C-051-080-SPC-0004 - c1 - Specification For Fire and Gas Detectors Rev. 003
C-051-080-SPC-0004 - c1 - Specification For Fire and Gas Detectors Rev. 003
Equipment Tag
No(s):
Purchase Order/ Contract Number SDDRL Code Sequence No. Sheet No.
2015-C-051-0000-DG10-SPC-0005
1 Reviewed – no comment.
4 Review not required – for information only. By sinol.dsouza at 4:44:19 PM, 10/1/2015
M0015K-0000-CD10-FRM-0001 Page 1 of 1
SIBA Field Development Project
Client:
Kuwait Energy,
P.O.Box. 5614, Salmiya, Kuwait
PMC:
Touchstone.
P.O.Box. 72129, Sharjah, UAE
Project Title:
SIBA FIELD DEVELOPMENT PROJECT
Contract No:
KEIL/SIBA/2015/C-051-REV-CPF EPC
Document Title:
Re-Issued for
1 27.09.15 NVP HVS JSD WME
Implementation
Prepared Checked Approved Approved
Rev. Date Rev. Description PMC Rep. Client Rep.
By By By PTJ
Format Pages
A4 1 Of 33
Page 1 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Amendment Summary
Disclaimer:- “This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It
should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or
containing any error or omission which is due to an error or omission in data supplied to us by other parties.”
Page2 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
TABLE OF CONTENTS
1. Introduction ................................................................................ 6
2. Scope .......................................................................................... 8
3. Definitions ................................................................................... 9
4. Abbreviations ............................................................................ 10
5. Standards and Specifications .................................................. 12
5.1 Document Reference ......................................................................... 12
5.2 National and International Codes and Standards............................ 12
6. Reference .................................................................................. 15
6.1 Order of Precedence .......................................................................... 15
7. Units of Measurement .............................................................. 16
8. Environmental Condition .......................................................... 17
9. Area Classification ................................................................... 18
10. EMC Compliance ....................................................................... 19
11. Fire and Gas Detectors – Technical Requirements................. 20
11.1 General ................................................................................................ 20
11.2 Flame Detector – UV/IR / Triple IR Type ........................................... 21
11.3 Deleted. ............................................................................................... 21
11.4 Flammable Gas Detector – Point Type ............................................. 21
11.5 Flammable Gas Detector – Open path Type .................................... 22
11.6 Toxic (H2S) Gas Detector .................................................................. 23
11.7 Hydrogen (H2) Detector ..................................................................... 23
11.8 Deleted ................................................................................................ 24
11.9 Linear Heat Detector / Heat Sensing Wire loop / Fire wire.............. 24
11.10 Deleted ................................................................................................ 25
11.11 Manual Call Point ............................................................................... 25
11.12 Alarms and Notification Devices ...................................................... 25
11.13 Addressable Detectors ...................................................................... 27
11.14 Air Sampling Detection System (ASDS) ........................................... 28
11.15 Building Fire Alarm Control Panel (FACP) ....................................... 29
Page 3 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 4 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
List of Figures
Figure 1-1 – Siba Field Location ................................................................................... 6
Figure 1-2 – Google Map for CPF and Possible Export Pipeline Route ......................... 7
Page 5 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
1. Introduction
The SIBA gas field was discovered in 1969 and is located in Southern Iraq, in the Basra
Governorate, some 30 km southeast of Basra City extending east to the Shatt Al-Arab River as
illustrated in Figure1-1.
Kuwait Energy Iraq Limited (KEIL), a wholly owned subsidiary of Kuwait Energy Plc, in partnership
with Turkish Petroleum (TPAO) and Missan Oil COMPANY signed with South Oil COMPANY
(SOC) in Iraq a Gas Development and Production Service Contract (GDPSC) for the Siba Field.
KEIL has been appointed the Operator for the field.
The Siba Field will be developed to produce 100 mmscfd of sales gas (annual average) as per the
terms within the GDPSC. The field is virgin land at this point in time, located in Basra, Governorate
of Iraq.
Page 6 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Figure 1-2–Google Map for CPF and Possible Export Pipeline Route
KEIL is committed to developing the Siba field in a staged manner, with an initial Early Production
Facility (EPF) subsequently expanded to a higher capacity Full Production Facility (FPF). The EPF
shall comprise of:
Page 7 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
2. Scope
This document describes the minimum requirement for the specification of Fire and Gas Detectors
to be installed at Siba Gas Plant Central Processing Facilities (CPF) and associated facilities.
The Devices Controlling/Monitoring other Services are not covered in this documents.
Page 8 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
3. Definitions
CLIENT/COMPANY Kuwait Energy Iraq Limited (KEIL)
CONTRACTOR The Petroleum Project & Technical Consultation Co. - Petrojet
PMC Touchstone LLC
CONSULTANT Mott MacDonald Pvt. Ltd.
SUPPLIER/VENDOR The party(s) which carry out all or part of the design, procurement,
installation support and testing of the equipment as specified by the
CONTRACTOR.
MAY Alternatives are equally acceptable
SHOULD Preferred or recommended
SHALL Provision is mandatory or is a statutory requirement
MUST Provision is deemed essential
Page 9 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
4. Abbreviations
BS British Standard
FM Factory Mutual
IP Ingress Protection
IR Infrared
Page 10 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
UL Underwriters Laboratories
Page 11 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
BS5839 Part 1 Fire detection and fire alarm systems for buildings
Page 12 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
IEC 60331 Test for Electric and Optical Fiber Cables Under
Fire Conditions – Circuit Integrity
Page 13 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 14 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
6. Reference
6.1 Order of Precedence
In case of any conflict between this specification, related data sheets and diagrams, codes and
standards and any other specifications noted herein, the most stringent of the requirements shall
govern. The SUPPLIER or CONTRACTOR shall refer any such conflict and any other matter,
which requires further interpretation to the attention of COMPANY, and COMPANY representative
interpretation, shall be final.
The following is the order of precedence for Requisition, Specifications and Codes:
Page 15 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
7. Units of Measurement
Units of Measurement shall be SI system unless otherwise stated in the datasheets with the
following few exceptions:
Page 16 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
8. Environmental Condition
Instrumentation shall be designed to be located outdoors under direct sunlight.
The atmosphere is extreme harsh desert environment with air borne fine penetrating dust and
sand. Traces of sour gas (H2S, SO2) will be present in the air. All electronic boards and
component shall be designed to withstand such an environment.
Page 17 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
9. Area Classification
Siba Gas Plant hazardous area classification shall be Zone 2, Gas Group IIA, T3. However all field
instruments associated with F&G detection/control shall be rated for Zone1, Gas Group IIA, IIB
temperature Class T3 as a minimum.
Page 18 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 19 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Current Signal
(mA) meaning
0 Common
fault
2 Optical
fault
4 No gas
20 Full scale
deflection
Page 20 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
All devices shall be supplied with a termination box with fixed screw type electrical connectors
(flying leads are not acceptable). Cable entries shall be M20 x 1.5mm ISO and shall be provided
with cable glands.
The SUPPLIER shall submit the following information:
x Maximum allowable distance between transmitter and F&G system panel according to
cable core section.
11.3 Deleted
11.4 Flammable Gas Detector – Point Type
Flammable gas detectors should be Infrared point source type.
The time of response for the point type flammable gas detectors shall be as below
x Less than 2 seconds for HVAC duct applications or any fast response applications.
Flammable Gas detectors shall be calibrated to provide two alarm signals considering the high
level at 20% LEL and High-High level at 50% LEL and for Flammable gas detectors at HVAC inlet
the set point shall be 15% LEL and 25%
Sensor life shall not be less than 3 years.
Detector and supporting electronic equipment shall detect and communicate any failure that might
prevent a response to hydrocarbon gas. Undetected failures in ability to respond correctly to
hazards are not acceptable.
Detectors shall have serial communication capability (or equivalent) for use with interrogation tools
or connection to smart control equipment.
Detectors shall have a full range of available accessories for commissioning and operational
activities such as Duct mounting kit, Field calibration and testing kit, Remote gas sampling
accessories and Weather protection/ splash guard.
The standard sensitivity range of the detector shall be 0–100% LEL.
Detector shall be calibrated so that it will never underestimate the flammability of any gas
compositions that it may see in the area it is installed. Detector shall be factory calibrated and shall
not be recalibrated in the field.
Detector shall not produce an alarm indication greater than 10% LEL in response to water or water
vapour in the optical path. Fouling of optical surfaces by common contaminants found in the area
of installation shall not cause unwanted alarms. Substantial fouling shall be communicated as an
optical fault. Optical test filters shall be provided to test function and accuracy of the detector. If
this is not available, calibration gas may be used.
Detector selection should be based on the Lower Explosive Limit (LEL) of the predominant
stream components to provide the earliest detector response considering high alarm at 1
LEL.m and High-High Alarm at 2.5 LEL.m.
Detector shall be calibrated so that the flammability of any gas compositions for the area where it
is installed shall not be underestimated.
System shall contain diagnostics for the following conditions:
x Improperly installed equipment shall be detected. Detection of either excess path length or
misalignment shall prevent equipment from going operational.
Page 22 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
x After initial setup, significant reduction in signal for more than 60 seconds shall
automatically indicate an optical fault.
x Reduction of signal strength to less than 5% of the initial setup value for more than 1 hour
detector shall indicate a common fault.
Solar interference (sunlight) shall not cause false alarms.
Detector shall not produce an alarm indication greater than 0,5 LEL in response to any
combination of obstructions, vibration, or external sources of infrared radiation (including solar and
hydrocarbon flare radiation) in the beam.
Fouling of optical surfaces by the common contaminants found in the area of installation shall not
cause unwanted alarms.
Substantial fouling shall be communicated as an optical fault.
Optical test filters to test function and accuracy of the detector shall be provided.
Using calibration gas to test these detectors is unacceptable due to the large volume of gas that
would need to be released into the optical path. OEM calibration test kit IR films set shall be
provided for field testing. Transmitter-Receiver alignment kit shall be provided.
Siting distance for open path detectors is up to 60 m (200 ft) for SIBA facilities. With the approval
of the COMPANY/Contractor, longer path-lengths may be deployed.
Page 23 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
The Hydrogen gas detector shall be Electro-chemical point type (Catalytic typeshall not be
employed except in specific circumstances from approval by EPC CONTRACTOR/COMPANY).
Hydrogen gas detector shall be microprocessor based smart intelligent type with local read out.
The transmitter shall operate on 24V DC loop power supply and output shall be 4-20mA with
HART protocol. Hydrogen gas detector shall remain fully functional with a power supply between
18V DC to 30V DC.
Hydrogen gas detector and transmitter shall be EEx’d’ certified and shall be suitable for Zone 1,
Gas group IIC, T3 class area.
Hydrogen gas detector shall be calibrated and designed to operate from 0 – 100 % LEL,however
High level alarm limit shall be 10% LEL and High-High level alarm shall be 25% LEL.
The detector shall have a pre-warning feature that identifies the need for maintenance whilst
remaining full functional. This feature removes the need for routine maintenance.
The following shall be alarm settings:
Low Alarm – 10% LEL
High Alarm – 25% LEL
SUPPLIER shall advise the long term stability for zero and span.
11.8 Deleted
11.9 Linear Heat Detector / Heat Sensing Wire loop/Fire wire
The fire wire shall be a twin conductor cable with a temperature sensitive insulation protected by a
polythene braid outer sheath to meet the specific application requirements. Colour of outer sheath
shall be Red with Black ID tracer.
The fire wire shall fuse at a temperature range of 79 to 90 Deg C, following the concept of point of
risk detection. Each conductor shall be made of tinned copper – covered steel with a conductor
diameter of 0.9 mm.
The operating principle shall be such that in the case of a fire or acceptable operating temperature
levels are exceeded, the temperature sensitive insulation shall melt at 80 Deg C and short circuit
the twin conductors, to provide an instantaneous and reliable signal to the Fire and Gas System.
The fire wire shall be continuously monitored by the input card in Fire and Gas System so as to
detect open circuit and short circuit conditions. The necessary resistors for line monitoring shall be
supplied by SUPPLIER.The outer jacket shall be made of material to resist corrosion, chemicals,
moisture etc.
The heat detection cable shall be capable of returningto normal operating mode following an alarm
condition without the necessity ofreplacement.
In the event of cable being damaged by exposure to overheat, the cable shall be capable
ofreplacement of only damaged section
Page 24 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
11.10 Deleted
11.11 Manual Call Points
Addressable Manual Call Points
Manual call points at entry/exit of buildings in safe area shall be Addressable type looped with
Addressable Fire Alarm Control Panel of the building.
Manual call point shall be of lift flap “break glass” double action type. Lift flap is used for extra
protection against inadvertent operation. It shall have Key operated test facility.
The alarm contacts shall be opened under normal standby conditions, closing on alarm and come
complete with end of line resistors.
All units shall be surface mounted and tamper proof.
Colour shall be signal Red (or equal).
They shall be provided with a scoured glass and protective anti-splinter film. A means shall be
provided to test the call point without removing the cover.
Each break glass unit shall be clearly identified by a traffolyte label firmly attached. It shall have
the instrument tag number and the word FIRE, in white letters on red.
Field Manual Call Points
Manual Call points in process area and field shall be Non-addressable type connected with F&G
system.
Manual call points shall be of the break-glass, auto-release type.
The complete housing of manual call points installed outdoors shall be constructed in accordance
with requirements for the classified hazardous areas, shall be corrosion-resistant and fully
weather-proofed. For identification, they shall be coloured signal red to DIN Standard RAL 3000 or
equivalent.
Page 25 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
All audible and visual alarms for fire and gas system shall be distinguishable from audible and
visual alarms used for other purposes. The audiosignal shall be of different tones, as mentioned
below for fire, flammable gas, toxic (H2S) gas alarms.
11.12.1 Sounders
Page 26 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
11.12.2 Beacons
The beacons consisting of a flashing beacon shall be installed to give warning of fire or gas
release.
The beacons shall be located so that they shall be visible in the area for which they are to provide
a warning and are accessible for maintenance.
The beacon shall have a flashing frequency of 60 flashes per minute. The effective luminous
intensity shall be 300 candela (cd) minimum. Lamp shall be Xenon -discharge type. The dome for
flash tube on the flashing beacons shall be made up of transparent toughened glass. A lens guard
/ cage shall also be provided for all the beacons.
The visual alarm shall be suitable for surface mounting on either walls or poles as required and
shall be readily visible under all probable lighting conditions.
Page 27 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Combination Detectors (Heat/Smoke) shall be used in kitchen areas, to detect heat during the day
and smoke during the night.
Page 28 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
ASD system shall provide a sensitivity range of 0.005% to 20% obscuration per meter. This range
shall be fully configurable.
Components, equipment and assemblies shall be corrosion resistant.
SUPPLIER shall be responsible for the number of sample points provided, the number of ASDS
units provided, the detailed design layout of sample points and the generation of drawings for the
sampling system.
Sampling system shall employ a number of tubes of varying lengths. SUPPLIER shall design the
entire sampling network, pipe/tubing sizes, using appropriate software and submit to COMPANY
for review and approval. Multi-tube units, with automatic switching valves in the sample inlet
manifold to allow multiple sample lines to connect to a single aspirator / ASDSunit, can be
considered. In such case, the system component shall be redundant to avoid single point failure.
Output alarm contacts shall be provided individually per sample line.
SUPPLIER standard Teflon or other polymer tubing shall be used with COMPANY approval.
Sample system shall be under the false floor with branches up into various electronic cabinets.
The sampling system shall be protected against any mechanical damages. The tubing shall be
supported at regular interval to ensure stability of the tubing and reduce possibility of breaks. Any
points shall be airtight to prevent air leakage or infiltration. SUPPLIER shall label sampling system
tubing at branches, wall or floor penetrations, and at regular intervals of tubing runs.
SUPPLIER shall advise the maximum sampling time to alarm for each aspirated sample as a
function of the overall sample scan. It shall not exceed 120 seconds. Sampling system shall be
designed so it can be manually purged without pressurizing the aspirator unit.
ASDS units shall be supplied with local digital indicators. The main detector unit shall be immune
to dust and dirt build-up. It shall be capable of generating high signal to noise ratios, with immunity
from vibration and high humidity.
SUPPLIER shall design the equipment for 30 years design life.
Information shall be engraved or stamped sufficiently deep to remain fully legible following several
years usage, inclusive of maltreatment such as scraping to remove paint.
Wire-on labels are not acceptable. The following information, where applicable, shall be shown on
the nameplate, as a minimum:
Page 30 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 31 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 32 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
14. Spares
SUPPLIER shall complete and submit an SPIR form for three-year operational period as a part of
required documentation.
The SUPPLIER shall provide:
Page 33 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
Page 34 of 35
SIBA FIELD DEVELOPMENT PROJECT
KEIL/SIBA/2015/C-051-REV–CPF EPC
16. Documentation
SUPPLIER shall submit the documentation in accordance with the Supplier data Requirement list
(SDRL) of the Material Requisition and Purchase Order. All documents, drawings, dossiers
including third party certificates shall be in English.All reference to any system and field instrument
on any document shall be by referenced by its tag number.
SUPPLIER shall ensure that all the documents can be reproduced clearly and completely.
Wherever safety is involved, documents shall be approved by certifying authority prior to proceed
to fabrication.
Typical documents include:
x Wiring Diagrams
x Test Procedures
x Software documentation
Page 35 of 35