Chapter 2 - Streamflow Estimation
Chapter 2 - Streamflow Estimation
Streamflow Estimation
What is stream flow?
Rising
limb Crest Recession
limb
Disccharge
Qt Q0K t
Qt = discharge t time units after Q0
Q0 = initial discharge at t = 0
K = recession constant
5 Time
Streamflow measurements
Serves as the
S th bbasis
i ffor many water
t resources
engineering designs
Two approaches
pp
Measurement of water stage;
Measurement of flow velocity
Measurement of Water Stage
Water stage: the elevation above some arbitrary
datum of water surface at a station
Types
T off Gages
G Measuring
M i River
Ri St
Stage:
Staff gage – vertical or inclined
Suspended – weight gage
R
Recording
di gage
Crest – stage gage ( used to indicate high water mark)
Measurement of stage
• Characteristics of staff
• Durable
D t i l Low
bl material L coefficient
ffi i t off expansion
i dued to
t
(temperature and moisture).
• Fixed rigidly to structure (e.g. bridge, pier, wall, etc
• Vertical or inclined clear and permanent markings
(temperature and moisture).
Stage data
Floats
Measurement of Velocity
Where ;
v = Stream velocity (m/s)
Ns = Revolutions per second
a, b = Constants
Note : T
N Typical
i l values
l off a andd b :-
For size 12.5 cm diameter a = 0.65 and b = 0.03
For size 5 cm diameter a = 0.30 and b = 0.003
Measurement of Velocity
Definition
What we do?
measure high water level, cross section, channel
slope and do calculation :-
1
Q AR 2 3So1 2 ... 5.14
n
Where ; n = Manning’s coefficient
A=W Wetted
tt d area
R = Hydraulic radius
So = Channel slope
Rational Method
The rational
Th ti l method
th d iis generally
ll considered
id d tto b be an approximate
i t
model for computing the flood peak resulting from a given rainfall,
with the runoff coefficient accounting for all differences between the
rainfall intensity and the flood peak
peak. Such differences result of
infiltration, temporary storage, and other losses.
Rational
R ti l method
th d iis wellll kknown as one off th
the b
basic
i approaches
h tot
compute stormwater flows from rainfall by relating peak runoff to
rainfall intensity through a proportional factor.
The type
Th t off surface
f in
i the
th drainage
d i b
basin
i iis also
l iimportant.
t t The
Th
Rational Method becomes more accurate as the amount of
impervious surface, such as pavement and rooftops,
increases. As a result, the Rational Method is most often used in
urban
b and d suburban
b b areas.
The Rational Method is less accurate for larger areas and is not
recommended for drainage areas larger than 200 acres
acres.
Some
Some precautions should also be considered such as obtaining a good
topographic map and defining the boundaries of the drainage area. A field
inspection of the area should be carried out to examine the natural drainage divides.
For
F larger
l catchments,
t h t storage
t andd timing
ti i effects
ff t become
b significant
i ifi t and
d the
th
hydrograph method is needed (DID, 2000).
Compute
C t the
th peakk run-off,
ff Qp, for
f a 25-year
25 storm
t using
i R Rational
ti lMMethod
th d ffor a
drainage basin of 24 acres and having the following parameters:
Time of concentration:
Overland: average grass surface, length 300ft and slope 2%,
Sh ll
Shallow concentrated
t t d flflow: llength
th 550ft and
d slope
l 4%,
4%
Stream: length 1000ft, slope 0.4% and average cross section of:
Run-off coefficient:
Impervious, 0.5 acre @ c = 0.90,
G
Grass, 11.5
11 5 acres @ c = 0
0.35,
35
Wooded, 12 acres @ c = 0.25.
so g
Also given
e P = 1.2 inches
c es
Rational Method – Example 1
Time of concentration tc : tc = t1 + t2 + t3
t1 = time for overland flow is found from the Monograph in
Figure C-2.
t1 = 19.5 min.
Rational Method – Example 1
Therefore tc = 19
Therefore, 19.5
5 + 2.9
2 9 + 3.7
3 7 = 26
26.1
1 min
min.
Rainfall intensity
y is found using
g the IDF curve;; it is
shown in Figure C-3. Use the 25-year curve, i = 2.2
in/hr.
Compute
C t the
th peakk run-off,
ff Qp, for
f a 10-year
10 storm
t using
i RRational
ti l
Method for a drainage basin of 19 acres and having the following
parameters:
Time of concentration:
Overland: average grass surface, length 250ft and slope 2.5%,
Shallow concentrated flow: length 550ft and slope 4%,
Stream: length 1000ft, slope 0.39% and average cross section of:
10’
n=0.035
2.5’
5.5’
Run-off coefficient:
Asphalt and concrete = 1.1 acres, c= 0.95
Residential suburban, 7.5 acres @ c = 0.35,
Parks, 10.4 acres @ c = 0.25.
As we
we’ve
ve discussed before
before, Rational Method is Q =
CIA, and is great and simple estimation of the peak
runoff. Built into the Rational method is the simply
conclusion that the peak flow reaches the outlet at the
time equal to the time of concentration.
The underlying
Th d l i assumption ti iis th
thatt th
the peak
k iintensity
t it iis
maintained for a long enough duration to reach peak
flow at the outlet of the catchment. This results in a
trapezoidal hydrograph as shown below.below
Culvert Analysis and Design
Figure 2
2.1:Outlet
1:Outlet Control Flow Types (Normann
(Normann, et al.,
al 2001)
g
The higher of critical depth
p or tailwater depth
p at the outlet is used for calculating g
outlet velocity. Since the barrel for Culvert D flows full to the exit, the full barrel
area is used for calculating outlet velocity.
Culvert Analysis and Design
Submerged
g outlets.
In Figure 2.1D, the tailwater controls the culvert outlet velocity. Outlet velocity is
determined using the full barrel area. As long as the tailwater is above the
culvert the outlet velocity can be reduced by increasing the culvert size.
culvert, size The
degree of reduction is proportional to the reciprocal of the culvert area. Table
2.1 illustrates the amount of reduction that can be achieved.
For high tailwater conditions, erosion may not be a serious problem. The
designer should determine if the tailwater will always control or if the outlet will
be unsubmerged under some circumstances. Full flow can also exist when the
discharge is high enough to produce critical depth equal to or higher than the
crown of the culvert barrel.
Culvert Analysis and Design
Unsubmerged Outlets (Brink Depth)
Brink depth, yo, which is shown in Figure 2.2, is the depth that occurs at the exit
of the culvert. The flow goes through critical depth upstream of the outlet when
the tailwater elevation is below the critical depth elevation in the culvert.
Figure 2.2:Definition
2 2:Definition Sketch for Brink Depth
Figures 2.3 and 2.4 may be used to determine outlet brink depths for
rectangular and circular sections. These figures are dimensionless rating
curves that indicate the effect on brink depth of tailwater for culverts on mild or
horizontal slopes. In order to use these curves, the designer must determine
normal depth or tailwater (TW) in the outlet channel and Q/(BD3/2) or Q/D5/2 for
th culvert.
the l t
Culvert Analysis and Design
Figure 2.2:
Fi 2 2 Dimensionless
Di i l R ti
Rating
Curves for the Outlets of
Rectangular Culverts on Horizontal
and Mild Slopes (Simons, 1970)
Culvert Analysis and Design
Figure 2.3:
Fi 2 3 Dimensionless
Di i l R ti
Rating
Curves for the Outlets of Circular
Culverts on Horizontal and Mild
Slopes (Simons, 1970)
Culvert Analysis and Design- Example 1
Solution
Step 1. Calculate the quantity KuQ/D5/2 and TW/D. From Figure 2.3 determine
yo/D. (See following table for calculations.)
Step 2. Calculate yc from Figure B.2 or other appropriate method. Note that critical
depth is greater than brink depth.
Step 3. Determine flow area based on yo/D using Table B.2 and outlet velocity.
Culvert Analysis and Design- Example 1
From Table B2
F
From figure
fi 2.3
23
From figure B2
1.811Q/D5 V=Q/A
D (m) /2 TW/D yo/D yo (m) yc (m) A/D2 A (m2) (m/s)
1.05 2.73 0.58 0.64 0.67 0.73 0.5308 0.5852 2.905
12
1.2 1 95
1.95 0 51
0.51 0 55
0.55 0 66
0.66 0 70
0.70 0 4426
0.4426 0 6373
0.6373 2 667
2.667
1.35 1.45 0.45 0.47 0.63 0.70 0.3627 0.6610 2.572
1.5 1.12 0.41 0.42 0.63 0.67 0.313 0.7043 2.414
Solution
Step 1. Calculate the quantity KuQ/D5/2 and TW/D. From Figure 3.4 determine
yo/D. (See following table for calculations.)
Step 2. Calculate yc from Figure B.2 or other appropriate method. Note that
critical depth is greater than brink depth.
Step 3. Determine flow area based on yo/D using Table B.2 and outlet velocity.
Culvert Analysis and Design- Example 2
V=Q/A
D (ft) 1.0Q/D5/2 TW/D yo/D yo (ft) yc (ft) A/D2 A (ft2) (ft/s)
3.5 2.62 0.57 0.63 2.21 2.4 0.5212 6.3847 9.397
4 1.88 0.50 0.54 2.16 2.3 0.4327 6.9232 8.667
45
4.5 1 40
1.40 0 44
0.44 0 46
0.46 2 07
2.07 23
2.3 0 3527 7.1422
0.3527 7 1422 8 401
8.401
5 1.07 0.40 0.41 2.05 2.2 0.3032 7.5800 7.916
1 Di
1. Discuss about
b t any 3 challenges
h ll ffaced
dbby th
the water
t resources sector
t
in Malaysia.
1
1. Discuss the importance of stream flow?
2. Determine the time of concentration for the drainage area having the following
conditions;
a. Overland: poor grass surface, length 200ft and slope 2.5%
b. Shallow concentrated flow: length 450ft, slope 4%
c. Stream flow: length 900ft, slope 0.3% and average cross section as below;
12’
n=0.035
3.5’
7’
Assignment 2
3
3. Calculate the peak run
run-off,
off Qp for a 10 year storm using Rational Method for a
drainage basin of 23 acres, rainfall depth of 1.6 inches and having the following
parameters;
Time of concentration
a
a. Overland: poor grass surface
surface, length 200ft and slope 2
2.5%
5%
b. Shallow concentrated flow: length 450ft, slope 4%
c. Stream flow: length 900ft, slope 0.3% and average cross section as below;
Runoff coefficient
a
a. Brick= 44.5
5 acres
acres, c= 0
0.85
85
b. Residential suburban = 7.5 acres , c= 0.36
c. Playground= 11 acres , c= 0.23
12’
n=0.035
3.5’
7’
Dateline for these two assignments
g is on 24
October 2012. Please submit it before the
dateline.
My room : South tower, level 5 room PM2.