0% found this document useful (0 votes)
29 views16 pages

Lecture - CPM Scheduling - AON Networks

CPM Scheduling - AON Networks

Uploaded by

soumya1986
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views16 pages

Lecture - CPM Scheduling - AON Networks

CPM Scheduling - AON Networks

Uploaded by

soumya1986
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

RMIT Classification: Protected

BUSM 1273 - Project Management Techniques

Critical Path Method (CPM) Scheduling –


Part 2: Advanced AON representation

Dr. Frank Boukamp


http://frank.boukamp.net

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
RMIT Classification: Protected
2

Activity on Node (AON) –


Different representations
Simple AoN Advanced AoN
Only used for FS Can be used for all types of
relationships relationship (FS, SS, FF, SF)
as there is a clearly defined
ES EF start side and finish side
Activity Activity
ES EF
name or ID
Duration
SL SL
LS LF
LS Duration LF

Relationship

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 2
RMIT Classification: Protected
3

Activity

Activity
ES EF
name or ID
Finish
Start

LS Duration LF

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 3
RMIT Classification: Protected
4

Finish to Start (FS)

Finish Start

ES ID EF ES ID EF

LS D LF LS D LF

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 4
RMIT Classification: Protected
5

Finish to Finish (FF)

Finish
ES ID EF

LS D LF

ES ID EF

LS D LF

Finish

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 5
RMIT Classification: Protected
6

Start to Start (SS)

Start
ES ID EF

LS D LF

ES ID EF

LS D LF

Start

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 6
RMIT Classification: Protected
7

Start to Finish (SF)

Start
ES ID EF

LS D LF

ES ID EF

LS D LF

Finish

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 7
RMIT Classification: Protected
8

Step one: draw the network


Activity Predecessor

A -
B A
C A
D A
B E
E B, C
F B, C, D H
G F
H E, G
A C F G

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 8
RMIT Classification: Protected

Step one: draw the network


Activity Predecessor
A -
B A
C A
D A E

E B
B
F B, C
G C, D H

H E, F F
I G, H

A C

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 9
RMIT Classification: Protected
10

Step two: forward pass

Earliest Times
• How soon can the activity start? (early start—ES)

• How soon can the activity finish? (early finish—EF)

1 2 3 4 5 6 7 8 9 10 11 12

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 10
RMIT Classification: Protected
11

Forward pass
Choose the latest date of
the predecessors

22
9
5 E 9 22 H 27
27

4 5

12 F 22

10

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 11
RMIT Classification: Protected
12

Step two: forward pass


Activity Predecessor Duration
A - 5
B A 15
C A 10
D A 5
E B, C 15
F B, C, D 10 5 B 20 20 E 35

G F 20 50 H 70
15 15
H E, G 20
20

0 A 5 5 C 15 20 F 30 30 G 50

5 10 10 20

5 D 10

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 12
RMIT Classification: Protected
13

Step three: backward pass

Latest Times

• How late can the activity finish? (late finish—LF)

• How late can the activity start? (late start—LS)

• Which activities represent the critical path?

1 2 3 4 5 6 7 8 9 10 11 12

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 13
RMIT Classification: Protected
14

Backward pass
Choose the earliest date of
the successors

5 E 9 22 H 27

19
9 4 23
13 23 5 28

23
13

12 F 22

13 10 23

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 14
RMIT Classification: Protected
15

Step three: backward pass


Act. Pred. Dur.
A - 5
B A 15
Critical Path: A-B-F-G-H
C A 10
D A 5
E B, C 15 5 B 20 20 E 35

F B, C, D 10 H
50 70
G F 20 5 15 20 35 15 50

H E, G 20 50 20 70

0 A 5 5 C 15 20 F 30 30 G 50

0 5 5 10 10 20 20 10 30 30 20 50

5 D 10

15 5 20

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License. Page 15
RMIT Classification: Protected

Questions?

Dr. Frank Boukamp


e-mail: [email protected]
Office hours: https://frank.boukamp.net/office-hours

This course material by Dr. Frank Boukamp is licensed under a


Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.

You might also like