0% found this document useful (0 votes)
18 views

PAS-PIDS IT Environment Preparation Procedure - Issue 1.1

This contains the details of the Elno TFT it system environment preparation system and manuals provides the issues and it's rectification used.

Uploaded by

Satish Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

PAS-PIDS IT Environment Preparation Procedure - Issue 1.1

This contains the details of the Elno TFT it system environment preparation system and manuals provides the issues and it's rectification used.

Uploaded by

Satish Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment

Preparation Procedure - Issue


PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

☐DEFENSE & SECURITY TRANSPORT ☐AIRCRAFT & INDUSTRY

Index Date Nature of the modification


1.0 27/07/2015 Creation
- Modification of the field of application from JB Section to DMRC Phase-III project
- Removal of passwords which were provided as examples
- Removal of references to OS for each type of machine
- Adding of the systematic installation of Visual C++ 2010 (x86) on all machines
1.1 29/02/2016
- Adding of the installation of Visual C++ 2012 (x86) on local & central announcers PCs
- Adding of Java SE Runtime Environment 8 (x86) for Local Servers
- Adding of Apache 2.2.25 Win32 x86 No SSL for Local Servers and Administration
Workstation

Writer Checker Approver


Name Arnaud BIGAND Bertrand COUROUBLE
Position Project Engineer Project Manager
Date 29/02/2016 08/03/2016

Visa

This document is the property of ELNO and may not be shared or reproduced without written approval. 1/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

CONTENTS

1 Purpose .......................................................................................................................................... 3
2 Field of application ........................................................................................................................ 3
3 Abbreviations ................................................................................................................................ 3
4 Input elements ............................................................................................................................... 3
5 Workstations preparation ............................................................................................................. 4
5.1 Common part ......................................................................................................................... 4
5.2 Local & Central Announcers Workstation ............................................................................... 4
5.3 NMS Workstation ................................................................................................................... 5
5.4 Administration Workstation .................................................................................................... 5
6 Local Servers preparation ............................................................................................................ 5
7 Central Servers preparation ......................................................................................................... 6
7.1 Common part ......................................................................................................................... 6
7.2 OCC/BCC Servers ................................................................................................................. 7
7.3 NMS Server ........................................................................................................................... 7

This document is the property of ELNO and may not be shared or reproduced without written approval. 2/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

1 PURPOSE
This document describes the different preparation steps that must be achieved before the installation of
the PAS/PIDS system on the IT equipment, in order to ensure a compatible IT environment.
It includes the configuration of the OS and the installation of one or several software components on the
machines.

2 FIELD OF APPLICATION
This document applies to the IT equipment of PAS/PIDS system for DMRC Phase-III project.

3 ABBREVIATIONS

OCC Operations Control Center


OS Operating System
PAS Public Address System
PIDS Passenger Information Display System
SCR Station Control Room

4 INPUT ELEMENTS
CS-15 tender and the associated contract.
Reference Revision

CS15-Instructions to tender NA

CS15-Instructions to tender-Appendix 3 NA

General Condition of Contract (GCC) NA

CS15-Special Condition of contract (SCC) NA

CS15 Employer’s Requirement-General


NA
Specifications

CS15-Particular specification-General Requirements NA

CS15-Particular specification-Public Address System NA

Tender technical proposal 1

MQ01-Quality manual F2

This document is the property of ELNO and may not be shared or reproduced without written approval. 3/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

5 WORKSTATIONS PREPARATION

5.1 Common part


OS Installation:
 Set a user name (if not automatically set)
 Set a password

No particular requirements about hard drive’s partitions (only one “C:” partition is sufficient).

Network parameters:
 Set a fixed IPv4 address
 Disable Windows firewall:

Keyboard’s layout (language) parameters:


1. English (US): set it as the default keyboard language
2. Hindi (Devanagari): set it as the second keyboard language

Microsoft .NET Frameworks installation:


 From the “Uninstall a program” page, click on “Turn Windows features on or off”:
o Activate the “Microsoft .NET Framework 3.5.1” (do not need to activate both “Windows
Communication Foundation” lines)
 Install “Microsoft .NET Framework 4.5.1”

Microsoft Visual C++ installation:


 Install “Microsoft Visual C++ 2010 Redistributable Package (x86)”

5.2 Local & Central Announcers Workstation


This part applies to the preparation of the Local & Central Announcers Workstation PCs only.

Microsoft Visual C++ installation:


 Install “Microsoft Visual C++ 2012 Redistributable Package (x86) – 11.0.61030”

This document is the property of ELNO and may not be shared or reproduced without written approval. 4/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

5.3 NMS Workstation


This part applies to the preparation of the NMS Workstation PC only.

Java Runtime installation:


 Install “Java SE Runtime Environment 8 (x86)”

5.4 Administration Workstation


This part applies to the preparation of the Administration Workstation PC only.

Java Runtime installation:


 Install “Java SE Runtime Environment 8 (x86)”

Apache server installation:


 Install “Apache 2.2.25 Win32 x86 No SSL”

6 LOCAL SERVERS PREPARATION


OS Installation:
 Set a user name (if not automatically set)
 Set a password

You must have two partitions on the Hard Drive Disk (partitions “C:” and “D:”), each partition should contain
around 50% of the total memory space.

Network parameters:
 Set a fixed IPv4 address
 Disable Windows firewall:

In Windows Update, select “Check for updates but let me choose whether to download and install them”.

Microsoft .NET Frameworks installation:


 Activate the feature “.NET Framework 3.5.1 Features”, then:
o Check the “.NET Framework 3.5.1” (do not need to check the other line “WCF…”)
 Install “Microsoft .NET Framework 4.5.1”

This document is the property of ELNO and may not be shared or reproduced without written approval. 5/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

Microsoft Visual C++ installation:


 Install “Microsoft Visual C++ 2008 Redistributable x86”
 Install “Microsoft Visual C++ 2010 Redistributable Package (x86)”

Java Runtime installation:


 Install “Java SE Runtime Environment 8 (x86)”

Install SQL Server (offline, or via the Web Platform Installer):


 Install “SQL Server Express 2008 R2 SP2”
 Install “SQL Server 2008 R2 Management Studio Express with SP1”

Database preparation:
 Configure the SQL server, for this launch “SQL Server Configuration Manager”:
o Inside “SQL Server Network Configuration/ Protocols for SQLEXPRESS”, enable Named
Pipes, TCP/IP and VIA
o Start the “SQL Server Browser” service

FTP server configuration:


 Install IIS: for this, open “Server Manager/Roles/Add Roles/Web Server (IIS)/”, check “FTP Server”,
then validate

Apache server installation:


 Install “Apache 2.2.25 Win32 x86 No SSL”

7 CENTRAL SERVERS PREPARATION

7.1 Common part


OS Installation:
 Set a user name (if not automatically set)
 Set a password

You must have two partitions on the Hard Drive Disk (partitions “C:” and “D:”), each partition should contain
around 50% of the total memory space.

This document is the property of ELNO and may not be shared or reproduced without written approval. 6/7
IT ENVIRONMENT PREPARATION PAS-PIDS IT Environment
Preparation Procedure - Issue
PROCEDURE 1.1.docx

Delhi Metro Rail Corporation Project Version : 1.1

Network parameters:
 Set a fixed IPv4 address
 Disable Windows firewall:

In Windows Update, select “Check for updates but let me choose whether to download and install them”.

Microsoft .NET Frameworks installation:


 Activate the feature “.NET Framework 3.5.1 Features”, then:
o Check the “.NET Framework 3.5.1” (do not need to check the other line “WCF…”)
 Install “Microsoft .NET Framework 4.5.1”

Microsoft Visual C++ installation:


 Install “Microsoft Visual C++ 2008 Redistributable - x86 9.0.21022”
 Install “Microsoft Visual C++ 2010 Redistributable Package (x86)”

Install SQL Server (offline, or via the Web Platform Installer):


 Install “SQL Server Express 2008 R2 SP2”
 Install “SQL Server 2008 R2 Management Studio Express with SP1”

Database preparation:
 Configure the SQL server, for this launch “SQL Server Configuration Manager”:
o Inside “Network Configuration/ Protocols for SQLEXPRESS”, enable Named Pipes, TCP/IP
and VIA
o Start the “SQL Server Browser” service

7.2 OCC/BCC Servers


This part applies to the preparation of the OCC/BCC Server PCs only.
FTP server configuration:
 Install IIS: open “Server Manager/Roles/Add Roles/Web Server (IIS)/”, check “FTP Server”, then
validate

7.3 NMS Server


This part applies to the preparation of the NMS Server PC only.

Java Runtime installation:


 Install “Java SE Runtime Environment 8 (x86)”