0% found this document useful (0 votes)
322 views20 pages

Previous Year Question Paper

Question paper

Uploaded by

jfun6858
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
322 views20 pages

Previous Year Question Paper

Question paper

Uploaded by

jfun6858
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

S H U d IM -C

SLR-HL-53
Seat
No. P21s363 Set P 3 1 - J a

Fourth. Y. (B.Tech.) (Sem- l) (New) (CBCS) Examination: Oct/Nov-2022


A H S
N U
I T C O R
3 E4R

CIVIL ENGINEERING
Construction Engineering, Management &Construction Practices
Day &Date: Tuesday, 31-01-2023 Max. Mark_fo
Time: 02:00 PM To 05:00 PM
Instructions: 1) Q. No. 1is compylsory and should be solved in first 30 minutes in Aniswer
Book. Page No (startingpage of the Answer Book). Each question
carry one mark.
2) Don't forgetto mention Question Paper Set (P/Q/R/S) at the top of the
same page
3) Figures to the right indicates full marks.
4) )Asgüme suitable data wherever needed and mention it clearly.
Duration: 30Minutes MCQ/Objective Type Questigns Marks: 14
Q.1 Choose the correct alternatives from the options.
2 8
14
P M
Crashing is
01:06:50
a) Abandoning the project P N
2 9 m e

Completing the project with allßossible haste


c) Reduction in duration for fewof the activities
L O 2 3
d) Reducing cost of the project with all possible modifications c O R3
E1R- J a n - 20012:
3 0 8 :

2) CPM method of network analysis is


i) ideally suited for linearly extending works
ii Meant essentially for R and D activities
ii) Activity Oriented
iv) Used for plasining, scheduling and controlling purposes
a) iand ii b ii and iii
C) ii andgv d) i and iv
3 Which odie of the folowing is captured in the Work Breaktown Structure
(WBSJ?"
a)f The life cycle phases b The logfcal order of tasks
The scope of the project d) Projeet costs
The critical path
e P A H S
M U
I T C O R E R

a) Is a path that operates from the startiig node to the end node o P A HMSI
U T C O R
3 E R
1

b) Is a mixture of all paths


C) Is the longest path
d) Is the shortest path
5 Freee float for any activity is def-t das the difference between
a) itsearliest finish time andearliest start time for its
b) its latest start time and earliest start time successor activity
C) its latest finish time and earliest start time for its successor activity
d) its earliest fini_h time and latest start time for its
The time with which direct cost does not reduce with the
successor activity
6)
known as increasgah time is
a) crashiHe b) normal time
c) optiiistic time d standard
23
Page 1 of 16
M I T C O R
3 E
1 R- J a r

2 9 =

P M

o 1 : 0 8 : 5 0

SLR-HL-53
Set P
3 1 - J a n 0 2 3

Independent float is the amount of time by wbih:


a) Start of the activity can be delayed without affecting EST of
R E R
subsequent activity N I T C O R
3 E1R - J a

b) reduces the float of subsequent:activities


c) completion of an activity can be delayed beyond EFT ithout
affecting EST
d) completion of an activity,tan be delayed beyond earliest possible
finishing time
8) According to Heinrich % are unsafe conditions and %
unsafe acts which are preventable.
a 10, 88 respectively b) 2, 98 respectively
c) 98, 2 respecively d) 88, 10 respectively
9 The very firstthing you should do if you are the first to witnes¼ or
an accident on the job site is to discover
a) Go find at least one co-worker to help you so youcan work as a team
b) Go to the scene and help the person(s) injured
Find and fill out the necessary forms to doçument the
Activate the emergency response syste incident
PH
2 9 9

The highway accidents occur mostly at


a) Both day and night Early morning hours Soen-207091;
P 06
2
N :9
504 e

Night time Day time


11) Which of these causes the most
OstOnstruction site fatalities?
O 2O31 :

a) Electrocution b) Trench collapses


c) Falls d) Contact with chemicals
12) Which of the following imoving machines has the shortest cycle
a Dragline b) Hoe
c) Clamshell d) Power Shovel
13) A is very seful equipment and it can be used for work
like to clear the site of work, to make the land level, etc.
a) Scraper b) Grader
c) Exéavator Bulldozer d)
14) In the production of prefabricated structures howwdogs the material used in
cofistruction affect the element?
material quality and economic design
a P A H S
M U
I T C O R
3 E1R- J a r

smaller members 2 9 s e

c) disuninting of members F N

d) Joints e P A S
N U
I T C O R3E1R

O 1 : 0 6 : 5 0

3 1 - J a n - 2 0 2 3

2 9 a e

M I T C O R E R

P N

0 1 : 0 6 : 5 0

o n P A H S U

Page 2 of 16
2 3
P A HMS U
I T C O3R1E R
- J a

I 0 8P
:5M
209

23
o
SLR-HL-53
|Seat Set Q
No. 3 1 - J a n

Fourth. Y. (B.Tech.) (Sem- I) (New) (CBCs)Examination: Oct/Nov-2022


rOORER CIVIL ENGINEERING o R E R

Construction Engineering, Management &Construction Practices


Day &Date: Tuesday, 31-01-2023 Max. Marks:
Time: 02:00 PM To 05:00 PM

Instructions: 1) Figures to the rightindicates full marks.


2) Q. No. 2 is compilsory. Attempt any two questions from Q. No.3dQ Q.
No. 5.
METCORER
3) Q. No. 6 is, cömpulsory. Attempt any two questions from Q, No.7 to Q.
No.

Section -|
12
Q.2 Find Prgj¿ct detailsinthe following table.
Duration (Days)
Activity
1-2 4
Pgêtedence
o 1 : 0 6P: 5N
20 9 e

1-3 5 0 1 : 0 6 :P5 0N
2o 9 a

2-3 3 1-2
3-4 1-3, 2-3
a) Draw the Bar Chart.
b) Draw the CPM Network
I0 c) Show the Critical Path and Duration of the Project.

Q.3 Answer the following questiohs.


a) Explain stepwise procedure of network compression using suitable example.
b What are the three time estimates in PERT? Explain how to calculate C O R3E R1

expected time usiig these three time estimates.


08
Q.4 Compare.
a) CPM witPERT
b) Resource leveling with Resource smoothening

Q.5 Answér following questions. 08


a) What is BIM? Which software is available as BIM? Explain the output of
BIM.
Explain reports possible using MS Projedtsoftware.
PAHMSU
ITCOREF% e P A H S U I T C3O1
R E R

Sectjon - Il
sge
ceg
Q.6 Write detailed Notes on.
a) Power Shovel
b) Bulldozer 31-3ar

c) Scraper 2 9 e a

Q.7 Explain.
P N
08
Safety Measures in Construction o1:06:50

b) Safety- against accidents


e P A

9 2 3

Page 7 of 16
a o P A HMSI
U T C O R
3 E
1 R- J e n

2 9 4

P M

5 0

1 1
;

0 6
SLR-HL-53
o11

Set Q
Q.8 Cgipare.
a) Tunnel
08
formwork with Mivan formwork o o P A H
M SIUT C O R
3 E
1 R
- J a n -

A SMUI T C O R g
b) Tower Crane with Mobile Crane
O
Explain.
a) Explain use of Dredging Equipment.
b) Stepwise procedure for constraetion of Diaphragm wall.
o P A HHSI
U T C O R
3 E
1 R
- J a n - 2 0 2 3

2 9 e o

0 1 : 0 6 : 5 0

3 1 - J a n - 2 0 2 3

2 9 e

P N

2 m e

M I T C O R E R

O 1 : 0 6 : 5 0

P M

0 1 : 0 6 : 5 0

e e P A H S U

z 0 2 3

3 1 - J a n - 2 0 2 3

2 9 s

P M

N I T C O R E R

o 1 ; 0 6 : 5 0

e P A H S U

a o P A HMS U
I T C O R
3 E
1 R
- J a n - 2 0 2 3

2 9 4

s o P A HMSIUT C O R3E1R

o 1 : 0 8 : 5 0

3 1 - J a n - 2 0 2 3

2 9 a

H I T C O R E R

P M

: 5 0

P A H S U
0 1 : 0 6

2 3

Page 8 of 16
SLR-GF-65
Seat
|No. Set P
Fourth Y. (B.Tech.) (Sem-) (New) (CBCS) Examination: Oct/Nov-2023
CIVIL ENGINEERING
Construction Management and Practices (BTNO1703)Max. Marks: 70
Day &Date: Saturday, 20-01-2024
Time: 10:00 AM To 01:00 PM
Instructions: 1) Q. No. 1 is compulsory. It should be solved in the first 30 minutes in
answer book Page no 03 (Starting page of the Answer Book). Each
question carries one mark.
2) Don't forget to Mention question paper set (P/Q/RIS) on top of page.
3) Figures to the right indicates full marks.
4) Assume suitable data if necessary.

MCQ/Objective Type Questions Marks: 14


Duration: 30 Minutes

Q.1 Choose the correct answer. 14


1) The time span between the start and completion of a project represent
a)
c) Project
Project vce
b)
d)
Project Duration
None of the above
2) cranes are used for handling loads over a large rectangular area in
factories, power stations, shipyards and workshops.
Mobile b) Derrick
Gantry d) Hydraulic
3) If for an activity optimistic time is 7 days, pessimistic time is 13 days and
most likely time is 10 days, its standard deviation will be
10 b) 3.28
10.77 d) 1
4) The area under the Beta distribution curve is divided into two equal parts
by
a Most likely time b) Optimistic time
Pessimistic time d) Expected time
5) IfD is the duration, ES and EF are the earliest start and finish, LS and LF
are latest start and latest finish time, then the following relation holds good
EF =ES +D b) D= EF- ES
a)
LF = LS +D d) All of the above
c)
6) Choose the best option that fits the following statement.
The of time management tools depends on the of the project.
a ldentity, Quality b) Utility, Complexity
c) Functionality, Creativity d) Equity, Quantity

Page 1 of 16
SLR-GF-65

7) A milestone chart
Set P
a
shows the interdependencies of various jobs
b depicts the delay of jobs, if any
C) points outgoing ahead of schedule of jobs, if any
none of these
8 are used to
stands.
excavate below the ground on which the machine
a) Hoes
c) b) Power Shovel
Trenchers d) Rippers
9 What is the process of incorporating
planning called? changes and rescheduling or re
a) Resource Allocation b) Resource smoothing
Resource levelling d) Updating
10) cranes are used for handling loads over a large
factories,power stations, shipyards and rectangular area in
a) Mobile workshops.
b) Derrick
Gantry Hydraulic
11) The size of the bulldozer is indicated by the
a Site dimension of its
C b) Tyre
Engine d) Blades
12) consists of a large bucket which is attached to a
a Bulldozer tractor.
C)
b) Scraper
Grader d) Escalator
13) Hot-mix plant is used for
a) Cement concrete pavement
b) Construction.
Bituminous pavement construction.
c) Water bound macadam
d) All the above construction.
14) Sheep foot roller is used for compacting
a) Granular soil
b) Non-plastic silts
C) Fine sands d) Clay soil

Page 2 of 16
SLR-GF-65
Seat
No. Set P
Fourth Y. (B.Tech.) (Sem-1) (New) (CBCS) Examination: Oct/Nov-2023
CIVIL ENGINEERING
Construction Management and Practices (BTNO1703)
Day & Date: Saturday, 20-01-2024 Max. Marks: 56
Time: 10:00 AM To 01:00 PM

Instructions: 1) from
Question no. 2is compulsory in section I, and solve any two questions
the remaining. (Q. No. 3, 4 &5)
2) Question no. 6 is compulsory in section II, and solve any two questions
from the remaining. (Q. No. 7, 8&9)
3) Figures to the right indicate full marks.
4) Assume suitable data wherever needed and mention it clearly.
Section -1
Q.2 Answer the following questions. 12
Consider a project shown in the Table.
1) Draw CPM Network
2) Find critical path
3) Find duration of the project
Activity Duration
(days)
1-2 3
2-3 4
2-4 4

3-7 4
4-5 2
4-7 2
5-6 3
6-7 2

Q.3 Answer the following questions. 08


a) What is WBS? Explain its importance in project management.
b) Explain the process of network compression in details with suitable
example.
Q.4 Answer the following questions. 08
a) Explain the process of resource allocation in detail,
b) Differentiate between Bar Chart and Milestone Chart.
Q.5 Answer the following questions. 08
a) Write a short note on MS Project Software.
b) What is BIM? Also explain the output of BIM.

Page 3 of 16
SLR-GF-65 SL
Set P
Section-I| 12
Q.6 Write Short notes on
a) Hoes
b) Compactors
c) Hot mix plant
08
Q.7 Explain in details.
construction sites.
a) Safety measures on
b) Safety against accidents.
08
Q.8 Explain in details.
Prefabricated construction.
a) Write a short note on Mivan formwork.
b) Write a short note on
08
Q.9 Explain in details.
equipment
a) Explain the uses of floating of diaphragm walls.
b) Explain the types and uses

Page 4 of 16
PM
02:23

Gars 023 SLR-WF-74


Seat
No.
Set P
Fourth. Y. (B. Tech) (Sem -I) (New) (CBCS) Examination:
MarchlApril-2023
CIVIL ENGINEERING
Construction Engineering, Management &Construction Practices 022
(197042702)
GMax. Marks: 70
Day &Date: Wednesday, 05-07-2023 h 0s072n
)
Time: 03:00 PM To 06:00 PM
Instructions: 1) Q. No. 1is compulsory and should be solved in first 30 minutes in Answer
Book. Page No.3 (starting page of the Answer Book). Each question(Barsha
(Bar carry one mark.
CORER
2) Don't forget to mention Question Paper Set (P/QR/S) at the top of the
same page. MIICORER
M
MITCo
3) Figures to the right indicates full marks.
4) Assume suitable data wherever needed and mention it clearly.

MCQJObjective Type Questions PM


Marks: 14
Duration: 30 Minutes 02:23
Choose the correct altermatives from the options. 14
Q.1 MITCC
2023
1) Scheduling helps in
a) Planning for the project
by Financial control of the project PM

C) Preparing the estimate for the project 23


Carrying out the project in an orderly and effective manner. 02
One of the main disadvantages of the bar chart is 05/07/2023

05/07 a) Progress of the work cannot be monitored


b) Does not show the interdependencies of the activities
c) The time schedule is not shown properly
ER
(Barsh
d) The financial aspect is not shown (Barsh)

3) Work Breakdown structure helps in


a) ldentifying the activities
b) Identifying the functional element ofa project and their MITCORER

interrelationship.
c) Breakínig the project into several lelements
d) Breaking the project into system PM
4) Amilestone chart is
223
a) Same as the bar chart
b)An improvement over the bar chart
C) Inferior to the bar chart
Ad) None of these
Construction costs mainly consists of expenditure on'
202
3 a) Labour & materials b) Plants and equipment's
c) Overheads d) All ofthese
07202
6) A-O-A network means
05/07
a) Activity on Arrow b) Act on Activity
c) Both a and b d) None of These

Page 1 of 16
MIIc

PM
23
02 SLR-WF-74
Set P
7) Precedence networks are more commonly used when PM
a) Repetitive tasks are involved 23
b) Overlapping of activities occur 02
c) Inter dependencies exist 05/07/2023
d) All of these
8) Pessimistic Time is
a) All conditions are not in favou
b)Allconditions are in favour (Barshi)
202302
c) Both above
(Barshi9
d) None (Bar
O s5
h /0
) 7:2023

Management Information Systems (MIS).


/Rars
a) create and share documents that support day-today office activities.
MITcORER
b) process businesstransactions (e.g., time cards, payments, orders,
etc.)
c) capture and reproduce the knowledge of an expert problem solver
d) use the transaction data to produce information needed by managers
to run the business.
PM

3
10) When you begin a new project in MS Project, you can identify its
timeframe by
a) Clicking on the Calendar and setting Timeframe
bGoing to the Project tab and in the Properties group72023
D2
choose Project
Ihformation. MITCC

c)Going to the backstage and choosing options


d) None of these
PM

11),,Scraper is used
U5/07/2023 for 02:23
a) Scraping of soils
b) Excavation only 05/07/2023
c) Excavation, transporting and dumping of soil
d) None of these

JRER
arshi
(Bars 12) are cranes of Swing jib type and are mounted on high Steel Towers,
a) Cableways n b) Swing jib (Barstu)
ITCORER
Bars
c) Tower d) Goliath
13) of every year is celebrated as National Safety Day. DRER
a) March 4 b) April 14
c) March 14 April 4
05/07/202
14) Width ofDiaphragm walls can be between n8
MTCORE
a) 0.5to 1.50 meters b) 0.5 to 2.0 meters
c) 05 to 3.0 meters d) 02:23
0.5 to 4.0 09-23
meterS
MITC (Barsh)
0507/202n
PM
MITCOREP
02:23

05/072023. (Barshi)
PM

02:23 cORER
shi)
23

Page 2 of 16
PM

23
02
2023 SLR-WF-74
Seat Set P
|No.
Fourth. A
Y. T C Tech) (Sem -I) (New) (CBCS) Examination:
March/April-2023
CIVIL ENGINEERING
Construction Engineering, Management &Construction Practices
0 7 20
0223:
(197042702)
Day &Date: Wednesday, 05-07-2023 Max. Marks: 56
Time: 03:00 PM To 06:00 PM
Instructions: 1) All question are compulsory in Section I and Section I
O(Barshi2) Figures to the rightindicate full marks.
4) Assume suitable data wherever necessary and mention it clearly. Bars
5) Use of non-programmable calculator is allowed
Section-|
PM
MITC
Q.2 Attempt all of the below question:
a) Construct the detail "Work Breakdown Structùre (WBS)" for Planning and 04
scheduling öf "Watch Men building of 1BHK Ground floor Frame Structure
Building
b) Write down the "Rules for constructionof Network Diagram with necessary 03 MMITCC
sketch". 06
Construct "Bar Chart as well as Network Diagram" of the project and
define its project duration and critical Path.
Activity Predecessor Activity Duration (weeks)
4 S02
B 202
6
D B
6
(Bars
RER
(Ba: 4
F D, E
15
Q.3 Attempt any three from below questions. In-direct Cost and Total Project?
a) Explain in briefthe about "Direct Cost,
Cost" necessary graph sketch.
b Write down the steps involved in "Project
Network Compression"
C) Write down the steps involved in "Updating of Project Network Diagram".
the "CPM and PERT Technique"
d) Distinguish between
e) Explain in brief importance and use of
"Microsoft Project Soffware of
Construction Project".
Section- |

Q.4 Attempt all of the below question:


Enlist the use of "Safety tools against accidents on various building
construction sites"O
b) Explain the variotus "Safety measures to be taken on building construction 03
sites".
Draw the neat sketchwith labeling "Buldo~ers and Scrappers". 06

Page 3 of 16
02 MIECO
2023

65/0t PM

23
si)
02
SLR-WF-74
023
Set P
M
PM
Q.5 Attempt any three from below question.
l e dbout Asphalt mixing and batching plant (hot mix
05002302
23

Ehist and explain in brief "Compactors and typess Compactors


Write anote on "Floating equipment's
MITCOR
Explain in brief steps involved in construction of "Diaphragm Walls
0507/2023
7 r 20
022
23

(Barshi)

PM 05/07/20

0223
MITCORER
(Barshi)

O5/07/2023 (Barsh)

MITCORER
PM
MITCORER
23
(Barsh)
02
05/07/2023
PM

MITCORER PM
3

23

(Barshi) 05/07/202302 MITCO

PM

PM
23
MITCORER
02.23
02

05/07/2023 (Barshi)
05/07/2023

PM
MITCORER
02:23
(Barshi)

(Barshi)
05/07/2023

JRER PM
MITCORER
02:23

(Barshi)
05/07I2023

PM
MITCORER
02-23
(Bashi))
05/07/2023

PM
MITCORER

02:23

(Barshi)
0507/2023

PM

TCORER
02:23

shi) 23
Page 4 of 16
SLR-WF-74
Seat
|No.
Set P
Fourth. Y. (B. Tech) (Sem -) (New) (CBcs) Examination:
MarchlApril-2023
CIVIL ENGINEERING
Construction Engineering, Management &Construction Practices
(197042702) Max. Marks: 70
Day &Date: Wednesday, 05-07-2023
Time: 03:00 PM To 06:00 PM
Instructions: 1) Q. No. 1 is compulsory and should be solved in first 30 minutes in Answer
Book. Page No.3 (starting page of the Answer Book). Each question
carry one mark.
2) Don't forget to mention Question Paper Set (P/Q/RIS) at the top of the
same page.
3) Figures to the right indicates full marks.
4) Assume suitable data wherever needed and mention it clearly.
MCQJObjective Type Questions
Duration: 30 Minutes Marks: 14
Q.1 Choose the correct alternatives from the options. 14
1) Scheduling helps in
the project
bl Eing Itor
control of the project
c) Preparing the estimate for the project
d) Carrying out the project in an orderly and effective manner.
2) One of the main disadvantages of the bar chart is
a) Progress of the work cannot be monitored
b) Does not show the interdependencies of the activities
c) The time schedule is not shown properly
d) The financial aspect is not shown
3) Work Breakdown struture helps in.
a) ldentifying the activities
b) ldentifying the functional element of a project and their
interrelationship.
c) Breaking the project into several elements
d) Breaking the project into system
A milestone chart is
4)
a) Same as the bar chart
b) An improvement over the bar chart
c) Inferior to the bar chart
d) None of these
5) Construction costs mainly consists of expenditure on
a) Labour & materials b) Plants and equipment's
c) Overheads d) All of these
6) A-0-A network means
a) Activity on Arrow b) Act on Activity
c) Both a and b d) None of These

Page 1 of 16
SLR-WF-74
Set P
7 Precedence networks are more commonly used when
a) Repetitive tasks are involved
b) Overlapping of activities occur
c) Inter dependencies exist
d) All of these
8) Pessimistic Time is
a) All conditions are not in favour
b) All conditions are in favour
c) Both above
d) None
9) Management Information Systems (MIS).
a) create and share documents that support day-today office
activities.
b) process business transactions (e.g., time cards, payments, orders,
etc.)
c) capture and reproduce the knowledge of an expert problem solver
d) use the transaction data to produce information needed by
to run the managers
business.
10) When you begin a new project in MS Project, you can identify its
timeframe by:
a) Clicking on the Calendar and setting Timeframe
b) Going to the Project tab and in the Properties group choose Project
Information.
c) Going to the backstage and choosing options
d) None of these
11) Scraper is used for
a) Scraping of soils
b) Excavation only
c) Excavation, transporting and dumping of soil
d) None of these
12) are cranes of Swing jib type and are mounted on high Steel Towers.
a) Cableways b) Swing jib
c) Tower d) Goliath
13) of every year is celebrated as National Safety Day.
a) March 4 b) April 14
c) March 14 d) April 4
14) Width of Diaphragm walls can be between
a) 0.5 to 1.50 meters b) 0.5 to 2.0 meters
c) 0.5 to 3.0 meters d) 0.5 to 4.0 meters

Page 2 of 16
SLR-WF-74
Seat Set P
No.
Fourth. Y. (B. Tech) (Sem -) (New) (CBCS) Examination:
March/April-2023
CIVIL ENGINEERING
Construction Engineering, Management &Construction Practices
(197042702) Max. Marks: 56
Day &Date: Wednesday, 05-07-2023
Time: 03:00 PM To 06:00 PM
Instructions: 1)All question are compulsory in Section I and Section I.
2) Figures to the right indicate full marks.
and mention it clearly.
4) Assume suitable data wherever necessary allowed
5) Use of non-programmable calculator is
Section-I

Q.2 Attempt all of the below question: 04


Structure (WBS)" for Planning and
a) Construct the detail "Work Breakdown1BHK Ground floor Frame Structure
scheduling of "Watch Men building of
Building". Diagram with necessary 03
b) Write down the 'Rules for construction of Network
sketch. of the project and 06
Construct "Bar Chart as well as Network Diagram"
define its project duration and critical Path Duration (weeks)
Activity Predecessor Activity
A
A
A 6

D B 10
C 6

D, E
questions. 15
Q.3 Attempt any three from below"Direct Cost, In-direct Cost and Total Project
a) Explain in brief the about
Cost" necessary graph sketch.
Write down the steps involved in "Project Network Compression".
b)
of Project Network Diagram".
Write down the steps involved in "UpdatingTechnique"
d) Distinguish between the "CPM and PERT
e) Explain in brief importance and use of "Microsoft Project Software of
Construction Project.
Section-1|

Q.4 Attempt all of the below question:


a) Enlist the use of "Safety tools against accidents on various building 04
construction sites".
Explain the various "Safety measures to be taken on building construction 03
b
sites.
c) Draw the neat sketch with labeling "Bulldozers and Scrappers". 06

Page 3 of 16
SLR-WF-74
Set P
Q.5 Attempt any three from below question. 15
a) Explain in brief the about "Asphalt mixing and batching plant (hot mix
plant)," necessary graph sketch.
b) Enlist and explain in brief "Compactors and types Compactors".
Write a note on "Mivan Technology'.
d) Write a note on "Floating equipment's.
e) Explain in brief steps involved in construction of "Diaphragm Walls.

Page 4 of 16
SLR-JE-39
Seat Set P
No.
Fourth Y. (B.Tech.) (Sem-) (New) (CBCS) Examination: MarchlApril-2024
CIVIL ENGINEERING
Construction Management and Practices (BTNO1703)
Day &Date: Friday, 17-05-2024 Max. Marks: 70
Time: 03:00 PM To 06:00 PM
Instructions: ))Q. No, 1is compulsory. It should be solved in the first 30 minutes in
answer book Page no 03(Starting page of the Answer Book). Each
question carries one mark.
2) Don't forget to Menton question paper set (P/Q/R/S)on top of page.
3) Figures to the right ndicates full marks.
4) Assume sultable data whenever necessary &mehtion it clearly.
MCQ/Objective Type Questions Marks: 14
SDuration: 30 Minutes
Q.1 Choose the correct answer. 14
1) crahes are used for handling loads over a large rectangular area in
factories, power stations, shipyards and workshops.
a) Mobile ASD) Derrick PM
MITCC
c) Gantry d) Hydraulic
2) is used for removing materials b)fromBack
cofferdams.
hoe
ca) Dragline 1
Clamshell d) Crane
are used to excavafe belowthe ground on whlch the machine stands.
a) Hoes b) Power Shovel u620
c) Trenchers d) Ripper 17/05
ER
(Bare
shi) 4) slack is an indication of 'on schedule' project.
a) Positive b) Negative
c) Zero d) Greater
5) In PERT, the distribution should have a probability of reaching the
optimistic time.
a) Big b) Average
c) Smal d) Medium
6) In a CPM network, if earliest start time of an activity is 8 day_ and activity
duration is 7 days, the value of earliestfinish time of that activity willbe
days.
917/05/2024
02:31
PM A 1 b) 15
Cc) 56 d) 23
PMMITCOB
If for an activity optimistic time is 7 days, pessimistictime is 13 days and
most likely time is 10.days, its standard deviation wil be
a) 10 b) 3.28
c) 10.77 d)
SLR-JE-39
Set P
Sea
8) If the scheduled completion time of a project is 40 days and earliest No
expected completion time is 35 days, what will be the value of probability
factor if the standard deviation is 2.87 days?
a) 1.74 b) 3.00
c) 2.74 d) 0.74
9) The area under the Beta distribution curve is divided into two equal parts
by 023+

a) Most likely time b) Optimistic time


c) Pessimistic time d) Expected time 17/05/2024

10) Whattiis the process of incorporating changes and rescheduling or re


planning called?
ORER
(Bar Resource Allocation
a) b) Resource smoothing
Resource leveling d) Updating (Barshi)

11) The key functions of safety management system are,


TCOF 1) Planning for safety 2) Organizing for sfety MITCORp
RER

3) Scheduling for safety 4) Controling for safety


a) 1,3 and 4are correct b) 2,3 and 4 are correct
c) 1,2 and 3are correct d),2 and 4 are correct
12) Pick up the correct statement from the following:
a) Programme Evaluation and Review Technique is event oriented
b Programme Evaluation and Review Technique is not event oriented MITCC
c)Critical Path Method is event oriented
d) Critical Path Method is not event oriented
sh
1705/2024
) nn PM
13) In the given figure, the networkof a project represents. 0231
Bcavation of footing
B
17/05/2024
a) Activity of an excavation of a footing
(Barshi) b Activity of an excavation which starts at evert No. 1 and ends at even
No. 2
Activity of excavation which takes 8 units óf time )
d) None of these
14) If Dis the duration, ES and EE are the earliest start and finish, LS and LF are
MITCORER
latest start and latest finish time, then the following relation holds good
a) EF =ÉS + D 02:
(Barsh 17/05/2024
b) D=EF-ES
c) LE =LS +D d) All of the above
MITCORER PM

02:31
(Barshi)

17/052024
PM
MITCORER
02:31

05/2024 (Barshi)

PM

02:31 DRER
SLR-JE-39
Seat Set P
No.
Fourth Y. (B.Tech.) (Sem-1) (New) (CBCs)Examination: MarchlApril-2024
CIVIL ENGINEERING
Construction Management and Practices (BTN01703)
Max. Marks: 56
Day &Date: Friday. 17-05-2024 023
Time: 03:00 PM To 06:00 PM
Instructions: 1)Question no. 2 is cornpulsory in section l, and solve any two questions
17/05/2024

from the remaining. (Q,No. 3,4 &5)


2) Question no, 6 is compulsory in section Il, and solve any two questions
from the remaining..(0. No. 7, 8 &9)
RER
(Barsh (Barsh)
3) Figures to the right indicate full marks.
4) Assune suitable data wherever needed and mehition it clearly.
Section -1 MITCORER

12
Q.2 Consider a project shown in the Table.
Activity Duration in Days PM
Optimistic Most Likely Pessimistic
1-2 5 9
MiTO 17 MiTCC
2-3 11 A14
2-4 13 15
2-5 4 6 8 PM

3-7 9 10 11
02.31

0 0 0
4-5
5-6 35 3 17105n024

6-8 5 12 17
7-8 Lo8
ER
(Barshi
i) Draw PERT Network. (Barshi)
i) Find expected criticalpath.
i) Find duration and Variance of the project.
Q.3 Ans wer the following questions. 08
a) What is WBS? Explain its importance ini project management.
b) Folowing activities pertains to a projet. Determine critical path and Duration.
1-2 2-32-4 34 3-5465-6|
Activity
Durdtion (Days) 14 13 16 15 18 23 15

08
Q.4 AnswerDifferentiate
the following questions.
between CPM and PERT
a)
b) What is process and different steps followed
Rin 3
RER network updating?
08
Q.5 Answer the following questions.
a) Write a short note on applications of software in construction industry.
b) What is BIM? Al[o explain the output of BIM.
( B a r1
s7h/i0
)5 / 2 0 2 4

PM

02:31
SLR-JE-39
23
P1MITC
M
17/05/2024 Set P
Q.6 Write Short notes on Section -l
12
Duldoz R(Barshi)
NPr shev
c) Hot mix plant
a r s1
h7i )/
2 00
52

Q.7 Explain in details. 08


a Satety equipment's used on constuction site 02:31
Causes of accidents on construction site
7/05/2024
Q.8 Explain in details.
Bars

tnote on Mivanor
Explain different components and elements Used in prefäbrica d construction.
MITCOR

fabricated c 1
(Barsha
PM
MITCORERQ.9 Explain in details.
a) Write note on Dredging equipment and their types. PM

Explain the types and uses of diaphragm walls.


(Barshi) 02:31
MITCORER

17/05/2024
MITCORER

PM

02.31

(Barshi)
PM MITCO
17/05/2024

0231
MITCORER
PM

17/05/2024 02:31
(Barshi)

17/05/2024
PM

MITCORER
(Barshi) 02:31

17/0S/2024
(Barshi)
KER

PM

02:31 MITCORER
(Barshi)
17/05/2024

MITCORER
PM

02:31
(Barsh)

17/05/2024
PM
MITCORER
02:31

17/05/2024
(Barshi)

PM

9231 5RER

You might also like