Date Boq of The Proposed Residential Building For MR: Praveen and Jyothi Sl. Description Qty Unit Rate No. Rs - Ps. A. Earth Work
Date Boq of The Proposed Residential Building For MR: Praveen and Jyothi Sl. Description Qty Unit Rate No. Rs - Ps. A. Earth Work
BOQ OF THE PROPOSED RESIDENTIAL BUILDING FOR Mr: PRAVEEN AND JYOTHI
A. EARTH WORK
NOTE: The rates quoted for the relevant excavation
items shall include the following
Shoring, strutting and protecting the sides
of excavation trenches,
Consolidation must be done with heavy
iron hammers
1 Earth work excavation in ordinary soil for foundation
trenches, isolated column footing, depth not exceeding
5' 3,675.00 CFT 20.00
4 Do as item no:3 but Earth brought from out side QRO CFT
Sub Total
B. CONCERETE WORK
6 Providing and laying PCC 1:4:8 using 40mm graded
granite aggregate below the footing including normal
ramming , compacting and curing.
421.00 CFT 322.20
7 Providing and laying PCC 1 : 4 :8 using 40 mm
graded granite aggregate below the flooring as
levelling course including ramming , compacting and
curing etc. 641.00 CFT 322.20
8 Providing and laying Plinth Beam Band (DPC) in 69.00 CFT 338.14
1:3: 6 mix
9 Providing and laying PCC in1:2:4 mix over Cinder 225.00 SFT 210.00
Sub Total
C. REINFORCED CEMENT CONCRETE
NOTE: With reference to the following reinforced
concrete items, the rates quoted shall include for
necessary shuttering and formwork (either steel or
wood-centering- /sft) machine mixing vibrating the
concrete wherever necessary scaffolding and curing,
but exclusive of reinforcement steel and fabrication
charges.
Sub Total
E. IRON AND STEEL WORKS
23 Supply,fabricate & tie in position MS round and cold
twisted ribbed tor steel reinforcement in RCC items
including necessary bending, cutting & tying with 16
guage G.I binding wire including precast concrete cover
blocks.
F. PAVINGS / FLOORING
24 Providing and laying Ultra tile or equivalent Cement 399.00 SFT 128.93
pigment tile for the flooring of parking & Drive way
( BP - Rs.45/sft )
Sub Total
G.PLASTER
NOTE: In the following items, the rates quoted shall
include for all drip moulds, throating arises etc., as and
where directed. The rate quoted shall include floor
making good chases patches etc. made by other
agencies and for necessary scaffolding and curing
b Diamond GI 6" Mesh for Plastering for column joints 1,736.00 RFT 50.00
( M/S Arpitha or equ )
Sub Total
H.PAINTING AND DECORATION
Note: The number of coats specified for paintiing items
shall be the minimum specification. The rate quoted
shall include for all necessary tools, scaffolding etc
I . WOOD WORK
41
Providing and fixing Doors with Berma Teak wood
frame of
3"X5",shutter of 1 1/2" thick panel of size not less
than1'6"
8"x1 1/2",width, 4 panels
side of withcentre
5"x 1 1/2", top side
vertical of 32.00 SFT 4,687.00
3"x1 1/2" and centre 3 horizontals 3"x 1 1/2".
All the rates are including fittings and
fixing charges as shown below.
1) Mortice lock of value 500
2)Brass tower bolt 8"size
3)Brass tower bolt 6"size
4) 4 nos of Brass hinges 5"size
Sub total
J .MISCELLENEOUS
45 Providing and fixing Staircase Ralling with 4"dia MS
pipe support (newel post)with 2.5"dia pipe on the top
and verticalsupport of 3/4" rods on each steps with
necessary fittings as per the design 176.00 SFT 400.00
Sub Total
K.ELEVATION FEATURES
79
Providing and fixing MS Pergola with toughened glass
on top for Balcony 52.00 RFT
ABSTRACT
A Earth Work
B Concrete Work
D Masonry
.
E Iron and Steel works
F Pavings / Flooring
G Plastering
I Wood work
J Miscellaneous
K Elevation detail
GRAND TOTAL
AREA IN SQ.FT
b Earth work excavation in ordinary soil for Wall footing 1,180.00 CFT
c
Providing & laying PCC 1:4:8 using 40mm graded
granite aggregate column and wall footing 168.00 CFT
d Providing & laying Sizestone masonsry in CM1:6 in
3courses,including racking out or flushing the 765.00 CFT
joints and curing
e Providing & casting RCC M20 with 3/4" graded granite 102.00 CFT
aggregate for Belt Beam
f Providing and laying DPC 4" Thick in 1:3: 6 mix 119.00 CFT
Sub total
Note:
RFT: Running Feet
SFT:Squire Feet
CFT:Cubic Feet
MT: Metric Tonne
BP: Basic Price
QRO : Quote Rate Only
GF:Ground Floor
FF:First Floor
SH: Stair Head room
Basic Price(Can change as per the fluctuation in the
market)
H SAND
I GRANITE AGGREGATE
6 mm jelly = Rs ./cft
12 mm jelly = Rs.24/cft
20 mm jelly = Rs. 24/cft
40 mm jelly = Rs.24/cft
AND JYOTHI
AMOUNT
Rs.Ps.
73,500.00
-
-
25,590.00
-
-
-
-
87,380.00
-
186,470.00
135,647.25
-
-
-
206,531.80
-
23,331.32
-
-
47,250.00
412,760.36
443,783.25
-
-
-
93,564.30
62,499.47
25,147.72
112,794.91
-
-
37,740.00
11,730.00
20,655.00
-
55,916.69
67,011.27
24,851.86
-
-
86,537.73
74,333.70
36,242.30
-
248,518.62
257,394.29
116,862.92
69,831.14
-
1,845,415.19
447,064.63
600,160.15
285,478.11
-
276,990.16
359,666.25
82,507.71
-
-
-
-
-
208,472.00
2,260,339.00
2,442,000.00
51,444.12
-
-
2,357.81
177,182.28
32,618.61
-
115,391.07
-
15,413.79
-
207,200.23
33,020.42
-
203,275.30
-
97,312.76
-
21,282.38
-
-
-
956,498.76
55,284.38
69,059.29
18,071.68
-
-
-
175,783.32
206,648.08
71,625.69
-
-
-
-
-
155,584.28
148,371.87
64,993.81
-
-
86,800.00
-
-
1,052,222.38
125,200.00
-
-
-
-
-
435,475.00
-
-
-
-
-
-
314,650.00
-
49,100.00
38,400.00
75,650.00
37,825.00
32,650.00
-
-
1,108,950.00
-
-
-
-
-
149,984.00
-
-
-
-
-
-
-
-
149,984.00
-
-
70,400.00
-
93,800.00
-
-
-
-
-
41,354.32
-
-
-
-
-
-
-
-
-
-
-
-
-
-
257,425.00
-
-
39,900.00
-
16,000.00
-
-
-
-
-
-
-
-
84,000.00
-
151,560.00
-
168,350.00
-
-
-
-
-
-
-
-
10,000.00
-
-
-
-
-
-
-
-
-
-
630,000.00
-
-
52,500.00
-
-
-
-
-
-
-
250,000.00
1,865,289.32
-
-
-
-
-
-
24,643.76
-
-
-
-
-
20,117.70
-
-
-
-
-
44,761.46
186,470.00
-
412,760.36
-
1,845,415.19
2,260,339.00
-
2,442,000.00
956,498.76
1,052,222.38
1,108,950.00
149,984.00
1,865,289.32
44,761.46
12,324,690.46
1,000,000.00
1,200,000.00
14,524,690.46
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
NDIDITON.
Kg/m2 Rate
Putty SFT 1000 10 100
B Material
41311.19
D Scaffolding 1% Extra 1% 413.11
E Transportation Cost 1% 1% 413.11
F Other Charges 2 % Extra 2% 826.22
Add for Water Charge @ 1%
G 1.5% 619.67
on Items Marked
Sr
Description Qty Unit Rate Cost
No.
Details of cost for 100.00 sq.m.
A Labour Charges
1 Mate 8.1 Day 500 4050
2 Mason 8.1 Day 700 5670
3 Helper 8.1 Day 400 3240
4 Bhisti 2.7 Day 400 1080
5 Coolie 8.1 Day 400 3240
B Material
Cement 10.51 Bag 320 3363.2
Wastage of Material 2% 2% 67.26
Sand 1.46 Cu.m. 1320 1927.2
Wastage of Material 7% 7% 134.9
D Scaffolding 1% Extra 1% 53.58
E Transportation Cost 1% 1% 53.58
F Other Charges 2 % Extra 2% 452.72
67.264
134.904
19.272 53.5766
457.5944
54.76391 5.47639 11
Thickness of Plaster = 12 mm
= 0.012 meter
[To convert wet volume of mortar to dry volume we have to add 30% to 33% extra of wet vo
Therefore total volume of
mortar become = 1.72 meter
cube
33% extra of wet volume.]
Providing and laying of Indian Marble using large size marble slabs as specified but not
less than 4' X 5' .laid on a bed cement mortar 1:6 of minium thikness 20mm,including
curing,machine polishing,tin oxide polishing etc,complete.(BP=150/SFT) (For Living ,
Dining & Family area
Therefore, 6/(Sum of
b Mortar proportion)
Therefore,6
cum/(1+6)
Therefore, Value for
One (1) is
0.857142857142857
Cement 0.857142857142857 30 25.71429 cum 450
(1cum = 30 bags)
Crushed Sand 0.857142857142857 6 5.142857 cum 1200
Add extra cement for 0.1 bag per Sqm x
10 bag 450
backing paste 100 sqm
Total of A
B Labour charges 100 sq-m 280
C Wastage @ 10%
D Scaffolding & tools @ 5%
Water & electricity
E
including curing @ 2%
Total
Add for profit & Overhead
F
@20%
For
Total rate
100sq-m
For 1sq-
Total rate
m
Providing and laying of Granite using large size granite slabs as
specified but not less than 4 sft.laid on a bed cement mortar 1.5 of
minium thikness 19mm,including cost of bedding
materials ,etc,complete.(BP-220/SFT)
Therefore, 6/(Sum of
b Mortar proportion)
Therefore,6
cum/(1+5)
Therefore, Value for
One (1) is
1
Cement 1 30 30 cum 450
(1cum = 30 bags)
Crushed Sand 1 5 5 cum 1200
Add extra cement for 0.1 bag per Sqm x
10 bag 450
backing paste 100 sqm
Total of A
B Labour charges 100 sq-m 280
C Wastage @ 10%
D Scaffolding & tools @ 5%
Water & electricity
E
including curing @ 2%
Total
Add for profit & Overhead
F
@20%
For
Total rate
100sq-m
For 1sq-
Total rate
m
b Mortar
for 100 Sqm = 6 cum
Therefore, 6/(Sum of
b Mortar proportion)
Therefore,6
cum/(1+5)
Therefore, Value for
One (1) is
1
Cement 1 30 30 cum 450
(1cum = 30 bags)
Crushed Sand 1 5 5 cum 1200
Add extra cement for 0.1 bag per Sqm x
10 bag 450
backing paste 100 sqm
Total of A
B Labour charges 100 sq-m 280
C Wastage @ 10%
D Scaffolding & tools @ 5%
Water & electricity
E
including curing @ 2%
Total
Add for profit & Overhead
F
@20%
For
Total rate
100sq-m
For 1sq-
Total rate
m
Amount
161400 150
11571.43
6171.429
4500
183643
28000
18364.29
9182.143
3672.857
242862
48572.43
291435
2914.346
270.85
Amount
236720 220
13500
6000
4500
260720
28000
26072
13036
5214.4
333042.4
66608.48
399651
3996.509
371.42
Amount
172160 160
13500
6000
4500
196160
28000
19616
9808
3923.2
257507.2
51501.44
309009
3090.086
287.18
Providing and laying Ultra tile or equivalent Cement
pigment tile for the flooring of parking & Drive way
( BP - Rs.45/sft )
Providing and laying coloured Vitrified tiles for flooring and fixing
them over 1/2" to 3/4" thick CM 1:6 backing and pointing the joints
neatly with white cement coloured to the tile. (BP-80/SFT) (for all Bed
rooms and Dress)
2'x2' size
Item No. Item Explaination Quantity Unit Rate/unit
A Material
a Vitrified tile 100 Sqm 860.8
For 1 Sqm = 0.06 cum
for 100 Sqm = 6 cum
Therefore, 6/(Sum of
proportion)
b Mortar
b Mortar
Therefore,6 cum/(1+4)
Therefore, Value for One
(1) is
1.2
Cement 1.2 30 36 cum 450
(1cum = 30 bags)
Crushed Sand 1.2 4 4.8 cum 1200
Add extra cement for 0.1 bag per Sqm x 100
10 bag 450
backing paste sqm
Total of A
B Labour charges 100 sq-m 280
C Wastage @ 10%
Scaffolding & tools @
D
5%
Water & electricity
E
including curing @ 2%
Total
Add for profit &
F
Overhead @20%
Total rate For 100sq-m
Total rate For 1sq-m
Providing and laying coloured ceramic tiles for toilet flooring and
dadoing in toilets and kitchen fixing them over 1/2" to 3/4" thick cm 1:6
backing and pointing the joints neatly with white cement coloured to the
tile(B.P-50/sft)( for all bath rooms& kitchen wall cladding)
48420 45
0.05 0.01
16200
5760
4500
74880
28000
7488
3744
1497.6
115609.6
23121.92
138731.52
1387.3152 128.93
Amount
86080 80
16200
5760
4500
112540
28000
11254
5627
2250.8
159671.8
31934.36
191606.16
1916.0616 178.07
Amount
53800 50
11571.429
4114.2857
4500
73985.714
28000
7398.5714
3699.2857
1479.7143
114563.29
22912.657
137475.94
1374.7594 127.77
RATE ANALYSIS FOR BRICKWORK
9" wall
Scafolding
@2% of prime cost
Sundries
@3% of prime cost
CONTRACTOR PROFIT
Contractor Profit 20
Scafolding
@2% of prime cost
Sundries
@3% of prime cost
CONTRACTOR PROFIT
Contractor Profit 20
1410
1028
150
2587.50
Amount
430.30
430.30
Amount
430.30
430.30
% 1893.32
1410
1028
150
2587.50
Amount
343.30
343.30
Amount
343.30
343.30
% 1510.53
Hard soil
Items Units Qty. Rate Amount
Hydraulic Excavator Day 40 450.00 18000
Tractor/Dumper Day 1 3500 3500
Unskilled Labor Day 2 1000 2000
Total 23500
Water charges @1.5% total 352.5
Tools & plants 5% LS 1 1175
OH & Contactor Profit @15% 4770.5
SUM 29798
Gross Amt./CUM up to 1.5m
COST 425.68571 12.055670187
depth
900
m3 per day working hours m3 per hour
Excavation 60 8 7.5
1.5
40 8 5
Explainati
Item No. Item Quantity Unit Rate/unit
on
A Material M20
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+1.5+3)
Therefore, Value for 0ne (1) is
2.76
1 Cement 2.76 30 82.91 bags 450
(1cum =
30 bags)
2 Crush Sand/FA 2.76 1 2.76 cum 1500
3 Metal/CA 2.76 2 5.53 cum 1600
Total of A
B Labour charges 10 no 3200
C Wastage @ 5%
D Plant & machinery @ 5%
Water & electricity including
E
curing @ 2%
Total
Add for profit & Overhead
F
@15%
Total rate For 10cum
Total rate For 1cum
Explainati
Item No. Item Quantity Unit Rate/unit
on
A Material M15
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+2+4)
Therefore, Value for 0ne (1) is
2.76
1 Cement 2.17 30 65.14 bags 450
(1cum =
30 bags)
2 Crush Sand/FA 2.17 2 4.34 cum 1500
3 Metal/CA 2.17 4 8.69 cum 1600
Total of A
B Labour charges 10 no 3200
C Wastage @ 5%
D Plant & machinery @ 5%
Water & electricity including
E
curing @ 2%
Total
Add for profit & Overhead
F
@15%
Total rate For 10cum
Total rate For 1cum
Explainati
Item No. Item Quantity Unit Rate/unit
on
A Material M10
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+3+6)
Therefore, Value for 0ne (1) is
2.76
1 Cement 1.52 30 45.60 bags 450
(1cum =
30 bags)
2 Crush Sand/FA 1.52 3 4.56 cum 1500
3 Metal/CA 1.52 6 9.12 cum 1600
Total of A
B Labour charges 10 no 3200
C Wastage @ 5%
D Plant & machinery @ 5%
Water & electricity including
E
curing @ 2%
Total
Add for profit & Overhead
F
@15%
Total rate For 10cum
Total rate For 1cum
Explainati
Item No. Item Quantity Unit Rate/unit
on
A Material M 7.5
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+4+8)
Therefore, Value for 0ne (1) is
2.76
1 Cement 1.17 30 35.08 bags 450
(1cum =
30 bags)
2 Crush Sand/FA 1.17 4 4.68 cum 1500
3 Metal/CA 1.17 8 9.35 cum 1600
Total of A
B Labour charges 10 no 3200
C Wastage @ 5%
D Plant & machinery @ 5%
Water & electricity including
E
curing @ 2%
Total
Add for profit & Overhead
F
@15%
Total rate For 10cum
Total rate For 1cum
35 35.31 1235.85
27 35.31 953.37
Amount
37309.09091
4145.454545
8843.636364
50298.18182
32000
2514.909091
2514.909091
1005.963636
88333.96364
17666.79273
106000.7564
10600.07564 300.12
69.7026
369.82 36.98
73.96 110.95
Amount
29314.28571
6514.285714
13897.14286
49725.71429
32000
2486.285714
2486.285714
994.5142857
87692.8
17538.56
105231.36
10523.136 298.02
69.7026
367.72
Amount
20520
6840
14592
41952
32000
2097.6
2097.6
839.04
78986.24
15797.248
94783.488
9478.3488 268.43
69.7026
338.14
Amount
15784.61538
7015.384615
14966.15385
37766.15385
32000
1888.307692
1888.307692
755.3230769
74298.09231
14859.61846
89157.71077
8915.771077 252.50
69.7026
322.20