Service water analysi
‘The following analysis ofthe service (desalinated) water supplied from the connection
to SPS is given below for information only. The Contractor at his own cost shall be
responsible to obtain sufficient samples and make analysis of the plant service water
for his use. Accordinaly the Contractor shall be responsible to include any
modification required for his plant and equipment, the total cost of which shall be
considered as included in his total offered contract price without any reservation in
this respect
Desalinated water analysis Normal
Nogtal lctcty conduct mero ohms @ 00
‘Total dissolved solids (based on 0.60 ppm 30
{micro onms,
PH 6-65
Free causte (#8 NaOH) pen i
Total caustic (as NaOH) ppm 4
Total chloride (as Cl ions) ppm 20
Total alkalinity (as CaCO) pm 10
Total sulphate(as SO.) ppm 5
Total hardness (as CaCOs) Pem 10
Free carbon dioxide (as COz) ppm 0.10
Total iron pm 010
Total silica (SiO) pm 010
Total ammoniacle nitrogen (free and saline) a 20
as NHs
5.1.6.7.3 Towns water analysis
Towns water (potable water)'s supplied to the site via the municipal system. The
typical analysis of the water is as below however it should be noted thatthe water is
Chlorinated, and on occasions this can be at high levels. The Contractor at his own
Cost is responsible for checking and confirming the analysis of the towns water
{potable water) without any reservation in this respect.
Total dissolved solid TDS (max) ppm 320-400
Total Alkalinity T Alkali as CaCod ppm 80-100
Chlaride Ton CF pm 60-80
Sulphate SOF ppm 40-60
Carbon Dioxide Coz Pem 18-3600
Total Iron Fe ppm 015
Silica ‘SiOz ppm W515
Caustic ‘OF Free) ppm 0
Caustic ‘OF (Total) pm a
Total Hardness T Hard pm 700-160,
Conductivity Cond usicm 400 - 500
PH pH range ppm 72-80