Tender Document For Swimming Pool and Gazebo
Tender Document For Swimming Pool and Gazebo
TENDER NAME:
PROPOSED CONSTRUCTION OF SWIMMING POOL
AND GAZEBO AT THE SPEAKER’S OFFICIAL
RESIDENCE..
TENDER NO:
CAK/003/04/2018/2019
CLIENT
COUNTY ASSEMBLY OF KWALE
P.O BOX 231-80403,
KWALE
PREPARED BY:
ACCOUNTING OFFICER
KWALE COUNTY ASSEMBLY
1
MONDAY 15TH APRIL 2019,
RETURN THE DOCUMENT ON OR BEFORE MONDAY 2019,
10:0
10:00AM
TABLE OF CONTENTS
PAGE
INTRODUCTION ..………………………………………………1
SECTION V: SPECIFICATIONS...…………………………………………… 40 - 41
2
INTRODUCTION
1.1 This standard tender document for procurement of works has been prepared
for use by procuring entities in Kenya in the procurement of works (i.e.
Buildings and associated Civil Engineering Works).
1.2 The following guidelines should be observed when using the document:-
(a) Specific details should be furnished in the Invitation to tender and in
the special conditions of contract (where applicable). The tender
document issued to tenderers should not have blank spaces or
options.
1.3
(b) Information contained in the invitation to tender shall conform to the
data and information in the tender documents to enable prospective
tenderers to decide whether or not to participate in the tender and shall
indicate any important tender requirements
I. Tender number.
II. Tender name.
III. Name of procuring entity.
3
SECTION I
1.1 1.2 Interested eligible candidates may obtain further information and inspect
tender documents at county Assembly of Kwale, P.O BOX 231, Kwale during
normal working hours. Tender documents can be downloaded for free at
www.kwalecountyassembly.co.ke
1.4 Prices quoted should be net inclusive of all taxes, must be in Kenya shillings
and shall remain valid for ( 120 ) days from the closing date of tender.
1.5 Completed tender documents are to be submitted with Tender name and
reference number via the online supplier portal platform.
(Accounting Officer)
FATUMA H MWALUPA
Ag CLERK KWALE COUNTY ASSEMBLY
4
SECTION II
INSTRUCTIONS TO TENDERERS
CLAUSE PAGE
1. General …………………………………………………. 4
5
INSTRUCTIONS TO TENDERERS.
1.2 All tenderers shall provide the Qualification Information, a statement that
the tenderer (including all members of a joint venture and subcontractors) is
not associated, or has not been associated in the past, directly or indirectly,
with the Consultant or any other entity that has prepared the design,
specifications, and other documents for the project or being proposed as
Project Manager for the Contract. A firm that has been engaged by the
Employer to provide consulting services for the preparation or supervision of
the Works, and any of its affiliates, shall not be eligible to tender.
1.3 All tenderers shall provide in the Form of Tender and Qualification
Information, a preliminary description of the proposed work method and
schedule, including drawings and charts, as necessary.
(b) total monetary value of construction work performed for each of the
last five years:
(c) experience in works of a similar nature and size for each of the last
five years, and details of work under way or contractually committed;
and names and addresses of clients who may be contacted for further
information on these contracts;
6
(d) Major items of construction equipment proposed to carry out the
Contract and an undertaking that they will be available for the
Contract.
(f) reports on the financial standing of the tenderer, such as profit and
loss statements and auditor’s reports for the past five years;
(i) information regarding any litigation, current or during the last five
years, in which the tenderer is involved, the parties concerned and
disputed amount; and
1.6 Tenders submitted by a joint venture of two or more firms as partners shall
comply with the following requirements, unless otherwise stated:
(a) the tender shall include all the information listed in clause 1.5
above for each joint venture partner;
(c) all partners shall be jointly and severally liable for the execution
of the Contract in accordance with the Contract terms;
1.7 To qualify for award of the Contract, tenderers shall meet the following
minimum qualifying criteria;
(a) annual volume of construction work of at least 2.5 times the estimated
annual cashflow for the Contract;
7
(c) two works of a nature and complexity equivalent to the Works
over the last 10 years (to comply with this requirement, works cited
should be at least 70 percent complete);
(d) proposals for the timely acquisition (own, lease, hire, etc.) of the essential
equipment listed as required for the Works;
1.8 The figures for each of the partners of a joint venture shall be added
together to determine the tenderer’s compliance with the minimum
qualifying criteria of clause 1.7 (a) and (e); however, for a joint venture to
qualify, each of its partners must meet at least 25 percent of minimum
criteria 1.7 (a), (b) and (e) for an individual tenderer, and the partner in
charge at least 40 percent of those minimum criteria. Failure to comply with
this requirement will result in rejection of the joint venture’s tender.
Subcontractors’ experience and resources will not be taken into account in
determining the tenderer’s compliance with the qualifying criteria, unless
otherwise stated.
1.9 Each tenderer shall submit only one tender, either individually or as a
partner in a joint venture. A tenderer who submits or participates in more
than one tender (other than as a subcontractor or in cases of alternatives
that have been permitted or requested) will cause all the proposals with the
tenderer’s participation to be disqualified.
1.10 The tenderer shall bear all costs associated with the preparation and
submission of his tender, and the Employer will in no case be responsible or
liable for those costs.
1.11 The tenderer, at the tenderer’s own responsibility and risk, is encouraged to
visit and examine the Site of the Works and its surroundings, and obtain all
information that may be necessary for preparing the tender and entering
into a contract for construction of the Works. The costs of visiting the Site
shall be at the tenderer’s own expense.
1.12 The procuring entity’s employees, committee members, board members and
their relative (spouse and children) are not eligible to participate in the
tender.
1.13 The price to be changed for the tender document shall be free.
8
1.14 The procuring entity shall allow the tenderer to review the tender document
free of charge before purchase.
2. Tender Documents
2.1 The complete set of tender documents comprises the documents listed below
and any addenda issued in accordance with Clause 2.4.
2.2 The tenderer shall examine all Instructions, Forms to be filled and
Specifications in the tender documents. Failure to furnish all information
required by the tender documents, or submission of a tender not
substantially responsive to the tendering documents in every respect will be
at the tenderer’s risk and may result in rejection of his tender.
2.4 Before the deadline for submission of tenders, the Employer may modify the
tendering documents by issuing addenda. Any addendum thus issued shall
be part of the tendering documents and shall be communicated in writing or
by cable, telex or facsimile to all tenderers. Prospective tenderers shall
acknowledge receipt of each addendum in writing to the Employer.
3. Preparation of Tenders
3.1 All documents relating to the tender and any correspondence shall be in
English language.
9
3.2 The tender submitted by the tenderer shall comprise the following:
3.3 The tenderer shall fill in rates and prices for all items of the Works described
in the Bill of Quantities. Items for which no rate or price is entered by the
tenderer will not be paid for when executed and shall be deemed covered by
the other rates and prices in the Bill of Quantities. All duties, taxes, and
other levies payable by the Contractor under the Contract, or for any other
cause relevant to the Contract, as of 30 days prior to the deadline for
submission of tenders, shall be included in the tender price submitted by
the tenderer.
3.4 The rates and prices quoted by the tenderer shall only be subject to
adjustment during the performance of the Contract if provided for in the
Appendix to Conditions of Contract and provisions made in the Conditions of
Contract.
3.6 Tenders shall remain valid for a period of sixty (120) days from the date of
submission. However in exceptional circumstances, the Employer may
request that the tenderers extend the period of validity for a specified
additional period. The request and the tenderers’ responses shall be made
in writing. A tenderer may refuse the request without forfeiting the Tender
Security. A tenderer agreeing to the request will not be required or
permitted to otherwise modify the tender, but will be required to extend the
validity of Tender Security for the period of the extension, and in compliance
with Clause 3.7 - 3.11 in all respects.
3.7 The tenderer shall furnish, as part of the tender, a Tender Security in the
amount and form specified in the appendix to invitation to tenderers. This
shall be in the amount not exceeding 2 percent of the tender price
3.8 The format of the Tender Security should be in accordance with the form of
Tender Security included in Section G - Standard forms or any other form
10
acceptable to the Employer. Tender Security shall be valid for 30 days
beyond the validity of the tender.
3.11 The Tender Security of the successful tenderer will be discharged when the
tenderer has signed the Contract Agreement and furnished the required
Performance Security.
(a) if the tenderer withdraws the tender after tender opening during the
period of tender validity;
(b) if the tenderer does not accept the correction of the tender price,
pursuant to Clause 5.7;
(c) in the case of a successful tenderer, if the tenderer fails within the
specified time limit to
3.13 Tenderers shall submit offers that comply with the requirements of the
tendering documents, including the basic technical design as indicated in
the Drawings and Specifications. Alternatives will not be considered, unless
specifically allowed in the invitation to tender. If so allowed, tenderers
wishing to offer technical alternatives to the requirements of the tendering
documents must also submit a tender that complies with the requirements
of the tendering documents, including the basic technical design as
indicated in the Drawings and Specifications. In addition to submitting the
basic tender, the tenderer shall provide all information necessary for a
complete evaluation of the alternative, including design calculations,
technical specifications, breakdown of prices, proposed construction
methods and other relevant details. Only the technical alternatives, if any,
of
the lowest evaluated tender conforming to the basic technical requirements
shall be considered.
3.14 The tenderer shall prepare one original of the documents comprising the
tender documents as described in Clause 3.2 of these Instructions to
Tenderers, bound with the volume containing the Form of Tender,
11
and clearly marked “ORIGINAL”. In addition, the tenderer shall submit
copies of the tender, in the number specified in the invitation to tender, and
clearly marked as “COPIES”. In the event of discrepancy between them, the
original shall prevail.
3.15 The original and all copies of the tender shall be typed or written in indelible
ink and shall be signed by a person or persons duly authorised to sign on
behalf of the tenderer, pursuant to Clause 1.5 (a) or 1.6 (b), as the case may
be. All pages of the tender where alterations or additions have been made
shall be initialed by the person or persons signing the tender.
3.17 The procuring entity shall reply to any clarifications sought by the tenderer
within 3 days of receiving the request to enable the tenderer to make timely
submission of its tender.
3.18 The tender security shall be in the amount of 0.5 – 2 per cent of the tender
price.
4. Submission of Tenders
4.1 The tenderer shall seal the original and all copies of the tender in two inner
envelopes and one outer envelope, duly marking the inner envelopes as
“ORIGINAL” and “COPIES” as appropriate. The inner and outer envelopes
shall:
(b) bear the name and identification number of the Contract as defined in
the invitation to tender; and
(c) provide a warning not to open before the specified time and date for
tender opening.
4.2 Tenders shall be delivered to the Employer at the address specified above not
later than the time and date specified in the invitation to tender. However,
the Employer may extend the deadline for submission of tenders by issuing
an amendment in accordance with Sub-Clause 2.5 in which case all rights
and obligations of the Employer and the tenderers previously subject to the
original deadline will then be subject to the new deadline.
4.3 Any tender received after the deadline prescribed in clause 4.2 will be
returned to the tenderer un-opened.
12
4.4 Tenderers may modify or withdraw their tenders by giving notice in writing
before the deadline prescribed in clause 4.2. Each tenderer’s modification or
withdrawal notice shall be prepared, sealed, marked,
and delivered in accordance with clause 3.13 and 4.1, with the outer and
inner envelopes additionally marked “MODIFICATION “and
“WITHDRAWAL”, as appropriate. No tender may be modified after the
deadline for submission of tenders.
4.6 Tenderers may only offer discounts to, or otherwise modify the prices of their
tenders by submitting tender modifications in accordance with Clause 4.4 or
be included in the original tender submission.
5.1 The tenders will be opened by the Employer, including modifications made
pursuant to Clause 4.4, in the presence of the tenderers’ representatives who choose to
attend at the time and in the place specified in the invitation to tender. Envelopes
marked “WITHDRAWAL” shall be opened and read out first. Tenderers’ and Employer’s
representatives who are present during the opening shall sign a register evidencing
their attendance.
5.2 The tenderers’ names, the tender prices, the total amount of each tender and
of any alternative tender (if alternatives have been requested or permitted),
any discounts, tender modifications and withdrawals, the presence or
absence of Tender Security, and such other details as may be considered
appropriate, will be announced by the Employer at the opening. Minutes of
the tender opening, including the information disclosed to those present will
be prepared by the Employer.
13
5.5 Prior to the detailed evaluation of tenders, the Employer will determine
whether each tender (a) meets the eligibility criteria defined
in Clause 1.7;(b) has been properly signed; (c) is accompanied by the
required securities; and (d) is substantially responsive to the requirements of
the tendering documents. A substantially responsive tender is one which
conforms to all the terms, conditions and specifications of the tendering
documents, without material deviation or reservation. A material deviation
or reservation is one (a) which affects in any substantial way the scope,
quality, or performance of the works; (b) which limits in any substantial way,
inconsistent with the tendering documents, the Employer’s rights or the
tenderer’s obligations under the Contract; or (c) whose rectification would
affect unfairly the competitive position of other tenderers presenting
substantially responsive tenders.
5.6 If a tender is not substantially responsive, it will be rejected, and may not
subsequently be made responsive by correction or withdrawal of the
nonconforming deviation or reservation.
(a) where there is a discrepancy between the amount in figures and the
amount in words, the amount in words will prevail; and
(b) Where there is a discrepancy between the unit rate and the line item
total resulting from multiplying the unit rate by the quantity, the unit
rate as quoted will prevail, unless in the opinion of the Employer,
there is an obvious typographical error, in which case the adjustment
will be made to the entry containing that error.
(e) The Error Correction Factor shall be applied to all Builder’s Work (as a
rebate or addition as the case may be) for the purposes of valuations
for Interim Certificates and valuation of variations.
(f) the amount stated in the tender will be adjusted in accordance with
the above procedure for the correction of errors and, with
Concurrence of the tenderer, shall be considered as binding upon the
tenderer. If the tenderer does not accept the corrected amount, the
14
tender may be rejected and the Tender Security may be forfeited in
accordance with clause 3.11.
5.8 The Employer will evaluate and compare only the tenders determined to be
substantially responsive in accordance with Clause 5.5.
5.9 In evaluating the tenders, the Employer will determine for each tender the
evaluated tender price by adjusting the tender price as follows:
(b) Excluding provisional sums and the provision, if any, for contingencies
in the Bill of Quantities, but including Day works where priced
competitively.
5.10 The Employer reserves the right to accept or reject any variation, deviation,
or alternative offer. Variations, deviations, and alternative offers and other
factors which are in excess of the requirements of the tender documents or
otherwise result in unsolicited benefits for the Employer will not be taken
into account in tender evaluation.
5.11 The tenderer shall not influence the Employer on any matter relating to his
tender from the time of the tender opening to the time the Contract is
awarded. Any effort by the Tenderer to influence the Employer or his
employees in his decision on tender evaluation, tender comparison or
Contract award may result in the rejection of the tender.
5.12 Firms incorporated in Kenya where indigenous Kenyans own 51% or more of
the share capital shall be allowed a 10% preferential bias provided that they
do not sub-contract work valued at more than 50% of the Contract Price
excluding Provisional Sums to an
Non-indigenous sub-contractor
6. Award of Contract
6.1 Subject to Clause 6.2, the award of the Contract will be made to the tenderer
whose tender has been determined to be substantially
responsive to the tendering documents and who has offered the lowest
evaluated tender price, provided that such tenderer has been determined to
be (a) eligible in accordance with the provision of Clauses 1.2, and (b)
qualified in accordance with the provisions of clause 1.7 and 1.8.
15
6.2 Notwithstanding clause 6.1 above, the Employer reserves the right to
accept or reject any tender, and to cancel the tendering process and reject all
tenders, at any time prior to the award of Contract, without thereby
incurring any liability to the affected tenderer or tenderers or any obligation
to inform the affected tenderer or tenderers of the grounds for the action.
6.3 The tenderer whose tender has been accepted will be notified of the award
prior to expiration of the tender validity period in writing or by cable, telex or
facsimile. This notification (hereinafter and in all Contract documents called
the “Letter of Acceptance”) will state the sum (hereinafter and in all Contract
documents called the “Contract Price”) that the Employer will pay the
Contractor in consideration of the execution, completion, and maintenance
of the Works by the Contractor as prescribed by the Contract. At the same
time the other tenderers shall be informed that their tenders have not been
successful.
6.4 The Agreement will incorporate all agreements between the Employer and
the successful tenderer. Within 14 days of receipt the successful tenderer
will sign the Agreement and return it to the Employer.
6.5 Within 21 days after receipt of the Letter of Acceptance, the successful
tenderer shall deliver to the Employer a Performance Security in the amount
stipulated in the Appendix to Conditions of Contract and in the form
stipulated in the Tender documents. The Performance Security shall be in
the amount and specified form
6.6 Failure of the successful tenderer to comply with the requirements of clause
6.5 shall constitute sufficient grounds for cancellation of the award and
forfeiture of the Tender Security.
6.7 Upon the furnishing by the successful tenderer of the Performance Security,
the Employer will promptly notify the other tenderers that their tenders have
been unsuccessful.
6.8 Preference where allowed in the evaluation of tenders shall not be allowed for
contracts not exceeding one year (12 months)
6.9 The tender evaluation committee shall evaluate the tender within 30 days of the
validity period from the date of opening the tender.
6.10 The parties to the contract shall have it signed within 30 days from the date
of notification of contract award unless there is an administrative review
request.
6.11 Contract price variations shall not be allowed for contracts not exceeding
one year (12 months)
16
6.12 Where contract price variation is allowed, the valuation shall not exceed 20%
of the original contract price.
6.13 Price variation request shall be processed by the procuring entity within 30
days of receiving the request.
6.14 The procuring entity may at any time terminate procurement proceedings
before contract award and shall not be liable to any person for the
termination.
6.15 The procuring entity shall give prompt notice of the termination to the
tenderers and on request give its reasons for termination within 14 days of
receiving the request from any tenderer.
6.16 A tenderer who gives false information in the tender document about its
qualification or who refuses to enter into a contract after notification of
contract award shall be considered for debarment from participating in
future public procurement.
7.1 The procuring entity requires that tenderers observe the highest standards
of ethics during procurement process and execution of contracts. A tenderer
shall sign a declaration that he has not and will not be involved in corrupt
and fraudulent practices.
17
SECTION III
CONDITIONS OF CONTRACT
Table of Contents
1 Definitions ………………………………………………… 15
2 Interpretation……………………………………………… 17
3 Language and Law ………………………………………… 17
4 Project Manager’s Decisions……………………………… 17
5 Delegation………………………………………………… 18
6 Communications ………………………………………… 18
7 Sub Contracting ………………………………………… 18
8 Other Contractors ……………………………………… 18
9 Personnel ………………………………………………… 18
10 Works……………………………………………………… 19
11 Safety and temporary works ……………………………… 19
12 Discoveries ………………………………………………… 19
13 Work Programme ………………………………………… 19 -20
14 Possession of site ………………………………………… 20
15 Access to site …………………………………………… 20
16 Instructions ……………………………………………… 20
17 Extension or Acceleration of completion date ………… 20
18 Management Meetings ………………………………… 21
19 Early Warning …………………………………………… 21
20 Defects …………………………………………………… 21 - 22
21 Bills of Quantities ………………………………………… 22
22 Variations ………………………………………………… 22- 23
23 Payment certificates, currency of payments and
Advance Payments ……………………………………… 23
24 Compensation events …………………………………… 25 - 27
25 Price Adjustment ………………………………………… 27 - 29
18
26 Retention ………………………………………………… 29
27 Liquidated Damages……………………………………… 29
28 Securities ………………………………………………… 29
29 Day Works ……………………………………………… 29 - 30
30 Liability and Insurance …………………………………… 30 - 31
31 Completion and taking over ……………………………… 31
32 Final Account …………………………………………… 31
33 Termination ……………………………………………… 31 - 32
34 Payment upon termination ………………………………… 32 - 33
35 Release from performance ………………………………… 33
36 Corrupt gifts and payments of commission ………………33 - 34
37 Settlement of Disputes ……………………………………… 34 - 36
19
CONDITIONS OF CONTRACT
1. Definitions
1.1 In this Contract, except where context otherwise requires, the following
terms shall be interpreted as indicated;
“The Contract” means the agreement entered into between the Employer
and the Contractor as recorded in the Agreement Form and signed by the
parties including all attachments and appendices thereto and all documents
incorporated by reference therein to execute, complete, and maintain the
Works,
“The Contract Price” is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.
“A Defect” is any part of the Works not completed in accordance with the
Contract.
“The Defects Liability Period” is the period named in the Contract Data
and calculated from the Completion Date.
20
“Drawings” include calculations and other information provided or approved
by the Project Manager for the execution of the Contract.
“Dayworks” are Work inputs subject to payment on a time basis for labour
and the associated materials and plant.
“Plant” is any integral part of the Works that shall have a mechanical,
electrical, chemical, or biological function.
“Site Investigation Reports” are those reports that may be included in the
tendering documents which are factual and interpretative about the surface
and subsurface conditions at the Site.
“Start Date” is the latest date when the Contractor shall commence
execution of the Works. It does not necessarily coincide with the Site
possession date(s).
21
“A Subcontractor” is a person or corporate body who has a Contract with
the Contractor to carry out a part of the Work in the Contract, which
includes Work on the Site.
“The Works” are what the Contract requires the Contractor to construct, install,
and turnover to the Employer, as defined in the Appendix to Conditions of
Contract.
2. Interpretation
2.3 The following documents shall constitute the Contract documents and shall
be interpreted in the following order of priority;
(1) Agreement,
(6) Specifications,
(7) Drawings,
22
Immediately after the execution of the Contract, the Project Manager
shall furnish both the Employer and the Contractor with two copies
each of all the Contract documents. Further, as and when necessary
the Project Manager shall furnish the Contractor [always with a copy
to the Employer] with three [3] copies of such further drawings or
details or descriptive schedules as are reasonably necessary either
to explain or amplify the Contract drawings or to enable the
Contractor to carry out and complete the Works in accordance with
these Conditions.
3.1 Language of the Contract and the law governing the Contract shall be
English language and the Laws of Kenya respectively unless
otherwise stated.
4.1 Except where otherwise specifically stated, the Project Manager will decide
contractual matters between the Employer and the Contractor in the role
representing the Employer.
5 Delegation
5.1 The Project Manager may delegate any of his duties and responsibilities to
others after notifying the Contractor.
6 Communications
7 Subcontracting
7.1 The Contractor may subcontract with the approval of the Project Manager,
but may not assign the Contract without the approval of the Employer in
writing. Subcontracting shall not alter the Contractor’s obligations.
8 Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors,
public authorities, utilities etc. as listed in the Appendix to Conditions of
Contract and also with the Employer, as per the directions of the Project
Manager. The Contractor shall also provide facilities and services for them.
The Employer may modify the said List of Other Contractors etc., and shall
notify the Contractor of any such modification.
9 Personnel
23
9.1 The Contractor shall employ the key personnel named in the Qualification
Information, to carry out the functions stated in the said Information or
other personnel approved by the Project Manager. The Project Manager will
approve any proposed replacement of key personnel only if their relevant
qualifications and abilities are substantially equal to or better than those of
the personnel listed in the Qualification Information. If the Project Manager
asks the Contractor to remove a person who is a member of the Contractor’s
staff or work force, stating the reasons, the Contractor shall ensure that the
person leaves the Site within seven days and has no further connection with
the Work in the Contract.
10 Works
10.1 The Contractor shall construct and install the Works in accordance with the
Specifications and Drawings. The Works may commence on the Start Date
and shall be carried out in accordance with the Program submitted by the
Contractor, as updated with the approval of the Project Manager, and
complete them by the Intended Completion Date.
11.1 The Contractor shall be responsible for the design of temporary works.
However before erecting the same, he shall submit his designs including
specifications and drawings to the Project Manager and to any other relevant
third parties for their approval. No erection of temporary works shall be
done until such approvals are obtained.
11.2 The Project Manager’s approval shall not alter the Contractor’s responsibility
for design of the Temporary works and all drawings prepared by the
Contractor for the execution of the temporary or permanent Works, shall be
subject to prior approval by the Project Manager before they can be used.
11.3 The Contractor shall be responsible for the safety of all activities on the Site.
12. Discoveries
13.1 Within the time stated in the Appendix to Conditions of Contract, the
Contractor shall submit to the Project Manager for approval a program
showing the general methods, arrangements, order, and timing for all the
activities in the Works. An update of the program shall be a program
showing the actual progress achieved on each activity and the effect of
24
the progress achieved on the timing of the remaining Work, including any
changes to the sequence of the activities.
The Contractor shall submit to the Project Manager for approval an updated
program at intervals no longer than the period stated in the Appendix to
Conditions of Contract. If the Contractor does not submit an updated
program within this period, the Project Manager
may withhold the amount stated in the said Appendix from the next
payment certificate and continue to withhold this amount until the next
payment after the date on which the overdue program has been submitted.
The Project Manager’s approval of the program shall not alter the
Contractor’s obligations. The Contractor may revise the program and
submit it to the Project Manager again at any time. A revised program shall
show the effect of Variations and Compensation Events.
14.1 The Employer shall give possession of all parts of the Site to the
Contractor. If possession of a part is not given by the date stated in the
Appendix to Conditions of Contract, the Employer will be deemed to
have delayed the start of the relevant activities, and this will be a
Compensation Event.
15.1 The Contractor shall allow the Project Manager and any other person
authorised by the Project Manager, access to the Site and to any place
where work in connection with the Contract is being carried out or is
intended to be carried out.
16. Instructions
16.1 The Contractor shall carry out all instructions of the Project Manager
which are in accordance with the Contract.
17.1 The Project Manager shall extend the Intended Completion Date if a
Compensation Event occurs or a variation is issued which makes it
impossible for completion to be achieved by the Intended Completion
Date without the Contractor taking steps to accelerate the remaining
Work, which would cause the Contractor to incur additional cost. The
Project Manager shall decide whether and by how much to extend the
Intended Completion Date within 21 days of the Contractor asking the
Project Manager in writing for a decision upon the effect of a
Compensation Event or variation and submitting full supporting
information. If the Contractor has failed to give early warning of a delay
or has failed to cooperate in dealing with a delay, the delay caused by
25
such failure shall not be considered in assessing the new (extended)
Completion Date.
17.2 No bonus for early completion of the Works shall be paid to the
Contractor by the Employer.
19.1 The Contractor shall warn the Project Manager at the earliest opportunity
of specific likely future events or circumstances that may adversely affect
the quality of the Work, increase the Contract Price or delay the execution
of the Works. The Project Manager may require the Contractor to provide
an estimate of the expected effect of the future event or circumstance on
the Contract Price and Completion Date. The estimate shall be provided
by the Contractor as soon as reasonably possible.
19.2 The Contractor shall cooperate with the Project Manager in making and
considering proposals on how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the
Work and in carrying out any resulting instructions of the Project
Manager.
20. Defects
20.1 The Project Manager shall inspect the Contractor’s work and notify the
Contractor of any defects that are found. Such inspection shall not affect
the Contractor’s responsibilities. The Project Manager may instruct the
Contractor to search for a defect and to uncover and test any Work that
the Project Manager considers may have a defect. Should the defect be
found, the cost of uncovering and making good shall be borne by the
Contractor, However, if there is no defect found, the cost of uncovering
and making good shall be treated as a variation and added to the
Contract Price.
20.2 The Project Manager shall give notice to the Contractor of any defects
26
before the end of the Defects Liability Period, which begins at Completion,
and is defined in the Appendix to Conditions of Contract. The Defects
Liability Period shall be extended for as long as defects remain to be
corrected.
20.3 Every time notice of a defect is given, the Contractor shall correct the
notified defect within the length of time specified by the Project
Manager’s notice. If the Contractor has not corrected a defect within
the time specified in the Project Manager’s notice, the Project Manager
will assess the cost of having the defect corrected by other parties and
such cost shall be treated as a variation and be deducted from the
Contract Price.
21.1 The Bills of Quantities shall contain items for the construction,
installation, testing and commissioning of the Work to be done by the
Contractor. The Contractor will be paid for the quantity of the Work done
at the rate in the Bills of Quantities for each item.
21.2 If the final quantity of the Work done differs from the quantity in the
Bills of Quantities for the particular item by more than 25 percent and
provided the change exceeds 1 percent of the Initial Contract price, the
Project Manager shall adjust the rate to allow for the change.
21.3 If requested by the Project Manager, the Contractor shall provide the
Project Manager with a detailed cost breakdown of any rate in the Bills
of Quantities.
22. Variations
22.2 The Contractor shall provide the Project Manager with a quotation for
carrying out the variations when requested to do so. The Project
Manager shall assess the quotation, which shall be given within seven
days of the request or within any longer period as may be stated by the
Project Manager and before the Variation is ordered.
22.3 If the work in the variation corresponds with an item description in the
Bills of Quantities and if in the opinion of the Project Manager, the
quantity of work is not above the limit stated in Clause 21.2 or the
timing of its execution does not cause the cost per unit of quantity to
change, the rate in the Bills of Quantities shall be used to calculate the
value of the variation. If the cost per unit of quantity changes, or
27
if the nature or timing of the work in the variation does not correspond with
items in the Bills of Quantities, the quotation by the Contractor shall be in
the form of new rates for the relevant items of Work.
22.5 If the Project Manager decides that the urgency of varying the Work
would prevent a quotation being given and considered without delaying
the Work, no quotation shall be given and the variation shall be treated
as a Compensation Event.
22.6 The Contractor shall not be entitled to additional payment for costs
that could have been avoided by giving early warning.
22.7 When the Program is updated, the Contractor shall provide the Project
Manager with an updated cash flow forecast.
23.2 The value of Work executed shall comprise the value of the quantities
of the items in the Bills of Quantities completed, materials delivered on
Site, variations and compensation events. Such materials shall
become the property of the Employer once the Employer has paid the
Contractor for their value . Thereafter, they shall not be removed from
Site without the Project Manager’s instructions except for use upon the
Works.
23.3 Payments shall be adjusted for deductions for retention. The Employer
shall pay the Contractor the amounts certified by the Project Manager
within 30 days of the date of issue of each certificate. If the Employer
makes a late payment, the Contractor shall be paid simple interest on
the late payment in the next payment. Interest shall be calculated on
the basis of number of days delayed at a rate three percentage points
above the Central Bank of Kenya’s average rate for base lending
prevailing as of the first day the payment becomes overdue.
28
the delayed payment as set out in this clause. Interest shall be
calculated from the date upon which the increased amount would have
been certified in the absence of dispute.
23.5 Items of the Works for which no rate or price has been entered in will
not be paid for by the Employer and shall be deemed covered by other
rates and prices in the Contract.
23.6 The Contract Price shall be stated in Kenya Shillings. All payments to
the Contractor shall be made in Kenya Shillings and foreign currency
in the proportion indicated in the tender, or agreed prior to the
execution of the Contract Agreement and indicated therein. The rate of
exchange for the calculation of the amount of foreign currency payment
shall be the rate of exchange indicated in the Appendix to Conditions of
Contract. If the Contractor indicated foreign currencies for payment
other than the currencies of the countries of origin of related goods and
services the Employer reserves the right to pay the equivalent at the
time of payment in the currencies of the countries of such goods and
services. The Employer and the Project Manager shall be notified
promptly by the Contractor of an changes in the expected foreign
currency requirements of the Contractor during the execution of the
Works as indicated in the Schedule of Foreign Currency Requirements
and the foreign and local currency portions of the balance of the
Contract Price shall then be amended by agreement between Employer
and the Contractor in order to reflect appropriately such changes.
23.7 In the event that an advance payment is granted, the following shall apply:-
29
R = A(x1 – x11)
80 – 20
Where:
(a) The Employer does not give access to a part of the Site by the Site
Possession Date stated in the Appendix to Conditions of Contract.
(b) The Employer modifies the List of Other Contractors, etc., in a way
that affects the Work of the Contractor under the Contract.
(c) The Project Manager orders a delay or does not issue drawings,
specifications or instructions required for execution of the Works on
time.
30
(h) Other contractors, public authorities, utilities, or the Employer does
not work within the dates and other constraints stated in the
Contract, and they cause delay or extra cost to the Contractor.
24.4 The Contractor shall not be entitled to compensation to the extent that
the Employer’s interests are adversely affected by the Contractor not
having given early warning or not having co-operated with the Project
Manager.
24.5 Prices shall be adjusted for fluctuations in the cost of inputs only if
provided for in the Appendix to Conditions of Contract.
24.6 The Contractor shall give written notice to the Project Manager of his
intention to make a claim within thirty days after the event giving rise
to the claim has first arisen. The claim shall be submitted within thirty
days thereafter.
Provided always that should the event giving rise to the claim of continuing
effect, the Contractor shall submit an interim claim within the said thirty
days and a final claim within thirty days of the end of the event giving rise to
the claim.
31
25.1 The Project Manager shall adjust the Contract Price if taxes, duties and
other levies are changed between the date 30 days before the
submission of tenders for the Contract and the date of Completion.
The adjustment shall be the change in the amount of tax payable by
the Contractor.
25.3 Unless otherwise stated in the Contract, the Contract Price shall be
deemed to have been calculated in the manner set out below and in
sub-clauses 25.4 and 25.5 and shall be subject to adjustment in the
events specified thereunder;
(ii) Upon J.B.C. determining that any of the said rates of wages or other
emoluments and expenses are increased or decreased, then the
Contract Price shall be increased or decreased by the amount assessed
by the Project Manager based upon the difference, expressed as a
percentage, between the rate set out
in the schedule of basic rates issued 30 days before the date for
submission of tenders and the rate published by the J.B.C. and
applied to the quantum of labour incorporated within the amount of
Work remaining to be executed at the date of publication of such
increase or decrease.
32
permanently incorporated in the Works as determined by the J.B.C.
and set out in the schedule of basic rates issued 30 days before the
date for submission of tenders. A copy of the schedule used by the
Contractor in his pricing shall be attached in the Appendix to
Conditions of Contract.
25.5 Upon the J.B.C. determining that any of the said basic prices are
increased or decreased then the Contract Price shall be increased or
decreased by the amount to be assessed by the Project Manager based
upon the difference between the price set out in the schedule of basic
rates issued 30 days before the date for submission of tenders and the
rate published by the J.B.C. and applied to the quantum of the
relevant materials which have not been taken into account in arriving
at the amount of any interim certificate under clause 23 of these
Conditions issued before the date of publication of such increase or
decrease.
25.7 The provisions of sub-clause 25.1 to 25.2 herein shall not apply in
respect of any materials included in the schedule of basic rates.
26. Retention
26.1 The Employer shall retain from each payment due to the Contractor the
proportion stated in the Appendix to Conditions of Contract until
Completion of the whole of the Works. On Completion of the whole of
the Works, half the total amount retained shall be repaid to the
Contractor and the remaining half when the Defects Liability Period
has passed and the Project Manager has certified that all defects
notified to the Contractor before the end of this period have been
corrected.
27.1 The Contractor shall pay liquidated damages to the Employer at the
rate stated in the Appendix to Conditions of Contract for each day that
the actual Completion Date is later than the Intended Completion Date.
The Employer may deduct liquidated damages from payments due to
the Contractor. Payment of liquidated damages shall not alter the
Contractor’s liabilities.
33
calculated from the date of payment to the date of repayment, at the
rate specified in Clause 23.30
28. Securities
29.2 All work to be paid for as Dayworks shall be recorded by the Contractor
on Forms approved by the Project Manager. Each
Completed form shall be verified and signed by the Project Manager within
two days of the Work being done.
29.3 The Contractor shall be paid for Dayworks subject to obtaining signed
Dayworks forms.
30.1 From the Start Date until the Defects Correction Certificate has been
issued, the following are the Employer’s risks:
(i) use or occupation of the Site by the Works or for the purpose of
the Works, which is the unavoidable result of the Works, or
34
(b) The risk of damage to the Works, Plant, Materials, and Equipment to
the extent that it is due to a fault of the Employer or in Employer’s
design, or due to war or radioactive contamination directly affecting
the place where the Works are being executed.
30.2 From the Completion Date until the Defects Correction Certificate has
been issued, the risk of loss of or damage to the Works, Plant, and
Materials is the Employer’s risk except loss or damage due to;
(b) an event occurring before the Completion Date, which was not itself
the Employer’s risk
(c) the activities of the Contractor on the Site after the Completion Date.
30.3 From the Start Date until the Defects Correction Certificate has been
issued, the risks of personal injury, death and loss of or damage to
property (including, without limitation, the Works, Plant, Materials,
and Equipment) which are not Employer’s risk are Contractor’s risks.
The Contractor shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start Date to the end of the Defects
Liability Period, in the amounts stated in the Appendix to Conditions of
Contract for the following events;
(a) loss of or damage to the Works, Plant, and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage to property (except the Works, Plant, Materials, and
Equipment) in connection with the Contract, and
(d) Personal injury or death.
30.5 If the Contractor does not provide any of the policies and certificates
required, the Employer may effect the insurance which the Contractor
should have provided and recover the premiums from payments
otherwise due to the Contractor or, if no payment is due, the payment
of the premiums shall be a debt due.
30.6 Alterations to the terms of an insurance shall not be made without the
approval of the Project Manager. Both parties shall comply with any
conditions of insurance policies.
35
31.1 Upon deciding that the Works are complete, the Contractor shall issue
a written request to the Project Manager to issue a Certificate of
Completion of the Works. The Employer shall take over the Site and
the Works within seven [7] days of the Project Manager’s issuing a
Certificate of Completion.
32.1 The Contractor shall issue the Project Manager with a detailed account of
the total amount that the Contractor considers payable to him by the
Employer under the Contract before the end of the Defects Liability Period.
The Project Manager shall issue a Defects Liability Certificate and certify any
final payment that is due to the Contractor within 30 days of receiving the
Contractor’s account if it is correct and complete. If it is not, the Project
Manager shall issue within 30 days a schedule that states the scope of the
corrections or additions that are necessary. If the final account is still
unsatisfactory after it has been resubmitted, the Project Manager shall
decide on the amount payable to the Contractor and issue a Payment
Certificate. The Employer shall pay the Contractor the amount due in the
Final Certificate within 60 days.
33. Termination
33.1 The Employer or the Contractor may terminate the Contract if the other
party causes a fundamental breach of the Contract. These
fundamental breaches of Contract shall include, but shall not be limited to,
the following;
(a) the Contractor stops work for 30 days when no stoppage of work is
shown on the current program and the stoppage has not been
authorized by the Project Manager;
(b) the Project Manager instructs the Contractor to delay the progress of
the Works, and the instruction is not withdrawn within 30 days;
(c) the Contractor is declared bankrupt or goes into liquidation other than
for a reconstruction or amalgamation;
(e) the Project Manager gives notice that failure to correct a particular
defect is a fundamental breach of Contract and the Contractor fails to
correct it within a reasonable period of time determined by the Project
Manager;
36
33.2 When either party to the Contract gives notice of a breach of Contract
to the Project Manager for a cause other than those listed under Clause
33.1 above, the Project Manager shall decide whether the breach is
fundamental or not.
33.3 Notwithstanding the above, the Employer may terminate the Contract
for convenience.
34.3 The Employer may employ and pay other persons to carry out and
complete the Works and to rectify any defects and may enter upon the
Works and use all materials on the Site, plant, equipment and
temporary works.
34.4 The Contractor shall, during the execution or after the completion of
the Works under this clause remove from the Site as and when
required, within such reasonable time as the Project Manager may in
writing specify, any temporary buildings, plant, machinery, appliances,
goods or materials belonging to or hired by him, and in default the
Employer may (without being responsible for any loss or damage)
remove and sell any such property of the Contractor, holding the
proceeds less all costs incurred to the credit of the Contractor.
Until after completion of the Works under this clause the Employer shall not
be bound by any other provision of this Contract to make any payment to
the Contractor, but upon such completion as aforesaid and the verification
37
within a reasonable time of the accounts therefore the Project Manager shall
certify the amount of expenses properly incurred by the Employer and, if
such amount added to the money paid to the Contractor before such
determination exceeds the total amount which would have been payable on
due completion in accordance with this Contract the difference shall be a
debt payable to the Employer by the Contractor; and if the said amount
added to the said money be less than the said total amount, the difference
shall be a debt payable by the Employer to the Contractor.
(a) Offer or give or agree to give to any person in the service of the
(b) Enter into this or any other contract with the Employer in connection with
which commission has been paid or agreed to be paid by him or on his
behalf or to his knowledge, unless before the Contract is made particulars of
any such commission and of the terms and conditions of any agreement for
the payment thereof have been disclosed in writing to the Employer.
38
Procurement Regulations issued under The Exchequer and Audit Act Cap
412 of the Laws of Kenya.
36.1 In case any dispute or difference shall arise between the Employer or
the Project Manager on his behalf and the Contractor, either during the
progress or after the completion or termination of the Works, such
dispute shall be notified in writing by either party to the other with a
request to submit it to arbitration and to concur in the appointment of
an Arbitrator within thirty days of the notice. The dispute shall be
referred to the arbitration and final decision of a person to be agreed
between the parties. Failing agreement to concur in the appointment of
an Arbitrator, the Arbitrator shall be appointed by the Chairman or
Vice Chairman of any of the following professional institutions;
On the request of the applying party. The institution written to first by the
aggrieved party shall take precedence over all other institutions.
39
36.5 Notwithstanding anything stated herein the following matters may be
referred to arbitration before the practical completion of the Works or
abandonment of the Works or termination of the Contract by either
party:
36.6 All other matters shall only be referred to arbitration after the
completion or alleged completion of the Works or termination or alleged
termination of the Contract, unless the Employer and the Contractor
agree otherwise in writing.
36.7 The Arbitrator shall, without prejudice to the generality of his powers,
have powers to direct such measurements, computations, tests or
valuations as may in his opinion be desirable in order to determine the
rights of the parties and assess and award any sums which ought to
have been the subject of or included in any certificate.
36.8 The Arbitrator shall, without prejudice to the generality of his powers,
have powers to open up, review and revise any certificate, opinion, decision,
requirement or notice and to determine all matters in dispute which shall be
submitted to him in the same manner as if no such certificate, opinion,
decision requirement or notice had been given.
36.9 The award of such Arbitrator shall be final and binding upon the
parties.
40
THE EMPLOYER IS
Name: _________________________________________________________________________
Address: ______________________________________________________________________
Telephone: _______________________
Facsimile: ________________________
Name: _________________________________________________________________________
Address: _______________________________________________________________________
Telephone: _______________________
Facsimile: ________________________
_________________________________________________________________________________
________________________________________________________________________________
The Intended Completion Date for the whole of the Works shall be
_________________________________________________________________________________
_________________________________________________________________________________
41
The Contractor shall submit a revised program for the Works within ________ days of
delivery of the Letter of Acceptance.
_________________________________________________________________________________
1.____________________________________________
2.______________________________________________
3._____________________________________________
4._____________________________________________
1. The minimum cover for insurance of the Works and of Plant and Materials in
respect of the Contractor’s faulty design is____________________
1. __________________________________________________________________________
2. __________________________________________________________________________
3. __________________________________________________________________________
4. __________________________________________________________________________
42
The period between Program updates is ________________ days.
_________________________________________________________________________________
The liquidated damages for the whole of the Works is Kshs. _____________(per day)
The Performance Security shall be for the following minimum amounts equivalent as a
percentage of the Contract Price--------------- percent (%)
The schedule of basic rates used in pricing by the Contractor is as attached [Contractor to
attach].
43
SECTION V - SPECIFICATIONS
2.0 Specifications from previous similar projects are useful and may
not be necessary to re-write specifications for every Works
Contract.
44
constructions, although not necessarily to be used in a
particular works contract. Deletions or addenda should then
adapt the General Specifications to the particular Works.
SECTION VI - DRAWINGS
BILLS OF QUANTITY
45
ITEM DESCRIPTION UNIT QTY RATE BQ AMOUNT
PRELIMINARIES
NOTES:
A Prospective Tenderers MUST
visit the site before filling their
bids. Tenderers will be required to
sign attendance register Non-
attendance is an automatic
disqualification.
Setting out
Program of works
46
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Materials
B Materials shall be sound and of
good quality and shall be supplied
in accordance with the provisions
and recommendations of Kenyan
and British standards. Whenever
requested, the Contractor shall
certify the origin of the materials
supplied to the site by producing
invoices, certificates of origin etc.
The Contractor shall submit at his
own expense in due time, a
sample of each specified material
to the Engineer for approval. If
this sample is accepted by the
Engineer, it shall remain
deposited in the Engineer’s office
and serve as evidence for the
reception of works of similar
quality. All materials that are not
approved shall be removed
immediately by the Contractor
when instructed by the Engineer,
who if his orders are not carried
47
out into effect, shall have the right
to have the materials disposed of
at the public dump site and at the
Contractors expense.
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Cleaning up
48
A The contractor shall remove all
rubbish from the site from time to
time and on completion he must
thoroughly clean up by sweeping
or otherwise to leave the site for
ready use. The Contractor shall
adopt all measures to ensure that
floor tiles, terrazzo work,
windows etc, are left clear and
free from dirt, stains etc.
Watching
49
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Records
A The Contractor shall allow for
keeping all records in English
appertaining to the works and
shall keep on the site a daily diary
recording weather conditions,
daily work done, delivery notes
for materials, visitors on site etc.
The Contractor is to supply to the
Engineer with such information as
he may require in connection with
work, including a statement
showing the number of men
employed in all trades daily, and
delivery notes (Stating the name
of the project) for all materials
delivered to the site.
50
Training levy
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Performance security
Insurance
51
PRELIMINARIES CARRIED TO
SUMMARY
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
52
L 50 mm thick blinding to surfaces
of hardcore SM 100
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Concrete work
Plain concrete 1:4:8 50 mm
thick:
A Under column bases SM 23
D Column bases CM 7
E Columns CM 1
F Ground Beam CM 4
Sawn formwork:-
G Vertical column sides CM 8
53
J Vertical Groung beam SM 41
Column bases
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
Columns
A 8 mm Diameter bars KG 44
(Ground Beam)
Walling
54
E 200 mm thick walls SM 82
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
C. RC SUPERSTRUCTURE
Floors
A Columns CM 2
B Ring Beams CM 4
55
SM 38
Reinforcement Supply and fix
the following reinforcement
including bending, hooking,
typing, cutting; and spacer
blocks and supporting: all as
required mild steel B.S. 4449
Columns
Beams
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
C. WALLING
Water proofing
B 225mm wide Hessian based 3-ply
bituminous felf damp proof
course LM 68
56
C Supply and fix Precast moulds
200 x200 1000mm high and make
good as directed by the project
architect NO 129
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
DOORS
Wrot mahogany in:-
A 200 x 25mm splayed liners
[expansion joint covers] LM 34
C 15 x 15 mm quadrant/beading LM 34
57
D 40 x 20mm Splayed architrave LM 34
H Tower bolts NO 6
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
WINDOWS
58
Supply and fix aluminium
glazed windows as ' Vista' or or
equally approved comprising 40
x 30 mm aluminium frame filled
in with 5 mm thick one way
tinted glass secured in rubber
linning, including all necessary
ironmongery to approval in:
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
59
ITEM
Brought forward
FINISHES
Floor finishes
A Ground slab SM 50
60
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
ROOF
Timber roof construction sawn
cypress grade II,maximum
moisture content 15%,seasoned
and pressure impregnated with
approved preservative at
27degrees pitch, hoisted to a
height of 12400mm above
ground level.
B 150 x 50 mm Rafters LM 96
61
Galvanised metal sheet gauge
:24 pre-painred
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
62
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
ELECTRICAL
INSTALLATIONS AT
SPEAKERS RESIDENCE
TO BE CARRIED OUT BY A
REGISTERED ELECTRICAL
CONTRACTOR, ATTACH
ERC AND NCA
CERTIFICATES
Supply,install,test and
commission the following:-
A LIGHTING POINTS
Lighting points wired with 3 x
1.5mm² single core PVCI copper
cables drawn in concealed 20mm
diameter HG PVCI conduit for:-
One way switching NO 28
B SWITCHES
10Amps,moulded plate flush
mounted switches with screw
covers,as CLIPSAL,BG or
approved equivalent being:-
1 gang 1 way NO 2
2 gang 1 way NO 4
63
C LIGHTING FITTINGS
Lighting fittings complete with
lamps and all other necessary
accessories:-
a) Polypro[paylene Bulkhead
fitting, grey finish, oval clear
NO 7
glass Size (HxWxPro)
100x180x130mm
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
A POWER POINTS
13Amps Power points wired ring
comprising of 3 x 2.5mm sq.
single core PVCI copper cables NO 10
drawn in concealed 25mm HG
PVC conduits.
64
20A DP fused switched
connection unit complete with
NO 2
neon indicator as MK or approved
equivalent for Hand drier/fan.
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
65
Two loop intelligent addressable 2
Zone Fire Alarm Control Panel,
Surface Mounted, complete with
alarm buzzer and 72 Hour Battery NO 1
Back-up and batery charger as
Menvier Catalogue DF series or
approved equivalent.
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
66
Brought forward
A SUB-MAIN CIRCUIT
Sub-mains cables consisting of
4C 16mm2, PVC/SWA/PVC CU
cables from the Lv switchboard to
the distribution boards "A&B"
LM 156
above drawn in 50mm diameter
full length heavy gauge PVC
conduits cast in floor slab and
concealed in the walls.
B DISTRIBUTION BOARDS
6-ways TP&N Distribution
Boards 200Amps rating,
MCB,flushmounted,metal cased
unit complete with 200Amps
TP&N integral mccb and NO 2
with"front hinged lockable metal
cover and glanding chamber to
suit as Schneider Electric or
approved equivalent.
10Amps,SP NO 4
20Amps, SP NO 2
30Amps,SP NO 2
blanking plates NO 7
67
Provide, lay to level HATARI
slabs on top of the sand layer in LM 128
the cable trench
Carried forward
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
Brought forward
68
Carried forward
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
1 SWIMMING POOL
Excavation
B Sump pit NO 1
Concrete work
J Blinding CM 3
69
K Steps CM 1
M Sump NO 1
Carried forward
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
Brought forward
Reinforced concrete 1:1,1/2:3
in:-
A Light pockets NO 2
B Pool channel CM 1
C 12 mm KG 980
D 10 mm KG 939
E 8 mm KG 33
Sawn formwork:-
G Steps SM 3
J Edges 75 - 150 mm LM 78
K Edges 150-225 mm LM 35
70
L Waterproofing SM 29
M Bitumenous paint SM 52
Walling
Machine cut block walling
bedded , jointed and neatly
pointed in cement and sand
(1:4) motar as desribed in:-
Carried forward
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
Brought forward
Finishes
71
Total for Swimming Pool
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
BALANCING TANK
Excavation
Concrete work
72
Plain concrete 1:3:6; 200 mm
thick in:-
F Blinding SM 3
K 12 mm KG 142
L 10 mm KG 98
M 8 mm KG 33
Carried forward
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
Brought forward
Walling
Machine cut block walling
bedded , jointed and neatly
pointed in cement and sand
(1:4) motar as desribed in:-
Sawn formwork:-
B Soffits SM 3
C Sides of walls SM 11
73
D Edges 75 - 150 mm LM 13
E Boxing NO 1
Finishes
G FloorScreeds SM 3
J Wall plaster SM 10
3 PUMP ROOM
Excavation
74
D Load surplus excavated materials
and cart away CM 2
Concrete work
F Blinding SM 4
J 10 mm KG 45
K 8 mm KG 33
Sawn formwork:-
L soffits SM 3
M edges 75 - 150 mm LM 8
Carried forward
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
Brought forward
Walling
Machine cut block walling
bedded , jointed and neatly
pointed in cement and sand
75
(1:4) motar as desribed in:-
A 200 mm thick SM 8
Finishes
B 50mm Thick cement and sand
(1:4) screed internally, finished to
receive ceramic floor tiles
(measured seperately)
C Floor screeds SM 3
D Skirtings - 100 mm LM 7
F Wall plaster SM 12
G Render externally SM 2
H Render soffits SM 3
J Walls - internally SM 12
K Walls - externally SM 2
L Soffits SM 3
76
Swimming pool electrical
installation
77
Total for electrical works
RATE BQ AMOUNT
ITEM DESCRIPTION UNIT QTY
Carried to collection
Collections
1 SWIMMING POOL
2 BALANCE TANK
3 PUMP HOUSE
4 ELECTRICAL WORKS
78
DESCRIPTION UNIT QTY RATE BQ AMOUNT
ITEM
79
PC & PROVISIONAL SUMS
CARRIED TO SUMMARY
1 GAZEBO
2 SWIMMING POOL
GRAND SUMMARY
1 PRELIMINARIES
2 MAIN WORKS
3 PROVISIONAL SUMS
TOTAL
Add 5% contingency
80
TOTAL CARRIED TO FORM OF TENDER
(b) when a Contract has been entered into, to provide a priced Bill of Quantities
for use in the periodic valuation of Works executed.
2.0 The Bills of Quantities should be divided generally into the following
sections:
(a) Preliminaries.
The preliminaries should indicate the inclusiveness of the unit prices, and
should state the methods of measurement which have been adopted in the
preparation of the Bill of Quantities and which are to be used for the
measurement of any part of the Works.
81
otherwise items such as security for the Works which are primarily part of
the Contractor’s obligations should be included in the Contractor’s rates.
(i) The items in the Bills of Quantities should be grouped into sections to
distinguish between those parts of the Works which by nature,
location, access, timing, or any other special characteristics may give
rise to different methods of construction, or phasing of the Works, or
considerations of cost. General items common to all parts of the
Works may be grouped as a separate section in the Bill of Quantities.
A Daywork Schedule should be included if the probability of unforeseen work, outside the
items included in the Bill of Quantities, is relatively high. To facilitate checking by the
Employer of the realism of rates quoted by the tenderers, the Daywork Schedule should
normally comprise:
82
together with a statement of the conditions
under which the Contractor will be paid for
Work executed on a Day work basis; and
(e) Summary
83
for Daywork, for physical (quantity) contingencies, and for price
contingencies (upward price adjustment) where appli
_______________________[date]
Dear Sirs:
Reference:______________________________________________[Contract Name]
We hereby invite you and other prequalified tenderers to submit a tender for the
execution and completion of the above Contract.
Yours faithfully,
FORM OF TENDER
Dear Sir,
85
1. In accordance with the Conditions of Contract, Specifications, Drawings and Bills
of Quantities for the execution of the above named Works, we, the undersigned
offer to construct, install and complete such Works and remedy any defects
therein for the sum of Kshs._____________________________[Amount in figures]Kenya
Shillings_________________________________________________________________________
__________________[Amount in words]
4. Unless and until a formal Agreement is prepared and executed this tender together
with your written acceptance thereof, shall constitute a binding Contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may
receive.
Witness; Name______________________________________
Address_____________________________________
Signature___________________________________
Date_______________________________________
LETTER OF ACCEPTANCE
[letterhead paper of the Employer]
_______________________[date]
To: _______________________
[name of the Contractor]
_____________________
86
[address of the Contractor]
Dear Sir/Madam,
You are hereby instructed to proceed with the execution of the said Works in accordance
with the Contract documents.
Attachment : Agreement
FORM OF AGREEMENT
87
(name and identification number of Contract ) (hereinafter called “the Works”) located
at______________________________[Place/location of the Works]and the Employer has
accepted the tender submitted by the Contractor for the execution and completion of
such Works and the remedying of any defects therein for the Contract Price of
Kshs___________________________[Amount in figures],Kenya
Shillings_____________________________________________[Amount in words].
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and shall be read and construed
as part of this Agreement i.e.
(v) Specifications
(vi) Drawings
IN WITNESS whereof the parties thereto have caused this Agreement to be executed the
day and year first before written.
88
Binding Signature of Employer ________________________________________
Address_____________________________________
Signature___________________________________
Address_____________________________________
Signature____________________________________
KNOW ALL PEOPLE by these presents that WE ……………………… having our registered
office at ………………(hereinafter called “the Bank”), are bound unto
……………………………(hereinafter called “the Employer”) in the sum of
Kshs.……………………… for which payment well and truly to be made to the said
Employer, the Bank binds itself, its successors and assigns by these presents sealed
with the Common Seal of the said Bank this ……………. Day of ………20…………
89
1. If after tender opening the tenderer withdraws his tender during the period of
tender validity specified in the instructions to tenderers
Or
2. If the tenderer, having been notified of the acceptance of his tender by the
Employer during the period of tender validity:
(a) fails or refuses to execute the form of Agreement in accordance with the
Instructions to Tenderers, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the
Instructions to Tenderers;
We undertake to pay to the Employer up to the above amount upon receipt of his
first written demand, without the Employer having to substantiate his demand,
provided that in his demand the Employer will note that the amount claimed by
him is due to him, owing to the occurrence of one or both of the two conditions,
specifying the occurred condition or conditions.
This guarantee will remain in force up to and including thirty (30) days after the
period of tender validity, and any demand in respect thereof should reach the
Bank not later than the said date.
___________________________ ______________________________
[date[ [signature of the Bank]
___________________________ ______________________________
[witness] [seal]
Dear Sir,
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor
shall furnish you with a Bank Guarantee by a recognised bank for the sum specified
therein as security for compliance with his obligations in accordance with the Contract;
90
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you,
on behalf of the Contractor, up to a total of Kshs. ________________ (amount of Guarantee
in figures) Kenya Shillings__________________________________________ (amount of
Guarantee in words), and we undertake to pay you, upon your first written demand and
without cavil or argument, any sum or sums within the limits of Kenya Shillings
_________________________ (amount of Guarantee in words) as aforesaid without your
needing to prove or to show grounds or reasons for your demand for the sum specified
therein.
We hereby waive the necessity of your demanding the said debt from the Contractor
before presenting us with the demand.
We further agree that no change, addition or other modification of the terms of the
Contract or of the Works to be performed thereunder or of any of the Contract
documents which may be made between you and the Contractor shall in any way release
us from any liability under this Guarantee, and we hereby waive notice of any change,
addition, or modification.
This guarantee shall be valid until the date of issue of the Certificate of Completion.
Address ________________________________________________
Date ______________________________________________________
Gentlemen,
91
Kshs._____________[amount of Guarantee in figurers] Kenya
Shillings_____________________________________[amount of Guarantee in words].
We further agree that no change or addition to or other modification of the terms of the
Contract or of the Works to be performed thereunder or of any of the Contract
documents which may be made between ________________________[name of Employer] and
the Contractor, shall in any way release us from any liability under this guarantee, and
we hereby waive notice of any such change, addition or modification.
No drawing may be made by you under this guarantee until we have received notice in
writing from you that an advance payment of the amount listed above has been paid to
the Contractor pursuant to the Contract.
This guarantee shall remain valid and in full effect from the date of the
advance payment under the Contract until
______________________________________________(name of Employer) receives full payment
of the same amount from the Contract.
Yours faithfully,
Address ______________________________________________________________
Date _________________________________________________________________
Address: __________________________________________________
Signature: ________________________________________________
Date: _____________________________________________________
92
93
QUALIFICATION INFORMATION
1. Individual Tenderers or Individual Members of Joint Ventures
1.2 Total annual volume of construction work performed in the last five years
Year Volume
Currency Value
1.4 Major items of Contractor’s Equipment proposed for carrying out the Works.
List all information requested below.
94
1.5 Qualifications and experience of key personnel proposed for administration
and execution of the Contract. Attach biographical data.
(etc.)
1.6 Financial reports for the last five years: balance sheets, profit and loss
statements, auditor’s reports, etc. List below and attach copies.
___________________________________________________________________________
_____________________________________________
1.8 Name, address and telephone, telex and facsimile numbers of banks that
may provide reference if contacted by the Employer.
__________________________________________________________________
____________________________________________________________
1.10 Proposed program (work method and schedule) for the whole of the Works.
95
2 Joint Ventures
2.4 The information listed in 1.1 – 1.10 above shall be provided for each partner
of the joint venture.
2.5 The information required in 1.11 above shall be provided for the joint
venture.
2.6 Attach the power of attorney of the signatory(ies) of the tender authorizing
signature of the tender on behalf of the joint venture
2.7 Attach the Agreement among all partners of the joint venture ( and which is
legally binding on all partners), which shows that:
a) all partners shall be jointly and severally liable for the execution of the
Contract in accordance with the Contract terms;
96
TENDER QUESTIONNAIRE
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
6. Details of tenderer’s nominated agent (if any) to receive tender notices. This is
essential if the tenderer does not have his registered address in Kenya (name,
address, telephone, telex)
………………………………………………………………………………………
………………………………………………………………………………………
_______________________
Signature of Tenderer
97
CONFIDENTIAL BUSINESS QUESTIONNAIRE
You are requested to give the particulars indicated in Part 1 and either Part 2 (a), 2 (b) or
2 (c) and 2 (d) whichever applies to your type of business.
You are advised that it is a serious offence to give false information on this Form.
Part 1 – General
Nature of Business…………………………………………………………………..
Branch…………………………………………………………………………………
Private or public……………………………………………………………
98
State the nominal and issued capital of the Company-
Nominal Kshs…………………………………………………………………
Issued Kshs……………………………………………………………………
1.
………………………………………………………………………………………
2.
………………………………………………………………………………………
3.
………………………………………………………………………………………
4.
………………………………………………………………………………………
99
STATEMENT OF FOREIGN CURRENCY REQUIREMENTS
(Figures)………………………… (Words)…………………………………
………………………………………………………………………………………
_____________________
(Signature of Tenderer)
100
DETAILS OF SUB-CONTRACTORS
If the Tenderer wishes to sublet any portions of the Works under any heading, he must
give below details of the sub-contractors he intends to employ for each portion.
………………………………
………………………………
………………………………
………………………………
………………………………
……………………………
____________________ _______________________
[Signature of Tenderer) Date
101
LETTER OF NOTIFICATION OF AWARD
Tender Name
This is to notify that the contract/s stated below under the above mentioned tender have
been awarded to you.
2. The contract/contracts shall be signed by the parties within 30 days of the date of
this letter but not earlier than 14 days from the date of the letter.
3. You may contact the officer(s) whose particulars appear below on the subject
matter of this letter of notification of award.
(FULL PARTICULARS)
102
FORM RB 1
REPUBLIC OF KENYA
PUBLIC PROCUREMENT ADMINISTRATIVE REVIEW BOARD
APPLICATION NO…………….OF……….….20……...
BETWEEN
…………………………………………….APPLICANT
AND
Request for review of the decision of the…………… (Name of the Procuring Entity) of
……………dated the…day of ………….20……….in the matter of Tender No………..…of
…………..20…
REQUEST FOR REVIEW
I/We……………………………,the above named Applicant(s), of address: Physical
address…………….Fax No……Tel. No……..Email ……………, hereby request the Public
Procurement Administrative Review Board to review the whole/part of the above mentioned
decision on the following grounds , namely:-
1.
2.
etc.
By this memorandum, the Applicant requests the Board for an order/orders that: -
1.
2.
etc
SIGNED ……………….(Applicant)
Dated on…………….day of ……………/…20…
SIGNED
Board Secretary
103
APPENDIX TO INSTRUCTIONS TO TENDERERS
EVALUATION CRITERIA
Preliminary Evaluation Stage (Knock out Level- Bidders Must Attach the below listed)
Technical Evaluation Stage ( Out of 80, Pass mark at 65/80,below which is elimination)
Point
Item Description
Scored
Tender Questionnaire Form 5
Tender Q.
104
Artisan with under 10 years relevant experience --------------- 3 mrks
Non skilled worker with over 10 years relevant experience--- 1 mrks
Ii Contract completed in the last five (5) years (Max of 3 No. Projects) 15
Project of similar nature, complexity and magnitude ------------5
Project of similar nature but of lower value than the one in consideration--- 3 mrks
No completed project of similar nature --------------------------- 0 mrks
Ongoing projects (Max of 3 No. Projects) 10
iii Project of similar nature, complexity and magnitude ------------3
Project of similar nature but of lower value than the one in consideration----- 2 mrks
No ongoing project of similar nature ----------------------------- 0 mrks
iv Schedule of contractors equipment and transport (proof or evidence of ownership) 6
Means of transport (Vehicle)---------------------------------------- 6 mrks
No means of transport ----------------------------------------------- 0 mrks
For each specific equipment required in the execution of the Work being tendered for. 4
(No. of equipment to be considered – at least 3 No.)- 4 mrks
(No. of equipment to be considered – at least 2 No.)- 2.6 mrks
(No. of equipment to be considered – at least 1 No.)- 1.4 mrks
FINANCIAL EVALUATION
Audited financial report {last three{3} years} 10
Turnover greater or equal to 5 times the cost of the project….. 10 mrks
Turnover greater or equal to 3 times the cost of the project….. 6 mrks
Turnover greater or equal to the cost of the project…………. 4 mrks
Turnover below the cost of the project………………………. 2 mrks
Evidence of Financial Resources{cash in hand, lines of credit, over draft facility} 10
Has financial resources equal or above the cost of the project---- 10 mrks
Has financial resources below the cost of the project---------------- 5 mrks
Has not indicated sources of financial resources--------------------- 0 mrs
Name ,address and telephone of banks{Contractors to provide} 5
Provided--------------------------------------------------------------------- 5 mrks
Not Provided-------------------------------------------------------------- 0 mrks
Litigation history 3
Filled-------------------------------------------------------------- 3 mrks
Not filled---------------------------------------------------------- 0 mrks
Sancity of the tender document 12
Having the document intact{not tempered with in any way}--------- 12 mrks
Having mutilated or modified the tender document -------------------- 0 mrks
TOTAL
105
KWALE COUNTY ASSEMBLY
Title
This code may be cited as the Code of Ethics for Suppliers in Public Procurement & Disposal
1. Interpretation
106
“Supplier” means a candidate, bidder, and tenderer, Contractor, service provider or a
consultant.
“Tenderer” means a person who submitted a tender pursuant to an invitation by a public
entity
For purposes of this Code, all terms used, unless expressly defined herein, have the meaning
assigned to them in the Act.
2. Application of the Code
b) The objective of the Code is to set minimum standards of ethical behavior for Suppliers to
ensure compliance with the Act and the Regulations and the adoption of good business
practices.
a) All public procurement & disposal shall be undertaken in accordance with the values and
principles of the Constitution of Kenya, 2010 (Article 10)
b) All Suppliers shall comply with the rule of Law.
c) Suppliers shall observe other laws, regulations, rules and practices relating to taxation,
labour, health and safety standards as well as environmental protection.
4. Professionalism
a) Suppliers are required to comply with professional standards of their industry or of any
professional body of which they are members. Where a supplier is a member of a
professional body, the Supplier shall uphold the code of ethics of the respective profession
and be of good standing.
b) Suppliers shall maintain the highest standards of integrity and professionalism in their
operations.
c) Suppliers in public procurement shall accord mutual respect and courtesy to the public
officer(s) and other suppliers without compromising their independent and distinct roles.
d) Public procurement & disposal activities shall be undertaken with the objective of meeting
the closest public scrutiny.
5. Impartiality
A supplier shall not engage in acts aimed at encouraging patronage, tribalism, cronyism and
nepotism.
107
6. Gifts, Favors and Corrupt practices
a) A supplier shall not offer or give gifts of any kind to public entities and/or the employees.
b) No supplier shall contact, unduly influence or exert pressure on any member of a
committee or any other employee of a procuring entity to take a particular action which
favours or tends to favour them.
c) A supplier shall not engage in fraudulent, collusive, or corrupt practices, or inappropriate
influences.
d) A supplier shall not act inappropriately by attempting to interfere with the procurement
process
7. Conflict of Interest
a) A supplier shall not accept contracts which would constitute a conflict of interest with any
prior or current contract. Suppliers shall disclose to all concerned parties those conflicts of
interest that cannot be reasonably avoided.
b) A supplier shall not enter into a contract with a procuring entity if the supplier is:
(i) An employee of the procuring entity or a member of a board or committee of the procuring
entity;
(ii) A State Officer, public Officer or a member of a board or committee of the Government or
any department of the Government or a person appointed to any position by the President or
a Cabinet Secretary;
(iii) A person, including a corporation, who is related to a person described in paragraph (a)
or (b). A relative has meaning assigned to it in section 33(2) of the Public Procurement and
Asset Disposal Act, 2015 or any amendment or modification thereof applies
(iv) Debarred from participating in procurement proceedings.
8. Performance of Duties
1) A supplier shall:
a. Duly sign this code of ethics and include it in a tender, proposal or quotation submitted.
b. Obtain and submit bid documents in the manner prescribed in the tender notice and
tender documents
c. Supply the right quantity and quality of the contracted item and deliver at the stipulated
time(s) and shall not abandon the work that they have been contracted to do.
d. Perform the obligations of the contracts efficiently and effectively
2) Suppliers shall not participate in procurement proceedings without invitation to tender
and understanding the instructions to tenderers.
108
3) While responding to tenders, quotations or request for proposals, bidders should not
include unfair, discriminatory or unreasonable conditions in their bids.
4) Suppliers should
a. Ensure that their deliverables provide value for money in terms of cost, quality, quantity
and timeliness of the delivered works, goods or services.
b. Ensure that competent persons carry out the contractual obligations of the supplier.
c. Accept full responsibility for all works, services or supplies provided
a. Obstruct or hinder an officer of the Authority or any other authorized person from
carrying out a duty or function or exercising a power relating to procurement and disposal.
b. Knowingly or in collusion with others lie to or mislead a person carrying out a duty or
function or exercising a power relating to procurement and disposal.
A supplier shall:
1) Observe strict communication limitations during the bidding process and as provided for
in the Act
2) Respond promptly and courteously to all proper requests for information, clarifications,
complaints or enquiries from procuring entities, the Authority or any law enforcement
agency.
3) Ensure that all information provided to procuring entities is given in writing by Authorized
Officers.
4) Ensure that certified copies of all mandatory certificates are availed
5) Ensure that information given while participating in public procurement or disposal is
true, accurate and fair, and not designed to mislead.
10. Confidentiality
A supplier shall reject and report to the PPOA and/or the relevant agency any procurement
practice which might be deemed improper.
109
PART III - OVERSIGHT BY THE PPOA
12. PPOA shall assist in undertaking continuous training of the suppliers to eliminate
malpractices which might arise due to ignorance of the public procurement system.
13. PPOA will exercise oversight in the enforcement of this Code of Ethics, including taking
remedial measures where the Code of Ethics is breached
14. PPOA shall revise the code of ethics as appropriate in consultation with the relevant
stakeholders
110
COMMITMENT TO THE CODE OF ETHICS (to be submitted as part of any quotation or
tender)
I …………………………………. (Supplier) Confirm that I have read and fully understood the
contents of the Public Procurement & Asset Disposal Act 2015 and the Code of Ethics for
Suppliers and my responsibilities under the Code.
I also certify that I am duly authorized to sign this Code on my own behalf and on behalf of
my organization, and agree to comply with the Code of Ethics.
Name………………………………………………. Sign……………………
Position……………………………………………….
Office address……………………………………………….
Telephone……………………………………………………
E-mail………………………………………………………
Name of the Firm……………………………………………
(Company Seal/ Rubber Stamp where applicable)
Sworn at …………... }
By the said …………. } ……………………………
Deponent
this………..…day of……………20………. }
Before Me }
}
Commissioner for Oaths/Magistrate}
AR 2016-2018