clearly brought out and shall be corrected. Any
change in the data or configuration etc. informed to the VENDOR shall be
recorded and carried out by the VENDOR.
After the field system installation and prior the starting of the commissioning
activities the system shall be tested. Test shall be repeated to demonstrate the
fullfunctionality after transportation and field installation, complete dynamic loop
check and alignment shall be performed, generating and verifying the signals
directly from field.
During the site acceptance test particular care shall be taken to check the
power supply system and the grounding network system and to verify the
system bus functionality in the final configuration and maximum extension
Before the system power up and prior the I/0 module field connections all the
field I/0 signals shall be checked for continuity and isolation, in addition it shall
be verified the presence of undesired electrical potential, due to wrong field
connection, that could damage the SIS input circuits.
5.1 Each cabinet shall carry a nameplate indicating its functional identification.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 163 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 REFERENCES
2.1 Pneumatic instruments shall have metal housing to protect them from
environmental and mechanical damage. They shall be of minimum IP 65 type as
per IEC 529.
2.2 Connections for air supply, pneumatic transmission and control signals shall be
threaded ¼" NPT. Connections for process measurement shall be threaded ½"
NPT.
3.0 MATERIAL
3.1 All parts exposed to the process fluid, such as diaphragms, burden tubes and
bellows shall be resistant to the corrosive properties of the specified fluid
providing hastelloy C 276 as a minimum. Carbon steel body shall be minimum
where not otherwise specified.
3.2 All moving parts, such as linkages, bellows, springs and coils of instruments
shall be stainless steel.
4.1 Pneumatic instruments shall have a standard 3-15 psig signal. Signal pressure
shall increase on increasing of process variable.
4.2 All pneumatic controllers shall be easily reversible and shall have manufacturer's
standard range of control function nearest to those defined in the individual
specification.
4.3 All automatic-manual air transfer switches shall be integrally mounted for local
pneumatic controllers.
4.4 Filter regulator assemblies shall be provided for all instruments requiring an air
supply and shall be designed for 50-100 psig inlet air pressure.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 164 / 379
Revision : 2
RESID UPGRADING PROJECT
4.7 Field mounted pneumatic controllers shall be of the force balance type, having
bypass relays. In addition, all field mounted controllers shall be supplied with
0-30 psig output and supply air gauges.
4.9 Force balance type transmitters shall have zero adjustment provision which does
not require removal of the instrument cover.
5.1 Instrument performance for all local pneumatic receivers, recorders, controllers
and transmitters shall meet or exceed the following requirements.
5.1.4 Proportional controller shall not change more than 0.25% of span as
the band is varied from minimum to maximum for a fixed process input.
6.1 All pneumatic instruments shall be checked concerning dimensions marking and
R2 nameplate according to the individual specifications, certified drawings and
codes. Hardness test as per NACE MR 0103 shall be provided where required in
individual specification. The following certificates shall be produced:
- Tag number
- Manufacturer's name, model and serial number
- Pressure rating
- Body and internal parts material
- Air supply
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 166 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 REFERENCES
1.4 NFPA 70
2.1 General
- In general, Instrument wiring between the field junction boxes and control
room shall be by means of multi-pair cables. In case of special
requirements for field mounted instrumentation, direct run (single) cables
shall be used. (e.g. frequency signals, governor signal, etc.)
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 167 / 379
Revision : 2
RESID UPGRADING PROJECT
Cable for single and main runs up to 24 pairs shall be stranded tinned
R2 copper wire with (Insulation materials) XLPE (cross-linked polyethylene)
insulated, colour coded pairs, twisted according to EN-50288-7. Pairs shall
be screened individually with one layer of aluminium-bonded polyester
tape, between two layer of polyester tape with a drain wire. The max. nos.
of strands shall be 7 only. In case of thermocouple cable the conductor will
be solid. -DELETED-. For overall screening one layer of aluminium bonded
polyester tape between two layers of polyester tape with a drain wire, an
armour consisting of one layer of galvanized steel wires between PE or
PVC inner and outer sheaths shall be provided. Multiple twisted pairs shall
be twisted at least 6 times per foot. Single runs shall also be armored and
screened.
2.1.2 The outer sheath of twin and multicore cables shall be colored light blue
for intrinsically safe signal cables. When intrinsically safe cables are
specified for thermocouple extension cables;
IEC-584-3 cable colour coding shall be followed for thermocouple
extension cables.
2.1.3 All multicore cables and terminals in junction boxes shall have a
minimum 15% spare pairs (4 spare pairs in multipair cables of 24 pairs)
at each multicore cables to be used for alarm, shutdown, signal and
temperature measurement. All spare pairs shall be connected to spare
terminals in the junction boxes and coiled in the control center with
sufficient length to reach the most distant termination point.
2.1.3 All cables for instrumentation shall be flame retardant according to IEC
60332 and shall conform to BS6346 ( PVC insulated) except for the
following applications:
R2 All cables connected to the SIS System , shall be fire resistant
according to IEC- 60331
If the cables are buried shall be flame retardant according to IEC- 60332
All cables shall also be hydrocarbon, water, oil and sunlight resistant,
gas and vapor tight according to IEC 60332.
2.1.7 The instrument cables shall be grouped according to the signal types.
The main groups are:
2.2.1 Cable for instrument power supplies external to the control house shall
be PVC insulated, 2,5 mm² (minimum) stranded tinned copper conductor
600/1000V grade, galvanized steel wires armored, PVC sheathed
overall. Power supplies cables included in Electrical Department Scope
R2 shall not be tinned copper.
2.2.2 Cables for instrument power supplies within the control house shall be
R2 PVC insulated 2,5 mm² (minimum) stranded tinned copper conductor,
600/1000V grade, PVC sheathed overall. Power supplies cables
included in Electrical Department Scope shall not be tinned copper.
2.2.4 DC power wiring shall be color coded as : positive red, negative black.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 169 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.2 Cross section of conductors for single pair shall be 1,5 mm² and for
multipair 0.75 mm² .
2.4.2 Minimum Cross section of conductors for singlepair and multipair shall
R2
be 1,5 mm² and for multipair 0,75 mm².
2.5.1 Single pair thermocouple extension cables shall be used for initial
installation and shall be manufactured as per item 2.1.
2.5.2 Multipair thermocouple extension cables shall only be used for providing
15% spare requirement from control room to junction boxes located in
the field. Multipair thermocouple extension cables shall be manufactured
according to item 2.1. Pair no. shall be 12.
2.5.3 Both single and multipair thermocouple extension cable conductor size
shall be 1,5 mm² .
2.5.6 The conductor size for thermoresistance cables shall be 2.5 mm².
2.6.1 Single and multiple cores (24 cores) cables shall be as per item 2.2.1.
R2
2.6.2 Conductors color shall be black and numbered.
2.6.3 Conductor size shall be 2,5 mm² for single and 1,5 mm² for multipair
cables.
3.0 WIRING
3.1 All multicore cables, between control room and field junction boxes shall run
under ground in cable trench. Single pair cables shall run in trays between
junction box and instruments. Separated tray/junction box system shall be used
for each of the following instrument wiring. As SWA ( steel wire armoured)
cables are used for any link between ınstrument/ thermo couples and junction
boxes and junction boxes and panel, no conduits are used.
R2 3.2 Extension cables and RTD cables may be run in the same tray but no other
wiring shall be included.
3.4.1 Signal wiring shall be adequately separated and installed with respect to
power wiring and electrical equipment to minimize electrical interference
by any of the following:
3.4.3 Tray to tray spacing in the above table indicates the minimum distance
in inches between the top of one tray and the bottom of the tray above
or between the sides of adjacent trays. This also applies to the distance
between trays and to power equipment of less than 100 KVA.
3.4.4 Tray to conduit spacing in the above table indicates the minimum
distance in inches between trays and conduits.
3.4.5 Conduit to conduit spacing in the above table indicates the minimum
distance in inches between the outside surfaces of steel conduit. This
also applies to the distance between conduits and power equipment of
less than 100 KVA.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 172 / 379
Revision : 2
RESID UPGRADING PROJECT
3.4.7 When instrument wiring and power wiring must cross either in trays or in
conduits, they shall cross at 90°C angles at maximum spacing. Where it
is not possible to maintain the spacing indicated in the above table, a
grounded steel barrier shall be placed between unlike wiring at the
crossover point.
4.1 Connections to instruments shall be provided with crimp type connection end.
No crimping shall be used on solid conductors.
4.2 All cables, their cores and terminals shall be identified as per drawing.
4.3 Screw clamp type terminals, snap fastened to a mounting channel shall be
used (Weidmüller SAK 2,5 or approved equal). They shall be non-hygroscopie
type.
4.4 Terminals shall be provided for each conductor and shield drain (where
R2 applicable). Typically analog signals require groupings of 3 terminals each,
digital signals require groupings of 3 terminals each.
4.5 Terminal blocks for thermocouple signals shall be constructed utilizing a metal
bar of the same material as the thermocouple extension wire.
4.6 All multicore cables (except initial T/C and RTD cables) will terminate in the field
at suitably positioned weatherproof (min. IP 65), suitable to hazardous area
classification, custom designed junction boxes.
4.7 RTD and T/C cables will terminate in the control house at receiving instruments.
4.8 Signal, alarm and shutdown multicore cables will terminate in the control house
at junction boxes, or suitably shielded terminal boards mounted on the panel
structure.
4.9 The cable tag as indicated in the cable list shall be used for cable identification.
Cable ends shall be provided with marker strips.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 173 / 379
Revision : 2
RESID UPGRADING PROJECT
4.10 Buried cables shall be provided with PE cable markers with stamped numbers
at each curve / branch and at 10 m intervals.
4.11 Wire ends shall be identified as per IEC 60391, with closed ring shaped coding.
Color of the ring coding shall be yellow with black lettering.
4.12 Cable glands shall suit the selected instrument cable and shall be suitable for
the area classification concerned, standard Ex-e di IIC/T6 and weatherproof to
R2
IP65 as a minimum with PVC hood. The thread of cable gland shall be NPT
Cable glands shall be brass with nickel (DELETED “cadmium”) plated.
5.1.2 The mounting length of junction boxes shall be 1500 mm from grade,
platform or floor to the centerline of the box.
5.1.3 Cables shall not enter junction boxes from the top. Entry at the bottom is
preferred; however side entry can be used if unavoidable. Cable glands
shall be closed and protected with a rubber gland shroud.
5.1.4 Each junction box shall be identified with a nameplate with 1" high
engraved letters. The nameplate shall be attached centrally by screws.
R2 5.1.6 DELETED.
5.1.7.1 All wiring shall be labeled at each end through the use of pre-
printed sleeve type wire markers and shall be oriented in such
a manner to be viewed without moving any wires. Non
corrosive punched metal tags or sleeve type weather proof
cabel labels can be used at field. Selection shall be approved
by Owner.
5.1.9 Separate junction boxes shall be provided for control and interlock
category of signals, which are destined for ESD or DCS marshalling
cabinets.
5.2 Routing
5.2.1 Separation of signal wiring from power wiring and electrical equipment
shall be according to item 3.4.
5.2.2 Instrument wiring shall not normally be routed through areas where
ambient temperatures exceed 80°C. Thermocouple extension wire is the
exception. The cable ladders/trays shall be routed away from hot
environments and places with potential fire risks, such as hydrocarbon
process pumps, burner fronts of furnaces and boilers, etc.
5.2.4 Where a strong magnetic field is known to exist such as electric motors,
RF equipment, arc or inductive welding equipment, etc., instrument
wiring shall be routed with respect to this field to minimize interference.
(routing is to be parallel to the magnetic flux lines).
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 176 / 379
Revision : 2
RESID UPGRADING PROJECT
5.2.5 Cable run shall enter control center underground in conduit. Sealing at
the point of entry shall be provided with a seal.
5.2.7 Main cable runs shall be routed away from fire hazardous area
especially considering critical instrumentation cables.
5.2.8 Covered cable tray system will be used between junction boxes and
instruments.
5.2.9 A fire within a process unit shall not disable critical circuits for other
process units not directly involved in the fire.
5.2.10 The cable ladders/trays shall be safely and easily accessible for
maintenance purposes.
5.2.11 The cable ladders/trays shall be located away from where they are
subject to mechanical damage, spilt liquids, escaping vapors and
corrosive gases. Where cable trays are liable to damage by traffic, they
shall be protected by freestanding and sturdy mechanical structures.
5.3 Conduit
5.3.2 Seal fittings shall be installed in all conduits between enclosures that are
required to be explosion-proof and enclosures or conduit systems that
are not; in all conduits leaving a Division 1 area; and in all conduits
running between Division 2 and non-classifiied (non-hazardous) areas.
Where seal fittings are required in instrument installation they shall be
installed so that the instrument can be removed for maintenance without
disturbing the conductors. An explosion-proof conduit union shall be
installed between the conduit seal fitting and the instrument.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 177 / 379
Revision : 2
RESID UPGRADING PROJECT
5.3.5 Horizontal runs of rigid metal conduit shall be properly fastened and
supported at intervals not exceeding the following.
5.3.7 Drain fittings shall be installed in the conduit near the instrument for
vertical conduit drops. The drain fitting shall be installed immediately
before the flexible conduit connectors.
5.3.8 Cable pulling lubricants shall be used when installing cables in conduit.
The type of lubricants shall be suitable for the cable insulation involved.
Pulling tensions applied to cables shall not exceed the cable
manufacturers limitations.
5.3.10 To prevent the introduction of foreign materials and the project threads
during construction, the open ends of conduit shall be capped with pipe
caps whereas openings in fittings, boxes and instruments are to be
plugged.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 178 / 379
Revision : 2
RESID UPGRADING PROJECT
5.3.12 Conduits run parallel to pipe or vessels shall be separated from the pipe
or vessels by a minimum of 300 mm.
Size Clearance
¾"- 2" pipe 100 mm
3" - 6" pipe 150 mm
8" and larger pipe and 200 mm
vessels
5.4.1 The raceways shall be supplied in sections of a length not less than 2
meters, and shall have the bottom perforated or slotted to allow for a
better ventilation of the cables laid on them.
5.4.2 Prefabricated raceways with the following nominal widths shall be used.
R2 All raceways shall be with covers of 1.5 mm min. thickness, and of
10 mm sidefin minimum.
5.4.4 Raceways, coupling joints, covers and any special elements to be used
shall be steel Fe 37A-hot dip galvanized.
5.4.6 Below table defines the crowding criteria for cables to be laid on
raceways. The number of cables, shown in the table, is calculated
considering the same arranged on one layer only.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 180 / 379
Revision : 2
RESID UPGRADING PROJECT
TABLE NO.1
5.5 Grounding
5.5.1 For all shielded instrument signals except thermocouple the drain wire of
shielded pairs and shielded cables shall be grounded at one point only.
The grounding shall normally take place in the control center unless the
control system vendor requires the ground to be elsewhere. In that case
the grounding shall be done at the field junction box.Special attention
shall be paid to the interconnection of cable screens, such that the
screening is earthed at the intended location only so that multiple
earthing does not occur. Generally all shields shall be earthed at
DCS/ESD marshalling panel side only. Vendor guidelines to be followed,
if applicable.
Care must be taken during the wiring installation to avoid unintentional
ground point by doing the following:
5.5.1.1 At the field instrument the pair shield and drain wire are to be
cut off even with the jacket and a length of tape or shrink
protector placed around the jacket and to protect the shield and
drain wire from possible ground contact.
5.5.1.2 At the field junction box, the multiconductor cable and pair
shields and the multiconductor drain wire are to be cut off even
with the jacket and taped or otherwise protected. The drain
wires from the pairs (individual and their corresponding
multiconductor pairs) are to be interconnected on designated
terminals. The drain wires are to be taped or sleeved from the
jacket end to the terminal to avoid possible ground contact.
5.5.1.3 At the control center the multiconductor cable shields and pair
shields are to be cut off even with the jacket and taped or
otherwise protected. The multiconductor cable drain wire and
pair drain wires are to be terminated at the designated
connections. The drain wires are to be taped or sleeved to
avoid contact with conductors or possible improper ground
contact.
5.5.2 For thermocouple signals, the signal shield shall be grounded near the
point of the circuit ground. For grounded junction thermocouples, the
signal shield ground shall be at the thermocouple head. For ungrounded
junction thermocouples, the signal shield ground shall be in the control
center. The overall multiconductor cable shield shall be grounded at the
control center for grounded and ungrounded junction thermocouples.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 182 / 379
Revision : 2
RESID UPGRADING PROJECT
5.5.3 The control panel earth, barrier earth and supply transformer earth must
be taken separately to the instrument system earth.
5.6.2 Wire and cable used in intrinsically safe installations is generally the
same as at other installations except that the individual conductor and
jacket color code is special, for intrinsically safe wiring.
Below stated check, tests and certificates shall be provided as a minimum and owner
shall reserve the right to witness for each one.
6.1 Conformity certificate for chemical analysis, tensile test of the thermoplastic
materials, tensile test of the conductors and armoring, galvanization test.
6.2 Check certified by the manufacturer for the calibration and gauging of
necessary instrumentation for the testing.
6.3 Check certified by the manufacturer for visual and dimensional control,
inductance-capacity measurement, test of traction thermoplastic material,
conductors and armoring tractions test, shock thermic test, cold bending test,
galvanization test, flame proof or flame retardant test.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 183 / 379
Revision : 2
RESID UPGRADING PROJECT
6.5 For all above test and checks related IEC/CEI standards shall be followed.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 184 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 REFERENCES
1.1 IEC
1.2 LİCENSOR CENTRE SPECIFICATIONS
2.1 Since microprocessor based DCS with LCDs shall be used, control panel needs
shall be kept to a minimum. Control panel ınstruments shall be grouped in a
logical pattern and arranged in a sequence related to the process flew spacing
of instruments shall be compact but shall not limit convenient access for
operations and maintenance, control room panel layout and design shall be
subject to OWNER’s approval control panel ınstruments shall be miniature case
type in a high density arrangement.Control panels will be provided with
adequate space for the installation of futures.Panel instruments ( controllers,
recorders, ındıcators, annunciator panels etc.) and back up ınstruments shall
be configurable, digitally processing equipment of latest design of
manufacturer. These configurator terminals must be supplied with these
equipment.
2.2 All the cabinets shall be of free standing, enclosed type and shall be designed
for bottom entry for cable connection.
2.3 Cabinet structure shall be sound and rigid which shall be classified according to
environmental condition and dust protected.
2.4 In order to effectively remove dissipated heat from the cabinets, vent louvers
backed by wire fly secreen shall be provided to cabinet doors. In case louvers
are insufficient, ventilation fans shall be provided.
2.5 Equipment within the cabinet, shall be laid out in an accessible and logically
segregated manner. Clamping rails shall be provided for incoming cables to
prevent excessive stress on the individual terminal.
2.6 All metal parts of the cabinet including doors shall be electrically continuous
and shall be provided with a common grounding lug.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 185 / 379
Revision : 2
RESID UPGRADING PROJECT
2.7 All interconnecting wiring and cables shall be provided and pre-wired by the
vendor. Cables shall be terminated in cable order.
2.7.1 Terminal blocks shall be of the clip-on disconnect type (Wield Müller,
KLIPPON or equal). Terminals shall be either tinned or silver plated and
terminal number shall be clearly identified.
2.7.2 PVC insulated stranded copper wires shall be used. Size of all internal
wiring shall be determined according to manufacturer standard ; power
supply wiring shall be 14 AWG minimum size.
2.7.3 When instruments are provided with screw type connecting terminals,
the wire ends shall be provided with crimped-on spade lugs (make: AMP
or equivalent)
2.7.4 Removable cover plates shall be provided over all terminals with
voltages above 50 Volts.
2.7.5 The spacing between terminal blocks for each type of signals shall be
provided.
2.7.6 All electrical instruments shall be mounted in such a way that positive
earthing is provided by metal to metal contact to cabinet.
2.7.7 Each wire shall have identifying markers, using sleeve or plastic ferrules
showing both the terminal number to which it is connected and the
number of terminal or instrument from which it is coming.
2.7.8 Each terminal shall have plastic marker showing sequential terminal no.
2.7.10 Minimum separation between power and signal wiring shall be at least
300 mm if they are running in parallel.
2.7.11 Within one multiconductor cable or cable duct only one type signal shall
be contained.
2.7.12 Wiring shall be routed in such a way that it will not interfere with
maintenance operation i.e. card removal, or insertion, etc.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 186 / 379
Revision : 2
RESID UPGRADING PROJECT
2.8 Each panel, cabinet and other equipment in control room shall be provided with
an earthing lug. All these lugs shall be properly secured to the AC mains
earthing bus.
2.8.1 All circuit grounds of electronic instruments, shields and drain wires of
signal cables shall be connected to instrument ground bus which is
electrically isolated from the AC mains earthing bus.
2.8.2 In any case, if the Vendor's equipment requires dedicated grounds the
proposal shall include sufficient information to determine how these
grounds are to be arranged.
2.9 All interconnecting cables into the cabinets will be supplied by Vendor.
2.10 The electric wiring shall be subdivided into the following categories.
feeding 220V 50 Hz
feeding 24V DC
4÷20 mA signals
other DC circuits
T/C, RTD, mV signals
2.11 All electrical wires shall be housed in plastic raceways of suitable dimensions
(max. crowding 60%). Sufficient raceways shall be provided to group together
the electric wires according to their voltage level and function as per above item
2.10. Terminal strips for wires shall be suitable for conductor sizes up to 2.5
sqmm.
2.12 Doors shall be equipped with handles with lock and concealed hinges with pull
pins for easy door removal.
2.13 All instruments on the "control board" shall be identified by black nameplates
having white engraving giving tag number and services.
2.14 Fuses, where used, will be of the easy replaceable type, having a neon failure
indication light.
2.15 All equipment on the control board, panel and cabinets shall be identified with
appropriate tags.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 187 / 379
Revision : 2
RESID UPGRADING PROJECT
2.16 Boards and panels shall be supplied already assembled, in sections, together
with all the necessary materials for final installation on site (nuts, bolts, etc.)
2.18 A 220V, 50 Hz electric power from reliable source (control center UPS) is
available to feed each section of control board.
Power supply shall be made available at one point. Further power distribution
network shall be designed such that a single power fault or overload in any
branch system shall not cause a trip of the entire system. Each branch shall be
provided with a separate switch and miniature thermal/magnetic switches (no
fuse) system. Cut-out selectivity shall be guaranteed by the supplier.
2.19 All the cables connected to panels shall be identified with a suitable cable
markers or tags.
2.20 Supply voltage to cabinets, panels and board shall be 220V, 50Hz. For all other
voltages needed to operate instruments, components or modules, etc., 2
separate (1 is redundant) power supply for each voltage level one being
capable of supplying rated power to the cabinet, shall be utilized in parallel
sharing load in normal operation but if one fails the other takes the fully load
automatically. Means of monitoring power supplies status shall be provided on
DCS. Two separate AC input shall be provided for redundant P.S. systems.
3.1 "Control Board" will include enough sections to include of multipoint recorders,
vibration and displacement measuring devices for pumps and compressors,
analysers control devices and power supply units. The control board will be
installed in control room to permit direct accessibility and operability to the
instruments.
3.2 Instruments will be mounted in front of panels; two rear access doors for each
section shall be provided.
3.3 Signals and power supply wiring from terminals of each instrument to the
terminal strip, which shall be located in the lower part of the rear of each
section, shall be provided according to the control board connection and power
distribution diagrams.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 188 / 379
Revision : 2
RESID UPGRADING PROJECT
3.4 A board clock, to be supplied by panel vendor, shall be digital type with 50 mm
minimum nominal height filamentary 7 segment display. It shall have crystal
controlled time base, shall display hours, minutes and seconds, and shall be
resettable and adjustable from front of panel.
3.6 All electronic instrumentation mounted on the control board shall be provided
with adequate radio frequency filtering to about 160 MHZ. 5W radio transmitter
of close proximity while the doors of the board are open a test report certified by
the manufacturer and showing that keying action doesn't affect the accuracies
of electronic instrumentation shall be supplied.
3.7 Control board shall be supplied with internal lighting and forced ventilation
system.
3.8 Due to very high sulphur and other corrosive vapours content in refinery
atraosphere all relay, switch, push button, etc. Contacts and all connectors in
the control room shall be gold plated except the ones hermatıcally sealed.
4.1 Below identified checks and tests shall be provided and a certification for each
one shall be supplied by manufacturer. Owner or his representative shall have
the right to witness of all the checks and test to be executed.
4.1.5 Check if protection covers are fitted to high voltage parts (>50 V)
4.1.15 Check separation of wirings (AC power, T/C, 4-20 mA, etc...)
4.1.20 Check RF immunity test with 5W radio when doors are open.
4.1.21 Check if all loose items are marked to enable easy assembly on site
without possibility for mistakes.
For points related with instrument control philosophy and design of complete RUP
R2 Project refer to Technical Specification for Control Philosophy and Instrumentation
Design, Chapter 29000.
1.0 REFERENCES
2.0 GENERAL
Lev. 2 Level 2 : this level regards the System equipment having the function of HMI.
Level 2 is the control and supervisory level of the Plant.
Lev. 3 Level 3 : this is the level dedicated to Advanced Control and Plant Optimisation
MPC : Multivariable Predictive Controller
MR : Material Requisition
MTTF : Mean Time to Failure
MTTR : Mean time to Repair
P&ID : Piping and Instrumentation Diagram
PID : Proportional, Integral, Derivative Controller
RISC : Reduced Instruction Set Controller
SIS : Safety Instrumented System
SOE : Sequence of Events
TCP/IP : Transmission Control Protocol / Internet Protocol
2.1.1 DCS shall be a digital process control and data acquisition system of
the latest field proven technology that includes a comprehensive set of
algorithms and auxiliaries and provides full control and monitoring
capabilities. It shall be a flexible system that can be tailored to a wide
range of process requirements at the loop or unit level. The system
shall allow dependable and effective process control and shall permit
control and data acquisition functions to be distributed to remote plant
location.
2.1.3 The control modules and operator stations are connected with a data
communications bus, based on open architecture.
2.1.5 The offered system shall have feature the latest technology (the latest
state of the art hardware and software platform and
hardware/software/firmware revisions of complete system will be latest
at the time of supply) available on the market at the time of bidding
and shall have a good record of competibility with the previous version
or systems offered by the Vendor.
In addition to these ,All the hardware and software of the DCS shall be
the most advanced model of DCS of vendor at the time of FAT.
Any deviation from the general terms and conditions attached herewith
and the technical specification shall be clearly indicated.
2.1.7 All plants shall be controlled by modern DCS .All the interlocks shall be
realized in a fail safe ESD (TMR/QMR).
2.1.10 All the system hardware of DCS shall be ISA G3 level corrosion
protection. All the hardware including control/communication
processors, networks, cables, all type of system cards, all type of I/O
cards shall be hot replaceable.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 193 / 379
Revision : 2
RESID UPGRADING PROJECT
2.1.11 The system shall be designed giving the most consideration to its
reliability, inparticular the selection of the electronic components and
the individual entities forming the system shall be particularly accurate,
considering a continuous operating time of 2 years.
2.1.12 The system shall be of modular construction and easily expandible; the
module typology shall take into consideration the need of
interchangeability and storage cost reduction.
System shall have both virtual and target testing & debugging tools to simulate
application.
The DCS shall be made of I/O modules for data acquisition and of processing
modules equipped with resident software to carry out control algorithms and
sequential control functions.Operator interface shall be implemented through
interactive workstations equipped with data display console, keyboard and
printer; plant will be controlled through graphic pages.Engineering workstations
for resident software configuration and management shall also be provided.The
DCS must have an "open" architecture, to interface with various electronic
devices and/or data communications standard networks.
2.3 Any part of the DCS system shall be capable of operation in the environment
conditions anywhere in between -10°C/+50°C for temperature and ±10% for
relative humidity deviation of environment design limits for the building in which
that part of the system operates.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 196 / 379
Revision : 2
RESID UPGRADING PROJECT
2.4 The system shall be able to operate and power the explosion proof field
instruments.
2.5 The DCS mentioned shall be suitable to operate with minicomputers and
computers on LAN, the data highway. They must be able to be interfaced to
LAN to operate with DCS for advanced control and optimization purposes.
Hardware and software requirements for APC shall not be provided. Hardware
and software requirements are for a microprocessor based digital data
acquisition and control system; Contractor shall design a whole system
according to his technology but within the limits of the characteristics of the
requirements of this section. In case of necessity of a minicomputer, Contractor
shall distinctly indicate it.
2.7 The operating center shall provide a common interface for all the following:
with all the capabilities of conventional control board with dedicated instruments
as a minimum.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 197 / 379
Revision : 2
RESID UPGRADING PROJECT
2.8 Operating system shall be Windows XP, Vista Professional (the latest version)
or Windows 7. This operating system shall be native (without modification) and
R2 single to guarantee fast response. Additional proprietary operating system is
not accepted. The operator station and the engineering work station of DCS
system shall have the capability to display simultaneously the DCS standard
graphic and application windows.
2.10 Operation status indication of all electric motors and turbine drivers shall be
included in DCS system. Color changing method shall be used for this purpose.
R2 2.11 DELETED.
2.12 Duplex type thermoelement will be used for temparature points to be connected
R2 one to DCS/ESD (by means of temeperature transmitter) and the other as
spare
2.13 For split range applications of two or more valves, dedicated controller output
range for each valve will be configured through the use of DCS software
techniques and then separate outputs will be assigned to each valve to be
operated in split range mode.
2.14 Each electrıcal/ steam drıven equipment will be indicated on DCS about their
R2 run/standby conditions. Speed from Governor for steam driven and auxılıary
contact of power supply contactor will be utılısed for this purpose.
2.16 DCS and all its auxiliary equipments shall be supplied as a turn key system.
2.17 Hardware and software composing the system shall be field proven and the
latest model withe respect to Bid submission date.
2.18 It is empnasized that this specification provides the minimum requirements and
does not relieve the vendor from his responsibilities concerning proper design,
reliability and safe operation of the supplied equipment.
2.19 Contractor shall include in the supply all what is required to deliver a fully
working system.
2.20 The offered system shall be composed by the most updated hardware and
software release (i.e last version of controllers and I/O cards, configuration
tools, communication bus, operator stations etc.) available at the time of factory
acceptence test start.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 198 / 379
Revision : 2
RESID UPGRADING PROJECT
2.21 Graphic pages showing a single line diagram of the electrical system shall be
carried out in DCS, for low voltage level, medium and high voltage levels shall
be shown in Electric Scada. These pages shall have facilities to indicate the
R2 position of incoming and bus-tie circuit breakers and low voltage switchgear
systems. DCS shall also indicate alarm and trip events of incoming and bus-tie
feeders, including transformer protections. The power requirment of unit both
medium and low voltage level shall be visible from DCS as kW and ampere.
2.22 Signals listed in the I/O list for each group in the plant shall be distributed
equally among all control modules assigned for each plant.
2.23 Process control of the units through DCS system shall be based on
uncompensated raw process data only. Flow control loops in DCS shall be
based on the measurement from the flow transmitter output in the field without
any compensation for temperature, pressure, molecular weight, specific gravity,
composition, and/or and other parameter that may influence the controller
output. Contractor, however, shall configure separate computation blocks,
graphic pages and/or other relevant means to report the compensated flows
based on the respective pressures and temperatures directly measured from
the field. Additionally, a separate laboratory data input page shall be prepared
on operator stations where the corresponding laboratory data such as specific
gravity, molecular weight etc. can be entered into DCS system to be used in
compensation calculation blocks. Compensation calculation blocks shall directly
receive the entered process data through the designated data entry page and
perform the compensation calculations on line.
2.24 Network load shall not exceed 50% and Vendor shall prove it during F.A.T. and
S.A.T. Total memory, memory backup time and detailed sizing shall be as per
CHAPTER 29.000. This load shall be calculated based on the following system
R2 usage.
- No alarm status
2.25 The idle time of processor and the status of each I/O card and controller shall
be displayed on a dedicated controller diagnostic panel, easily accessible to
operator on the operator station.
2.26 DCS to achieve safe and effective control system shall be of the latest proven
design, model, the most advanced DCS on the market of DCS vendor’s
2.29 All DCS equipment including operator station, printers, control modules and all
related nests for interfacing with field wiring shall be supplied with fans to
circulate sufficient amount of air to remove the heat dissipated by electronic
boards so that no excessive temperature rise occurs on any system
components. Also each piece of equipment and component in the system
(operator stations, printers, control modules, cabinets, etc.) shall be equipped
with proper filtration systems to eliminate the possibility of any dust
accumulation on electronic boards and in system components due to circulating
air through the system components. All pieces of equipment shall be assumed
that be kept in the controlled and safe environment in the control room.
2.31 Engineering work station and operator station shall be a high performance
commercially available PC work station capable of engineering and configuring
any DCS device linked on the network. BIOS customization for EWS is not
accepted. Stem shall support coexistence of 3rd party software such as virus
buster, PIMS, asset management or analyzing software to run on operator and
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 200 / 379
Revision : 2
RESID UPGRADING PROJECT
2.32 VENDOR under the responsibility of CONTRACTOR shall specify the proper
start up and shut down procedures for all DCS modules, operator stations,
R2 computers, operating systems and any other relevant system components. All
component of DCS can be stopped or powered off at any time, without affecting
the others.
2.33 All parts included in any section of the system shall be easily accessible for
maintenance. Any part, card, cable, piece of equipment installed in any section
of the system shall be accessible without having to dismantle or remove
another part, card or a piece of equipment.
R2
2.34 VENDOR under the responsibility of CONTRACTOR shall, during bidding
stage, specify clearly the air quality required in the control room where the parts
of the DCS system are located, modifications required in the control room to
meet the air quality to minimise the corrosion on the parts of the system taking
into account that the DCS system shall be operating in a refinery environment.
2.35 All the necessary engineering for configuration, software applications, graphics
and logging shall be performed by CONTRACTOR. However, CONTRACTOR
shall ask for approval of OWNER for all activities in each phase of DCS
engineering.
2.36 The vendor shall have noticable systems installed base in Turkey and had to
continuous activity industry for the 10 last years. The vendor shall have
engineering and maintenance capability in Turkey (provide reference list).
2.37 The proposed system shall feature windows XP, Vista or Windows 7 operating
system for the operator interface.
R2
Operating system shall be native (without modification) and single to guarantee
fast response. Additional proprietary operating system on operator interface is
not accepted
2.38 The proposed system shall feature OPC server to enable exchange of data with
R2 computers, connected to ethernet. If required, Exaopc software shall be
implemented to DCS.
2.39 Deleted.
A. Level 1 functions
The Level 1 equipment shall be suitable to carry out the following
functions:
- interface with field instrumentation such as transmitters and final
elements controlling the process parameters such as rate of flow,
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 201 / 379
Revision : 2
RESID UPGRADING PROJECT
B. Level 2 functions
Level 2 represents the operator's interface towards the plant.
Each operator station will have its own real time and historical database.
R2 DELETED.
Each independent operator station shall handle/allow the following
functions
- indication of all analog or digital process variables, open or closed
loops and all related parameters;
- manipulation of control loops, including: set-point change, operating
mode, output, tuning, computation constants;
- alarm announcing;
- display of process graphics;
- logging and possibility of both historical and trend recording;
- SOE presentation
- display of self-diagnostics messages.
Still at Level 2, but through engineering station, the following functions
are handled in addition to the above mentioned ones:
- changes, additions, cancelling to the configuration of Level 2 (user
software) or of the lower levels.
C. Communication systems
The communication network in the system shall be a digital
communication bus providing a high speed (100Mb/1Gb) and reliable
data transfer. The operator stations and the process controllers are
preferred to be on the same physical redundant process network. If not,
the gateways to be used will be redundant, industrial type, reliable and
high performance models. System real-time control network shall be
deterministic (response time and network load guaranteed). Data link
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 202 / 379
Revision : 2
RESID UPGRADING PROJECT
Modularity
The system is of a modular construction and easily expandable; the
module typology holds in due consideration the requirements of
interchangeability and reduction of storage costs.
System requirements
- The system is installed in a non-classified area (control room,
equipment room). (ISA S71.04 & S71.01 G1AX).
- All the system components and panels shall be ATEX certified.
- The system can be supplied at 220 VAC at 50 Hz. from a UPS
with the following tolerances:
- Voltage 220 VAC +/-10%
- Frequency 50 Hz -4% / +3%
2.41.2 Vendor shall specify the proper start up and shut down procedures for
all DCS modules, operator stations, computers, operating systems and
any other relevant system components. All components of DCS can be
stopped or powered off at any time, without affecting the others. Any
card changes (I/O card, power supply card, bus communication card
and CPU card) shall be allowed on line.
2.41.3 All parts included in any section of the system shall be easily
accessible for maintenance. Any part, card, cable, piece of equipment
installed in any section of the system shall be accessible without
having to dismantle or remove another part, card or a piece of
equipment.
manufacturer.
2.41.7 Availability
The system shall be highly reliable and available. The availability shall
be not less than 99.5%.
The malfunction of a unit of the system, at any level, shall not
propagate to other devices of other levels.
2.41.8 Database
All I/O signals in the system shall be identified with the tagname of the
field instrument.
The system allows the I/O signals or in general the functions to be
identified with a name of 12 digits at least.
2.41.9 Memory
- Memory of non-volatile type shall be provided for the configuration
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 204 / 379
Revision : 2
RESID UPGRADING PROJECT
2.41.10 Synchronisation
2.42.1 The DCS shall be able to interface level 3 computers in the following
ways:
- by means of dedicated gateways;
- on client/server basis in a open systems architecture.
2.42.2 The proposed system shall feature OPC server to enable exchange of
data with computers, connected to Ethernet.
The digital communication bus handles the transfer of data among the devices
of Lev. 0, Lev. 1, Lev. 2 and Lev. 3.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 205 / 379
Revision : 2
RESID UPGRADING PROJECT
All input and output points to and from field or elsewhere except data bus(es) shall
terminate in proper, separate marshaling cabinets (following separation criteria as per
CHAPTER 29.000 ““TECHNICAL SPECIFICATION FOR CONTROL AND
R2
INSTRUMENTATION DESIGN”) located in the technical room area within the control
room.
Only indication
Only recording
Controlling and/or indication, recording and controlling
Only alarming
Alarming prior or after processing of the signal
3.1.2 The system shall have input capabilities of accepting digital or 4-20 mA
DC signals from transmitters, on-off inputs (from switches, relays, etc.)
millivolt inputs from thermocouples of all types at various levels, resistive
inputs from RTDs, voltage inputs, pulse inputs (0-6 KHZ) ; 1-5V DC
analog and relays digital outputs.
System shall support I/O redundancy for all type of I/O cards available
in the system when necessary.
3.1.3 In case of transmitter, power shall be supplied by the system from I/O
units through two wire signal cables, except some analysers or field
R2 devices externally powered. Isolation shall be provided for externally
powered transmitters. Short circuit protection shall be provided.
Input resolution for I/O cards shall be at least 12 bits for all analog
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 206 / 379
Revision : 2
RESID UPGRADING PROJECT
inputs. Output resolution shall be at least 1500 steps for the requested -
25% to +25% range to ensure additional force at the control valve
actuator to overcome plug unbalance forces and insure valve closure.
3.1.6 I/O card replacement shall be possible without power shut-down and/or
disconnection/reconnection of wires (including any kind of input
conditioning card if available, functioning as termination unit or module).
Any card changes (I/O card, power supply card, bus communication
card and CPU card) will be allowed on line.
3.1.9 All I/O cards shall follow Isolation Requirements described in RUP
R2 project Technical Specification for Control Philosophy and
Instrumentation Design, Chapter 29000, point 5.3.24.
3.1.10 Deleted.
3.1.12 Contractor shall indicate the minimum scan time available for each kind
of signals. For data acquisition subsystem scan time shall be smaller
than below values:
Digital inputs: 100 msec. (except the ones involved in item 3.2.6, 2
msec)
Analog inputs : 250 msec. max
Temperature inputs : 1 sec. max
Digital inputs: 100 msec. max (except the ones involved in
item 3.2.6, 2 msec)
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 207 / 379
Revision : 2
RESID UPGRADING PROJECT
Changing the input scan time on line while the plant is in operation shall
be possible.
Data update period of analog I/O cards shall not exceed 10 msec, for
digital I/O cards it shall not be more than 8 msec, for temperature cards
no more than 1 sec.
Logic or sequential control functions performance times shall be as
follows:
- SOE digital inputs 1 msec.;
- digital inputs 20 msec.;
- digital loops 100 msec.
3.1.15 Analog output cards shall have the capability to act immediately upon
loosing communication with controller part failure by the driving the
output to predefined level.
3.1.16.1 General
3.1.16.6 Scanning
The control functions of the system shall be carried out by control processors.
The controller modules shall have equivalent, high level technology,
multifunction capability and be 32 (or more) bit high performance RISC
microprocessor-based with multiple inputs and multiple outputs for control and
data acquisition. The data acquisition system and the process control system
shall be fully integrated in order to guarantee a very high level of reliability,
availability and data integrity.
This controller equipped with resident software to carry out analog control
algorithms, interlocks and sequential control functions.
Controller shall be in dual-redundant configuration for processor, power
supplies, real-time control network and communication network with I/O sub-
system. Controller shall support I/O redundancy for all type of I/O cards
available in the system.
Input monitoring
In addition to basic PID control algorithms, logic, sequence,
cascade and modulating control functions,
Various type and quantity of algorithms which can be
implemented with each control type will at the minimum be
enough to realize algorithms, calculations necessary for refinery
operations.
PID control with dead band
Two position on-off control
Three position on-off control
Pulse duration on-off control (time proportioning)
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 214 / 379
Revision : 2
RESID UPGRADING PROJECT
Manual control
Ability to bias a signal and sum it with controller output for feed
forward control
Ratio setting
Automatic signal selector
Data exchange
Signal switch
Ramp functions
Totalizing/Integration
Mass flow computing (with compensation of temperature,
pressure and density)
First order lead/lag unit.
Rate limit
Dead-time compensation control
External feedback to prevent wind-up (for required loops)
Moving/cumulative average
Line segment function for non-linear signal
Calculations (square-root, addition, subtraction, e-ponential
function, logarithmic function, multiplication/division, Sin/Cos
functions, ...etc.)
Various advanced and control functions
3.2.3 Controllers shall be able to scan close loops in minimum 4 times per
second; and for digital loops 10 times/second. The control system
shall have sufficient memory to support twice as much as control
blocks that are necessary for application.
3.2.7 Controllers shall also support ladder logic and high level
programming language to allow customized application programs to
be run. Necessary utility software packages which enable the user to
develop high level programming language (i.e. BASIC, C or other
special manufacturers programming utilities) shall be provided. All the
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 215 / 379
Revision : 2
RESID UPGRADING PROJECT
3.2.9 Signals listed in the I/O list for each group in the plant shall be
distributed equally among all control modules assigned for each
plant.
3.2.16 Also the followings are the minimum functions required for each
monitoring point in the regulatory control (including temperature
monitoring).
3.2.17 Smart field instrument integration: The system input card shall be
capable to separate the two signals and transfer digital information to
R2
the system engineering work station for transmitter setting,
maintenance and diagnostics. For this purpose, hardware and
software shall be offered.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 217 / 379
Revision : 2
RESID UPGRADING PROJECT
3.2.20 System vendor shall clearly define a migration path for maintaining
upward compatibility.
3.3.1 All the cabinets shall be of free standing, enclosed type and shall be
designed for bottom cable entry. Cabinets shall be equipped with rear
and front access doors, lamp with door switch, safety ground bar,
isolated instrument (reference) ground and name plate of appropriate
dimensions (white engrave on black background). Doors shall be
equipped with lockable handles and concealed hinges with pull pins for
easy door removal.
3.3.2 In order to effectively remove dissipated heat from the cabinets, vent
louvers backed by wire fly screen shall be provided to cabinet doors
together with ventilation fans. Cabinet fans and temperature status shall
be checked continuously by the system self diagnostics and shown on
the operator station.
3.3.3 Equipment within the cabinet shall be laid out in an accessible and
logically segregated manner. Clamping rails shall be provided for
incoming cables to prevent excessive stress on the individual terminal.
The field cables shall terminate on rail mounted, disconnect type
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 218 / 379
Revision : 2
RESID UPGRADING PROJECT
marshalling racks.
3.3.4 All metal parts of the cabinets including doors shall be electrically
continuous and shall be provided with a common grounding lug.
3.3.5 The multicare cables with industrial type, multi-pin plugs and connectors
(ELCO connector or equal, so called system cables) shall be executed
in the Vendor's shop. The multicore cables shall be standardized on the
length, number of lead and lead connection. The plugs and socket
system shall have the following features as a minimum.
3.3.5.3 All spare cables to terminate on the terminals after the socket,
and all cables and incoming panel no. shall be marked clearly.
R2 3.3.7 DELETED.
3.3.8 There shall not be any components on the lowest 100 mm. of the
marshalling cabinet mounting plate. This space can not be considered
as spare space in calculations.
4.20 mA
pulse
mV/RTD
Digitals
1-5 V DC
Scan speed shall allow each point to be updated between 3-7 sec.
Alarm points to be adjustable
Alarm print-out to be digital and to include true point number (i.e. not
coded) temperature, date and time.
All temperatures to be logged at a preset frequency (for example
every six hours) and alarm conditions to be printed.
Printer to be normally inoperative unless either an alarm point is
exceeded or total record print-out is initiated on time cycle.
4.1.2 Control network shall be dual redundant with self-diagnostic function for
data integrity check and with on-line self recovery functions In case of
main bus failure or any communication device failure, the transfer to the
back-up bus or device shall be automatic without interrupting the system
operation and without any operator's action. Information about the failed
bus/device shall be displayed on the operator consoles. Bus switch over
time shall not exceed 50 msec and bus error recovery time shall not
exceed 20 msec
enough capacity for the load envisaged from the start, plus the load
deriving from expansion of functions. Such capacity should exist at
every condition of the plant:at start-up, when running, during shut down,
etc The network load must not exceed 50%.
4.1.5 The real time LAN shall be capable of accomotating a large number of
devices and be able to provide extended communication up to 3
kilometers minimum with proper active repeaters and fibre optic cables.
4.1.7 Each node on the network shall be notified of the status of all nodes for
any trouble or failure on diagnostic panel.
4.1.8 Process data accessed by the displays shall be continuous and in real
time.
5.1.1 The operator stations shall be provided with their electronic system.
Each operator station shall have its own separate keyboard and
electronics and shall provide a means for centralizing the task of
monitoring and manipulating the process while using distributed devices
to perform actual process interface and control functions.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 223 / 379
Revision : 2
RESID UPGRADING PROJECT
Each operator station shall keep its own application database (all real-
time and historical process data, trends, alarms & events) to provide
multiple functional redundancy. Separate process servers or common
historical modules even in redundant configuration can be accepted
R2 under Tüpraş’s approval. System shall support remote operation,
maintenance and engineering from multiple remote client PC’s without
needing direct connection to system real-time control bus and special
software. System shall also support remote operation over internet.
Failure of any operator workstation should not effect more than one
operator station.
The operator station and the engineering work station of DCS system
shall have the capability to display simultaneously the DCS standard
graphic and application windows.
5.1.3 Each operator station shall be able to provide the following functions, as
a minimum:
Reports/ logs
Custom keys
x- Window
Status indication.
Operating displays
Window from computer application
Self diagnostic messages.
Input high and low values
Deviation from set point
5.1.4 The real time clock on each operator station shall be crystal controlled,
which shall be independent of line frequency. All the real time clocks in
the system shall be synchronized with each other.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 225 / 379
Revision : 2
RESID UPGRADING PROJECT
5.1.7 Each LCD shall have industrial high resolution min. 27" color screen
R2
capable of displaying alpha-numeric and graphic displays.
The upper LCD monitors shall have swivel, tilt, rotate and height
adjustment facilities.
Bulk storage devices: Hard disks drive of the operator stations shall be
of redundant RAID-5 type 500GB hard disk with hot swappable
configuration which is avaible in the open market for all station wherever
applicable.
5.1.11 Refresh time and screen call-up time of real time data on standard
operation display for all windows (not only predefined Windows) shall be
one second (max) and not exceed one sec. Call up time to bring full
display with all information of a standard operation display shall take no
more than 1 second. This shall be tested and proved during F.A.T. and
S.A.T.
CONTRACTOR shall note that failure to comply with this will result in
removal from TÜPRAS’s vendor list for DCS vendor.
5.1.12 The operator stations shall be connected directly to the real time
network (gateways are not acceptable).
5.1.13 System shall support coexistence of 3rd party software such as virus
buster, asset management or analysing software to run on operator and
engineering stations without the need of a dedicated computer.
5.1.14 The system shall be secure against unauthorised use by means of key
locks, passwords or equivalent methods; The vendor shall detail the
system security provisions and the number of access levels.
5.1.16 Keyboard
of all parameters;
- possibility of requesting the prints of the graphics, logging
and alarms, addressing signals and trend recorders;
- possibility of changing the operating mode
(automatic/man/cascade) of each controller with
"bumpless" action, the state of a user (placed in manual)
and the state of a group of users.
The displays on the LCD screens, consisting of fixed format displays and
variable format displays or custom graphics shall include as a minimum the
following features.
Each operator station shall have the following displays and functions
Overview display
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 228 / 379
Revision : 2
RESID UPGRADING PROJECT
Group display
Point detail display
Alarm display
Trend display (real time and historical)
Configuration display
System status display
- the range and the value of the analog variable both in the
form of "bar graph" and in engineering units by means of
alphanumeric display;
- the value of the set point both in the form of "bar graph"
and in engineering units by means of alphanumeric
display;
- the value of the analog output both in the form of "bar
graph" and in percentage by means of alphanumeric
display;
- mode of operation for controller (man/auto/cas);
- alarm limits and alarms of the variable, deviation alarms,
etc.;
- indication of the selected loop (inside the group);
- position of the valve in case of "failure";
- the inputs and outputs with contacts shall be represented
graphically and also by means of alphanumeric
descriptions of the state.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 230 / 379
Revision : 2
RESID UPGRADING PROJECT
- tuning constants;
- zero and span;
- alarm set;
- control mode;
- output;
- for the digital points, it will be possible to execute start/stop or
open/close commands.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 231 / 379
Revision : 2
RESID UPGRADING PROJECT
5.2.2.1 Custom graphic pages are intended to be the primary tool for
the operator to monitor and control the plant activity in an
interactive fashion. per display page.Each page shall be
capable to include at least 500 parameters (live data) per
display page without degrading performance,where each point
may have more than one parameter including PV, SP, OP,
mode, alarm condition, etc. (no more than 5 parameters per
point shall be accepted for performance evaluation purposes).
Graphic displays capacity shall be equal or more than 500
pages and shall graphically show process lines, equipment and
relevant instrumentation as per ISA-5.1 and 5.3. The call up
time for any of those graphics shall be within one second.
- Process alarms
- Faceplate indication to allow manipulation of the control
made, set point output.
- Graphical trends
- Plant overview
- Detail display. The detail display shall be composed of a
graphic showing a part of a process and be completed with
detailed information, which is selected from the available
fixed format displays.
Aricmatic expressions
5.2.2.4 Graphic pages shall be built by the Vendor on the basis of plant
P & IDs. Items or pieces of equipment more commonly
displayed in these graphic pages shall be available in a system
library for future use; moreover, display building facilities shall
be available to make easier and independent of programming
languages for the generation of new graphics. Each graphic
page shall represent on indenepdent part of the process units
arranged in a logical manner to show all interrelated process
variable. A given proces variable may accessible from more
than one graphic page if this process variable is common in
more than one independent graphic page. The operator shall
be able to call up any operation displays from graphic display.
5.2.2.8 In particular the red colour shall be used for the alarm
conditions. Symbols and colours shall meet the EN60073
requirements.
5.2.2.9 All flows shall have totalizer. All tag numbers should defined
minimum character. Examp : 47PIC1542A. All graphic pages
should have title. All tag description should be in Turkish.
Control function shall be developed without compensation. All
trend and control group pages should be adressed to soft
touch buttons. Those soft touch buttons should be on bottom
line of the releated graphic pages. All major equipments colour
should be grey and line weight : 3
(furnaces,exchangers,pumps,compressors,reactors,column,etc)
All analog Instruments should have real time and historical
trends. Historical trends should have minimum 32 days
historian. DCS should have process report.(Alarms, Status
changes, operator actions etc.). All digital enstruments should
have alarm voice when it's in alarm condition. Last 3 process
alarm with tag description allways should be appear top line of
the graphic panel. Sistem alarms should be separated from
process alarms. First page of the graphic panels should be
''graphic index''. All graphic pages should have ''next page'' and
''previus page'' soft buttons. Same specific calculations should
be implemented and dispay in graphic panels (
Ratio,conversion,yield, etc.). All analog İnstruments should
have HH, LL, L and H alarm set points. All cascade controllers
should have set point traking between master and slave
controller. All controllers should have manuel traking between
PV and SV. ESD, System and Process alarm voices should
have different alarm sound. All alarms should be stored in the
alarm page. Acces level should be defined occording to
costomer requirement
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 234 / 379
Revision : 2
RESID UPGRADING PROJECT
INDICATORS :
A - Flows : FI
B- Temperatures : TI
C- Pressures : PI
D- Levels : LI
C-101
and
Blinking Acc. to
PH,HH,PL,LL
CONTROLLERS :
A- Flows : FIC
If controler mod MAN : Red Line (Size :3 Dot)
If controler mod AUTO:Yellow Line
If controler mod CAS :Blue
Line
B- Temperatures : TIC
Pozition
Red line
C- Pressures : PIC
D- Levels: LIC
Columns:
If controler mod MAN : Red
Line
If controler mod AUTO:Yellow Line
If controler mod CAS :Blue
Red line Line
C - 201
Red Box (Line Size :3 Dot)
Grey Tag Number , turn to red
and
LIC-252 Blinking Acc. to PH,HH,PL,LL
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 237 / 379
Revision : 2
RESID UPGRADING PROJECT
P0000
% Green Process Variable
S0000
% Green Set Value
M0000 Green Valve
% Pozition
Drums:
Red
Box
Grey Tag Number turn to red
D - 20 and
LIC-255 Blinking Acc. to PH,HH,PL,LL
P0000
% Green Process Variable
S0000
% Green Set Value
M0000 Green Valve
% Pozition
LI-246
0000 %
Red
Box
HIC-224 Grey Tag Number
M0000 Green Valve
% Position
Red line
3-LEVELS:
HI Limit
4-PUMPS:
5-AIR COOLERS:
Equip. Number
:Grey
E-21
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 239 / 379
Revision : 2
RESID UPGRADING PROJECT
A B C D E F G H
6-DIGITAL ALARMS
(LAL,LAH,PAH,PAL,ZAL,ZAH,VAH,TAH,TAL etc.)
D - 21 LAH223
LAH221 LAL222
LAL220
7-SHUT-OFF VALVES :
TYPE A
: TYPE B :
8-SOFTWARE SWİTCHES :
A: Three-way Switches :
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 240 / 379
Revision : 2
RESID UPGRADING PROJECT
Mod-1 : ( 1 connected to 2 )
Line-1 to Line-3 : Disappear ( Black )
2 Line-1 to Line-2 : Appear ( Red )
1
B: Four-way Switches
9-MAJOR ALARMS
For major alarms please make special graphic pages.
10-PROCESS LINES:
Weight : 3
Colour
:
Steam
Liquid : Grey : Blue
Dark
H2 : Pink Water : Blu
Air
Gas : Yellow : White
Chemical: Green
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 241 / 379
Revision : 2
RESID UPGRADING PROJECT
Weight : 1
Colour : Blue
and Round dot
Weight : 1
Colour : Blue
and Round dot
13- TEXT :
All equipment names and other texts colour should be grey , size minimum 14
All process data size should be minimum 14
A - IF TOUCH SCREEN :
FIC-188
Touch Target
P0000m3 Area
S0000m3
M00000%
Curser 0000 OC
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 242 / 379
Revision : 2
RESID UPGRADING PROJECT
A - IF NO TOUCH SCREEN :
FIC-188
P0000m3 Active area for track ball or mouse
S0000m3
M00000%
Indicators : LI , PI , FI , TI , AI , SI
a-) ...etc.
GRAVITY DT01
FROM LAB.
TI-
TI-315 315.PV
0000 OC
CO
COMPENSATION RV
CALCULATION
IF ANY
PI-
PI-286 286.PV
0000 Kg
FIC-188.PV
FIC-188
P0000m3
S0000m3
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 244 / 379
Revision : 2
RESID UPGRADING PROJECT
M00000%
GR10:DEBUTANIZERSİSTEMİ
TI-1532 A B
PI-1710
VAH151
TIC-1535
TI-1533 P0000 C
8 S0000 C
M00000%
E-112 C-108
TI-1537
FIC-1701
P00000M3
S00000M3
M00000%
TI-1576
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 245 / 379
Revision : 2
RESID UPGRADING PROJECT
All trend and control group pages should be adressed to soft touch buttons.
Those soft touch buttons. should be on bottom line of the releated graphic
pages.
5.2.3.5 Trend display shall be single line type or bar graph type with
additional information like loop tag number, engineering units,
span, present value of the trended point, alarm status etc.
5.2.3.6 Selection of the tag number and displaying time basis for real
time and historical trending shall be possible from operator
keyboard. Saved trend data shal be of the same accuracy
engineering unit, scale and range of the actual process valve.
5.2.3.8.6 Condensate :
f. Input and output signal open alarms for each point due to
short circuit or open circuit signals. Thermocouple open
circuits for each point with MV input.
5.2.5.5 Displaying and printing of all events and operator actions shall
be provided (e.g. start/stop of motors, set point changes),
including as a minimum.
b. Event description
5.2.8.2 All parameters required for logging are stored in the memory
with the data base updating time. However. it is possible to
make arithmetical calculations (summation, efficiency
calculations, average values, etc.) before logging.
The logging format is, in general, defined by the user.
5.2.8.4 At least 1000 of the most recent events shall be saved on the
hard disk and then archived for long-term storage.
5.2.9.5 The idle time of processor and the status of each I/O card and
controller shall be displayed on a dedicated system status
display, easily accessible to operator on the operator station.
The software applications wich are part of Integrated Manufacturing Execution System,
R2 MES, are not included in RUP Contractor Scope.
6.1 Heat and material Weight Balances for the feedstocks, products, utilities
flowrates of each process unit.
All the flowrates used will be compensated with actual temperature, pressure
and specific gravity according to the needs and totalized. Moreover the same
streams are used in the yield calculations (volume or weight flowrate ratio
between each output stream and the feed stream) and in the specific
consumption calculations.
These calculations are based on the so-called "MEKLER and UNGAR" method.
Calculated efficiency is a thermal balance made of fuel/flue gas system.
On the basis of the amount of fuel oil and fuel gas it is possible to determine the
released heat and consequently the absorbed heat for each heater. These
results, adequately scheduled or on demand, will be available for reports and
display.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 256 / 379
Revision : 2
RESID UPGRADING PROJECT
The thermal balances are based on a series of heat duty calculations like:
CP(S,K,T)=1.00067 * {0.6811-0.308*S+(0.000815-0.000306*S)*T}
* (0.055*K+0.35) Kcal/Kg°C.
where:
S= Stream specific gravity 60°/60°F
K= Stream characterization factor
T= Stream temperature in °F.
6.4 Deleted.
6.5 For DCS, the configuration programming and data base assembly shall be
determined by the Owner such that the complete configured system can be
inspected at the factory before delivery.
6.6 Any software package providing relational data base for console tag list,
function block configuration and display files, and allowing checking for
consistency and concordance while letting user to search for specific items in
data base through simple English-language like statements shall be provided.
6.8 Any software package combining system monitoring and data analysis in one
package allowing the user to view current process data in a Microsoft Excel
spreadsheet or compatible graphic format. The program shall access all
records in the spreadsheet format and also in graphic format at a time. Briefly it
shall allow the user to manipulate the data once it is in the database.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 257 / 379
Revision : 2
RESID UPGRADING PROJECT
6.9 The software package in DCS shall also be capable to enable APC computer
system to communicate with his DCS. but not supplied in this project. The DCS
system shall have the capability to interface with upper level computers and
networks using Ethernet with TCP/IP protocol. Future hierarchical integration of
DCS together with the other existing system in various plants in the refinery,
shall be taken into consideration during specification work of the system
OWNER tends to have a 100 % redundancy, however contractor should feel free to
recommend another degree of redundancy provided that operation of processes will
not be effected by the failure of any part of the system. Key components of the DCS
system shall be fully redundant so that neither a hardware nor software failure shall
result in the loss of the features supplied by the components. The system shall be
%100 fault tolerant. These means, all central control processors, all communication
processors and all other central rack and individual node’s common cards, all the
communication cards, networks, power supply cards and cables etc. shall be %100
fault tolerant. All the hardware including control processors, all communication
processors, all type of system cards, all type of I/O cards, networks, power supply
cards and cables etc. shall be hot replaceable.
Vendors shall note that there shall be no difference between the primary and backup
units (including the busses) physically or operationally. Any backup or secondary unit
can become primary when the primary unit fails or it is manually forced to. It shall be
on duty without any restriction on time or operation till the above conditions apply
again.
In order to provide the maximum degree of reliability the system shall be configured in
such a way that the malfunction of each component, except for the I/O cards, cannot
cause malfunction or incorrect operations of the continuous control, Boolean logics
and sequence functions.
a. Hard disks carrying: real time database, images of displays, historical events,
redundancy shall include disk drives and disk path to the real time LAN.RAID5
shall be applied with at least 5 number of hard disks.
c. Control processor
Redundant power supply shall be designed with no more than 80% load
one each unit when operating individually.
The transfer from a unit to the back-up one shall be in any case
alarmed.
The DCS shall be provided with a dual redundant communication bus. No loss
of data shall occur due to switch over. Standby redundancy is not acceptable.
7.3 Deleted
7.5 Beyond the requirements for redundancy stated above any other component
failure shall not affect more than one loop (single loop criteria)
8.1 The engineering workstation is meant as the basic configuration tool for all
system nodes, including display pages and report generation. Engineering work
station shall run in window based operating system, allowing multiple pages
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 260 / 379
Revision : 2
RESID UPGRADING PROJECT
displays simultaneously.
CAD based system engineering tools which do not require special
programming knowledge shall be provided. System shall support concurrent
engineering at different locations for flexible and effective system engineering.
8.2 All data shall be able to be stored on disks. Data must be able to be up/down
waded to/from disk. Back up must be possible on commercially available media.
8.4 Configuration and programming activities shall be possible while the system is
on-line. Human error shall be minimised with the use of confirmation dialog
windows before executing commends that may affect the system database.
8.7 The system shall be suitable to carry out programs written in high level
languages such as C and visual BASIC. Furthermore there shall be utilities
suitable to connect programs prepared with such types of languages with the
pre-configured control blocks.
8.9 The system contains routines suitable to verify that the changes/additions are
R2 normally correct (DELETED)
8.10 The engineering workstation is equipped with password system to avoid that
unauthorised personnel may tamper with the software.
8.11 Equally the engineering workstation stores both the date and time of the
intervention and the originator of the change.
8.13 The configuration database shall run on the newer versions of the application
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 261 / 379
Revision : 2
RESID UPGRADING PROJECT
8.14 Any software package providing relational data base for console tag list,
function block configuration and display files, and allowing checking for
consistency and concordance while letting user to search for specific items in
data base through simple English-language like statements shall be provided.
8.16 The system shall be secure against unauthorised use by means of key locks,
passwords or equivalent methods; The vendor shall detail the system security
provisions and the number of access levels.
8.17 The engineering workstation shall have an MS Excel licence and DDE software
to exchange data between process database and Excel spreadsheets.
8.18 System shall support concurrent engineering at different locations for flexible
and effective system engineering.
8.19 Partial database modifications shall be possible while the system is on-line.
System shall be sized according to the given basic I/O list. In the sizing, the system,
the contractor shall consider the expansion capability of process and the system
loading described in accordance with the response times described else where in this
document. The following spare requirements shall be respected by Vendor when sizing
the system.
10.1 Controller software load and memory occupation shall be smaller than 50% with
reference to the I/O list. The calculation shall be supplied by Vendor. Controller
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 262 / 379
Revision : 2
RESID UPGRADING PROJECT
10.2 A minimum of 20% fully equipped and wired ready to use spare capacity in I/O
cards for each process units in TR-1, TR-5, TR-6 and TR-9 and 10 % in TR-2,
R2 TR-3 and TR-4, no matter they are for control or acquisition.
10.3 A minimum of 20% free space in system cabinets (that is, these cabinets shall
be loaded at most, at 80% of their rated capability).
10.4 A minimum of 20% spare terminal strips.( included in 20% of wired spare)
All components of the system shall be suitable for the refinery environment. Immunity
to radio frequency and electromagnetic interference, such as generated by hand held
walkie-talkie of 5 watt set about 450-470 MHZ (UHF), within near proximity of system
components (doors of cabinets open and within 300 mm distance) shall be provided.
The vendor shall confirm this system immunity together with the specification for the
equipment limitations, e.g.: maximum wattage, minimum distance, and frequency
band.
12.0 TRAINING
The Vendor shall provide training courses for ten of Owner's engineers at Vendor's
training facilities. This training shall cover the following subjects such that the
engineers can later operate, reconfigure, maintain the system and generate graphics,
logs and reports.
For each proposed course the Vendor shall submit a summary including subject,
prerequisites (if any), and course position in the training program.
For the attendees may have sufficient time to plan their participation, they shall be
given notice at least 8 weeks before the course scheduled date. The course outline
and training documents shall be submitted 10 weeks ahead for review.
The Vendor shall provide supervision to installation, commissioning and start-up of the
systems.
The Vendor shall quote separately the cost of a single additional day of this personnel
at site.
Separate quotation for up to three service visits to site in three years time after start-up
of units is requested too.
The Vendor shall also quote any other optional service deemed useful in installing and
support the system; The Owner reserves the right to select between the offered
services.
Equipments shall be submitted to all necessary tests and checks to verify that the
supply is in accordance with this specification and referenced standards.
The Vendor shall submit for approval a test procedure based on the requirements
included in this specification and in "ISA RP 55.1-ANSI MC8.1, Hardware Testing of
Digital Process Computers".
Tests will be organized in two phases: first, tests during manufacturing of the
system; second, the final factory acceptance test which will be carried out on
the system completely assembled as if it were installed at site.
Vendor shall test and demonstrate the functional integrity of the system
hardware and software. No material or equipment shall be transported until all
required tests are successfully completed and certified.
Owner reserves the right to be involved and satisfy himself at each and every
stage of inspection. Owner shall be free to request any specific test on any
equipment considered necessary for him although not listed in this
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 264 / 379
Revision : 2
RESID UPGRADING PROJECT
The schedule for the factory testing shall be included in the proposal by the
Vendor.Vendor shall not replace any system component/module/sub-system
unless it has failed. A log of all failed components/modules in a sub-system
shall be maintained which shall give description of the failed
component/module, effect of failure on the subsystem, cause of failure and
number of hours of operation before it failed. If malfunction of a
component/module in a subsystem repeat, the test shall terminate and Vendor
shall replace the faulty component/module. Thereafter the test shall commence
all over again. The minimum requirements for testing during each phase are as
follows.
14.1.1 Phase -I
Vendor shall perform test at his works to insure that all components
function in accordance with their respective specifications for each type
of test. A test report shall be submitted to the Owner/Consultant for
review within two weeks of completion of each type of test giving details.
The test log book shall contain the following information about the tests:
a. Date/time
b. Assembly designation/loop tag number
c. Test input
d. Test result and sign off with personnel name
e. Action required (if deficiency is detected)
f. Action taken, date of completion and sign off.
g. Special test methods (including special equipment requirement,
bypasses used etc.)
Test Details:
14.1.1.1 Quality control tests shall be carried out to assure quality of all
components and modules in accordance with Vendor's own
quality control and assurance procedures.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 265 / 379
Revision : 2
RESID UPGRADING PROJECT
This test shall systematically, fully and functionally test all the
hardware and software in the presence of Owner representative. All
the sub-system shall be inter-connected to simulate, the total
integrated system.
System shall be shipped to site only after this testing and certified
ready for shipment by Owner.
Testing Record
g. Checking of LCD refresh rate, data base update and display call-
up time.
All the equipment shall be checked throughly after its receipt at site. The tests,
as a minimum, shall include:
14.3.1 The Owner will take over the system from the Vendor after the final
acceptance test, which is defined as successful uninterrupted
operation of the integrated system for two weeks after the positive
conclusion of the field tests. Vendor's personnel shall be present
during the test.
The test is relevant to all those equipment that are not part of the DCS but are
interfaced to the system in order to allow the centralised operation from the
DCS operator workstation. Scope of this test is to demonstrate the correct
functionality of the communication hardware and software communication
protocols between the DCS equipment and external specialised dedicated
equipment, and to allow the testing of the DCS application software relevant to
physical I/0 not handled by the DCS but displayed at the DCS operator stations.
The test shall be performed in accordance with an agreed test procedure and
shall be carried out in parallel with the DCS software test (parallel test is
mandatory as the DCS need to be physically connected to the external
equipment to demonstrate the full hardware and software functionality).
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 269 / 379
Revision : 2
RESID UPGRADING PROJECT
After the field system installation and prior the starting of the commissioning
activities the system shall be tested. Test shall be repeated to demonstrate the
full functionality after transportation and field installation, complete dynamic
loop check and alignment shall be performed, generating and verifying the
signals directly from field.
During the site acceptance test particular care shall be taken to check the
power supply system and the grounding network system and to verify the
system bus functionality in the final configuration and maximum
extension.Before the system power up and prior the I/0 module field
connections all the field I/0 signals shall be checked for continuity and isolation,
in addition it shall be verified the presence of undesired electrical potential, due
to wrong field connection, that could damage the DCS input circuits.
14.6 Documentation
Note: All drawings shall be produced using CAD tools, AutoCAD or Intergraph
Microstation compatible.
One drawing for each cabinet shall show all the positions of
the devices into the panels (plan and front views).
Drawings showing:
- system modules layout;
- tag assignment (points layout).
14.6.2.1 Database
1.0 REFERENCES
2.0 GENERAL
2.1 This section states the requirements for the design of electrical heat tracing
systems to maintain minimum specified process temperature under very low-
flow or no-flow condition in order to prevent freezing or condensation in
instruments and relevant impulse piping.
2.2 All heating cables and the ancillary materials for installation in a classified area
ZONE 0, ZONE1, ZONE2, Shall be approved for the purpose by an authorised
laboratory .
2.1 Heater cables shall not be designed for spiral wrap installations on pipe
2.2 All heater cables shall have an overall grounded metal covering
2.4 System shall be designed minimum 125 % excess capacity of the calculated
wattage.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 273 / 379
Revision : 2
RESID UPGRADING PROJECT
2.6 Heat tracing systems shall be supplied from their own distribution panelboards.
Compound filled insulation transformers with thermal overload type
primary protection shall be provided. A main breaker and individual circuit
breakers for each heater shall be provided with a minimum initial spare
capacity of 20 % for each panel board.
E. Each MI heater shall be factory fabricated to required length with a cold lead
for connection to power or where splices are required. Cold leads shall be 4
ft. or 7 ft. long. Cold leads shall have a gland type fitting for termination in
threaded hub junction boxes. Cables shall be factory terminated and sealed.
F. Each MI cable shall have a metallic tag attached to the cold lead. The tag
shall show the heat tracing circuit number and heater characteristics such
as length, voltage, current, watts, cold lead length, and catalog number.
3.3 All heating cables, except M.I. type, shall have a metallic braid for use as a
ground path. An overjacket shall also be required for all heating cables. For low
temperature heating cables the overjacket material shall meet the requirements
in the application as defined below:
4.1 GENERAL
Each process will impose a unique set of constraints on achieving proper
temperature control. Such constraints may include maintenance and operating
flexibility, energy efficiency, acceptable temperature span, time and manpower
available to correct deficiencies, and the cost assignable to lost production.The
installation and selection of temperature control depend on the following
criteria:
- process/product considerations;
- energy saving;
- temperature limitation for safety reasons;
- protection against overheating of the heating elements.
If self-regulating cable is used (e.g. for winterisation) on impulse lines, the
‘power off’ point shall be below the temperature at which the impulse line liquid
starts to strip/evaporate.
4.1.1 Type I
A process where the temperature should be maintained above a
minimum point. An ambient sensing thermostat is acceptable.
Equipment might consist of a mechanical thermostat and few, if any,
alarms. Large blocks of power might be controlled by means of a
single thermostat, a contactor, and a panel board. Since heat input will
be provided unnecessarily at times, wide temperature excursions
should be tolerable, and maximum energy efficiency is not essential.
Energy efficiency can be improved through the use of dead leg sensing
control.
4.1.2 Type II
A process where the temperature should be controlled within a
moderate band. Pipeline temperature sensing devices, along with
some facilities for monitoring and alarming, are typical. Redundant
equipment is not generally specified, and the tracing requirement
would be sufficiently seasonal to permit planned maintenance and
repairs.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 278 / 379
Revision : 2
RESID UPGRADING PROJECT
4.2 The type of temperature control shall be discussed with the Contracter and
Manufacturer in the detailed engineering design stage.
1.0 REFERENCES
2.0 SCOPE
2.1 This standard shall govern the design and installation of the steam tracer and
enclosure required to protect instruments. Condensate return and temperature
control shall be by means of temperature control thermostatic valves (make
GONTZ or equal).
2.2 The term "instruments" when used herein, shall mean all instrument items
which are mounted externally to the process line or equipment. In-line items
such as control valves, variable area meters, etc. which require steam tracing
shall be traced with the process line tracer and shall not be considered part of
this standard.
2.5 This standard shall govern steam tracing of instruments to prevent the
following:
2.6
2.3.1 The freezing of fluids in instruments and lead lines.
2.3.2 Interference with the proper operation of an instrument by a viscous
fluid.
2.3.3 Damage to the electronic portion of an instrument.
2.3.4 Condensation of process vapors where condensation would be
detrimental.
This standard shall be supplemented by design data which will give the following
information.
4.0 MATERIALS
4.1 Tracer
4.1.1 Copper tubing shall normally be used for that portion of the steam tracer
that is fastened to and insulated with the instrument piping or instrument
being traced. However, carbon steel tubing or stainless steel tubing shall
be used in the following instances.
(d) Compression type tube fittings shall be used, brass for copper
tracers, carbon steel for carbon steel tracers and 316 SS for SS
tracers.
Where possible, pre-insulated tubing bundles shall be used rather than traced
and insulated instrument lead lines. This does not apply to line mounted D/P
flow transmitters, etc., where the bending radius of the bundle would prohibit its
use. However, where longer lead lines are encountered, a considerable cost
saving can be realized by utilizing a pre-insulated bundle. The bundle shall
have a factory-applied insulation and a PVC jacket, as manufactured by the
Unitherm Division of the Eaton Corporation, or of equal manufacture. The
following specifications shall be to the pre-insulated bundle:
4.2.1 Tubing specifications shall be the same as stated above for bare tubing.
4.2.2 Jacket surface temperature with 200°C tube and 26°C ambient=60°C.
(c) Minimum recommended slope for condensate runoff = 1/4" per foot.
(d) End sealant of sealing patch (insulation, fiberglass tape and rubber
cover) shall be used to protect and cover the tubing where it has
been stripped of the original insulation and covering during
installation.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 283 / 379
Revision : 2
RESID UPGRADING PROJECT
Enclosure heating systems shall use steam as the heating source. The method
of heating shall be as follows:
(a) Pressure gauge enclosures- The heating system shall either utilize the
inherent heat present in the process line by insulating up to the
enclosure for heat conservation or shall continue the steam tracer
around a cast aluminum heat transfer block located at the gauge
connection which will transfer heat into the bourdon tube.
4.6 Miscellaneous
4.6.1 Wire for fastening the tracers shall be 14 ga.(0.083") galvanized copper
bearing iron wire, ASTM A 111 grade BB or A 112 grade B. For stainless
steel piping or tracers, use stainless wire 14 ga., ASTM A 580 annealed.
DO NOT use galvanized wire.
4.6.2 All enclosures shall be supplied with a stainless steel identification tag
and seal kit.
5.2 Instrument lead lines being traced shall be grouped, wherever practical, and
insulated with a common tracer.
5.4 Each tracer shall be provided with an individual thermostatic valve allowing the
steam/condensate temperature to be controlled at the required temperature.
5.5 Sufficient unions shall be placed in the steam tracer, outside the insulation, to
allow the instrument to be removed for repair.
5.6 Tracers for horizontal lines shall be parallel to the line and located near the
bottom.
5.7 Tracers for vertical lines shall be parallel to the line and located where they
offer the least interference. Wrap-around tracing shall not be used unless
otherwise specified.
5.8 Where tight bends are required, tube bending, tube bending tools such as those
made by Parker or Ridgid shall be used.
5.10 Close coupled pressure gauges connected to steam traced lines may be traced
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 286 / 379
Revision : 2
RESID UPGRADING PROJECT
with a loop in the line tracer. All other instruments or groups of instruments shall
be traced with a separate steam tracer.
5.11 Each instrument to be traced shall have its own separate tracing block valve.
6.0 INSTALLATIONS
6.1 The inlet of this section is to show typical instrument steam tracing installations.
The actual installations may differ from those shown to meet the requirements
of the specific application.
6.2.1 Steam line, -25°C ambient temperature, 25 MPH wind, utilizing AGCO
CT-7 siphon. See figure 1.
6.2.2 Steam traced line with 3/8" or 1/2" line tracer. See figure 2.
6.2.3 Separate steam tracer. See figure 3.
6.2.4 Diaphragm seal. See figure 4.
STEAM TRACING
OF INSTRUMENTS
SCREWED
PRESSURE GAUGE HEAT BLOCK COUPLING AT
ENCLOSURE GAUGE CONN.
TRACER
A A VIEW "A-A"
STEAM TRACING
OF INSTRUMENTS
STEAM TRACING
OF INSTRUMENTS
D/P TRANSMITTER
3/8" OD TRACER PARTIAL ENCLOSURE
FROM STEAM SUPPLY
A
A CLAMP TO HOLD
TRACER TO
TRANSMITTER BOD
TO THERMOSTATIC VALVE
NOTE: TRACER
INSULATE PIPING UP TO FIGURE 5 VIEW "A-A"
ENCLOSURE FOR HEAT FLOW TRANSMITTER
3/8" OD TRACER
FROM STEAM SUPPLY
A
D/P TRANSMITTER
PREINSULATED PARTIAL ENCLOSURE
TUBING BUNDLE A
STEAM TRACING
OF INSTRUMENTS
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 291 / 379
Revision : 2
RESID UPGRADING PROJECT
D/P TRANSMITTER
3/8" OD TRACER PARTIAL ENCLOSURE
TO THERMOSTATIC VALVE
NOTE:
INSULATE PIPING UP TO FIGURE 7
ENCLOSURE FOR HEAT CONSERVATION FLOW TRANSMITTER
LINE MOUNTED WITH HOLLOW STUD
NOTE: FIGURE 8
INSULATE PIPING UP TO ENCLOSURE PRESSURE TRANSMITTER
FOR HEAT CONSERVATION WITH HEAT TRANSFER BLOCK
STEAM TRACING
OF INSTRUMENTS
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 292 / 379
Revision : 2
RESID UPGRADING PROJECT
3/8" OD TRACER
FROM STEAM SUPPLY
COMPLETE ENCLOSURE
TRANSMITTER, CONTROLLER,
RECORDER, ETC.
FINNED HEATER
TO STEAM TRAP
NOTE:
INSULATE PIPING UP TO ENCLOSURE
FOR HEAT CONSERVATION FIGURE 9
COMPLETE ENCLOSURE
GAUGE GLASS
TO THERMOSTATIC VALVE
NOTE:
INSULATION FOR GAUGE GLASSES TO BE ONE FIGURE 10
HALF SECTION OF PIPE INSULATION CAULKED LEVEL GAUGE GLASS
WITH PLASTIC
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 293 / 379
Revision : 2
RESID UPGRADING PROJECT
STEAM TRACING
OF INSTRUMENTS
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 294 / 379
Revision : 2
RESID UPGRADING PROJECT
TO THERMOSTATIC VALVE
NOTE:
INSULATE INSTRUMENT FIGURE 11
AND PIPING FOR EXTERNAL DISPLACEMENT TYPE LEVEL INSTRUMENT
HEAT CONSERVATION
S TANDPIPE
NO TE:
INS ULATE INS TRUMENTS AND PIPING FIGURE 12
H EAT C O NS ERVATIO N MULTIPLE LEVEL INS TRUMENTS O N A VES S EL S TANDPIPE
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 295 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 REFERENCES
2.4 On all units, all instrumentation (mounted externally to the process line or
equipment) will be electrically heat traced for winterising applications when it is
labelled as “WISI” on the P&IDs or for maintaining the temperauture indicated in
the P&ID independent of the temperature objective. This criteria shall be
followed unless another definition will be indicated as mandatory by licensor.
Electrical heat tracing will be the first choice for winterization, compensation
heating and protection of the instruments. Contractor shall design heat tracing
for instrumentation according to the licensor specifications, TGPS-P1 (Section-
25) and TGPS-J1 (Section XVIIIA-XVIIIB-XIX).
2.5 DELETED.
R2 2.6 DELETED.
2.7 DELETED.
2.8 DELETED.
2.9 DELETED.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 296 / 379
Revision : 2
RESID UPGRADING PROJECT
3.0 GENERAL
3.1.1 Insulation of the instrument and/or the instrument piping to prevent heat
loss or gain.
3.1.3 Purging the instrument and/or the instrument piping to keep undesirable
liquids, solids or gases from entering the instrument.
3.1.4 Isolating the instrument from the process fluid through the use of a
diaphragm seal.
3.1.5 Isolating the instrument and the instrument piping from the process fluid
through the use of a sealing liquid. This method shall be applied instead
of the one stated in item 3.1.4 above.
3.1.5.2 Water may be used as a sealing liquid where the only purpose
is to protect against the entry of the process fluid. However, if
freezing temperatures are encountered, water seals must be
protected by tracing.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 297 / 379
Revision : 2
RESID UPGRADING PROJECT
3.2 The recommended method of winterization and protection for a particular type
of instrument in a specified ambient condition can be determined from the
following:
3.2.1 Fourteen (14) fluid types have been established and listed, covering
virtually all fluids normally encountered (Table I).
3.2.2 The various methods of winterization and protection have been listed
(Table II).
3.2.3 Two schedules cross-referencing fluid type and instrument type against
the recommended method of winterization and protection have been
devised. The recommended method is indicated by the upper case letter
or letters. The lower case letters represent alternate methods of
protection which will be selected, by TUPRAS, when the standard
method is not considered feasible. Schedule A is given for ambient
condition above 32°F (0°C ), Schedules B for 32°F (0°C ) and below.
* Apply tracer and insulation only when temperature can go below 60°F.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 301 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 GENERAL
1.1 Scope
1.1.1 Safety valves and rupture disks shall be designed in accordance with
the API ST 520 "Recommended Practice for the Design and Installation
R2 of Pressure-Relieving System in Refineries" and API STD 2000 Venting
Atmospheric and Low Pressure Storage Tanks" latest edition.
1.1.3 Safety relief valves shall be used to protect vessels or systems from
pressure above design or maximum allowable working pressure
( MAWP).
2.1 General
2.1.1 Safety valves body and rupture disks materials shall be in accordance
with line or vessel classification as defined in individual specifications.
2.1.2
Flanged connections and rating shall generally be as per line/vessel
specifications and according to API ST 526 “Flanged Steel Pressure
R2 Relief Valves” latest Edition. Not threaded connections shall be used,
neither for Thermal Expansion Valves. The connections must be in
accordance with ANSI Code.Where 125 Ra is specified for flange
surface finish, the range for acceptance shall be 63 Ra minimum to 250
Ra maximum. Finishes shall be judged by visual comparison with
surface finish roughness standards conforming to ANSI B46.1. It is the
Vendor's responsibility both to comply with the above finish
requirements and to assure that such flange finishes be protected from
damage during shipping, storage and installation. The preferred method
of protecting flange finishes is as follow:
R2 2.1.2 If NACE requirements apply, valve shall comply with NACE MR-0103
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 303 / 379
Revision : 2
RESID UPGRADING PROJECT
2.2.1 The following criteria have been taken into account for the valve
type selection:
2.2.2 Lifting devices shall be provided for pressure relief valves weighing
more than 45 kg.
R2 2.2.3 Trim material shall be stainless steel min. Suitable Trim for liquid shall
have to be considered, when applicable.
2.2.4 All calibration screws must be protected by a cap and provided with
R2 sealing to prevent temperings. Cap will be bolted for all valves, except
for ASME I, that it will be screwed.
2.2.6 Packed lifting lever, when requested (for water T>60ºC, air or steam),,
R2
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 304 / 379
Revision : 2
RESID UPGRADING PROJECT
must be provided on valves with closed bonnet for ASME VIII valves.
Lifting Lever will be Plain with Open Bonnet for ASME I valves. All Lifting
Levers shall be incast iron. Lever will not be considered for thermal
expansion valves.
R2 2.2.7 All valves with seal or balancing bellows must have a bonnet with
threaded vent holes 1/2" ANSI B2.1 NPT. with SS bug screen
2.2.8 All flanged valves shall be supplied with full capacity nozzle.
2.2.9 Valves with flanged connections must have the flanges integral with the
body. (not joined by welding or coupled with half threading). Only for the
R2 thermal relief valves (3/4”x1”), flanges will not be integral with the body
but they will be welded.
2.2.10 Heating connections for valves with jacketed body must be threaded
1/2" female ANSI B2.1 NPT.
2.2.11 Each valve shall have identification markings containing all data
required by the applicable ASME Code and/or API Standard 526 (ANSI
B146.1), latest edition.
2.2.15 Admissible losses with a pressure at he inlet equal to 90% of the tripping
value, a back pressure of 1/2" of H2O, and a drainage duct with an
internal diameter of 6 mm, are as follows:
- Spring material tobe selected according to the API STD recommendations for
the discharge temperature.
R2 2.2.18 Weather Hood and ½”NPT drain, will be included for all ASME I valves
2.3.1 The admissible tolerance of rupture disks is ±5% of the rupture value.
2.3.2 Each rupture disk must show in a suitable place the following data:
2.3.4 Burstıng dıscs shall be used with OWNER approval to protect vessels or
systems from high pressure above which these vessels and system
have been designed. They will be used either in series with relief valves
where necessary, or where conditions preclude the use of relief valves.
2.3.5 Bursting discs shall be mounted in holders designed to fit inside the bolt
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 306 / 379
Revision : 2
RESID UPGRADING PROJECT
2.4.2 Vacuum breakers shall be sized in accondance with API RP. 520 and
RP 2000.
3.1 General
3.1.1 Shop inspection is required. The Vendor shall carry out all inspection
and testing indicated below and provide all the certification there
indicated.
- Visual inspection for steel casting (Quality STD. for steel casting
according to CODE MSS-SP 55.
- Hydrostatic inlet body test (on valves with short nozzles only)
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 307 / 379
Revision : 2
RESID UPGRADING PROJECT
R2 - DELETED
- Popping test
- Marking check
- Painting check
R2 - DELETED
1.0 REFERENCES
All ILD's shall be multi-loop drawings. Each type loop shall have a graphic
sheet and one or more data tabulation sheets. Sheet #1 of any multi-loop
drawing, the graphic sheet, shall contain the graphic portion of the type
loop with identifying symbols for the variable information required to make
the type loop drawing correct for any specific loop. Subsequent data
sheets of any multi-loop drawing (sheets # 2,3,etc.) shall be tabular listings
of the information required for a specific loop; cross referenced to the
identifying symbols appearing on the graphic sheet (sheet #1) of that
multi-loop drawing.
Power wiring shall not normally be shown on ILD's. Power wiring is shown
on other contractor or Vendor-supplied drawings.
a. All devices within the loop and a clear identification of each component
(with set points if applicable);
b. The interconnection of the devices;
c. The location of each device;
d. The power sources and auxiliary systems required for the loop;
e. The control action of the major components.
LD's shall define the interlock, sequence on trip system logic. LD's shall not
define hardware on software. Identification of hardware or software shall be
made in other contract documents, but no specification of hardware or
software shall be made or implied on LD's
All the set-points values activating logic systems shall be determined on the
Logic Diagrams.
LD's shall be single sheet drawings whenever possible. When the logic is
too extensive to be shown on the largest standard drawing ( # 1 size), LD's
shall be shown on two or more equal-sized sheets.
2.4.1 Philosophy:
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 310 / 379
Revision : 2
RESID UPGRADING PROJECT
2.4.3 Format
They shall show the physical location of all equipment in the control room and,
if necessary, in the auxiliary equipment and computer rooms as well. The term
"equipment in this case refers to panels, racks, consoles, controllers, cable
trays and power panels.
a. A plan view (floor plan) of the rooms walls, doorways, windows, and non
removable equipment and furniture;
b. A sectional view showing access to the control room for equipment
installation;
c. All cable trays; and
d. Special section views or details required for correct equipment installation.
These one-line diagrams shall show the interconnection cables between major
devices within the control room and those between auxiliary equipment and
field devices. The control room one-line drawings are primarily used to show all
cable interconnections and their relationship to the equipment, as well as to
identify all of the equipment located in the control room and auxiliary equipment
rooms.
a. All major devices in the control room, auxiliary equipment rooms, and
computer rooms;
b. Schematics of all interconnecting cables;
c. Schematics of all control room cable trays;
d. Tables of all wires and cables; and
e. Wire and cable symbols, including wire size, type, number of conductors,
and length of runs.
These drawings provide an overall view of the location of field devices and
details about their installation.
a. Junction boxes;
b. Field devices;
c. Wire and conduit symbols, including wire size, type, number of conductors,
and length of runs;
d. Table of wires and cables, and
e. References to drawings and installation details.
Field pneumatic location and tubing plans are similar in purpose and content to
those of electronic diagrams preceding. All references to air manifolds, tubing,
and pneumatic devices shall be shown on an Instrument Location and Air Plan
Diagram.
The field air supply and pneumatic one-line drawing shall show in schematic
form the field air supply tubing and the pneumatic signal tubing. A pneumatic
one-line drawing shall show:
These detail drawings shall provide the information for exact mounting,
orientation, and connection of each device in the project. The actual details will
vary depending upon the hardware the project requires. Installation details
should contain all pertinent notes, diagrams of the installation, and lists of
materials and labor required.
2.11.1 Primary Drawings, showing the typical sketches the process primary
piping between instruments and process take off points containing the
materials list to be used.
Power Panel Schedules schematically show the power sources for all of the
different instrument systems. The information on this shall include:
a. Panel voltage and amperage rating, with frequency, phase and number of
supply wires;
Terminal arrangements will show the layout of any wiring terminal strip and the
interconnecting wiring. They shall be applicable for computer rooms, control
rooms, auxiliary equipment rooms, field terminal strips, control panels, and any
place elsewhere that multiple wires are admitted to an area and must be
interconnected to other multiple services. A typical terminal arrangement shall
include:
a. Type of terminal;
b. Number of terminals;
e. Spare wires.
This diagram is a specific form of a terminal arrangement. It will show the layout
of the terminal blocks and any interconnecting wiring or tubing. A junction box
interconnecting diagram will contain:
a. Type of terminal;
b. Location of terminals;
c. Number of terminals;
d. Wire or tubing numbers; and
e. All interconnecting wiring or tubing.
It shall contain all the parameters involved in the instrumentation scope. It shall
include:
13.2 Vendor/Contractor shall acquire and provide all information and complete parts
data packages for subvendors/manufacturer/suppliers, that are needed for the
procurement of operating spare parts. It is the Vendor/Contractor responsibility
to expedite the subvendor/manufacturer/supplier to provide the follow-up for
any missing or incomplete data.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 317 / 379
Revision : 2
RESID UPGRADING PROJECT
A data base programming shall be provided for each unit instrument tag (indication,
alarm, shutdown, transmitter, control valve, switch, converters, contact inputs/outputs,
etc.) containing below information as a minimum.
a. Device tag/model
b. Service
c. P&ID no
d. Line spec.
e. Range (rated/calibrated)
f. Set point (in terms of process variable)
g. Calibrated electronic switch set value
h. Junction box no.
i. Terminal wire in J.B.
j. Rack-in name and terminals
k. Rack-out name and terminals
2. CONSTRUCTIONAL SPECIFICATION
2.1 General
2.2 Valve
2.2.2 The valve, stem and yoke shall be able to withstand the actuator at
maximum delivery torque.
2.2.3 A corrosion resistant name plate shall be fitted to each valve including
requested identifications as per relevant valve specification.
R2 2.2.4 The wafer or lug type butterfly valves shall not be used in hydrocarbon
service however they should be used in systems which non-flammable
products unless specified by licensors.
R2 2.2.5 All CS Valve shall be rating min CLASS 300 up and including 6”.
2.3 Actuator
2.3.1 General
2.3.1.3 The valve supplier will be responsible for the correct operation
of the actuator and its sizing. The actuator shall develop a
torque which is sufficient to open and close the valve within the
limits set by the design of the mechanical parts of the valve
itself.
2.3.1.5 The actuator shall include a device to ensure that the motor
runs with the correct rotation for the required direction of valve
travel with either phase sequence of the 3-phase power supply
connected to the actuator.
2.3.1.6 It shall be possible to carry out the setting of the torque and
turns and configuration of the indication contacts without the
necessity to remove any electrical compartment covers. .(Non-
intrusive)
2.3.2.2 The operating speed shall be such as to give valve closing and
operating at approximately 10-12 inches per minute unless
otherwise stated in the individual specification. "Water hammer"
effect shall be avoided.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 320 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.3 Motor
2.3.3.1 The electric motor shall be Class F insulated, with a time rating
of at least 15 minutes at 104°C (40°C) or twice the valve
stroking time, whichever is the longer, at an average load of at
least 33% of maximum valve torque.
2.3.5 Gearing
2.3.5.2 Where the actuator operates gate valves or large diameter ball
or plug valves, the drive shall incorporate a lost-motion
hammer-blow feature.
2.3.5.3 For rising spindle valves the output shaft shall be hollow to
accept a rising stem, and incorporate thrust bearings of the ball
or roller type at the base of the actuator and the design should
be such as to permit the gear case to be opened for inspection
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 321 / 379
Revision : 2
RESID UPGRADING PROJECT
2.3.8.3 The electrical circuit diagram of the actuator should not vary
with valve type, remaining identical regardless of whether the
valve is to open or close on torque or position limit.
The necessary wiring and terminals shall be provided in the actuator for
the following functions:
2.3.13.3 The internal circuits associated with the remote control and
monitoring functions are to be designed to withstand simulated
lightning impulses of to to 1.1 kV.
2.3.16 Enclosure
2.3.16.3 The enclosure shall have an external and internal terminal for
earthing purposes.
3.0 INSPECTION/TESTING
3.1 Actuator
Each actuator must be performance tested, and individual test certificates shall
be supplied.
– Current at maximum torque setting
– Torque at maximum torque setting
– Flash test voltage
– Actuator output speed or operating time
– Checking of the stall torque
– Checking of the thermostat operating temperature
– Checking of the electrical circuit continuity and insulation
– Checking of the electrical and mechanical operation.
3.2 Valve
3.3 Certificates
Each actuator shall have a stainless steel plate showing the following:
2. CONSTRUCTIONAL SPECIFICATION
2.1 General
Shut-off valves shall be supplied as a single assembly, valve body and actuator
with torque, limit and other required switches,selonoid valves and other devices
already workshop calibrated and ready for on-line assembly and pneumatic
connection.
2.2 Valve
2.2.2 The valve, stem and yoke shall be able to withstand the actuator at
maximum delivery torque.
2.2.3 A corrosion resistant name plate shall be fitted to each valve including
requested identifications as per relevant valve specification.
2.3 Actuator
2.3.1 General
2.3.1.4 The torque requirements for the actuator at any point in the
stroke shall be 1.5 times the valve torque required to
operate at max differential pressure for general duty
application and 2 times for protective applications.
3.0 INSPECTION/TESTING
3.1 Actuator
R2
Each actuator must be performance tested, and individual test certificates shall
be supplied.
– Maximum torque
– Actuator output speed or operating time
3.2 Valve
3.3 Certificates
Each actuator shall have a stainless steel plate showing the following:
– Valve tag.
– Name of manufacturer, model and serial number.
– Actuator specification.
– Degree of electrical protection (Solenoids and switches).
This specification will be generally used and shall govern for all instrumentation
design.
The following standards and drawings will be considered, but will only be used to
amplify the data herein, or to supplement it where not adequately covered, or inferior.
Should any conflicts arise between this specification, TÜPRAŞ standards and
LICENSOR specifications they will be resolved by TÜPRAŞ after obtaining
CONTRACTOR comments.
SR.
NO. TOPIC
1 INTRODUCTION
2 ABBREVIATIONS
3 POWER INTERFACES
3.1 INSTRUMENT POWER SUPPLIES
3.2 LIGHTING SUPPLY/ANALYSER HOUSE SUPPLY
3.3 PACKAGE UNIT SUPPLY
3.4 ELECTRICAL HEAT TRACING TO INSTRUMENT LINES
5 MANAGEMENT SYSTEMS
6 E&I PLANT DESIGN INTERFACES
7 FIRE, SMOKE AND GAS DETECTION / WARNING SYSTEMS
8 EARTHING
9 AREA CLASSIFICATION
1.0 INTRODUCTION :
This Electrical and Instrument interface specification defines the basic division of
responsibilities between the two disciplines and involves both specialists engineering
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 332 / 379
Revision : 2
RESID UPGRADING PROJECT
In addition this specification indicates how to organize the different interfaces. The
definition of the split of work and division of responsibilities as outlined shall be followed
unless specific circumstances dictate otherwise. These deviations shall be properly
recorded and routed as job instructions within the discipline’s task forces for each
project. It is the responsibility of both the E&I lead engineers that the procedures as
described in this specification are followed.
Interface control documents shall be prepared by the agreed responsible discipline for
each interface activity (power supplies, process I/0’s, etc) at the start of the project.
These interface control documents shall be maintained, updated and communicated by
the agreed responsible discipline in pre-planned intervals during the development of the
project. This shall be approved by OWNER before finalization.
2.0 ABBREVIATIONS:
3.2 The various feeders of 220 V AC UPS supply from Electrical to I&CS Central
Cabinet rooms at diff. PDB shall be laid and terminated by Electrical dept.
3.3 Power supply distribution panels shall be the responsibility of Instrument dept.
3.4 In case sizing of power supply cable > 2.5 mm2, engineering, design and
supply by Electrical. The information and requirements for all I&CS users for
which Electrical shall provide the electrical power, shall be communicated by I&CS to
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 333 / 379
Revision : 2
RESID UPGRADING PROJECT
3.5 Electrical to take care about distribution of various feeders amongst various
PDB panels located at cabinet rooms in I&CS area and panel allocations, circuit
allocations, cable number and cable size (no of cores and cross section area; to
allow for terminal and gland ) based on the requirement on the “E / I&CS power
supply interface list”.
3.6.1 220 V A.C. Lighting for Level Gauges and various local panel as well complete
lighting of central cabinet room, central control room and central engineering
room shall be included in the “E / I&CS power supply interfaces list” with a
reference to the level gauge tag number for which the lighting fixture is
required.
3.6.2 For level gauge, supporting bracket (part of level gauge assembly) and fixture
specification is the responsibility of Instrument dept.
3.6.4 Distribution boards, if applicable, shall be located on the outside of the analyzer
house and shall be suitable for hazardous area classification of the plant.
3.6.5 In case of installation inside the analyzer house, this requirement can be
relaxed to general purpose.
3.6.6 No UPS supply shall be provided to analyzer house, local panel for any of the
instruments by Electrical. These shall be laid from the various UPS PDB panels,
located at central cabinet room by Instrument dept, as per requirement.
3.6.7 For Electric motor operated valves, position switches or position transmitters
shall be the responsibility of Instrument dept including supply of cables, glands,
terminations, etc.
3.6.8 Power supply to these MOV’s is the responsibility of Electrical, while the power
requirement of instruments attached to MOV shall be by I & C from the
DCS/ESD system ( if low voltage power
3.7.1 This shall be provided by I &C from the central PDB panel located at cabinet
rooms at only one location. Further sub distribution shall be carried out inside
the package unit by package unit vendor.
3.7.2 220 V A.C. power supply required for non-instrument purpose shall be provided
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 334 / 379
Revision : 2
RESID UPGRADING PROJECT
By electrical group, Electrical heat tracing power supply for critical instruments
according to process conditions (to be discussed during the detailed engineering
stage) shall be feeded by UPS .
4.1 Deleted.
4.2 The IFC will also be used for analogue signals (e.g. VSDS), Pump/Motor
bearing & winding temperature RTD sensors, and Current to Current transducer
installation. From this panel, all 4-20 ma or low voltage RTD signals shall be
wired to relevant I&C DCS panels.
4.3 Engineering, procurement and laying of cables and all termination from
MCC/Field Motors to IFC shall be carried out by Electrical for all these signals.
4.4 Configuration, interlock and control shall be designed by I&C based on process
requirement.
4.5 All potential free/dry contacts for pump / motor running indications, etc. from
MCC/SWB or VSD panels from electrical shall be wired to IRC and by
Electrical, including design, procurement and installation/laying of various
cables between MCC/SWB/VSD panels to IRC.
4.6 All Digital output commands from I&C DCS/ESD systems for various purpose
like Motor Trip/Auto-Manual Command( if used), Emergency Stop, etc. shall be
wired from respective DSC/ESD panels to IRC via interposing relays by I & C.
4.7 All Digital output commands from interposing relays meant for Electrical
MCC/SWB/VSD panels, etc. from IRC shall be wired from IRC panel to
MCC/SWB/VSD panel by Electrical. All cables shall be designed, procured and
laid by Electrical.
4.8 All IRC/IFC panels shall be of standard RITTAL make panels with 1200mm (W)
R2
x 800mm (D) x 2100 mm(H) size, with RAL7035 color and shall be located at
switchgear rooms in substations. within the premises of I & C. It is the
responsibility of I & C .
4.9 All cabling between the IRC/IFC and MCC/SWB or other electrical control
panels (i.e. VSDS panels), field Motors, etc. is the responsibility of Electrical.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 335 / 379
Revision : 2
RESID UPGRADING PROJECT
4.10 The measurement of power factor, frequency, power consumption and other
typical electrical signals to be processed / handled in instrumentation systems
is the responsibility of the Electrical discipline. I&CS will be responsible for
incorporation of these measurements into their system(s) from the interface
point (IFC) to respective ESD/DCS panel. Measurements shall preferably be
presented by Electrical as isolated analogue signals of 4-20 mA DC.
4.11 The monitoring and alarms annunciating associated with motors, switchgear,
transformers and any other electrical equipment, which are to be, annunciated
on instrument panels and/or in I&CS are the responsibility of Electrical. I&CS
will be responsible for incorporation of these alarms into their system(s) from
the interface point (IRC).
4.12 I&CS will be responsible for the detailed control, alarm, safeguarding
requirements as shown on the P&ID's and passing all signals required for
electrical control to the interface point as detailed for each Project.
4.13 I&CS shall include the tag number on the interface document
4.14 Instrument Loop Diagram shall show the complete loop inclusive a reference
drawing number with respect to the electrical wiring up to the point of interface,
i.e. IRC/IFC.
6.1.1 Each discipline is responsible to provide the required input of the cable
tray/ladder routing. The coordination with Piping, Civil, Structural and
Pipe-support with respect to main tray/ladder routing (e.g. space
management, road crossings etc.) will be done by Electrical for both
disciplines.
In general
All high voltage cables carrying Electrical control voltage
signal/current shall be routed in separate ducts/tray
All low voltage instrument signals like Run indication ( carrying 24 or
5 V DC interrogation voltage from DCS), low voltage electrical
signals like VSD 4-20 ma input/outputs, etc. shall be laid in a
separate tray/duct
All high voltage cables carrying Electrical control voltage
signal/current shall be routed in separate ducts/tray
All low voltage instrument signals like Run indication ( carrying 24 or
5 V DC interrogation voltage from DCS), low voltage electrical
signals like VSD 4-20 ma input/outputs, etc. shall be laid in a
separate tray/duct
6.1.3 All the trenches/cable trays between instrument cabinet rooms and
electrical substation/MCC room shall be sized in such a way to have
50% spare capacity for future use
7.0 EARTHING
7.1 The main earthing, involving static earthing, protective earthing, lightning
protection and instrument earthing systems are the responsibility of Electrical.
This is the responsibility of the Electrical discipline in close coordination with Process.
Area classification schedules, layouts and if required sections will be prepared, from
which both E and I&CS disciplines shall obtain the material selection requirements to
ensure suitability in the specific areas.
A common database will be filled with information from I&CS, Electrical and Process
Group, based on various process requirement, facilities and interlock/control necessity.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 338 / 379
Revision : 2
RESID UPGRADING PROJECT
1.0 INTRODUCATION
This specification and all additional documentation as listed under the appendices
covers the materials and methods to be followed by Contractor when installing and
testing instruments and associated cabling, tubing, tray work etc. in the entire project
3.2 Instrument Installation work as per OWNER’s specifications, drawings and good
engineering and construction practice.
3.5 Co-ordination (as and when required with OWNER/other contractors/ agencies
working in the same area)
3.6 Providing guarantees for the work carried out/ materials supplied.
3.7 Submitting the bar chart, progress report on weekly basis for the work done
during the period, Tag wise status for all tags of instruments list of all complete
section, manpower and construction equipments, deployment details and such
other activities as per requirements of OWNER. Submission of monthly material
appropriation statement for cables, tubing, piping materials fittings, indicating
the quantity issued and expended in standard performa.
3.8 providing proper tools, manpower (fully conversant with their job), consumables
required for carrying out and completing the job correctly and within the
scheduled time.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 339 / 379
Revision : 2
RESID UPGRADING PROJECT
4.0 STANDARDS
4.1 The instrumentation installation and calibrations works shall be carried out
generally in accordance with various international listed below but not limited to
the following.
R2
i. API-RP-551/552/553/554 Manual on installation of refinery instruments and
control system.
ii. ISA standards and practices for instrumentation.
. All engineering documents enclosed with this enquiry and those issued
subsequent to awarding of contract and during execution of contract.
. Manufacturers’ standards and practices.
4.2 The Contractor shall carry out the work in accordance with the
documents/standards /drawings listed herein, and in accordance with any local
‘Statutory Regulations’, client’s requirements and supplementary
documentation.
4.3 The Contractor shall instruct his staff. Skilled and semi-skilled, in the standards
required by the purchaser and shall ensure that only competent persons are
allowed to handle or work on instruments or instrument systems.
4.4 All tools including welding sets, gas-cutting sets required for carrying out the
work uninterrupted shall be provided by the Contractor. Contractor shall furnish
details of all calibration equipment, their makes, model, calibration certificate
etc. to OWNER before commencement of work. Any instrument without proper
and valid calibration certificate from a recognized certifying agency will not be
allowed to be used.
4.5 Deleted.
4.6 The working hours, holidays, weekly off etc., shall be followed as per OWNER’s
rules/ regulations. However, if required Contractor shall arrange their personnel
to work extra after office hours and / or in shifts and on holidays to meet project
completion schedule with the prior permission of OWNER site In charge.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 340 / 379
Revision : 2
RESID UPGRADING PROJECT
5.1 The Contractor shall be responsible for protecting installed equipment from
damage .
5.3 Only the best construction and engineering practices are to be used, and all
work must be done to the satisfaction of OWNER engineer who should be
consulted on any point requiring clarification. The Contractor is free to suggest
to OWNER engineer alternative methods for the execution of the work where
this would result in improvement.
5.4 The Contractor shall take adequate precautions during use and storage of gas
cylinders
5.4 Deleted.
5.5 Upon completion of the work, the Contractor shall promptly remove his
equipment and return to the relevant places and shall return any unused
material supplied by the engineer-in-charge. Finally the Contractor must clear
the site of all rubbish and scrap deposited by him to the satisfaction of the
engineer-in-charge.
5.6 The engineer-in-charge will with due reference to the relevant section of the
conditions of the contract lay down the safety regulations for the site and
Contractor shall ensure all his personals understand and comply with this
regulations. For working at height Contractor shall provide safety belts, ladders,
proper approach, etc at its own cost.
5.7 The Contractor shall prepare a comprehensive schedule for carrying out the
installation before commencement of actual work.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 341 / 379
Revision : 2
RESID UPGRADING PROJECT
6.1 The instrumentation erection work covers various jobs listed under the various
schedules. However to ensure proper execution and completeness of the
instrumentation work any or all of the following shall also form the part of the
scope and shall be covered in the quoted rates.
6.3 Fabrication of seal pot/siphon/drain pot as per standards. Filling of seal pots
with filling liquids as per instructions from engineer-in-charge.
6.7 Minor civil works like chipping of pavements & grouting on the pavements the
instrument panels/supports/stanchions, & chipping, refilling & finishing of the
pavement for conduits.
6.8 Sealing of cables/tube entries into the control room after laying and testing of all
tubes, cables etc.
6.11 Painting of all structural supports for trays, pipes, junction boxes, instruments,
ducts, etc. as per painting specifications.
6.13 Coordination with mechanical and other sub contractors for proper installation
of lines/vessels/ equipments mounted instruments like control valves, orifice
assemblies, mass flow meter, level transmitter, level gauges, level switches,
other type of flow meter, flame arresters, breather valves etc., which involves
removal of instruments, disconnection of tubes / cables, reconnection for
alignment and proper installation etc. These instruments will be required to be
uninstalled and reinstall before final installation for flushing.
6.14 Drilling holes and making cut outs as required on panels, shutdown cabinets,
power supply cabinets, control panel pneumatic enclosures, junction box etc,
for cables/ multi tubes/glands/ grommets.
6.15 Grounding of shield of all shielded cables to respective instrument earth bus
provided in the control room/ local panel/ thermocouple head/ junction boxes.
6.16 Laying and termination at both ends between instrument earth buses provided
in the control room/ local panel to instrument earth pit provided by others.
6.17 Progress Reports: Contractor will provide progress report on weekly basis for
the work done during the period. Tag wise status for all tags of instrument list of
complete PROJECT area shall be prepared. Submission of monthly material
appropriation statement for cables, tubing, piping materials fittings, indicating
the quantity issued and expended in standard Performa.
6.18 Deleted.
6.19 Deleted.
6.20 Deleted.
6.21 Deleted.
6.22 Deleted.
6.23 Deleted.
6.24 Deleted.
6.25 Deleted.
6.26 Installation and terminations of tubing, cables etc. For analyzers (from field to
analyzers house and within analyzer house) and its accessories like sample
cooler etc.
6.27 Deleted.
6.28 Deleted.
6.29 The Contractor shall be responsible for the supply of installation materials as
detailed elsewhere in this document.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 343 / 379
Revision : 2
RESID UPGRADING PROJECT
6.30 The installation will be tested in accordance with the instrument installation
testing procedures given elsewhere in this specification. If, however, others
carry out the testing, the Contractor shall ensure that instruments are
adequately protected during flushing and pressure testing.
6.31 The Contractor shall be responsible for the supply and cost of all replacement
material and labor necessary to rectify faults which show up during instrument
installation/ testing / commissioning, provided such faults are due to faulty
workmanship of faulty materials in the Contractor’s scope of supply.
6.32 The Contractor shall be responsible for the expediting and inspection of all
materials in his scope of supply. However, Owner reserves the right to expedite
and inspect such materials. OWNER reserves the right to reject any material
supplied by the Contractor if not found technically acceptable or of specified/
required quality.
6.33 The Contractor is expected to hand over a fully operable system and any
defects of design omission or discrepancies found which would impede this
achievement must be brought to the attention of OWNER representative
without undue delay.
6.34 The main instrument air header will (unless otherwise specified) be installed by
others as a part of piping upto and including the take off point (including the
isolation valve) on air header. Generally the Contractor shall be responsible for
the tubing downstream of a given isolation valve and this valve together with all
upstream pipe work will have been previously installed and tested by others (as
a part of piping work).
6.35 The installation of orifice plate assemblies, safety valves, breather valve, flame
arrestor, rupture disc, control / switching valves, mass flow meter, Rota meters,
sample connection points up to and including the first isolation valve for flow,
pressure, analysis, provision of flanged connection for temperature and any
other in-line equipment will be carried out as a part of piping work by a
contractor or agency responsible for piping.
6.36 All welders deployed on the job by the Contractor shall be approved by
OWNER. Any expenses to be incurred for welders’ qualification as per
requirement of OWNER shall be borne by Contractor.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 344 / 379
Revision : 2
RESID UPGRADING PROJECT
The instruments coming in the package items, apart from above all items
mentioned at … to …, additionally the Contractor scope shall include the
dismantling of all the instruments for the calibration & refixing of the instruments
at their respective location with proper electrical connections.
9.1 The list of drawings and documentation to be provided to Contractor shall include
Schematic hook-up drawings, indicating the typical arrangement for air supply
and process impulse tubing for each instrument or group of instrument together
with tag numbers and installation materials. Related isometric numbers will be
shown on hook-up diaghrams.
The responsibility of Contractor for the supply of all materials will unless otherwise
specified be as follows, but not limited to the
10.1 Materials to be supplied by the Contractor at his own cost, as part of these
specifications.
10.2 The supply of consumables like Teflon tape, insulation tape, welding rods, gas
cutting sets, piping compound, nitrogen in cylinders etc.
10.3 Bolts and nuts for supports, U bolts with nuts, clamps for tubes and pipes,
anchor bolts for panels, expansion bolts of various sizes for fixing to concert
structure.
10.4 All industrial gases like oxygen, acetylene or inert, and all types of electrodes,
brazing rods, flux etc for welding purposes, with necessary facilities for testing
the welded joints.
10.6 All structural supports for instruments (including 2” pipe with SCH40 as a min.),
JB’s, Trays etc. Including their supply and fabrication including painting shall be
in scope of Contractor.
10.7 All materials for minor civil work like grouting etc.
10.8 Deleted.
10.9 Accessories like tees, bents, crosses, bolts, supports etc as required for
instrument to JB, JB to main branch cable tray, for sampling tubing from field to
analyzer house and within the analyzer house, small branch cable within
analyzer house as required.
10.12 Silicon carbide paper, painting brushes, yellow cloth, waste cotton for cleaning,
wire brushes, paint brushes, etc.
10.15 Araldite, M-seal, locktite, quick fix, rubber compound, silicon rubber tube.
10.16 Deleted.
10.17 Any other items not specified, but required for completion of the job.
10.19 The Contractor shall procure the various installation materials from reputed
vendors and such materials shall be of good quality. OWNER reserves the right
to inspect and approve such materials.
11.2 The Contractor shall then take it from where it is stored, lift it into position and
ensure it is leveled, plumbed and firmly secured.
11.5 Instruments shall not be bracketed directly off process lines except where
specified by engineer-in-charge.
11.7 Local instruments with the exception of those on lines and vessels shall be
mounted with the centerline at approximately 1.2 meters above the platform or
floor in a position accessible for operation and maintenance.
11.11 All cable entries to instruments shall be preferably from bottom. If bottom entry
is not possible due to any reason, the cable entry shall be from side.
11.12 The instrument already mounted on the equipment shall be removed by the
Contractor for the calibration check and re-fix back.
11.13 The case of the Instrument shall be earthed by earthling wire to the nearest
earth bus bar provided by others for the safety reasons.
12.2 Pipes/ Tubes shall be bent using pipe / tube bender; any hot bending will be
totally rejected. These shall be cut using pipe / tube cutting devices. Hot cutting
will not be allowed. Cutting of the tubes/tubing by hacksaw shall not be
acceptable.
12.3 Pipes or tubes installed, but not connected, shall have the ends closed in an
approved fashion to, prevent the entry of foreign material. For a period of up to
one week, adhesive tape may be used, for a longer period caps or plugs shall
be used.
12.4 Where instrument tubing is run parallel to each other, joints should be
systematically staggered and neatly offset. There must be at least two pipes /
tubes between adjacent joints.
12.5 Threaded fittings will have their threads specified in the purchaser’s
documentation. All threaded joints shall have Teflon tap as sealing medium
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 350 / 379
Revision : 2
RESID UPGRADING PROJECT
12.6 Where compression fittings are used, the fittings shall be installed in strict
accordance with the manufacturer’s recommendation. Due care shall be taken
while handling the compression fittings to avoid loss of ferrules.
12.7 Where stainless compression fittings are used, the Contractor must ensure that
stainless steel nuts and olives are fitted unless otherwise specified by engineer.
12.8 Any discrepancies between the materials / fitting specified, and the material /
fittings provided shall be brought to the notice of the engineer-in-charge without
delay.
12.9 The number of joints in the tubing shall be kept to a minimum consistent with
good practice and also to keep the wastage to the minimum.
12.10 Sufficient flexibility shall be provided in meter leads, air supply and tubing lines
to allow for movement (e.g. expansion, of the lines or the equipments to which
connected.)
12.11 Horizontal runs of pipes and tubes shall have pipes / tubes laid vertically one
above the other as far as possible and shall be run with the minimum number of
changes of direction consistent with good practice and neat appearance.
12.12 All pneumatic signal tubing shall be cleaned by blowing through with instrument
air prior to installation.
12.13 Single tubing shall be run in such a manner as to give the maximum protection
against mechanical damage.
12.14 Where permanent enclosure trunking or conduit, etc., are left, space for tubes
to be pulled at some future date, a galvanized draw wire of adequate size shall
be left in the enclosure.
PROCESS TUBING
12.15 Impulse lines shall be kept as short as possible consistent with good practices.
12.16 All impulse tubing shall, in general, be run with a slope of not less than 1 in 12
except where otherwise specified. The slope of the impulse tubing shall be up
from the tapping point for gas service unless special provisions are made for
venting and draining.
12.17 S.S. tubing shall be joined by compression fittings, or by screwed connections
as shown on the instrument hook – up drawing.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 351 / 379
Revision : 2
RESID UPGRADING PROJECT
12.18 Instrument air and signal tubing shall be adequately supported wherever
possible to prevent any mechanical damage.
12.19 Angle iron or 50 mm perforated trays shall be used for continuously supporting
four or more SS tubes and the tubes shall be secured to the tray at 0.5 meter
intervals by suitable Uclamps.
12.20 The tray must be provided with suitable supports to prevent sagging.
13.1 The Contractor must ensure that whenever an electrical specification is issued
the appropriate sections shall be read in conjunction with these specifications
and any omission or ambiguities should be resolved with the engineer-in-
charge.
13.2 The cable installation drawings and documentations will normally specify or
incorporate regulations for the electrical noise pick up. However following
general rules apply,
13.3 Parallel runs of the instrument cables and power cables should be avoided
where parallel runs must be made cable spacing specified in the documentation
must be maintained.
13.4 Where instrument and power cable cross in close proximity the cross shall be
made at right angle.
13.5 Multi core / multi pair cables shall be cut after the exact site measurements are
taken between ends the cable drum schedule shall be followed before cutting
the length to avoid any wastage. Drum schedule shall be provided by Owner
during execution.
13.7 All cables shall be terminated at junction boxes and instruments by proper
glanding, using proper size crimping lugs of approved design and with
appropriate crimping tools.
13.8 Qualified electrician who is well experienced in this type of work shall do the
junction box or instrument wiring connections in an approved manner.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 352 / 379
Revision : 2
RESID UPGRADING PROJECT
13.9 Where conduit terminates at cabinets, terminal box, it shall be secured with a
lock nut, brushed and ferruled in an approved manner. Sharp edges shall be
removed and conduit not otherwise connected shall be terminated in smooth
brushes.
13.11 All cable shall be tagged with permanently punched strip of aluminium and
identified as given in cable schedule. The cable tag shall be on instrument side,
junction box side, & control room panel. The aluminium strips shall be securely
fastened to cables using SS wires. Cable identification tags shall be provided
as following :
at an interval of 10 mtrs for cable laid above ground. at an interval of 5 mtrs. For
cable laid under ground.
13.12 Shield, drain wire, terminated in junction boxes or earthling strips shall be
provided with PVC sleeve cover. This shall be supplied by Contractor.
13.13 Yellow color continuous Ferrules sleeve (with black font) of proper size shall be
provided for each terminated wire as per termination drawing. Double cross
ferruling philosophy shall be used at all locations, which indicates
sour/destination side detail at each end.
13.14 Spare wires shall also be ferruled / tagged and neatly dressed.
13.15 Cables shall not be bent to radius less than the manufacturer’s
recommendations (i.e 10 times the cable O.D).
13.16 All copper cables shall be terminated at junction boxes and instruments by
proper glanding with PVC hood covering.
13.17 Clips and saddles securing to steelwork or tray shall be of aluminium. These
clips shall be spaced at 0.5-meter intervals.
13.18 The cable laid on the cable tray shall be properly dressed in such a manner that
the crossing of cables shall be minimized. The cable on the cable tray shall be
clamped with strip at every 0.5 mtrs in vertical tray & 2 mtrs in the horizontal
cable tray.
13.19 Deleted.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 353 / 379
Revision : 2
RESID UPGRADING PROJECT
14.0 PAINTING
14.1 All ferrous materials for brackets and supports supplied by the contractor and
other material not already protected in an approved way shall be cleaned and
primed before erection with primer as per painting specification given by
OWNER.
14.2 Painting of instrument supports, cable tray supports, all structural, all structural
supports shall be as under
14.3 The surface to be painted shall be throughly cleaned with wire brush/ sand
paper to remove all scales.
14.4 After cleaning, one coat of red oxide zinc chromate primer shall be given and
allowed to dry.
14.5 One coat of final red oxide shall be applied prior to first coat of paint.
14.6 Final coat of color shall be given before handing over the plant / commissioning.
14.8 The primer & final paint shall be of first class quality. The paints shall be confirm
to the specifications given above & first class quality in their products range of
any of the following manufactures
15.1 All site mounted instruments, cables, junction boxes, air header isolation
valves, tubing’s and wiring termination, shall be labeled or tagged in a manner
approved by Owner.
15.2 All cable termination shall be identified by ferrules. The ferrules shall be
continuous sleeve type, white or yellow PVC with black lettering. Contractor
shall supply ferrules of different sizes based on the cable sizes.
16.0 TESTING
All the necessary test equipments for performing the following tests shall be provided
by the instrument installation contractor. The instrument installation contractor shall
furnish a list of test and calibration equipments with make / model no that will be
provided by him. other types of test equipment shall be provided by contractor, if
required in order to carry out work as per specifications. Owner shall check the
calibration of the test equipments of contractor
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 354 / 379
Revision : 2
RESID UPGRADING PROJECT
16.1 All pneumatic signal lines shall be disconnected and blown through with
instrument air for 15 minutes to remove traces of oil, dust and moisture. Air
manifolds shall also be blown with instrument air after installation.
16.2 All instrument air mains shall be isolated from the instrument and pressurized
pneumatically, 1.5 times maximum working pressure and isolated from the
source of pressure. The pressure shall not fall by more than 0.1kg/cm2 in ten
minutes. Also leak test by soap solution shall be performed in presence of
OWNER on each joint, which are to be leak tested.
16.3 All impulse lines shall be isolated from the instrument and hydraulically tested
to 1.5 times the working pressure and isolated from the source of pressure. The
pressure shall not fall by more than 0.1 kg/ cm2 in ten minutes.
16.4 All thermocouple, electric, power, and electronics instrument wiring shall be
tested for resistance between conductor and earth and for insulation between
conductors with a potential of 500V /1.1KV DC. This test shall be carried out
with all conductors disconnected except from the test instruments. The
resistance shall not be less than 10 M ohm.
16.5 Transmitter connection to the correct receivers and polarity shall be checked.
16.7 The written results of the test in duplicate for retention by owner/ Engineer in
charge shall be approved by the engineer in charge.
16.8 The instrument installations contractors are responsible for supplying the
necessary test equipment and reasonable evidence of the satisfactory condition
of this shall be provided, if required.
16.9 All errors all faulty workmanship discovered during this testing or during
subsequent testing and commissioning shall be corrected by the instrument
installation contractor at his cost.
16.11 All cable connections at field instruments and control rack terminals shall be
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 355 / 379
Revision : 2
RESID UPGRADING PROJECT
checked for:
• Correct polarity
• Correct Numbering
• Proper jointing / termination using copper lugs and PVC sleeves
• Cable continuity check: This check shall be done from junction box to
individual instrument under supervision and as per the instruction of
OWNER.
16.12 All cables shall be checked for proper clamping / support and shall be neatly
dressed.
16.13 Solenoid Valves shall be checked for operation by energizing them and
checking their operation. Suitable power source (as per the voltage value and
type of voltage specified on the nameplate of the solenoid valve.) and suitable
voltmeter shall be arranged by Contractor for this purpose.
16.14 All control valves prior to stroke checking shall be externally cleaned
thoroughly.
16.15 The stroke of the valve shall be checked for opening & closing with 25% steps
16.16 Any adjustments required for obtaining full stroke & reducing hysteresis shall be
carried out.
16.17 Each on / off valve shall be checked by closing/ opening the valve a few times
(through respective solenoid valves) and noting the time of travel.
16.19 Temperature Elements shall be checked for continuity and resistance value (at
0%, 25%, 50%, 75%, 100% of the range and vice versa) using a suitable
temperature bath. Temperature transmitters (if any) shall be checked for
operation.
16.20 The level switches (external cage type) shall be set by filling the cage with
water to the desired alarm / trip level, while setting the switch, it shall be
ensured that the micro switches do not reset for full rate travel of the float.
16.21 The Contractor shall be responsible to keep proper record of all the tests
performed and these shall be approved by Owner. These records shall be
finally submitted to Owner.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 356 / 379
Revision : 2
RESID UPGRADING PROJECT
17.1 Loop test shall be performed after calibration of all instruments and leak test of
signal lines. Loop test are conducted to check the functional performance of all
element comprising the loop, thereby ensuring proper conditions and
operations. Instrument installation contractor should bring all the field cable and
terminate in the termination cabinet in the rack room. The loop testing shall be
done by Contractor with complete co-ordination with DCS/SIS supplier and
OWNER in presence of OWNER Engineers / Technicians.
17.2 Loop testing for all control loop shall be generally by simulation of process
condition and shall fix points namely 0%, 25%, 50%, 75%, 100%,75%,50%,
25%, 0% of full scale inputs. Detailed procedure shall be submitted to Owner in
charge for approval before proceeding with the loop testing.
17.3 In case of shutdown system field / receiver pressure transmitters are simulated
for abnormality by disconnecting the wires at terminal and function of all
associated system are checked.
17.4 After the loop testing is completed, the contractor shall connect back any
terminations and connections removed for loop test./ marking shall be done on
“loop checked” instruments.
17.5 A loop shall be considered as handed over only after all the tests are over in
that particular loop are completed and certified by Engineer in charge, in
addition to loop sheets being duly filled in all respects and approved and
accepted by Engineer in charge.
17.6 Final certified loop sheet should be submitted in two copies to OWNER.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 357 / 379
Revision : 2
RESID UPGRADING PROJECT
SR
TOPIC
NO.
1 SCOPE
CLARIFICATIONS OF THE
2
INSTRUMENT DELIVERABLES
INSTRUMENTATION INTERFACES
3
WITH OTHER DESCIPLINES
INSTRUMENTS DELIVERABLES
4
OVERVIEW LIST
1.0 SCOPE
2.3 The CONTRACTOR shall provide at the start of the project the
design/drafting specification applicable for the project . The OWNER or his
representative will review these specifications. The specifications are as a
minimum but not limited to :
- Instrument symbology and identification specification as per ISA
- Instrument indices and nomenclature specification as per ISA
- Instrument Tag naming philosophy
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 359 / 379
Revision : 2
RESID UPGRADING PROJECT
NOTES :
1. Preliminary calculations are by the Process department. Final calculations
for control valves and safety/relief device may be replaced by seller
calculations.
2. Instrumentation shall provided Process with the selected CV value of
control valves for final relief valve load calculations.
3. All sizing programs shall be provided to owner.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 360 / 379
Revision : 2
RESID UPGRADING PROJECT
The instrument index list instruments and/or functions that are required for
control and safeguarding of a process plant. As such, it functions as
instrumentation ‘’ scope of plant ‘’ and is the basic document next to the
P&ID’s from which the instrumentation work is executed. No instrument tag
numbers shall exist that are not listed in the instrument index. It includes as a
minimum the following, but not limited to the following.
- Tag
- Description
- Service
- Line no
- P& I no
- Loop number
- Location
- Type of instrument
- Make and model of instrument
- Range of instrument
- JB schedule
- Cable schedule
- Alarm/trip setting
- Control valve acting
- Interlock number
- Loop sheet no
- Vendor Name
- POR No
etc…
Note : timer settings are either provided in the narratives by the process
department or default.
2.8 REQUISITION
The requisition covers the requirements for purchasing of equipment,
materials and related services. The requisition shall consist of the following
attachments, But not limited to the
Notes :
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 362 / 379
Revision : 2
RESID UPGRADING PROJECT
This drawing will show the physical location and their interrelation on the
signal type/carrier level of above mentioned hardware . It is assumed that the
CONTRACTOR shall develop the instrument system block diagram.
The PCD elaborates the functionality as shown on the P&I D’s and gives a
graphical overview of the functions of a loop or a combination of related loops,
their physical location and their interrelation. It is assumed that for consistency
purposes the CONTRACTOR shall develop the loop type templates listing
that are used to populate the instrument data base ıntools.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 364 / 379
Revision : 2
RESID UPGRADING PROJECT
DCS Graphic display information shall be provide with highlighted P&I D’s
showing the main process equipment to be implemented in the DCS displays.
Implementation shall be based on the DCS configuration and man
machine interface convention by DCS supplier. It is assumed that the
CONTRACTOR together with the Plant Automation System Vendor shall
developed the graphics based on the graphic design philosophy developed
by the CONTRACTOR.
The instrument installation schedule shall contain all tag numbers of field-
mounted instruments with relevant PI&D. number , location of instrument
,installation drawings and requisition number , which shall be extracted from
the instrument index (index data base ). Instrumentation shall prepare the
instrument installation index.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 365 / 379
Revision : 2
RESID UPGRADING PROJECT
The instrument field location layout drawing shall be based on the plot plan.
The plot plan shall be divided instrumentation logical parts with preferable a
scale of 1:50 and a drawing size of A1. The layouts shall show the location
of instruments, local panels, cabinets , junction boxes and air header systems.
Similary piping will also model displacer instruments, capacitive probes, tuning
forks, servo level instruments, level gauges, thermowells, analyzer probes and
orifice flanges. For all in-line instrumentation initially when the
seller/manufacturer and model are not yet selected instrumentation will
provide dimensionally data based on generic catalogue data and/or
preliminary sizing calculations. The quality of the dimensional data will be
improved by instrumentation once the seller/ manufacturer and model are
selected. Finally instrumentation will provide dimensional data based on the
approved seller data.
The instrument field cabling layout shall be based on the plot plan. The plot
plan shall be divided in to logical parts, with a preferable scale of 1:100 . The
layout shall show the location of local panels, cabinets, junction boxes, cable
main trenches/trays, cables, etc. Local panels, cabinets and Junction boxes
shall be indicated by means of an identification number. Instrumentation
shall use ıntergraph’s raceway module to support PDS areas in modelling
all space trays >=300 mm . Instrumentation shall prepare the instrument
field cabling layout . Conduit/tray installation details and drawings are by the
instrument installation contractor. Trenches are not foreseen.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 366 / 379
Revision : 2
RESID UPGRADING PROJECT
The control room and instrument field auxiliary building equipment layout
shall show the location and main dimensions of control panels and/or
consoles, telecommunications equipment, and if applicable , computer room
equipment, fire alarm panel, semi graphics, etc. Consoles will show monitors,
keyboards, trend recorders, radio and communication systems, etc. In case
other rooms are shown on the layout the related equipment will be shown too.
The basis is the hardware , as shown on the instrument system block diagram,
and the sizing, based on the hard I/O count. The CONTRACTOR shall
prepare the Instrument Control Building And Instrumentation Field Auxiliary
Building Layouts. Instrumentation provides preliminary dimension information
for any instrumentation in the control building.
The cable layout for control rooms, technical/auxiliary/rack rooms shall show
the route of the cables between cabinets, racks, panels, consoles, etc. Also
the route of the in coming field cables will be shown. The contractor shall
prepare the Instrument Control Building And Instrumentation Field Auxiliary
Building Cable Layout.
On the earthing layout the several earthing systems shall be shown. For
safety earth, instrument earth, computer earth, etc. All earthing systems will
be connected to a bus bar; each system will have its own bar. The
connection between the bus bar and the earthing electrode will be the
responsibility of the electrical discipline. The CONTRACTOR shall prepare the
Instrument Control Building And Instrumentation Field Auxiliary Building
Earthing Layout.
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 368 / 379
Revision : 2
RESID UPGRADING PROJECT
Fire and gas detection layout is based on the plot plan. The plot plan shall
be divided in logical parts with preferably a scale of 1:50 and a drawing size
of A1. The layout shall show the location of detectors, manual call points
installation, status lamps, alarm siren, junction boxes, panels, etc. Each
instrument will be indicated by means of a symbol. Fire and gas panels,
cabinets and junction boxes will be indicated by means of a rectangle and an
identification number. A layout with general notes, symbols and reference
drawing numbers shall show all general notes and symbols of fire and gas
detection layouts and further a listing of all relevant installation drawings.
Instrumentation will prepare the fire and gas detection layouts.
Fire and gas detection installation detailed drawings shall show typical
mounting and electrical installations, such us detector installations, horn
installations, manual call points installation. Instrumentation will prepare the
fire and gas detection installation details.
Instrument cable list shall show all instrument cables. Furthermore, the
cable list shall show the cable number, type, length and size of cable, type of
signal, color of outer sheathing, description of run(from-to) requisition and item
number, drum number and a remarks column. Instrumentation shall prepare
the instrument cable list.
3.3 MECHANICAL
3.3.1 GENERAL
3.3.1.1 Specification for package unit instrumentation
Instrumentation prepares a general specification for
package unit instrumentation based on the general
instrument specifications provided in this document. This
specification covers the minimum requirements for the
engineering , design, supply and installation of
nstrumentation equipment and commodities forming part
of package units. Electrical instrument installations shall
also follow the requirements set forth in the specification
‘’Electrical requirements for package units’’.
3.3.1.2 Complex Package
Instrumentation prepares for each inquiry requisition for
complex package units a specific. Technical description
and specification including instrument data sheets. The
instrument data sheets shall be completed by the selected
seller.
Note : scope split for filling-in the instrument datasheet
shall be agreed upon in co-operation with the
seller.
3.4.1.2 Foundations
In addition to the building information instrumentation provides
to civil/structural Location, size and weight of instrumentation
supplied, pre-fabricated structures like analyzer houses/sheds
and free-standing local panels.
3.5 ELECTRICAL
3.6 SUBCONTRACTING
3.7 OPERATIONS
3.7.1 CONSTRUCTION
3.8 SCHEDULES
Cable lists
Instrument, thermocouple signal cables and instrument power cables
Instrument fittings, tubings, valves and manifolds
Logic diagrams
Terminal drawings and wiring diagrams
Terminal strip connections
One line loop diagrams
Analyzers
Sequential diagrams
DCS&ESD I/O List and database
DCS graphic display information.
DCS&ESD system architecture
DCS&ESD typical loops
DCS&ESD loop wiring diagrams
Instrument installation schedule
Instrument List
Instrument piping specifications
Comments to typical piping details
Instrument field location layout (electronic and pneumatic instrumentation )
Instrument location layout for field ESD-switches
Analyzer drawings
Material Requisitions
Material Requisitions for Order (MR for Order)
Technical evaluation of Bids
Vendor Drawings, datasheets, documentation, calculations, etc. checks, comments,
finalization with Vendor and approval.
Vendor quotations review, comments, checks, direct contact by e-mail and/or phone
correspondences and meeting with vendors, preparation of technical bid evaluations of
vendors, conditional letters to vendors, revision and finalization of the vendor
quotations.
Vendor fabrication and final documents, drawings approval.
Instrument field cabling layout
Instrument process piping details
Instrument air piping details
Site surveys and supervision during detail engineering stage, construction and
commissioning stage
Instrument steam tracing details
Instrument installation details
Instrument nameplate schedule
Instrument local panel layout
Instrument rooms equipment layout
Instrument rooms cable layout
Instrument rooms earthing layout
Instrument electric supply
Control room and technical room layouts
Electric-inst. Signal list
Instrument Layouts
Section : TGPS –J1
Date : August, 2010
Turkish Petroleum Refineries Co.
İzmit Refinery Page No : 379 / 379
Revision : 2
RESID UPGRADING PROJECT