Method Statement Final
Method Statement Final
Page 1 of 21
CONTRACTOR METHOD STATEMENT
CONTRACTOR DETAILS:
Office Location: Ware House No: 19, RKM Compound, Al Quoz 3, Dubai, UAE.
Page 2 of 21
METHOD STATEMENT:
PERSONS
Sr.No. NAME DESIGNATION
REQUIRED PPRE :
Safety Boots
Hard Hats
Safety Gloves
Hearing Protection
Eye Protection
Respiratory Protection
EQUIPMENT :
MATERIAL TO BE USED :
12mm Glass
Ceramic tiles
Raised Flooring of 60 x 60 concrete tiles
Gypsum Board
Page 3 of 21
Fenomastic Emulsion paint
Silicone & Glue
G.I. Channel
o
Tiling Work Floor
o
Ceiling work
o HVAC
o Electric work
o
Glass Partition
o
Painting.
1. PURPOSE
The purpose of this Work Method Statement for Floor and Wall Tiling Works is to outline and
Describe in detail the procedure such as setting and lay-out plan on actual location, pre-laying of tiles,
mixing of tile grout, final laying of tiles and all other related activity. Inform all concerned supervisor
including workers the value and importance of this activity prior to implementation. This Activity should
be performed with strict compliance and implementation of Safety Requirements & Procedure and project
specifications to complete the work both for floor and wall tiling.
2. SCOPE OF WORKS
o The scope of this Method Statement covers the works in any Project:
o Floor and wall ceramic tiles on plastered concrete/masonry block
o Ceramic tile on Drywall partition
o
3. STEP OF WORKS
3.1 Preliminary preparation
Approvals
o Obtain approval on SOP (setting out plan)
o Obtain on direction of tiles
o Obtain approval on glue, grout and thickness of grout.
o Obtain access permit from the General contractor
o Obtain the final fix dimension/samples from the General contractor
o Obtain dry layout approval if the works are typical rooms and huge quantity
o Obtain approval on work area restriction to prevent unauthorized entry and the area should be kept
closed with red tape until the mortar/glue set.
Page 4 of 21
Before carrying out tile-fixing works ensure that:
a. All surfaces must be structurally sound, clean, free from dust, oil and any traces of foreign materials that
may affect adhesion of the tile adhesive on the substrate.
b. Brick, floors must be allowed to cure for a minimum of 4 weeks prior to tiling.
c. Cement render and screed must be allowed to cure for at least 7 days and finished to Semi-smooth finish
with a wood float. After curing, a thorough check on the Soundness in adhesion of the screed and render
should be carried out. All substrate Defects should be properly rectified.
Access preparation
Vacuum/brush the residues and the particles before starting the tile installation, as to make sure the thin-set
will lock them to the concrete sub-floor/plastered block. In addition, sprinkle Water on the
concrete/plastered surface before installing the ceramic tiles, to increase the Bond of the adhesive. Soaking
ceramic building materials in water are a common practice. This is a necessity when laying tile that is very
soft, like Saltillo tile, or low-fired, unglazed terracotta. When a tile (or brick for that matter) is too porous,
it will suck the water out of the mortar without allowing it
to set properly, leaving weak bonds between mortar and tile.
3.5 Protection:
o Brush off loose materials, wash with clean water and remove surplus water with cloth.
o Treat with an appropriate acid cleaner in accordance with the Manufacturer’s instructions.
o Before applying the cleaning agent, wet the floor and remove any surplus water; after
CEILING WORK
This is one of the most important steps before commencement of actual ceiling installation. Here grid
layout is arrived by taking into consideration room dimensions {length (l) x breadth (b) x height (h)} Points
to remember: In practical conditions, often the room dimensions are not exactly square in dimensions. In
the basement where there are many ducts, pipes, and cables that may occasionally need maintenance,
installing a suspended ceiling grid system makes a lot of sense. The installation is easy and will make the
basement space more appealing. Suspended ceilings are also ideal for first floor bathrooms where there is a
bathroom on the floor above to allow for plumbing access.
TOOLS
• Chalk line
• String
• Hammer
• Tin snips
• Pliers
• Screwdriver
• Utility knife (with extra blades)
• Level
• Spirit level
•
MATERIALS
• acoustical tile
• T structural system
• Main T members
• Cross T members
Page 7 of 21
• L-shaped angle mold
• 16-gauge wire to hang the structural T’s
• Eyelet hardware
BEFORE THE INSTALLATION
• This suspended ceiling step-by-step installation guide is based on the room having wood
construction walls.
• If installing a suspended ceiling grid into a room that has masonry walls, the installation is virtually
the same as that of wood construction. Simply use a masonry drill, bit, and screws.
• If removing older tile, take care at how it is disposed of if it was installed before 1960 as there may
be asbestos in the tiles.
• Choose the style of the acoustical tile first and then begin the design, purchase, and installation
work thereafter.
• There are different types of acoustical tiles available. Keep in mind that regular tiles have recessed
flanges that protrude below the grid roughly 1/4". Regular tiles may be tricky to cut and trim.
• A licensed electrician may be needed to install light fixtures
Step 1
How to Plan and Design a Suspended Ceiling for Installation
The first step if you have purchased your Suspended Ceiling from Ceiling Tiles UK you will have likely
received a drawing to show the layout of your ceiling. This will show the position of the components
required to complete your project.
However, if you have chosen not to receive a drawing or you want further assistance on planning the lay
out of your ceiling, please find below the information you will require.
• You will need to have the dimensions of the room or rooms you will be installing your ceiling in.
• Draw the dimensions as close to scale as possible.
Page 8 of 21
• Graph paper can help you with this.
• You can choose from either a 600×600 or a 600×1200 configuration. The configuration you pick
will determine the material requirements for your ceiling.
• You can now draw the layout onto your graph paper.
• Remember whichever option you have selected (600 x 600 or 1200 x 600) you must set the Main
Runners at 1200 centers. Position the tees so that the cuts around the perimeter are equal on both
sides and are as large as possible
• This will make it easier to cut the tiles to size.
• If you are using a 600×1200 configuration, space the 1200mm cross tees 600mm apart. For a
600×600 configuration, add 600mm cross tees between the midpoints of the 1200mm cross tees.
• If you are also putting recessed lights in the ceiling now is the time to plan where they will be
going as it’s easier to move the position of these on paper first.
The second step is to install your Edge Trim around the perimeter of your room.
Page 9 of 21
Perimeter Edge Trim/
Wall Angle Installed
Step 3
The third step, now that you have successfully fitted your Edge Trim is to measure out your suspension
wire and plot the points at which you will be suspending your ceiling.
• Please refer to the drawing that Ceiling Tiles UK has provided you as this will show the location of
the Main Runners. These will be shown on the drawing as a red line
• Measure and mark out the position of each main tee along the perimeter trim.
• The clip on the end of the Main Runner have to be cut off on the end that will rest on the trim.
• Now secure your:
•
• Wire Hangers – if the ceiling is suspending from concrete
• You will need to straighten the suspension wire to enable you to hang the Main Runners.
• If you can secure a hook or vine eye into a drill you can attach a length of wire to a fixed secure
point and the other end is wrapped around the hook of vine eye in the drill. When you spin the drill
this will pull the wire straight. Please only do this until the wire is straight as overdoing this can
snap the wire and ALWAYS ensure that you have correct safety glasses and gloves on when
doing this
• Measure how long the wire has to be cut based on the drop you originally calculated (the distance
from the original ceiling to the new suspended ceiling.
• Add 300mm to the length you need to allow you to have plenty of wire to wrap round to secure the
Main Runner.
Page 10 of 21
• Fix the wire to the fixings that have been provided by putting the wire through the location holes
and securely wrapping the wire round.
• Give the wire a hard tug to confirm it is secure.
• Fix the first suspension wire for each main tee at 400mm – 600mm from the perimeter trim. Check
the drawing we have provided you with for the locations.
• Attach a suspension wire every 1200mm along the line of the main runner.
Step 4
How to Install the Main Runners (3600mm)
The fourth step to installing your suspended ceiling is to fit your main runners into your edge trim to form
the foundation of your gridwork system.
• Most Main Runners are 3600mm long and have slots at every 100mm for your Cross Tees to fix
into. These will begin 50mm from each end.
• Put the first Main Runner in place closest to the Perimeter Trim, ensuring the slot for the first Cross
Tee is in line with the location of the Cross Tee as per your drawing.
• Proceed to measure and cut the Main Tees to size, always checking that the slots on the Main
Runner are in line with locations or the Cross Tees.
• Use a string line across the room to show where the first row of Cross Tees will be located. This
lets you know where the first pre-punched slots need to be.
• Place the Main Tee on the Edge Trim/Wall Angle.
• If the room that you are installing the ceiling in is shorter than 3.6m long, cut the Main Runner to
size
• If you need to do this remember that the clips on the end will have to be removed also.
• For rooms wider than 3600mm, Main Tees can be joined together.
Page 11 of 21
Step 5
How to Install Cross Tees (1200mm) Cross Tees (600mm)
The fifth step once your Main Runners are all connected into your Edge Trim is to connect your Cross Tees
into the gaps within your Main Runner.
• The Cross Tees connect to the Main Runner by fitting into the slots.
• Depending if you have selected to install a ceiling with 600×600 or 600×1200 this will determine
the location of the Cross Tees, Please refer to your drawing.
• To install the Cross Tees; The 1200 Cross Tees go into Main Runner & 600 Cross Tees go into
centre slot of 1200 Cross Tees, this will form 600 x 600 squares.
• If you are installing 1200 x 600 tiles this will sometimes mean that you do not have to use any 600
Cross Tees and vice versa on smaller 600×600 Ceilings 1200 Cross Tees may not be needed.
• Before cutting and fixing the perimeter cross tees, drop a few full tiles into the grid to ensure the
grid remains square.
• The perimeter Cross Tees are cut to size and rest on Edge Trim/Wall Angle. (See picture).
The sixth step is to fit your Ceiling Tiles into the gaps in your newly created Suspended Ceiling Gridwork
system.
• Now the grid is in place and ridged the tiles can be put into place. Angle the tiles up through the
grid and gently lower the tiles into place.
• If you have a tile with a pattern make sure the tile is aligned correctly before installing and also it
is a good idea to use gloves when handling the tiles to ensure no fingerprints are left on the tiles.
• When you cut the tiles to go on the edges of the ceiling this can be done very simply with a Stanley
Knife.
Step 1
Step 2
Step 3
Step 4
Page 13 of 21
Step 5
HVAC WORK
SCOPE
SCOPE OF WORK
• This procedure is to define the method used to ensure that the Chilled Water Pipework System comprising all pipes,
tubes, valves, fittings, reducers, expanders, nipples, vents, bleed off, expansion and contraction devices, hangers,
brackets, anchors, supports, sleeves, plates and all accessories and components connected thereto as an integrated
pipework system, installation final connections and workmanship, is correct and acceptable and conforms to the
contract documents and General Specifications.
• This procedure defines the method that will be used to ensure that the insulation to all supply and return mains, headers,
branches, risers, drips, runouts, pump suction and discharge, pipework, fittings, flanges, valves, expansion and
movement devices, flexible connections associated with the chilled water system installation and final connections and
workmanship, is correct and acceptable and conforms to the contract documents and General Specification
PURPOSE
Purpose of this procedure is to define the inspection, method and criteria for installation work for the
HVAC air distribution system to achieve mechanical completion.
Page 14 of 21
INSTALLATION PROCEDURES
GENERAL REQUIRMENTS
o All material received at site shall be inspected by the engineer’s representative, handled and stored
upon receipt.
o All installation / Construction / Testing works shall be carried out in compliance with the contract
specifications and project safety manual.
o Inspection and testing shall be conducted by the site supervisor and/or be co-ordinated with
Mechanical representative / Engineer (as applicable).
o All test equipment shall have valid calibration certificate.
o All equipment provided shall be inspected to ensure that it is free from any physical damages.
a. This "Method Statement" covers the nature and type of work for the installation of Chilled Water
Piping and Accessories in the building and the frequency of which the inspections are to be carried
b. This procedure also covers the method of installation and inspection of Chilled Water Piping with Accessories.
a. All the materials delivered to site are inspected properly and stored as per the manufacturer recommendations.
c. Work shall be carried out by the site staff under the strict supervision and guidance of the concerned Supervisors /
Engineers.
3.0 Tools
• Following indicative hand tools list shall be used for the installation works.
• Drilling Machine
• Hammer
• Sprit Level
• Pipe Wrench
• Grooving Machin
• Thread Cutting Machine
• Pipe work Tools box
Page 15 of 21
4.0 INSTALLATION OF AIR HANDLING UNITS
o Examine areas & conditions to receive equipment, for compliance with installation tolerances & other
conditions affecting performance of air handling units.
o Examine roughing-in of hydraulic, condensate drainage piping & electrical cabling & wiring to verify
actual locations of connections before installation.
o Install air handling unit’s level & plumb, slope for drain, etc., according to manufacturer’s instructions
and applicable specification.
o Arrange installation of units to provide access space around air
5.0 SAFETY
b. Ensure all concerned personals shall use PPE and all other items as required.
d. Ensure deep manhole excavations / shaft openings are protected with barricade, tape, safety nets.
Electric Work
Scope / Objectives.
This Method Statement details general procedures to be followed for construction of Electrical Works for
Projects.
Method Statement / Procedure for Activities.
o Before casting any wall in the site, we have to check if there is any Switch Socket, bell or break glass
fixed on the column. If there is any, we have to fix the GI or PVC box in the proper way so that it will
be touch with shatter of the. Column from inside and the conduit will be extended to the top of
the column.
o Before starting the wiring for the above mentioned activities, we have to make sure that the plasterwork
is finished completely in that area / floor & there is no more water still on the walls.
o Before start pulling the wires we will be sure that there is no water or any rubbish inside the conduits.
Page 16 of 21
o At the false ceiling area (60 x 60), we have to use a ceiling rose with a heat resistance wire & where are
coming a gypsum board ceiling, we have to extend the wires from the slab to the expected level of the
gypsum ceiling through a flexible conduits.
o For the light & Power circuits, wires & cables will be used as per the approved material submittal
(2.5mm
o for the lighting circuits & 4.0mm
o For the power circuits).Lighting & Power circuits will be run in separate conduits.
o The wires & cables will be installed in conduits, trucking and ladders as per the approved shop
drawings.
o For branch circuit work, originating from light & power panel boards will be arranged as per the
approved drawings. Loads on various phases of panel boards will be balanced as per he approved load
schedules.
o Gangs as indicated and shall be grid type.
o Pole configurations - Single pole, double pole, 2 way or intermediate as indicated.
o Local lighting switches for the control of lighting circuits shall be of the following types:
o For single and multi-gang units in locations in the building where installation work is on the surface
switches shall be of the surface pattern and shall be mounted in proprietary metal boxes.
o For single and multi-gang units in all areas throughout the building where installation work is
concealed, switches shall be of the 10A grid switch type flush pattern and shall be mounted in suitable
metal boxes.
o For areas where switches are shown connected to different phases, in the same location, multi-gang
switches are to be used with an approved phase barrier and shall also be to the requirement of the local
authority.
o An "array" of single gang switches adjacent to each other shall be avoided by usingmulti-gang switches
ii) Install sleeves for main telephone incomer. Install telephone boxes & telephone junctions boxes. Prior co-
ordination with Etisalat is required for exact location of telephone main cable entry sleeve.
iii) Install PVC Conduits embedded in concrete slabs and walls
iv) Install trunking / cable trays in risers as highlighted in relevant shop drawings.
v) Run wires from various telephone / data outlets in to intermediate telephone distribution frames, via
trucking / pipes in corridors false ceiling area.
vii) Run telephone / data cables from intermediate distribution frame panel into main distribution
frames in ground floors low current room via trucking / cable riser.
viii) Install distribution frame panels, telephone / data outlets and terminate relevant wires and cables.
Testing and Commissioning of telephone installations
Page 17 of 21
Glass partition work
Step 1 - Measuring
a) Measure the floor to ceiling height - check it in at least 3 places, ceilings are not always level!
b) Measure the width - check its straight with a spirit level.
c) Measure the depth - again check the wall the glass will join to is straight with a spirit level.
d) Check if the floor is concrete, wooden floor boards or a suspended floor
e) Check if the ceiling is solid or suspended.
Choose one of our standard room sizes based on the measurement you have taken, and then also let us
know what your ceiling and floor and made of. We can then do the rest for you and send you a kit with
everything you need.
If your measurements don’t fit one of our standard room sizes we can make the glass to fit your project,
use our handy wall cost calculator.
The first stage of installation is to fix the Aluminium U channel provided around the perimeter of where
the glass partition wall is going to be. Cut the Aluminium channel to length, drill some holes in the
channel and then fix the aluminium channels to the floor, walls and ceiling using screws and wall plugs
(not supplied). Ensure the screws are fixed into something solid.
In the case of a suspended ceiling you should fix the U channel directly into the frame work of the
suspended ceiling and then reinforce this above the ceiling with some timber where necessary. Once the
U channel is in place, the glass just slides into the channel wither at the door opening, or you can just lift
the glass up into the top channel and then drop it down into the bottom channel.
The glass is then secured into the U channel by pushing a rubber gasket into the channel on each side of
the glass. The wedges the glass securely into the channel, clamping it so it can’t move. Allow a 5mm
vertical gap between each glass panel and then once the rubber gasket has been pushed in all around, fill
this gap with clear silicon to fix all the panel together.
Page 18 of 21
Step 5 - Door Installation
Painting Works
After completion of preparatory works such as installation of block, plaster preparation, plaster works and
then the painting works will carry out. In this article will show the procedure on how painting activities will
be done.
The purpose of this method is to define the measures and ways of proper application of paint in this project.
Works shall be carried out in compliance with the drawings, project’s specifications and materials. We
required 4 working days for the mobilization after completion of contractual
Procedure.
Work procedure
Preparation
• Other trades works those are already installed will protect covered/protected acceptably by the liable agent
prior to surface preparation and painting will commence.
• All floor finishes, that already installed to be protected by the flooring contractor.
• We will check the base surface where the paint decoration to be done prior to painting base preparation and
confirm the level of finishes required for the application of painting. Mainly surface plaster/drywall
imperfection, unevenness, sagginess, bump, heavy scratches/cracks, improper corners MEP cut-outs etc.,
that need to be modified to an adequate level to receive paint finishes.
• Once the base structure is adequately good enough to receive paint decoration then we will commence
removal of the dust and dirt etc.,
• The surface of the area to be painted would be prepared by removing loose particles etc., by using
sandpaper.
Page 19 of 21
• Engineer has to confirm all the final fix marking and cut outs are made by the responsible agent and release
access clearance prior to 1st and 2nd coat painting. All final fix items will be covered by ISD.
• 1ST coat painting will apply and allow 6 hours to dry prior to succeeding coat. Engineer has to release
access clearance to apply 2nd and final coat. Please note that at this stage any missing final fix items can be
installed without doing any damage to the paint system
• We applied already. In case of any damage that will be charged as
• General Contractor has to provide all necessary, suitable and safe scaffolds and platform for working at
height that more than the reach of 3Mtr.
• General contractor has to provide necessary, suitable and safe Narrow and Pony scaffolds and platform for
the application of paint system at all narrow/congested areas to avoid working on ladder. General
contractor has to provide necessary, suitable and safe
• Movable scaffolds and platform to be provided at wider areas.
Safety
• All works shall comply with safety procedure or instruction set out in
• Project safety plan and Municipality rules and regulations.
• Basic PPE to be worn by all staff or operatives.
• All operatives involve in this work shall be inducted before entering
• The site.
• Tool box talk shall be conducted regularly.
• Wheel borrow
• Drip tray
• Roller brush and hand brush
• Electric, pole and hand sander
• Drill machine for paint mix
• Sand papers
• Scrapers
• Rug cloth
• Approved paints
• Scope of works or specification
• Approved drawing
Page 20 of 21
TOOL BOX TALK ON:
1. Importance of PPE
2. Use and service of hand tools and electrical tools
3. Safe handling of power supply
4. Use of mechanical equipment and service
5. Housekeeping safety
6. Risk Assessment
7. MSDS (Material Safety Data Sheet)
8. Access clearance
9. Lifting, Shifting and Storing
10. Rest Area
11. Restriction of Mobile and Radio
12. Noise restriction
13. Cutting of materials that makes noise and dust
14. Approved shop drawing
END OF DOCUMENT
.
MADAN LAL
Project Manager
Page 21 of 21