Method of Statment For Roof Thermal Insulation
Method of Statment For Roof Thermal Insulation
: 00
Method of Statement of roof
thermal Insulation Date:21-9-2021 Page: 1 of 4
00 Hytham El-Nouby
Rev.: 00
Method of Statement of roof
thermal Insulation Date:21-9-2021 Page: 2 of 4
05
04
03
02
01
00 - Original Issue
Rev.: 00
Method of Statement of roof
thermal Insulation Date:21-9-2021 Page: 3 of 4
1- Scope:
The scope of this method is to define the detailed sequence of the installation of
thermal Insulation work for roof
2- Responsibilities:
2-1 Site Manager:
2-1-1 The Site Manager shall be responsible for the overall implementation of
this Method statement, and for ensuring that Site and Section Engineers
are well informed of its requirements.
2-3 Surveyors:
2-3-1 setting out and recheck the locations and elevations of MEP sleeves.
2-4 QC Manager:
2-4-1 Reviewing all relevant documentation and test reports and prepare all
handing over reports.
2-4-2 Clearing all the non-conformances relevant to the activity.
2-4-3 Ensuring that the Engineer’s Representative / Inspector clears all
discipline activities that must be inspected and tested.
2-4-4 Organizing and allocating of inspection works to Quality Control
Inspectors.
2-4-5 Ensuring that all inspection are performed and recorded as per project
specifications.
2-4-6 Ensuring inspections are carried out in a timely manner and documented
as per project inspection plan.
2-5 QC Engineers:
2-5-1 Informing Engineer’s Representative by works Inspection Request as and
when his presence is required to carry out inspections as per the approved
project inspection plan.
2-5-2 Inspect the work as per approved project inspection plan and approved
shop drawings and make sure the work is ready for Owner’s representative
inspection if required.
2-5-3 Accompanying Owner’s Representative \ Inspector to carryout
inspections and release hold points.
2-5-4 Preparing, Signing and obtain signatures from Owner’s Representative/
Inspector on the relevant External Request and ITP.
Rev.: 00
Method of Statement of roof
thermal Insulation Date:21-9-2021 Page: 4 of 4
3- Equipment:
4- Material
4-1 Chema foam thermal insulation density 29 kg/cm3 not less than 1.76 km2/w
as approved material
4-2 Polyethylene sheet 250 micron
5- Procedure:
5-1 Pre-work
5-1-1 Material receiving and storage:
5-1-1-1 Checking supplier’s certificates of compliance to
conform to specification and referenced Standards
prior to installation.
5-2 Work
5-2-4 Over the approved thermal proofing sheets, lay a layer of sloped concrete.
6- Safety:
6-1 All the necessary safety rules, precautions should be followed as indicated in
project safety plan.
6-2 All the necessary safety tools and equipment should be provided as indicated in
project safety plan.
7- Reference:
7-1 Egyptian Code.
7-2 Project Specification.
7-3 Shop Drawings.
Manufactory Data Sheet