ACS - L2 & L3-Access Control System-Testing and Commissioning Script
ACS - L2 & L3-Access Control System-Testing and Commissioning Script
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
Access Control System Testing and commissioning
Page 4 of 13
1.0 PURPOSE
This “Commissioning MS” covers the Guidance of testing & commissioning of Access Control
System in accordance with the approved project quality plan and relevant system specifications.
.
1.1 This procedure is to be read in conjunction with relevant Operators Manual & User’s guide.
1.2 SUPPLIER’s Engineer will carry out the testing and commissioning of the Access Control Panel along with
commissioning team.
1.3 Purpose of this manual to ensure the methods used for Testing & Commissioning of Access Control
described above are correct, acceptable and in line with the consultant quality system procedures to achieve
the optimum results.
2.0 SCOPE
This document details the Access Control system testing and commissioning procedures, for
Implementation as follow:
3.0 REFERENCE
4.0 DEFINITIONS:
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
SK : Store Keeper.
WIR : Work Inspection Request
MIR : Material Inspection Request
ACS : Access Control System
CCTV : Closed Circuit Television
PIN : Personal Identification Number
LAN : Local Area Network
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant
steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Technician from supplier
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
- The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
- Provision of all necessary information and distribution of responsibilities to his Construction team.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
Access Control System Testing and commissioning
Page 6 of 13
- The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for
the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received from the Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
- The monitoring of executions of works at site and should be as per the approved shop drawings and
project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole work
force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the
work activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
Access Control System Testing and commissioning
Page 7 of 13
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
5.8 Technician:
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and
engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
6.0 EQUIPMENTS
▪ Tool Box
▪ Digital Multimeter for voltage and continuity tests.
▪ Measuring Wheel.
▪ Ladders.
▪ Scaffolding (to be provided by the contractor for the High level Area).
▪ Commissioning Laptop
▪ Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest,
and safety gloves to insure maximum ability of safe work and dust mask when required.
7.0 PROCEDURE
- Persons engaged with Testing have to be skilled and have received proper and adequate training on
safety and should be maintained in safe condition and the Testing methods not to create danger
either for the operator or for other persons or livestock.
- Necessary PPE to be worn while working in energized to be worn while working in energized
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
Access Control System Testing and commissioning
Page 8 of 13
circuits.
- Ensure adequate lighting is provided in the working area at night time and if inside the building area
to be well illuminated.
- Ensure service area/work area openings are provided with barricade, tape, safety nets and warning
signage to be provided.
- Emergency evacuation plan and procedure to be developed prior to start of testing.
- PTW to be applied and obtained to start work on the required area.
- Calibrated Instruments only to be used.
- Access Control Panel to the Field Devices such as Card Readers, Push Button, Break Glass, Power
Supply unit, Network Switch and Electro Magnetic Locks etc. must the tested.
- Ensure the Power Cable Tests between Panel and Power Supply unit and Electro Magnetic Lock to
the Power Supply units.
7.2.B. Power up
- Check Mains (PE,N,L) cables
- Check Mains Voltage.
- Check all cable termination.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
Access Control System Testing and commissioning
Page 9 of 13
1. Turn-On the Power Supply (Must be equipped with Battery) of Main Access Control Panel and
check the faulty notices.
2. Use Multimeter and check the output voltage of the Power Supply unit for the ACS Panel and Field
Devices.
3. Install the Access control software in PC/Server and start communicating the Access Control Panel
through the live Network.
4. Install, Configure the SQL Server for the Access Database.
5. Start Configuring the Access Control Panel and Field devices through the live Network
6. Once the Access Controllers are communicated, and then assign all the parameters.
7. Start the testing with the field Devices by:
a. Pressing the Push Button to check the Door Operation through the Magnetic Lock.
b. Break Glass to check the Door Operation through the Magnetic Lock & Alarm Generation in
the PC.
c. Flashing the Smart Card into the Card Readers to check the Door Operation through the
Magnetic Lock.
8. Ensure all the Field Devices (Card Reader, Push Button, Door Contacts, Break Glass, and Power
Supply Units) and Controllers are working properly.
9. Ensure Interlocking with Fire Alarm system is verified.
10. Ensure all alarms generated are noticed in the graphic loaded monitoring PC/Server.
11. Ensure Access Control System had an interface with C.C.T.V. system.
12. Ensure from the software that locking hardware functioning correctly.
13. Ensure the I/O configuration is done as per the requirements in the Software.
14. All the doors and door equipment’s is Label as per approved drawings in the graphic loaded
monitoring PC/Server.
15. Verify that all the door opening status is displayed in the PC/Server.
16. Ensure all events are report back to the PC where Access Control Software installed
17. Configure the Redundant Server and connect to the LAN.
18. Monitor the Software functionalities (PC/Server related) and its operations.
7.3.2. BatteryConnection
- NOTE: The Control Panel will not operate on Batteries until the Mains Power has been applied.
- Connecting the batteries to the Control Panel should only be performed after the wiring checks have
been completed successfully.
- After the successful completion of testing & commissioning the system will be ready to be
demonstrated to the facility management team and all concerned parties.
- During this period SUPPLIER engineer will assist the involved parties to operate and familiarise with
the system.
- All operations will be carried out by the operators and facility team in this period until they are able to
handle the system without any doubts.
- One day demonstration will be provided by SUPPLIER engineer and next 3 days will be assumed as
familiarisation period to the concerned parties. Any doubts or clarifications they may require to be
clarified in these days will be done by SUPPLIER engineer
8.0 ATTACHMENTS
- Risk Assessment
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 1 of 9
REVISION RECORD
This cover page is a record of all revisions of the documents identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 3 of 9
CONTENTS
1.0 SCOPE
2.0 PURPOSE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 PROCEDURE
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 4 of 9
1.0 SCOPE:
.
This procedure applies to all the inspection activities related to monitoring and measurement of
products and Processes related for the Installation or testing of subject activity where applicable for the
project and Applicable to:
• Method Statement.
• Quality Control Procedure.
• Inspection and Test Plans.
• Risk Assessments
• FORMS.
2.0 PURPOSE:
o Identify processes / products those are to be installed before using them in intended application.
o Define the methods to verify the quality of products and ensure that products that meet the stated
requirements are only used in the intended application.
3.0 REFERENCES
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 5 of 9
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
- Coordinating with QA/QC Engineer and site Team and foremen for all activities on site.
- The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
- Provision of all necessary information and distribution of responsibilities to his Construction team.
- The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for
the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received from the Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
- The monitoring of executions of works at site and should be as per the approved shop drawings and
project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 6 of 9
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available resources in coordination with
the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole work
force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the
work activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material delivery to the site and
Ref. No. :
TITLE Rev. No. 0
Quality Control Procedure
Date :
Page 7 of 9
keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
- If QA/QC not available the adequate QA/QC Engineer will be responsible for quality control
activities.
- If the P.M. not available the Construcion manager will be resposible for all of his activities.
- If the HSE Engineer not available the adequate HSE Engineer are resposible for safety activities.
- If Engineer not available Construction manager will assign his duties to the concerned supervisor,
forman or alternate Engineer.
- Replacing staff, in case of absent, with another designation can be accepted only for a minimum
period of days absent otherwise the Contractor shall replace the relevant person with same
designation which required approval from CONSULTANT.
6.0 PROCEDURE:
- Check that all the following documentations have been approved by the Consultant to proceed with
the installation activities:
- Check all the delivered materials are inspected and approved by the Consultant’s Engineer.
- Ensure that the respective work area has been cleared by previous trades for start-up installing the
system.
- Ensure that the installation of the material is as per approved shop drawings, approved method
statement, Manufacturer’s recommendation, and prevailing quality standards.
- Ensure the following checks are performed during the installation progress:
- Check all materials are as per approved submittal.
- Check all Material are installed as per approved shop drawings.
- Check if coordinated with other services.
- Check installation if it is carried out as per approved method statement.
- Check that the system checked and approved by Consultant.
- Ensure WIRs are issued on time without delay. (Min. 24 Hours notice for site inspection).
- Ensure all inspection is performed as per approved Inspection Test Plan.
- Check ITP, Check List, WIR, and NCR (if any) are signed off and cleared by the Consultant
Engineer.
Ref. No. :
TITLE: ITP Rev. No. 0
Date :
ITP
INSPECTION & TEST PLAN
PROJECT NAME & DETAILS
REF. NO.
REV. NO. 0
DATE :
PAGE : 1 OF 1
AREA/LOCATION:
1 DOCUMENTATION
Once (Approval prior to
1.1 Pre-Qualification subcontractor Project Specifications and drawings. H H R
submit the submittal)
1.2 Shop Drawing Approval Each Shop Drawing Project Specifications and drawings. H H R
NAME : NAME :
SIGN : SIGN :
DATE: DATE:
PAGE 1 of 1
Ref. No. :
TITLE Rev. No. 0
Date :
T&C CHECKLISTS
T&C CHECKLISTS
Project Name Client Consultant Contractor
DOCUMENT TYPE: METHOD OF STATEMENT T&C FOR SECURITY ACCESS CONTROL SYSTEM
HATCO CX ENGINEER
CXA ENGINEER
EDARAT GROUP
Project Name Client Consultant Contractor
DOCUMENT TYPE: METHOD OF STATEMENT T&C FOR SECURITY ACCESS CONTROL SYSTEM
L3 CHECKLIST / COMMISSIONING OF SECURITY ACCESS CONTROL SYSTEM
PROJECT : RIYADH DATA CENTRES TIER III RFI Ref No: Date:
CLIENT : SFC-MIS MST Ref No:
CONSULTANT : EDARAT GROUP MEP Ref. Drawing No.:
CONTRACTOR : HATCO Control unit manufacturer:
Manufacturer: Building Name:
Model: Panel location:
ACTIVITIES/ITEMS TO BE INSPECTED STATUS
Ok Not Ok N/A REMARKS
REMARKS:
HATCO CX ENGINEER
CXA ENGINEER
EDARAT GROUP
Project Name Client Consultant Contractor
DOCUMENT TYPE: METHOD OF STATEMENT T&C FOR SECURITY ACCESS CONTROL SYSTEM
L3 CHECKLIST / COMMISSIONING OF SECURITY ACCESS CONTROL SYSTEM
PROJECT : RIYADH DATA CENTRES TIER III RFI Ref No: Date:
CLIENT : SFC-MIS MST Ref No:
CONSULTANT : EDARAT GROUP MEP Ref. Drawing No.:
CONTRACTOR : HATCO Control unit manufacturer:
Manufacturer: Building Name:
Model: Panel location:
ACTIVITIES/ITEMS TO BE INSPECTED STATUS
Ok Not Ok N/A REMARKS
REMARKS:
CXA ENGINEER
EDARAT GROUP
Project Name Client Consultant Contractor
DOCUMENT TYPE: METHOD OF STATEMENT T&C FOR SECURITY ACCESS CONTROL SYSTEM
RISK ASSESSMENT&MATRIX
RISK ASSESSMENT&MATRIX
Ref No:
ACTIVITY– Access Control System Testing and commissioning Rev.No:0
Page 1 of 5
Ref No:
ACTIVITY– Access Control System Testing and commissioning Rev.No:0
Page 2 of 5
Ref No:
ACTIVITY– Access Control System Testing and commissioning Rev.No:0
Page 3 of 5
Ref No:
ACTIVITY– Access Control System Testing and commissioning Rev.No:0
Page 4 of 5
Ref No:
ACTIVITY– Access Control System Testing and commissioning Rev.No:0
Page 5 of 5
RISK MATRIX
Probability
A B C D E
Improbable Remote Occasional
Probable Frequent
Severity People Assets Environment Reputation 1 in 100,000 1 in 10,000 1 in 1000
1 in 100 years 1 in 10 years
Years Years years
Multiple
fatalities or
Extensive International
5-Catatrophic permanent Massive effect
damage impact
total
disabilities
Single
fatalities or
4-Severe permanent
Major
Major effect National impact
High Risk
damage
total
disabilities
Major injury
Local Considerable
Medium Risk
3-critical or health Localised effect (ALARP)
damage impact
effects
Minor
Minor
2-Marginal injury or Minor effect Minor impact
damage
health effects
Slight injury
Slight
1-Negligble or health
Damage
Slight effect Slight impact Low Risk
effects
3-E
HIGH 4-C,D,E
5-B,C,D,E
1-D,E
2-B,C,D,E
3-A,B,C,D
MEDIUM 4-A,B
5-A
LOW 1-A,B,C
2A