Back-Up AC Auxiliary Oil Pump & Forced-Air Cooling of Steam Turbine
Back-Up AC Auxiliary Oil Pump & Forced-Air Cooling of Steam Turbine
Forced-Air Cooling
Proposed Design,
System for Steam
Installation,
Turbine for
Operation and
3x135MW CFB of
Maintenance of
FDC-MPC,
Back-up AC
Villanueva Misamis
Auxiliary Oil Pump
Oriental
2 ENGINEERING REPORT
PROPER
Outline
3 ENGINEERING ECONOMICS
4
EVALUATION, OBSERVATION,
CONCLUSION AND
RECOMMENDATIONS
5
GLOSSARY OF TERMS,
BIBLIOGRAPHY, REFERENCES,
APPENDICES
CHAPTER 1 : INTRODUCTION
4 Organization
5 Location
Project A: Project B:
➢The power plant is expected to run uninterrupted ➢The Thermal power plant outages, plant layups and
unless a program such as PMS is scheduled. Any system shutdowns are part of the power plant's
unforeseen stoppage is a huge loss to company. overall availability program. It is important to
As such, redundancy equipment is sometimes maximize the shutdown duration in order to start
needed when that particular system could directly earlier than the forecast schedule.
cause big impact if fail.
➢The Forced-Air Cooling System will provide
➢The back-up AC Auxiliary Oil Pump will be the additional cooling air (hot air lower than internal
additional security when the current pump fail. This temperatures) to hasten the process. The project is
ensure continuity of operations and prevent huge composed of blower, electric heater, safety
losses like damage turbine bearings, turbine instruments, temperature controller, and is mobile
blades, as well as damage turning gear trains for ease of transportation.
during run-up.
Filinvest’s flagship power project stared its commercial operations in 2016 and has three (3)
generating units with a total capacity of 405MW gross. Located at the PHIVIDEC area in Misamis
Oriental, the power plant uses the latest in clean coal technology: the Circulating Fluidized Bed
(CFB) boiler technology. Considered as the cleanest process to burning coal, the technology is also
known for having higher steam generator efficiency thus lowering carbon emissions. FDC Misamis
Power Corporation helps drive progress for com munities in Mindanao.
AREA OF MY PROJECTS
MAIN BLOCK – TURBINE HALL
Subject of Reports
Current and Proposed back-up AC Forced-Air Cooling System for Steam
Auxiliary Oil Pump Turbine:
EXISTING AC AUXILIARY
LUBE OIL PUMP
Subject of Reports
EXAMINE:
Bearing Failure
Bearing failure occurs due to abrasion, bond
failure, cavitations erosion, corrosion, fatigue,
overheating, surface wear, structural damage.
Subject of Reports
EXAMINE: Temp
Longer Shutdown
Duration
Natural Convection takes longer period to
bring down the temperature to minimum to
allow maintenance team to start their
activities.
MAIN BLOCK
MAIN BLOCK
MAIN BLOCK
ENTRY
EXIT
HARNESSING ENERGY. EMPOWERING COMMUNITIES.
CHAPTER 2 : Engineering Proper
❖ To design a back-up AC Auxiliary Lube Oil Pump for Unit 1, 2, & 3 as additional cooling Pump during Turbine
Start-up and Shutdown;
❖ To outline the installation, commissioning, operation, and maintenance consideration of a backup
circulating water pump; and,
❖ To determine the cost and feasibility of the project.
The specific objectives above shall be the basis for the development of the document and technical report for the
study
❖ To identify the type of cooling system appropriate to the steam turbine application without causing harm to
the equipment.
❖ To formulate and elaborate in details the design, installation, commissioning, operation and maintenance of
the FDCMPC steam turbine force-air cooling system.
❖ To determine the technical requirements, specification and calculation for the application of forced-air
cooling of the FDCMPC steam turbines.
❖ To determine the feasibility of the proposed project to the FDCMPC steam turbine.
The specific objectives above shall be the basis for the development of the document and technical report for the
study
The proposed back up unit takes over when the existing AC Overhauling of steam turbine is as complicated as it is, and would
Auxiliary Oil Pump fail to start or malfunction during operation. take long time to disassemble/assemble, and with a little help from
The loss of lubrication of rotating parts could bring huge the proposed system could lessen these burdens. The machine is
damage and profit loss to the company. assembled on a mobile support which allows to use a single system
to provide forced cooling air to different turbines in the plant, if
desired. Since excessive thermal stress is generated on the surface,
it is necessary to introduce air at a temperature slightly lower than
that of the Steam Turbine’s metal temperature to gradually cool the
metal. Therefore, the electric heater is used to preheat the air, and
the air is forcibly fed directly into the steam turbine, or after
temporarily storing it.
Type/Model DKY2-1N30U
MOTOR PUMP
Steam Turbine
Speed 3600 RPM
Manufacturer WEG Manufacturer ALLWEILER
Power Output 135,000 KW (142,000 KW)
Power, kW 30 Power, kW 17.1
Rotating Direction Counter clock wise
Speed, RPM 3550 Speed, RPM 3520 Live Steam Pressure 132.4 barA
Rated Flow,
Hertz, Hz 60 79.2 Live Steam Temperature 540 C
m3/h
Reheat Steam Pressure 2.52 barA
Voltage, V 480 Head, m 54.8
Reheat Steam Temperature 540 C
Current, A 45.4 Sp. Gravity 0.848
Main Steam Flow 420 kg/sec
MAIN BLOCK
Steam
Turbo – Generator
Set-up
HP IP LP G
TURNING GEAR M
AC
HP IP LP G
TURNING GEAR M
AC 1 AC 2
13 6 12 7 11
11
8
8 10
10 9
9
ø = 254 mm
v = 0.361 m/s
Z2 = 7 m
H1 = 56 mmWC
ø = 152.4 mm
2 3 Q = 290 GPM
14 v = 1.005 m/s
4 5
1 PV = 0.5
` mm Hg
VG 46 Mineral oil
Orange line = Return from Turbine
Z S= 1 m
Pipe velocity refers to the speed at which a fluid (such as a liquid or gas) is flowing through a pipe or conduit. It is
an important parameter in fluid mechanics and engineering, as it affects various aspects of fluid transport, including
pressure drop, energy efficiency, and the ability to carry solid particles or suspended materials.
PIPE πD2
Q = AV A= Description Dimensions
VELOCITY where
4 Baseplate Dimension 45 cm x 74 cm
Given: Return Pipe 254 mm
Q = 290 gal/m or 0.01830 m3/s (design flow) Discharge Pipe of pump 152.4 mm
Ddis = 152.4 mm or 0.1524 m (discharge pipe diameter) Operating Temperature 46 C
Dret = 254 mm or .254 m (return pipe diameter)
Formula to find discharge velocity, Vdis of the pipe: Length of Pipeline 112 m
Density of Oil 848 kg/m3
3
0.01830 𝑚 ൗ𝑠
Vdis = 1.005 m/s Flow Rate 290 GPM = 0.01830 m3/sec
Vdis = 𝜋𝑥 0.1524 𝑚 2
4 Vret = 0.361 m/s Operating Discharge Pressure 2.77 Bars
FRICTION From Cameron Hydraulic Data by Westaway and Loomis, Chapter 3-3, Using Darcy-Weisbach’s formula for friction
head losses for lubricating oil as follows:
HEAD
𝐋 𝐕2
𝐇𝐟 = 𝐟 𝐱 𝐱
𝐃 2𝐠
Since the pipe diameter changes between points 1 and 2, it is necessary to determine the frictions occurring
between these points; thus, our friction head loss, Hf can be separated into two (2): the pipe friction HFP and the
fitting friction HFF. the friction produced by fittings (for example elbows, isolation valves, etc.) between the same
two points.
𝑳𝒅𝒊𝒔 𝐕 𝟐 𝒅𝒊𝒔 𝑳𝒓𝒆𝒕 𝐕 𝟐 𝒓𝒆𝒕
Hf = HFP + HFF HFP = f (
𝑫
.
𝟐𝒈
+
𝑫
.
𝟐𝒈
)
𝒅𝒊𝒔 𝒓𝒆𝒕
Solving for Reynold’s number (Cameron Hydraulic Data, Chapter 3-3): µ = Dynamic Viscosity
𝝆𝑽𝑫 ρ = Density of the fluid
𝑹𝒆 = V = Velocity of the fluid
FRICTION 𝝁 D = pipe diameter
FACTOR Temperature = 46 C
For the pipe we will used pipe material Stainless Steel same as existing
pipe. In Figure 2.19.2, the Pipe roughness of stainless steel is ε =
FRICTION 0.015 x 10-3 meter.
FACTOR
The Colebrook–White equation is defined as f for the Darcy friction
factor, the function of for Reynolds number as Re, pipe relative
roughness expresses as, ε / Dh for both smooth pipes and rough pipes.
[3]
𝜺
𝑹𝒆𝒍𝒂𝒕𝒊𝒗𝒆 𝑹𝒐𝒖𝒈𝒉𝒏𝒆𝒔𝒔 = Figure 2.19.2: Pipe Relative Roughness for fully developed
𝑫𝑰𝑫 flow in circular pipe [11
factor:
𝑯𝑭𝑷 = 𝟕. 𝟗𝟔 𝐦
In fluid mechanics, friction losses occur in pipe systems when fluid flows through various components such as bends,
FRICTION elbows, tees, valves, and other fittings. These losses are due to the resistance encountered by the fluid as it navigates
HEAD changes in direction and velocity. To calculate head losses in a pipe system with various fittings, you need to know the
LOSS IN loss coefficients (K factors) specific to the type and configuration of each fitting. These coefficients are often available
FITTINGS in engineering references and standards, for this report, we’re going to use “Cameron Hydraulic Data” as a reference
for various K factors for our system.
FRICTION
HEAD
LOSS IN
FITTINGS Figure 2.22: Hydac International Manufacturer’s Filter Calculation Graph [1]
Figure 2.23.1: K factor for Gradual Contraction (Cameron Hydraulic Data) [3] Figure 2.21. Friction Losses in Pipe Fittings Resistance Coefficient K3 by Cameron
Hydraulic Data [3]
study. To calculate the losses, we need to solve ∆Phousing – Housing curves is available based on ISO 3968. (See Figure 2.20 A)
SK – Gradient Coefficient (See Figure 2.20 B)
individual’s friction head alphabetically using the Q– Flow Rate = 290 GPM or 1098 L/min
general equation, µ- Oil Viscosity = 46 centistokes = 46 mm2/s
𝒗𝟐
Hf = K 𝟐𝒈
28600 𝑘𝑔/𝑚𝑠2
Hf-str = 𝑚
(848 𝑘𝑔/𝑚3)(9.81𝑠2)
𝟒ˑ𝒍ˑ𝒅𝒑𝒍𝒂𝒕𝒆
𝒗𝟐 Dh =
𝟐(𝒍+𝒅𝒑𝒍𝒂𝒕𝒆 )
Hf-SV = 2 x KSV x 𝟐𝒈
FRICTION (1.005𝑚/𝑠)2 ∆PCOLLECTOR = 1.4ˑNpˑ (
𝒎
) ˑ(
𝟏 2 µ -0.17
) ˑ (µ )
Hf-SV = 2 x 0.12 x 𝝅𝑫𝟐
HEAD 2(9.81𝑠2)
𝑚
𝒄𝒐𝒍𝒍𝒆𝒄𝒕𝒐𝒓
𝟒
𝟐𝜌 𝒘
HEAD 𝑘𝑔
861
𝑚
(1.005 )𝟐 1.47 𝑚
∆PCHANNEL = 4 ˑ0.043 ˑ 𝑚3 𝑠
ˑ
LOSS IN 2 0.0012 𝑚
FITTINGS
The two (2) Thermowave TL 650 KBIL is single-pass type of Plate
Heat Exchanger installed in FDC – MPC for each Unit. It has a ∆PCHANNEL = 91615.68 Pa
capacity of 116.9 liters for both medium, water and oil, and has an
operating pressure of 8.0 bars. Each unit is equipped with frames
that can hold up to 190 plates and has a dimension of 19x23x58
inches, with thickness of 5 mm.
FRICTION m = 𝜌𝑣𝐴
Convert to Head in meter by using formula: P = ρ x g x Hf-HE
𝜋 𝑥 0.15242
HEAD m = 848 kg/m2 x 1.005 m/s x
4
LOSS IN m = 15.54 kg/s
𝒎 𝟏 µ 183231.36 𝑘𝑔/𝑚𝑠2
∆PCOLLECTOR = 1.4ˑNpˑ ( 𝝅𝑫𝟐 ) ˑ( )2 ˑ ( )-0.17 Hf-HE =
FITTINGS 𝒄𝒐𝒍𝒍𝒆𝒄𝒕𝒐𝒓
𝟒
𝟐𝜌 µ𝒘
𝑚
(848 𝑘𝑔/𝑚3)(9.81𝑠2)
15.54 𝑘𝑔/𝑠 1 46 𝑐𝑆𝑡 0.17
∆PCOLLECTOR = 1.4ˑ1ˑ ( 𝜋 𝑥 0.15242 ) ˑ( 𝑘𝑔 )2ˑ ( )
2(848 ) 1 𝑐𝑆𝑡
4 𝑚3
Hf-HE = 22 meters
∆PCOLLECTOR = 2.16 x 10-4 Pa
∆P = 2 (∆PCHANNEL + ∆PCOLLECTOR)
∆P = 2 (91615.68 Pa + 2.13 x 10-4 Pa)
∆P = 183230.72 Pa
Since the diameter of our pipelines are given, as you can see from our Figure 2.24, the pipe’s diameter entering the
blocks is 152.4 mm, while the exit pipe is 254 mm. The area of each block is already given by the product
manufacturer in Table 2.6. These dimensions are important since we are going to calculate the losses of fluid entering
and leaving the blocks.
By using the formula given by Figure 2.23.2, The same approach used in E-1, but instead of using only
we can now solve the coefficient, K, of each equation 4, we will now use equation 2 for diameter smaller
FRICTION entry point. For entry, the arrangements of pipe than exit pipe i.e., HP-IP Journal Bearing and Generator DE
HEAD are between 45° to 180°, thus, equation 4 will Journal Bearing and use equation 3 for diameter larger that
LOSS IN be used. exit pipe. These equations satisfied the given exit angle of
FITTINGS 𝒅𝟐𝟏
<45°.
K= (1- 𝟐 ) Ɵ 𝒅𝟐𝟏 2
𝒅𝟐 K = 2.6 𝑆𝒊𝒏 (1- 𝟐 )
𝟐 𝒅𝟐
(0.361𝑚/𝑠)2 (0.361𝑚/𝑠)2
(1.005𝑚/𝑠)2 (1.005𝑚/𝑠)2 Hf-EXT = {2 x 0.143 x 𝑚 }+ {2 x 0.151 x 𝑚 }
Hf-ENT = {2 x 0.176 x 𝑚 }+ {2 x 0.665 x 𝑚 } 2(9.81 )
𝑠2
2(9.81 )
𝑠2
2(9.81 ) 2(9.81 )
𝑠2 𝑠2
For calculating elbows, we will now use again the table Entry: KT-en = 3 x 0.30 = 0.90
from Figure 2.19. Given from Table 2.4, we can now Exit: KT-ex = 4 x 0.30 = 1.20
FRICTION solve the K
HEAD 𝒗𝟐 𝒗𝟐
Entry 152.4mm: K90 = 5 x 0.45 = 2.25; K45 = 4 x 0.24 = 0.96 Hf-TEE = KT-en 𝟐𝒈 + KT-ex 𝟐𝒈
LOSS IN Return 254mm: K90 = 3 x 0.45 = 1.35; K45 = 5 x 0.24 = 1.20
FITTINGS Hf-TEE = 0.90
1.0052
+ 1.20
0.3612
𝒗𝟐 𝒗𝟐 2(9.81) 2(9.81)
Hf-ELB = KENT 𝟐𝒈 + KEXT 𝟐𝒈
With all these friction head losses, we can now solve the total friction head in our system:
Our lube oil system is not pressurized since the tank is fully equipped with Vapor Extraction Fan (Exhaust fan) to
create a slightly negative pressure to pull out those non-condensable and combustible gasses. Therefore,
STATIC HEAD
HS = 𝟎
It takes energy to pump fluids from a lower level to a higher one. There is often a significant difference in
ELEVATION elevation between the inlet of a system (point 1), and the outlet (point 14, see slide 26).
DIFFENCE,
HZ
z2 = 7 meters z1 = 3 meters
where:
ha - absolute pressure (in feet of liquid) on the surface of the liquid supply level (this will be barometric pressure if
suction is from an open tank or sump; or the absolute pressure existing in a closed tank such as a condenser
hotwell or deaerator).
The formula given by Cameron Hydraulic Data [8],
hvp - The head in feet corresponding to the vapor pressure of the liquid at the temperature being pumped.
hst -
hf -
Static height in feet that the liquid supply level is above or below the pump centerline or impeller eye.
All suction line losses (in feet) including entrance losses and friction losses through pipe, valves and fittings, etc. NPSHa = ha – hvp + hst – hf
𝑝𝑠𝑖 𝑥 2.31
Liquid Head in feet = by same reference above.
𝑆𝑝.𝐺𝑟𝑎𝑣𝑖𝑡𝑦
By plotting the corrected flow and head of viscous fluid, 284.3 GPM
(64.6 m3/h) and 94.8 feet (28.9 meters), respectively, using the
Figure 2.30, it will intersect on size 50-160 which give us a detailed
description on Table 2.9 provided by the manufacturer Allweiler. Figure 2.30: Allweiler’s Performance Curve of NSS series at 3500 rpm
𝐇𝐲𝐝𝐫𝐚𝐮𝐥𝐢𝐜 𝑷𝒐𝒘𝒆𝒓
𝐒𝐡𝐚𝐟𝐭 𝐏𝐨𝐰𝐞𝐫 =
𝑬𝒇𝒇𝒆𝒄𝒊𝒆𝒏𝒄𝒚
𝑷𝒉
𝑷𝒔 =
SHAFT ƞ
POWER 4.38 KW
Ps =
0.78
𝑷𝒔 = 𝟓. 𝟔 𝑲𝑾
472 °C
Steam Turbo-Generator
designed to encompass the entire turbine spaces. This can HP Pressure 0 bar 0 bar
be achieved by maintaining a continuous supply of dry air at
IP/LP Surface Temp 324 °C 99 °C
<30% RH from a blower discharging into the condenser hot-
well, providing air flow. LP Exhaust Pressure 1.02 bar 1.01 bar
FORCED-AIR
COOLING SYSTEM
EXIT
FLASH TANK
ENTRY
To identify the total heat energy to be removed from Solving for Tm:
the system at certain temperature, we will calculate Tm =
𝑇𝑖 + 𝑇𝑜
=
150 𝐶+160 𝐶
= 155°C
2 2
first the heat generated of individual system.
q = hc A ∆T = hc A (Tw – Tm) – (HMT Data Book, Page 114) Refer to Table 2.3, Dry Air properties at 155 °C
at 1 atm:
where:
With these, we can now solve the convective heat transfer using the formula for internal flow at smooth pipe from Heat
Transfer Formula Sheet, Page 3,
𝑊
𝑁𝑢 𝑘 84.97 (0.03476𝑚𝐾)
hc = = = 9.85 W/m2 °K
𝐷 0.300 𝑚
Specific Heat, CP 1014.5 J/kg °K 1015.25 J/kg °K 1016.75 J/kg °K 1018.25 J/kg °K
Thermal Conductivity, k 0.034425 W/m °K 0.03476 W/m °K 0.03545 W/m °K 0.0361 W/m °K
Dynamic Viscosity, γ 2.86 x 10-5 m2/s 2.9175 x 10-5 m2/s 3.03 x 10-5 m2/s 3.15 x 10-5 m2/s
Nu = Pr0.333 [0.037Re0.80 –
(0.037Recr0.80 – 𝑁𝑢 𝑘
HPT MSV 170 180 175 472 25396.83 93.96 hc = 8.48 14.5
0.664Recr0.50)] 𝐷
Nu = Pr0.333 [0.037Re0.80 –
LP Turbine 𝑁𝑢 𝑘
150 160 155 80 211482.43 (0.037Recr0.80 – 271.43 hc = 3.06 30.9
Section 𝐷
0.664Recr0.50)]
Nu = Pr0.333 [0.037Re0.80 –
(0.037Recr0.80 – 𝑁𝑢 𝑘
IPT-LPT MSV 170 180 175 324 22160.66 0.664Recr0.50)]
87.7 hc = 7.92 35.9
𝐷
60𝑚𝑖𝑛
Q (m3/min) = 12.93 m3/min( )
1 ℎ𝑟
And we can also calculate the mass flow rate that needs to dissipate by using the equation:
m = 0.179 kg/sec
Brand MANVAC
Model 2MV-840-H37
Motor Power 12.6 kW
Frequency 60 hz
Electric Heater 102 kW
Air Volume 1050 m3/hr or 17.5 m3/min
Heating Area 200-300 m2
Dimension 1200mm x 750mm x 760mm
Exhaust Diameter 300mm
Differential Pressure 285mbar
Remarks Automatic Temperature Controller
The measuring point required for monitoring of the forced cooling process is shown in Figure 8.1. Cooling of the HP
turbine section is monitored using measuring point MAA10CT905, which is located in the inlet part of the inner casing and
is also used for TSE-monitoring of the HP-shaft. The cooling behavior of shaft and inner casing is derived from this point.
Calculations using Finite-Elements-Method are done previously to ensure that, using a certain cooling ramp rate, radial
and axial clearances remain within permissible values. Figure 2.21 shows the maximum permissible transient for the
measuring point during forced cooling.
The measuring point required for monitoring of the forced cooling process is shown in Attachment 6. Cooling of the IP
shaft is monitored using the inner casing measuring point MAB50CT011, which is located in the inlet area and is also
used for TSE monitoring of the IP-shaft. Calculations using Finite-Elements-Method are done previously to ensure that,
using a certain cooling ramp rate, radial and axial clearances remain within permissible values. Figure 2.22 shows the
maximum permissible transient for the measuring point during forced cooling.
MAA10CT931 MAC10CT981
LBC10CT001
LCA01CT108
LBH20CT901
450 °C
400 °C
350 °C
300 °C
250 °C
200 °C
150 °C
100 °C
10 h 20 h 30 h 40 h 50 h 60 h 70 h
permanently installing this nearby the steam turbine area for quick connect and setup. By practicality, Mobile Forced-air
Cooling System via portable container is the most practical and easiest to maintain thus the following connection for the
dryer unit to the steam turbine shall be followed as;
CONNECTIONS
• Observed all instructions for use provided by the blower manufacturer or supplier.
• Set up the portable blowing unit in the immediate vicinity of the turbine connecting flange for layup force cooling.
• Availability of power on site should be in line with manufacturer's instructions; such as MANVAC: 220 V and 60Hz
with approximately 10 to 15 kW load demand.
• Connect the blowing unit with the connecting flange on the turbine vacuum breaker using a flexible air hose.
• The Mobile Forced-air Cooling System shall be required to open in a suitable outlet for exhaust air. Proper
ventilation of Turbine Hall building, where steam turbines are located, should be in place.
• The blower unit should be indoor installation intended and compliance to any standard require.
Connection and hoses shall be compliance to the manufacturer’s manual and recommendations.
Electrical supply Check fuses/circuit breakers. Check for switches turned off or disconnected. Check for correct supply voltage.
Fan Doesn’t Operate Drive Check for broken belts. Tighten loose pulleys
Motor Assure motor is correct horsepower and not tripping overload protector.
Lubrication Check for excessive or insufficient grease in the bearings.
Overheated Shaft Bearing Mechanical Replace damaged bearing. Relieve excessive belt tension. Align bearings. Check for bent shaft.
System unbalance Check alignment of shaft, motor and pulleys. Check wheel balance, rebalance if necessary.
Excessive Vibration Coupling misalignment
Check alignment between coupling, motor and fan shafts. Any adjustments should be made per coupling
manufacturer’s instructions. Shim only under motor.
4 Return of Investment
40,000,000.00), CST
200,000,000 + 40,000,000 + 7,000,000 + 1,000,000 − 11,473,800
3. Cost of damage bearings - Radial and Thrust 𝑅𝑂𝐼 =
5,713,200 + 25 𝑦𝑒𝑎𝑟𝑠 𝑥 230,424
𝑥 100%
bearings (Php. 7,000,000.00), CB
4. Cost of damage labyrinth seals due to deformation
(Php. 1,000,000.00), CL
ROI = 2061%
11,473,800 𝑥 25
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 𝐴 =
200,000,000 + 40,000,000 + 7,000,000 + 1,000,000
365 𝑑𝑎𝑦𝑠
𝑃𝑎𝑦𝑏𝑎𝑐𝑘 𝑃𝑒𝑟𝑖𝑜𝑑 𝐴 = 0.575 years x 1 𝑦𝑒𝑎𝑟
• The computation for payback period showed the time it will need to take to recover the initial costs of
around 210 days with 2061x ROI.
294 hours or
Total Saved Hours 12.25 days per
year
• The computation for payback period showed the time it will need to take to recover the initial costs of
around 2 days with 17800x ROI.
Total Project A O&M cost for 25 years (Php. 230,424 x 25) Php. 5,760,000.00
1 Evaluation
2 Conclusion
3 Recommendation
The backup AC auxiliary oil pump, on the other hand, provides critical redundancy, prevents equipment damage,
facilitates quick emergency response, allows for maintenance flexibility, enhances system resilience, improves
operational efficiency, ensures regulatory compliance, contributes to cost savings, and adapts to changing
conditions. The presence of such a backup system is an integral part of a comprehensive risk management and
reliability strategy in industrial applications should be carefully evaluated based on the characteristics of the turbine
and the requirements of the power generation facility.
Having the two projects have a significant impact to the power station. These projects bring a huge profit to the
table and could give ease to operations and maintenance.
The implementation of the back-up AC Auxiliary Oil pump and Forced-Air Cooling System will need considerations on cost,
downtime, storage conditions, effectiveness, and regulatory compliance. Thus, consideration for these items should be
accepted and identified during implementation or upgrading the systems.
The Forced-Air Cooling System for the steam turbine is dependent on the steam turbine layup or shutdown durations and
programs. Thus, the system may mostly be not used all throughout the year. In this case, maintaining the equipment is as always
necessary in order to prevent deterioration of the equipment. Regular operation without connecting to the turbine system should
be considered in order to replenish the system functions. Thus, maintain its readiness and availability anytime. On the other
hand, the back-up AC auxiliary oil pump is fully integrated to the system, and should be included in weekly routine as discussed
in the previous chapters, including the schedule of cleaning and preventive maintenance.
Lastly, the emerging new technology to preserve the turbine life is already available in the market. It is just to apply these
technologies and spend a penny now in exchange for longer profitability. The steam turbine is the heart of the power plant, a
single day of downtime could cause a huge loss to the company.