Overload Mitigation SIPS Based On DC Model Optimization and PMU Technology
Overload Mitigation SIPS Based On DC Model Optimization and PMU Technology
17559/TV-00000000000000
Original scientific paper
Abstract: System integrity protection schemes (SIPS) supported by phasor measurement unit (PMU) technology are based on the concept of collecting information from
remote stations, sending the information to a central concentrator that executes a decision-making algorithm and initiates specialized actions to prevent the spread of
system disturbance. This paper gives application of overload mitigation SIPS. Described protection scheme is based on a mixed integer linear programming (MILP)
optimization of the DC power flow model whose objective is to maximize total load on the observed part of the network. Inaccuracy of the used DC model and the actual
state is replaced by using the PMU technology. In this way, the influence of reactive power, that is ignored in the DC model power flow model calculation, is replaced in
real-time with real synchronized measurements. Described SIPS is tested on IEEE 14 busbar test system. Conducted simulations indicate that developed optimization
algorithm can mitigate potential element overloads with extremely high accuracy by using load shedding methods. Example on real part of Croatian power transmission
network is given at the end of paper. This specific analysis demonstrates benefits of using SIPS based on synchro phasors in real world.
Keywords: optimization; overload mitigation; phasor measurement unit; system integrity protection scheme
part of the network in order to determine in real time the - δi, δj – voltage phase angle for node i and j,
difference in the loads imposed by the assumptions set - Xij – element reactance between nodes i and j,
when using the DC power flow model in relation to the - Tij – element connection between nodes i and j,
actual power flows. defined as binary value 0 for disconnected or 1 for
connected state,
2 MILP BASED ON DC POWER FLOW MODEL - N – number of nodes,
- δREF – reference voltage phase angle.
The task of the optimization algorithm is to mitigate
the overload in the network by optimizing consumption The node sum is defined by the following expression:
with the aim of preserving the transmission system. The
algorithm applies MILP based on the method of ∑ , (5)
branching and fencing.
MILP studies the optimization problems within the where:
system's default limits. Optimization can be based on the - VARi – load shedding solution at node i, defined as
problem of maximizing or minimizing the default binary value 0 for load disconnection or 1 for load
objective function by finding appropriate decision connection at node i,
variables along with the constraints described by certain - Li – active load power at node i in MW,
equations and inequalities. At MILP, a certain decision - Gi – active generation power at node i in MW.
variable can take values from a set of real or integer
numbers. The method of branching and fencing is based Real-time adjustment factor kQ is created in order to
on the principle of successive solving the objective compensate inaccuracy of the DC model. It represents
function, while the permissible values of the decision impact of reactive power in the real system relative to its
variables do not reach the optimal solution. The details of neglect in the DC model.
the integer programming can be found in [12].
The mathematical model of used algorithm is based , (6)
on the power flow calculation of the simplified model of
the network, the so-called DC model. The DC model where:
assumes three assumptions: - kQ – adjustment factor that is calculated in real time
when overloading occurs in MW/MVA according to
- line resistance RL is negligible in relation to line Eq. (7),
reactance XL, - SijMAX – maximum transmission power between nodes
i and j in MVA.
, (1)
Adjustment factor is calculated in real time when
- per unit voltage |VN| is the same for all nodes, overloading occurs in MW/MVA according to Eq. (7),
and its value is always less than 1.
| | , (2)
, (7)
- voltage angles difference δi-δj of the adjacent nodes is
small, which derives:
where:
( ) ( ) ( ) , (3) - PijDC – calculated active power flow based on the DC
model from node i to node j when overloading
Obviously, taking into account these assumptions occurs,
affects the accuracy of the DC model. According to [13], - SijREAL – real time measured apparent power of the
the total error of the DC model is 5 % compared to the overloaded connection between node i and node j
more accurate AC nonlinear model. Though the accuracy when overloading occurs.
of the DC model is smaller than the AC model, it is
characterized by the simplicity and the speed of the As an additional release condition the model allows
calculation conditioned by its linearity, which is why it is definition of critical loads which must remain connected
proposed in making SIPS. according to Eq. (8).
(∑ ), (9)
Table 1 Assumed rated power of lines and transformers
Defined mathematical model finds a combination of Rated power
Elements
loads whose total real time measured sum represents (MVA)
Lines
maximum possible load due to the constraints of
1-2 (1), 1-2 (2), 1-5, 130
transmission power capacity of all connections in the real 2-3, 2-4, 2-5, 3-4, 4-5
time topology of the transmission network. Transformers
Block diagram of proposed optimization algorithm is 85
4-7, 4-9, 5-6
given in Fig. 2. Lines
6-11, 6-12, 6-13, 7-8, 7-9, 70
9-10, 9-14, 10-11, 12-13, 13-14
( )
, (10)
( )
Figure 5 Checking optimization result on nonlinear model with implemented load supply priority
Table 2 Optimization results Table 3 Optimization results with implemented load supply priority
Optimal load solution Supply priority
Busbar Load (MW) 0 – not connected, 0 - can be Optimal solution
1 – connected Busbar Load (MW) disconnected 0 – not connected,
1 0 0 1 - cannot be 1 – connected
2 21,7 1 disconnected
3 94,2 1 1 0 0 0
4 47,6 1 2 21,7 0 1
5 7,6 1 3 94,2 0 1
6 11,2 0 4 47,6 0 1
7 0 0 5 7,6 0 1
8 0 0 6 11,2 1 1
9 29,5 1 7 0 0 0
10 9 1 8 0 0 0
11 3,5 0 9 29,5 0 1
12 6,1 1 10 9 0 1
13 13,5 1 11 3,5 1 1
14 14,9 1 12 6,1 0 1
Total load before optimization(MW) 259 13 13,5 0 1
Total optimized consumption (MW) 244,3 14 14,9 0 0
Load that needs to be disconnected (MW) 14,7 Total load before optimization(MW) 259
Total optimized consumption (MW) 244,1
Load that needs to be disconnected (MW) 14,9
3.5 Checking optimization solution on nonlinear model
4 APPLICATION ON THE REAL PART OF CROATIAN Model base scenario is defined according to
TRANSMISSION NETWORK following:
Matulji-Lovran and 131,3 MW on line Buje–Kopar. AC phasor measurement technology allows you to collect
model power flow calculation gives apparent power of real-time network data and provide fast and reliable
169,2 MVA for line Matulji-Lovran and 153 MVA for performance of SIPS.
line Buje-Kopar. Universality of described algorithm was tested on the
Adjustment factor kQ for case of overloading lines IEEE 14 busbar test system. From the analyses carried out
Matulji–Lovran and Buje–Kopar is calculated according we can conclude that described optimization algorithm
to Eq. (11) and (12): offered results that successfully mitigate overloading of
test system with extraordinary accuracy.
, (11) Algorithm applicability on the real model of EPS has
been shown by checking algorithm on subsystem Istria.
Analyses showed that it has been successful in overload
, (12) mitigation while simultaneously utilizing the available
transmission power of connection lines. It is therefore
Adjustment factor kQ of 0.86 MW/MVA is selected as concluded that the described algorithm can be used in
input parameter in the overload optimization algorithm further development of SIPS in subsystem Istria.
for case of overloading lines Matulji–Lovran and Buje– In further development, it is necessary to analyse
Kopar. possibility of applying optimization algorithm to
subsystems with a high share of reactive power, as well as
4.3 Optimization results to subsystems where there is electricity production at
certain nodes.
Tab. 7 shows output results of optimization algorithm
according to the defined scenario. 6 REFERENCES
Table 7 Optimization results for defined scenario [1] Zhang, Z., Chen, W., & Zhang˛, Z. (2015). Research on the
Total load before optimization 279,39 MVA relay protection system of micro-grid. Technical Gazette,
Loads that need to be disconnected 3,8,10,14,16,18,20 22(1), 51-59.
Total load that needs to be disconnected 119,19 MVA https://doi.org/10.17559/TV-20150210221236
Total optimized consumption 160,20 MVA [2] Zbunjak, Z., & Kuzle, I. (2013). Advanced Control and
System Integrity Protection Schemes of Croatian Power
Transmission Network with Integrated Renewable Energy
Tab. 8 gives power flows for connection lines Sources. Eurocon 2013, Zagreb, 706-711.
Matulji–Lovran and Buje–Kopar after implementing https://doi.org/10.1109/EUROCON.2013.6625060
optimization algorithm. Overloading of connection lines [3] Phadke, A.G., & Thorp, J.S. (2008). Synchronized Phasor
has been mitigated and the high availability of Measurements and Their Applications. New York, NY:
transmission power is achieved. Power flow of 97,1 % Springer.
was achieved for line Matulji-Lovran and 92,7 % for line [4] Kirincic, V., Skok, S., & Frankovic, D. (2016). A
Buje-Kopar. noninvasive inclusion of synchrophasors in the power
system state estimation. Technical Gazette, 23(5), 1457-
Table 8 Power flows for connection lines after optimization 1462. https://doi.org/10.17559/TV-20150118204850
Nonlinear AC model after optimization [5] Martin, K.E. et al. (2008). Exploring the IEEE Standard
P Q S SMAX C37.118-2005 Synchrophasors for Power Systems. IEEE
Line % Transactions on Power Delivery, 23(4), 1805-1811.
(MW) (MVAr) (MVA) (MVA)
Matulji- https://doi.org/10.1109/TPWRD.2007.916092
84,6 17,6 86,4 89 97,1 [6] Terzija, V., Valverde, G., Cai, D., Regulski, P., Madani, V.,
Lovran
Buje- Fitch, J., Skok, S., Begovic, M., & Phadke, A. (2011). Wide
79,0 23,8 82,5 89 92,7 Area Monitoring, Protection, and Control of Future Electric
Kopar
Power Networks. Proceedings of the IEEE, 99(1), 80-93.
https://doi.org/10.1016/j.ifacol.2016.10.724
In the study of optimization algorithm on real part of [7] Anderson, P.M., & LeReverend, B.K. (1996). Industry
Croatian transmission network, supply priority was not Experience with Special Protection Schemes. IEEE
given to individual nodes. In the further development of Transactions on Power Systems, 11(3), 1166-1179.
optimization algorithm, in cooperation with distribution https://doi.org/10.1109/59.535588
system operator in the observed network part, it will be [8] Madani, V., Novosel, D., Horowitz, S., Adamiak, M.,
necessary to define criteria for selecting importance of Amantegui, J., Karlsson, D., Imai, S., & Apostolov, A.
consumers of subsystem Istria, according to which supply (2010). IEEE PSRC Report on Global Industry Experiences
priorities of certain nodes should be defined. With System Integrity Protection Schemes (SIPS). IEEE
Transactions on Power Delivery, 25(4), 2143-2155.
https://doi.org/10.1109/TPWRD.2010.2046917
5 CONCLUSION [9] Zbunjak, Z., & Kuzle, I. (2011). Possible savings in
electricity transmission using wide area monitoring
Optimal overload mitigation algorithm based on the technologies in Croatian power transmission network. 8th
DC model and synchronized measurements is given in International Conference on the European Energy Market
this paper. Calculation of power flows according to DC (EEM11), Zagreb, 495-500.
network model is characterized by simplicity and speed. https://doi.org/10.1109/EEM.2011.5953062
There are no convergence problems as in other non-linear [10] Quiros-Tortos, J., Wall, P., & Terzija, V. (2016). Reducing
models making it suitable for use in time-limited excessive standing phase angle differences: A new
approach based on OPF and wide area measurements.
applications such as WAMPAC systems. Synchronized
International Journal of Electrical Power & Energy [16] Kotorac, D., Andrić, A., Frlan, K., Sokolić, L., & Zbunjak,
Systems, 78, 13-21. Z. (2016). Activities for preventing EPS blackouts in the
https://doi.org/10.1016/j.ijepes.2015.11.078 Istria region. 12th symposium on power system
[11] Cai, D., Wall, P., Osborne, M., & Terzija, V. (2016). management, Split, (CD edition)
Roadmap for the deployment of WAMPAC in the future
GB power system. IET Generation, Transmission &
Distribution, 10(7), 1553-1562. https://doi.org/10.1049/iet- Contact information:
gtd.2015.0582
[12] Wikipedia, Integer programming. Zoran ZBUNJAK, M. E.E.
https://en.wikipedia.org/wiki/Integer_programming Croatian Transmission System Operator Ltd.
(Accessed 2018-07-15) Transmission Area Rijeka
Marinčićeva ulica 3, 51211 Matulji, Croatia
[13] Purchala, K. (2005). Modelling and analysis of techno-
[email protected]
economic interactions in meshed high voltage grids
exhibiting congestion. PhD thesis, University of Leuven Igor KUZLE, Ph.D. E.E.
(K.U. Leuven), (CD edition) University of Zagreb
[14] University Washington, Power system test case archive. Faculty of Electrical Engineering and Computing
http://www.ee.washington.edu/research/pstca/pf14/pg_tca1 Unska 3, 10000 Zagreb, Croatia
4bus.htm [email protected]
(Accessed 2017-09-23)
Dino MAĐAR, M. E.E.
[15] Kotorac, D., Zbunjak, Z., Valentić, V., Sokolić, L., &
Croatian Transmission System Operator Ltd.
Šumberac, B. (2013). Analysis of application possibilities Transmission Area Rijeka
of advanced control system on the electrical power Marinčićeva ulica 3, 51211 Matulji, Croatia
subsystem of Istria. 11th HRO CIGRÉ Session, Cavtat, (CD [email protected]
edition)