Testing and Commissioning of HV Power Transformers Circuit Breakers CTs and VTs
Testing and Commissioning of HV Power Transformers Circuit Breakers CTs and VTs
Testing and commissioning of HV power transformers, circuit breakers, CTs and VTs
This technical article provides guidance to substation personnel in carrying out testing
and commissioning oF high voltage power transformers, circuit breakers, current and
voltage instrument transformers.
One of the prime requirements of a good substation is that it MUST have regular
maintenance. Testing and commissioning procedures are crucial and ensure safety of
the operation and maintenance personnel.
Table of content:
1/11
1. Power transformers
Oil should be admitted into the transformer from its bottom valve and suction side to be
connected to the top valve to evacuate nitrogen/dry air inside the transformer as the
oil fills from the bottom.
It is preferable to fill the oil received from the works (in barrels) into an oil tanker of
sufficient capacity and filter this oil separately. This helps in removing moisture absorbed
in the oil during transport and storage. Fairly moisture free filtered oil now can be
admitted from the oil tanker to the transformer.
The following check list provides various checks to be conducted for transformer
assembly.
3 Rinsed all the piping, radiators, conservator etc. with 60kV tested oil Yes/No
and blocked with dummy plates.
4 Filtered the oil for 60kV BDV and recorded in the erection register. Yes/No
6 Washed with hot oil (in case of other bushings of plain porcelain type). Yes/No
7 Assembled the bushing after fixing corona shield and removing links Yes/No
and bends in pull through leads, on the turret at proper incline.
8 Complete assembly of HV, LV, Ter. & Neutral bushings done correctly. Yes/No
9 Completed all piping work, conservator, explosion vent, equalizer pipes Yes/No
etc. as per the drawing and filled with oil , Bucholz relay checked.
11 Measured IR values with temperature after filling of oil and compared Yes/No
with factory test value and recorded in the register.
2/11
Applied proper lagging around the transformer. Fire fighting equipment Yes/No
kept at site.
Filter connected with outlet into the conservator and inlet from the Yes/No
bottom tank.
Filter heaters switched on and the filter temperature maintained less Yes/No
than 60°C and filter vacuum maintained at 755 mm of mercury.
Dehydration process for 7 days maintained oil temperature 60°C in the Yes/No
transformer (thermometer pockets filled with oil).
13 Filled the radiators with 60kV BDV tested oil. Opened the bottom Yes/No
butterfly valve provided between main tank and radiators after opening
top air release valve to communicate with main tank.
14 All gases released from different release points in the order of Yes/No
ascending heights.
15 HV, LV, Tertiary Neutral earthing provided. Body earthing at two sides, Yes/No
earthing of DM and FCC provided.
17 Blue silica gel crystals of 2.5 to 4mm size filled in the breather. Breather Yes/No
filled with oil after removing bottom cup, transit protection cover, cork
packing etc.
18 Removed blanking plates on explosion vent pipe and fixed diaphragm. Yes/No
20 All air release points and other points thoroughly checked to ensure Yes/No
that there is no oil leakage.
3/11
After installation and assembly at site, the following pre-commissioning tests on
transformer should be conducted. These are basically low voltage tests.
1. Ratio
2. Polarity and vector group
3. Measurement of magnetizing current and no load losses (3-phase 415V to be
supplied on low voltage side of the transformer)
4. Measurement of short circuit current, load losses and impedance at all taps (3-
phase 415V supply to be given on the high voltage side and the other side shorted)
5. Magnetic balance test
6. Measurement of winding resistance at all taps
7. Insulation Resistance and polarization index
Checking for running /stopping of cooler fans and/or oil circulating pumps in groups
at the set temperatures/pressures. Conduct all checks and tests on turret mounted CTs
as indicated under CTs.
You might find interesting reading an article about the most important alarms coming from
a substation.
6 alarms coming from a substation transformer you MUST take very seriously
1. Checking for manual and electrical operation (both local & remote and lower &
raise) of On Load Tap Changer and for continuity between the operations.
2. Check for operation of limit switches at the extreme tap positions and mechanical
interlock between manual and electrical operation.
3. Check for Master/Follower and out of step relay operation of transformers if parallel
operation is intended.
4/11
Go back to Content Table ↑
The following tests should be done before commissioning and the results compared
with the factory test results. These results should be kept as reference values for
comparison with the future test results of these tests while conducting, as a part of O&M
later.
The following protective relays connected to the transformer HV/LV/Tertiary sides shall be
tested for proper operation duly adopting the settings communicated by the power
systems:
Testing procedures for protective relays are not described in this article, but you can read
about this subject in details here.
2. Circuit breakers
5/11
Physical checks for any damages to components of the circuit breaker should be
made. Tightness of connections at all jumpers, flanges, joints in pipes, valves etc. should
be checked. Check for oil/ gas/ air leakages at concerned valves/pipes and all oil seals,
gaskets should be made. Checking and tightening of all foundation bolts should be done.
6/11
Circuit breakers allow the flow of energy to be controlled by safely switching currents on
and off at all voltage levels of the energy grid. The interrupter and the mechanical drive
are the main components that are subject to wear and aging.
In order to ensure the proper operation of a circuit breaker throughout its lifetime,
diagnostic tests are performed, such as resistance, timing, minimum pick-up, travel,
and power factor.
Physical observation of the CTs for proper installation with respect to the drawings and
substation layout should be made. Tightness of bolts of support structures to the
foundation and CT base mounting to the support structure shall be ensured.
Oil leakages in case of oil filled CTs and SF6 gas leakages/rated pressure of gas in case
of SF6 gas filled CTs to be observed. Bellows provided for taking care of oil expansion
shall be checked for proper functioning.
The following checks and electrical tests shall be conducted:
1.
1. Checking of tightness of all electrical connections including connections made
in the marshalling box.
2. Checking for tightness of CT secondary terminals and checking healthiness of
secondary terminal bushings.
3. Checking for short circuiting the secondary terminals of such CT secondary
windings which are not required. Shorting should be done at secondary
terminals in the CT secondary terminal box.
4. Checking for earthing of common point of three phases of each secondary
winding at one point only, preferably at the marshalling box.
5. Measurement of IR values including Di-electric absorption ratio and
Polarization index of primary to body and primary to secondary with a 5 kV
Megger testing device.
6. Measurement of IR values between secondary winding of each core to body
and between different secondary windings of the CT with a 0.5 kV Megger
testing device.
7/11
Each CT should be individually tested to verify the polarity markings on primary and
secondary windings. Test circuit is given below.
Ammeter “A” is a robust moving coil permanent magnet center zero type instrument.
Primary winding is given DC supply momentarily from a low voltage battery through a
push button. When push button is pressed with the above markings on CT and ammeter,
the ammeter should give a +ve flick, indicating correct polarity.
Multi meters and Digital ammeters can also be used. CT secondary connections to
transformers, busbars, and feeders:
8/11
3.2 Transformer CT’s secondary connections
Where CT secondary connections are to be made in star, the star point should be made
as follows.
Irrespective of the polarity on the primary side, star point on secondary side shall be on
line side for feeders and on the equipment side for the bus bars, and transformers as
shown in the figures above. In case of a feeder protection, if P1 is towards the bus, then
S2s’ are to be shorted and if P2 is towards bus then S1s’ are to be shorted.
9/11
Testing protection current transformers with CT Analyzer (VIDEO)
Important parameters of a protection current transformer are its ratio, its excitation
curve, the knee point, its winding resistance, and the burden.
CT Analyzer determines all relevant current transformer data during a test duration of
approximately one minute: it measures the burden of the secondary circuit, the winding
resistance and the excitation curve, calculates the accuracy limiting factor for rated and
actual burden, determines its ratio, amplitude and phase angle accuracy, and verifies the
polarity.
Tightness of foundation bolts connecting the support structures to the foundation and
the bolts connecting base of the VTs/CVTs to the supporting structures should be
ensured.
The following checks shall be made:
1. Check for tightness of all electrical connections on primary and secondary sides of
CVTS/VTs including connections in the marshalling box.
2. Check for oil leakages and oil level.
3. Ratio test –voltage in all the secondary windings should be measured.
4. Insulation resistance of primary to body and primary to secondary windings to be
measured by a 5 kV Megger testing device.
5. Insulation resistance of secondary to body and between secondary windings to be
measure by a0.5 kV Megger testing device.
6. Measurement of capacitance and tan ∂ of CVTs.
7. Checking of HF point in case of CVTs. Caution given on the name plate by the
manufacturer should be followed.
8. Check for adopting the approved ratios and connections for different secondary
windings.
Voltage transformers (VTs) are used around the clock throughout the energy grid, and
their life span can reach up to 40 years. During that time, the effects of aging, regular
operation, network faults, or external influences may affect the integrity of a voltage
transformer.
10/11
Utilities perform various tests during commissioning and maintenance to find any
irregularities that have been caused by transportation, installation or daily
operation.
11/11