0% found this document useful (0 votes)
62 views

Reinforcement Checklist

this is reinforcement checklist checked by client and report to start a reinforcement job

Uploaded by

surenbhunia
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

Reinforcement Checklist

this is reinforcement checklist checked by client and report to start a reinforcement job

Uploaded by

surenbhunia
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION CHECKLIST

Name of the Project: Oxygen Plant 1250-TPD, ASU, Sail DSP


Location of Inspection : Cold Box and Compessor Area Piling
Name of the Contractor : M/s Nirman Construction
Name of the Client : Air Water India Pvt. Ltd.

STEP C : CHECKLIST FOR REINFORCEMENT WORK


Sl No.
CHECK ITEM Reference YES NO NA Comments
1 Material of re-bar and re-bar processing:
i. Re-bar strength and ductility (grade) are as per design
and specifications (supported by Test Reports).
ii. Hooks and bends are provided appropriately as per
specificaton.
iii. Rebar is free from any crack or injuries defect.
iv. Samples are taken and sent for testing.
v, Brand of reinforcement is within CE's schedule.
2 Re-bar installation:
i. Size (Length and Diameter) of re-bar are as per
drawing.
ii. Number of re-bar are as per design.
iii. Spacing of re-bar are as per design.
iv. Main re-bar dirction are as per design instruction.
v. Re-bar is tied with 24G wire (in each and every joint).
vi. Splice length is accurate.
vii. Horizontal alignment of re-bar is proper.
viii. Verticall alignment of rebar is proper.
ix. Clear cover is set properly (Saline & none-saline).
x. Mortar Blocks is set properly.
xi. Re-bar is cleaned from all loose scale, dirt, and paint
oil, grease or other foreign substance.
3 Special check for footing:
i. Vertical rods from pile are embeded in the footing as
per drawing.
ii. Development length, Hook, splices etc are as per
specification.
iii. Bottom layer re-bar direction is OK as per design.
iv. Top layer re-bar (both direction) for combine footing/ pile
cap are placed properly as per design
v. Seperator is provided properly between top and bottom
re-bar.
4 Special check for Column:
i. Location of splice is at the middle of column.
ii. Tie spacing is maintained properly.
iii. Closer tie spacing near splice zone is as per design.
iv. Inner tie is provided as per design.
v. Not more that 50% rod are spliced at any section.
5 Special check for slab and beam:
i. Stirrup spacing is proper (beam).
ii. At the Beam-column joint, ties are provided properly as
per drawing.
iii. Length of extra top bar from column/beam face is as
per design.
iv. Crank position of slab reinforcement from beam face is
proper.
v. Re-bar at middile position for torsion is set proper (for
beam).
vi. Top re-bar lapping is provided at the center of beam.
vii. Bottom re-bar lapping is provided as shown in the
drawing.
viii. Corner re-bar for slab is provided properly.
ix. Seperator is provided properly between two layer of re-
bar.
x. Development length and seismic stirrups are placed
properly.

Contractor Representative Signature