Earned Value Management
Earned Value Management
Actual Cost (AC): The actual cost incurred for the work completed
(also known as Actual Cost of Work Performed - ACWP).
1. Formula: AC = Total cost incurred for the completed work
Cost Variance (CV): The difference between earned value and actual
cost; measures cost performance.
1. Formula: CV = EV - AC
2. Interpretation: Positive CV = Under budget, Negative CV = Over budget
Schedule Variance (SV): The difference between earned value and
planned value; measures schedule performance.
1. Formula: SV = EV - PV
2. Interpretation: Positive SV = Ahead of schedule, Negative SV = Behind
schedule
Data Provided:
1. Planned Value (PV): The project was planned to spend $40,000 by the end of Month 4.
2. Earned Value (EV): The actual work completed by Month 4 is valued at $35,000.
3. Actual Cost (AC): The actual cost incurred by Month 4 is $45,000.
Calculations:
Cost Variance (CV):
o Formula: CV=EV−ACCV = EV - ACCV=EV−AC
o Calculation: CV=$35,000−$45,000=−$10,000CV = \$35,000 - \$45,000 = -\
$10,000CV=$35,000−$45,000=−$10,000
o Interpretation: The project is over budget by $10,000.
Summary:
Cost Variance (CV): -$10,000 (over budget)
Schedule Variance (SV): -$5,000 (behind schedule)
Cost Performance Index (CPI): 0.78 (cost inefficiency)
Schedule Performance Index (SPI): 0.875 (schedule delay)
These EVM metrics provide valuable insights into the project's health, highlighting
areas where corrective actions might be necessary.