Index: Case Study: Biomass in India
Index: Case Study: Biomass in India
INDEX
1. INTRODUCTION
1.1.1. National electricity policy 2002..2 1.2. Achievement....3 1.3Installation cost.3
References..14
Page 1
CASE STUDY: BIOMASS IN INDIA 2011 BIOMASS AS A RENEWABLE ENERGY SOURCE IN INDIA 1. INTRODUCTION
Biomass has always been an important energy source in India. Although, the energy scenario in India today indicates a growing dependence on the conventional forms of energy, about 32% of the total primary energy use in the country is still derived from biomass and more than 70% of the countrys population depends upon it for its energy needs. The Government of India, through its Ministry of Non-conventional Energy Sources (MNES), has been aware of the potential and role of biomass energy in the Indian context and, hence, has initiated a number of programmes for promotion of modern technologies for its use in various sectors of the economy to ensure derivation of maximum benefits. Biomass power generation in India is an industry that attracts investments of over Rs.600 crores ever y year, generating more than 5000 million units of electricity and yearly employment of more than 10 million man-days in the rural areas. The three main technologies being promoted by the MNES for productive utilization of biomass are bagasse-based cogeneration in sugar mills, biomass power generation, and biomassgasification for thermal and electrical applications. The Government of India has a well-framed national policy with objectives to promote biomass power generation systems. Requisite clauses are inserted in the Electricity Act, 2003. There is an installed capacity of 302 MW through biomass gasification and 437 MW through cogeneration till March 2005. Case studies of a few of the installed plants are collected and analyzed to consolidate the value of learning and experience. 1.1.1. National electricity policy 2005 a) The National Electricity Policy aims at achieving the following objectives: b) Access to Electricity available for all households in the next five years, c) Availability of power demand to be fully met by 2012. Energy and peaking shortages to be overcome and spinning reserve to be available, d) Supply of reliable and quality power of specific standards in an efficient manner and at reasonable rates, e) Per capita availability of electricity to be increased to over 1000 units by 2012, f) Minimum lifeline consumption of 1 unit/household/day as a merit good by 2012,
Page 2
1.2. Achievements
A power-generation capacity of about 302 MW has been commissioned through 54 projects, as on March 2005. A further capacity addition of about 270 MW through 39 projects is reported to be under implementation. The biomass materials that have been used for power generation in these projects include rice husk, cotton stalk, mustard stalk, Prosopis juliflora (Vilayati babul), poultry litter, bagasse, cane trash, etc. State-wise distribution of the commissioned plants and the plants under implementation is given in Table 1 below (as on 31 March, 2005). : Table 1 Details of power projects commissioned and under implementation State Andhra Pradesh Chhatisgarh Gujrat Haryana Karnataka Madhya Pradesh Maharashtra Punjab Rajasthan Tamilnadu Uttarpradesh Total Commissioned capacity No. of projects 37 2 1 1 5 1 1 1 1 4 54 (MW) 194.2 11.0 0.5 4 36 1 3.5 10 7.8 34.5 302.5 Under implementation capacity No. of projects 11 5 11 1 1 4 6 39 (MW) 70.25 51 61 6 6 29.10 48.50 271.85
Source: Booklets on Renewable Energy - No.2 Biomass published by Ministry of Nonconventional Energy Sources, Government of India
2.5 Investment
The project is set up at a total cost of Rs.2440 lakhs including land, buildings, plant and machinery and fixed deposit collected by IREDA Means of finance: Term Loan Equity Rs. 1827 lakhs Rs. 613 lakhs
The project was funded by IREDA. Subsequently due to increase in the cost of biomass fuel, reduction in tariff, the company shifted the loan to a commercial bank to reduce the interest cost. Equipment packages: a) Turbo generator and auxiliaries b) Boiler and Auxiliaries c) Fuel handling system d) Cooling water circulation system e) Ash handling system f) Compressed Air System g) RO/DM Water treatment system h) Air conditioning and Ventilation i) Fire protection j) Power evacuation and auxiliary power distribution system k) Controls and instrumentation l) Civil and structural works 2.6 Parameters of main equipment
Page 5
Page 6
A view of the Biomass storage and conveyer system of the biomass power plant in Andhra Pradesh
Page 7
CASE STUDY: BIOMASS IN INDIA 2011 3. Case Study: Biomass based Power Project at Kothara, Gujarat
3.1 The demonstration project: Blazing a new trail The Gujarat Energy Development Authority (GEDA) took up Energy Plantation Programmes in the wastelands of Kuch in a major way since the early 1980s. These programmes are multidimensional in nature with linkages to energy supply, food and fodder, soil regeneration, ecological development and local employment generation. 3.2 Tree species The tree species for plantation were Acacia nilotica, Prosopis juliflora, Acacia tortillas, Eucalyptus, Subabul and Casurina. These are hardy specimens that can survive in harsh climates, poor soils and minimal water conditions. At the same time, they are also able to regenerate the soil. By their very name, energy plantations mean that they are grown for cyclical harvesting whereby the trees, once they attain specific height, are cropped or coppiced periodically for their biomass, a sustainable resource. Biomass yields from energy plantations usually range from 4-8 tonnes per ha per year. GEDAs energy plantations in district Kuch cover 1450 ha at different agro-climatic locations in villages Moti Sindhodi, Lathedi, Vingabe and Kosha in taluka Abdasa. 3.3 Cost break-up The total project cost is Rs.200 lakhs, with plant and machinery at Rs.160 lakhs and civil work at Rs.30 lakhs. The project objective is to feed a minimum of 500 kW electric power into the grid at Kothara Sub-station. The salient features are as under in table 6.13
3.4 Location When the proposal for a demonstration power project was mooted, village Kothara was selected as the project site from among two other sites, Moti Sindhodi and Nalia, for the
Page 8
Page 10
Page 11
CASE STUDY: BIOMASS IN INDIA 2011 5. Case study: Energy recovery from urban wastes in India
5.1 Potential for urban waste Indias population as per census 2001 is 1027 million, of which 285.35 million reside in 5161 urban areas. It constitutes 27.8% of the total population of the country. The problem of urban waste management is notable for only because of large quantities of waste involved, but also due to its spatial spread across 5161 urban local bodies, and the enormity and variety of problems faced in setting up of systems for collection, transportation, and disposal of waste. According to a recent estimate, about 42 MT (million tonnes) of solid waste (1.15 lakh tonnes per day) and 6000 million cubic meter of liquid waste are generated every year by our urban population. The composition of the urban waste in given in table 10 below: Table 10: Composition of urban waste
This translates into a potential for generation of over 1700 MW of power from urban waste in the country. 5.2 Municipal solid-waste based power project at Hyderabad A waste-to-energy plant was taken by M/s SIL (Selco International Ltd) in 1999 based on the RDF (refuse derived fuel) technology, for production of RDF pellets, which can be used as an alternative to coal for energy production. While a project for production of RDF pellets was taken in 1999 as Phase I of the project, the second phase of the project for utilization of RDF for generation of power was completed in November 2003. The total cost of the project is about Rs.43.50 crores. The plant was commissioned in November 2003, and has been operational since then with maintenance shutdown for 1-3 days per month. Phase I (Pelletization project) This plant is located next to the Gandhamguda municipal waste dump, which receives 1300 MT of garbage every day from Hyderabad city. The installed capacity of the plant is 1000 TPD (tonnes per day), and it has the capacity to produce 200-250 TPD of fuel pellets. The calorific value of fuel pellets produced in the first phase was of the order of 3000 kcal/kg (kilocalories per kilogram), and pellets were reported as having ash content
Page 12
The special design features are as follows: a) The boiler tubes are protected with special alloy coating. This alloy has a high thermal conductivity and protects the boiler tubes from corrosion and erosion. b) This was also filed for an Indian patent. c) Secondary air is pre-heated and sent into the boiler at various points for proper burning of RDF. d) Air-cooled condenser has been employed in place of conventional water-cooled condenser. e) The initial ash fusion starts at a temperature of 860 C, hence low- furnace temperature has to be maintained, and the boiler is designed accordingly to prevent clinker
Page 13
References: 1. http://powermin.nic.in/rural_electrification/definition_village_electrification.htm 2. Mr. A Mohan Reddy, Zenith Corporate Services, Hyderabad, at One-day Business Meet on Biomass Energy and Co-generation (Non-Bagasse) Projects for Industries on 22.12.05 organised by Haryana Renewable Energy Development Agency. 3. NH Ravindranath, HI Somashekar, S Dasappa and CN Jayasheela Reddy 2004 on Sustainable biomass power for rural India: Case Study of biomass gasifier for village electrification a Special Section of S&T to rural areas. 4. Gujarat Energy Development Agency (GEDA), Suraj Plaza-II, Sayajiganj, Vadodara390005, Ph:+91-265-363123, Fax:+91-265-363120, Email: [email protected] 5. Akshay Urja (an MNES publication), Vol.1, Issue 5 (Sep-Oct.2005) 6. Biomass Gasifier illuminates Gosaba Island, Sundarbans, published in Success Story section in Akshay Urja, of Nov-Dec.05, Vol.I. 7. Energy recovery from urban wastes in India by AK Dhussa, Director, MNES, in Technology section in Akshay Urja, of Nov.-Dec.05, Vol.1 Issue