Short Circuit Study
Short Circuit Study
Condition 1: Electric potential difference and fault impedance is equal to Zero – Bolted
fault current.
Condition 2: Electrical potential difference is equal to Zero and fault impedance has some
value.
2
Effects of short circuit:
Short circuit occurs even in well designed power systems, can cause large decaying
transient current generally much above the load current.
(Electrodynamic stress – For example; when an load is suddenly added, so thus the
generator must force it to run at the higher speed instead of the normal running speed
that causes the overcurrent).
Excessive overvoltage that not occurs at all the conditions that means when the
short circuit happens thus the voltage and the fault impedance must have the
some values hence the excessive voltage might take place.
Overloading
Improper laying
3
Poor Maintainance
Wrong selection of application ( For a 30A cable; If we put a 20A cable however
the 30A current will flow in the 20A cable so thus causes damage(fault) to the
cable)
Ageing of the cable (cable is used for a past long years that causes fault occurs in
the cable).
Ageing
Overloading
Poor Maintainance
Ageing
Overloading
4
Poor Maintainance
Bearing failure
Moisture
Deterioation of Insulation.
Ageing
Overload
Poor Maintainance
Moisture
Deterioation of Insulation
Lightning surges ( when lightning strikes hits the transformer causes fault
current)
Switching surges ( When the transformer tap change is occurs; so thus the
current rises takes place as fault current).
5
In short circuit study: when Impedance increases thus the short circuit current will
decreases and when impedance decreases thus the short circuit current will
increases.
Fault current will higher at near to the source because of the low impedance.
Fault current will lower at near to the load because of the higher impedance.
Fault cannot prevented, we can attempt to mitigate to certain extend and contain their
potential damaging effects.
To avoid the insufficient rating of equipment’s For a 30A cable; If we put a 20A
6
cable however the 30A current will flow in the 20A cable so thus causes
damage(fault) to the cable)
IEC 60909 (2016) – Short circuit in Three phase AC system (Grid connected)
IEC 61363 (1998) - Short circuit calculation procedure for Three phase AC
isolated system
Applicable for low voltage and high voltage three phase AC system
Not applicable for short circuit testing station (Deliberately created short circuit)
For the duration of the short circuit there is no change in the type of short circuit
involved. E.g. - 3phase remains 3phase during the time of short circuit.
For the duration of short circuit, there is no change in the network involved.
All the line capacitances and shunt admittances and non rotating loads, except those
of the zero sequence system are neglected.
C Factor:
C factor or voltage factor is defined as the ratio between the equivalent voltage source
and the nominal system voltage.
C factor has two types:
Cmax – Maximum shirt circuit current
Cmin – Minimum short circuit current.
8
VOLTAGE FACTOR (C) FOR THE CALCULATION OF
9
The above picture shows that when you click the ETAP software to open the short
circuit project file and to click the short circuit study case; click the standard option in
the study case to view the Cmax values for the respective voltage ratio.
Choose to Min. (Exclude Duty Calc) to view the Cmin of the respective voltage ratio.
10
Formula for Impedance correction factor:
KT =( 0.95*Cmax/1+(0.6*XT) )
XT – Transformer Reactance
ZTK = KT *ZT
In the above picture shows that to perform the short circuit study in ETAP; firstly to give
the rating of the voltage in the rating option of the power grid editor.
11
STEP 2:
In the above picture shows that, to click the short circuit option of the power grid editor
to give the X/R ratio and KASC for three phase and single phase should be equal; hence
the MVASC and (Pos, Neg, Zero sequence impedance of 100 MVA base) for the Short
circuit will automatically calculate by the software itself.
In the short circuit study only, we have to give values for the short circuit option in the
power grid editor but not for the load flow study.
12
STEP 3:
After the system has to be modelled, you should fault the bus by right click the mouse to
strike on the bus. or else click the short circuit study case and go to info option; to choose
the which bus make to fault as shows in the below figure.
13
After made the bus to be faulted, the faulted bus shows in the red colour.
14
In the above picture shows that the transformer with the impedance tolerance of + or – 10%.
For short circuit study only the tolerance of the impedance should be taken as -10% because
of the worst case of the Short circuit study is that when the impedance is low then only the
short circuit current will be higher.
15
The foremost thing before you run the simulation for the short circuit is that you can
ensure that whether your power grid editor is in the swing mode option, hereafter only
run the condition.
16
Fault occurs at BUS 70:
In the below picture shows that the fault current has to be run by the three phase duty
cycle of three phase of symmetrical fault current with -10% impedance tolerance.
The above figure shows that to click the display option in the right corner to change the
three phase fault current of initial sys. rms to peak current to display the peak fault
current at the Bus 70.
17
The above figure shows that the peak fault current value at the Bus 70. The system has
the transformer with the impedance tolerance of -10%. (Run at three phase device
duty)
The below figure shows thus the fault occures at Bus 69 and Bus 70, hence the fault current
occures at the two buses as symmetrical fault current with the transformer impedance
tolerance of -10%. (Run at Three phase device duty).
18
The below figure shows that the fault current occurs at the Bus 69 and 70, hence the fault
current occures at the two buses as symmetrical fault current of peak values with the
transformer impedance tolerance of -10%. (Run at Three phase device duty).
19
What you are done in the project has to be analyse through the report. Click the report
manager in the right corner of the software home page, click the complete option and to
choose the report as the pdf file type then the software will generate the report for the project
for the better covinience.
The above picture shows that the general information about the project such as which study
have u taken and which fault you have to be run, which standard yo have run the short
cicrcuit and also the how many swing and load buses
are present in your project.
20
The above picture shows that adjustments made in the transformer impedance and
recatance and also the transmissionn line length, cable length.
21
The above figure visualize that Bus input data means how many buses are there in the
project in which type of bus and KV of the bus and also the sub – sys details.
The above picture shows that the two winding transformer input data as MVA, primary
and secondary voltages in KV and also the % of Z, X/R, % of Tolerance and finally with
the %Z adjusted.
22
The above picture shows that the branch connection details, In the branch connection option
itself only the value of impedance include the impedance correction factor and also the
impedance with 100 MVA. The resistance and reactance with 100 MVA base value.
23
Impedance at branch connections at report
24
25
The above figure shows that the power grid input data consists of MVAsc, KV, (R, X’’,
R/X of 100 MVA Base value).
BUS 69: BRAKING AND DC FAULT CUURENT (TOTAL BUS FAULT CURRENT)
In the above figure, at the time duration of 0.30 seconds thus the I b asym current will
changes to Ib sym of 25KA with Dc decay of 0.042 KA decreases gradually.
26
BUS 70: BRAKING AND DC FAULT CUURENT (TOTAL BUS FAULT CURRENT)
27
Thus the above figure show the Short circuit summary report itself only the two buses
peak fault current and also the symmetrical fault current has to be shown.
28
In the above ETAP result with conditions; thus the 1 st condition receiving end bus voltage
is higher than the 2nd condition, thus the 1st condition receiving end bus fault current is
decreases as compared to 2nd condition receiving end bus fault current.
29
Types of Fault:
1) Series Fault
2) Shunt Fault
Series Fault:
The open circuit fault mainly occurs because of the failure of one or two conductors. The
open circuit fault takes place in series with the line, and because of this, it is also called
the series fault. Such types of faults affect the reliability of the system. The open circuit
fault is category as:
1) One Conductor open
2) Two Conductor open
When one conductor is opened, thus the voltage flows in the R phase will diverged into
the other conductors. Hence the negative sequence has to be created so thus the motor
rotates in the reverse direction to create the fault current.
30
Two Conductor open:
When the two conductors are opened, hence the voltage at the two conductors will
diverged into the remaining one conductor However, this situation is more critical as it can
lead to significant unbalance and further exacerbate negative sequence effects. The system
might still operate, but with increased risk and potential damage.
Shunt Fault:
In this type of fault, the conductors of the different phases come into contact with each
other with a power line, power transformer or any other circuit element due to which the
large current flow in one or two phases of the system. The short-circuit fault is divided into
two fault.
31
Symmetrical Fault
Unsymmetrical Fault
Symmetrical Fault:
Three Phase fault
Three phase to ground fault
Unsymmetrical Fault
Single line to ground fault
Line to line fault
Double line to ground fault
32
Single Line to ground fault:
The single line of ground fault occurs when one conductor falls to the ground or
contact the neutral conductor. The 70 – 80 percent of the fault in the power
system is the single line-to-ground fault.
33
Double Line to ground Fault:
In double line-to-ground fault, the two lines come in contact with each other along with
the ground. The probability of such types of faults is nearly 10 %.
34
Fault percentage at each components:
35
Severity of Faults:
36
CONDITION 1:
LG Fault current is greater than the three phase fault current at receiving end bus
when transformer at no load conditions and also the transformer at delta – star
solidly grounded without load condition :
37
Three phase Device duty – IEC 60909
38
CONDITION 2:
There is no LG fault current at receiving end bus is greater than the Three phase
fault current at the receiving end bus due to delta – star resistive grounded without
load condition :
39
Line to Ground Fault – Run IEC 60909:
40
CONDITION – 3:
LG fault current at the receiving end is not greater than the three phase fault current
at the receiving end of delta to star solidly configuration of transformer due to with
load condition:
41
Run IEC 60909 SLG:
42
CONDITION -4:
SLG fault current at receiving end is higher than the three phase fault current at the
receiving end due to generator in voltage control mode in no load condition:
Three phase fault current : (Generaator with no load condition in voltage control
mode)
43
Single line to ground fault ( Generator at no load condition with voltage control mode)
44
Nature of the Fault current:
45
When a fault initially occurs in a power system, asymmetrical waveform components are
present due to the presence of DC offset or DC decay components.
These components can arise from various sources such as transformer magnetization,
saturation effects, or DC offset in the faulted circuit. Initially, the fault current waveform
may exhibit asymmetry, but as the DC offset or decay components dissipate, the
waveform transitions to a symmetrical RMS waveform. This symmetrical RMS current
represents the balanced three-phase fault current flowing through the system.
46
Initial Symmetrical Short Circuit Current: (Ik”)
RMS value of AC symmetrical component of short circuit current applicable at the instant
of short circuit if the impedance remains zero-time value.
RMS value of an integral cycle of the symmetrical AC component of the short circuit
current at the instant of contact separation of the first pole to open of a switching device.
RMS value of short circuit current which remains after the decay of transient phenomena.
47
Asymmetrical Fault current:
Asymmetrical fault current refers to the unbalanced flow of fault current in one or more
phases of a power system during a fault condition. Unlike symmetrical faults where the
fault current is balanced across all phases, in an asymmetrical fault, the fault impedance
or fault location causes the fault current to be unequal in magnitude or phase angle across
the phases
48
During a fault condition in an inductive load system, the fault current waveform initially
exhibits asymmetrical characteristics due to the presence of both the symmetrical
waveform components and the DC decay components. These DC decay components
arise from the transient effects caused by the sudden change in the system's operating
conditions. As the fault persists, the DC components gradually decay, typically within
one cycle, transitioning the fault current waveform to a symmetrical form.
50
PEAK CURRENT WILL AFFECT BY CHANGE IN X/R RATIO:
51
There are three methods available in ETAP for the X/R Ratio
Method 1:
Method 2:
X/R = 17 - 60 HZ
Method 3:
Transmission Line ( Three phase fault current) Fault at two buses: symmetrical
value (No load conditiion) length – 1Km
52
Transmission Line ( Three phase fault current) Fault at two buses: peak value ( No
load condition) length – 1Km
Transmission Line ( Single line to ground fault current) Fault at two buses: (No load
condition) length – 1Km
53
Transmission Line ( Three phase fault current) Fault at two buses: symmetrical
value (No load conditiion) length – 10 Km
Transmission Line ( Three phase fault current) Fault at two buses: peak value ( No
load condition) length – 10 Km
54
Transmission Line ( Single line to ground fault current) Fault at two buses: (No
load condition) length – 10 Km
55
Transformer with transmission line as length of 10Km with 0% tolerance of Single line
to ground fault condition: 2 bus fault condition
56
Transformer with transmission line as length of 10Km with 0% tolerance of Single
line to ground fault condition: 3 bus fault condition
57
Transformer with transmission line as length of 10Km with 0% tolerance of Single
58
line to ground fault condition: 2 Bus fault condition
It is importantly to note that when the transmission line lengh increases; due to this
factor line reactance, inductance and capacitance factor has increases hence the
short circuit current will limited.
Fault far from source and nera to source:
59
In ETAP, we used only the sub transient mode:
In power systems, the sequence network is a mathematical model used to analyse and
understand the behaviour of three-phase electrical systems. In a three-phase system, there
are three conductors carrying alternating currents, typically labelled as phases A, B, and
C.
The sequence network represents the system in terms of three sets of phasors: positive
sequence, negative sequence, and zero sequence. Each set of phasors represents the
balanced components of the voltages and currents in the system under different
conditions:
60
1. Positive Sequence: Represents the balanced components of voltages and currents in the
system when all three phases have the same magnitude and are equally spaced apart. This
is the normal operating condition of the system.
3. Zero Sequence: Represents the unbalanced components of voltages and currents in the
system when all three phases have the same magnitude and are in phase with each other.
This typically occurs in situations like ground faults.
The sequence network allows engineers to analyse the effects of various faults,
disturbances, and unbalanced conditions on the system.
61
ETAP RESULTS FOR SEQUENCE NETWORK AND SEQUENCE IMPEDANCE
FOR TRANSFORMER:
Positive, negative and zero sequence transformer switching ( Fault current flows) –
Line to Ground fault
62
NAME : SARANYA PRAKASAM
ETAP COURSE
Positive, negative and zero sequence transformer switching ( Fault current flows) –
Three phase fault
From thus, when we run three phase for the above condition there is no changes of KA
injcetd to the buses occursdue to the transformer vector configuration, because three
phase does not mine the configurtaion and it takes normally as delta to star solidly
grounded for all possible conditions but not for Line to ground fault condition.
63
Fault current contribution to the different types of load
1) Motor load ( Constant Power load)
2) Lumped load ( static load and motor load)
3) Static load ( Constant Impedance laod)
4) VFD
Motor load:
( THREE PHASE FAULT – FAULT AT TYWO BUS) ( INDUCTION MACHINE)
64
Lumped load: ( 60% Motor load and 40% static load)
( THREE PHASE FAULT – FAULT AT TWO BUS)
65
STATIC LOAD ( THREE PHASE FAULT – FAULT AT TWO
BUS) ( STATIC LOAD – 100% IMPEDANCE LOAD) NO SHORT CIRCUIT
CURRENT PRODUCE AT STATIC LOAD
66
VFD Enabled: ( THREE PHASE FAULT ) – FAULT AT TWO BUS
67
VFD BYPASSED
68
VFD BYPASSED
69
EARTHING
What is Earthing and why we need it?
System Earthing
Equipment Earthing
Lightning protection Earthing
Static Earthing
System Earthing:
Earthing associated with the current carrying conductor (transformer and generator)
in which neutral of the phase is connected to the general mass of the earth.
Essential for the security of the system
1. Solid Earthing
2. Resistance Earthing
3. 3. Reactance Earthing
Solid Earthing:
Neutral point of the generator or transformer is connected to the ground mass directly
without any impedance or resistance are been intentionally inserted.
71
Advantages of Solid Earthing:
72
Resistance Earthing:
73
Reactance Earthing:
Low Reactance
High Reactance
74
High Reactance Earthing:
Equipment Earthing:
75
SOLIDLY EARTHING (SLG)
76
RESISTANCE EARTHING: (SLG)
77
RESISTANCE EARTHING: (SLG)
78
NEUTAL TRANSFORMER EARTHING/ Xfmr RESISTOR: (SLG)
79
NEUTAL TRANSFORMER EARTHING/ Xfmr RESISTOR: (SLG)
80
REACTANCE EARTHING
81
REACTANCE EARTHING
82
ETAP RESULT: CB WITHSTAND (THREE PHASE FAULT CURRENT)
83
METHODS TO LIMITING FAULT CURRENT
84
CURRENT LIMITING REACTOR
85