Method Statement of Brick Works
Method Statement of Brick Works
Masonry Workings
1/9
Methods of statement for Brick
Masonry Workings
1-Title:
2-Introduction:
3-Goal / Purpose :
2/9
*Building retaining walls.
*Constructing all the various architectural details, including
internal and external fences and walls, and all related
facilities, such as internal sewage rooms, surface tanks, etc.
4-References :
*Project specifications
*Approved shop drawings for the project.
*Approved materials submittal for building workings.
*Egyptian Code.
5-Materials :
* Cement Bricks
* Cement
* Water
* Fine aggregate:
* Mortar:
*Cord
*Nylon chord.
*Marker chalk line
*Galvanised fishtail
*Brush
*Scraper
*Trowels
3/9
*Hammer
*Chisels
*Wheelbarrow
*Brick cutter
*Wooden straight edge
*Scaffold
*Meters measure
*Shovel
*Fixing screws
*Level machine
7-Manpower :
*Construction Manager.
*Project Engineer / Site Engineer.
*QC Engineer
*Foreman
*Safety officers with helper.
* Brick masonry technician
*Skilled and unskilled labors.
8-Responsibilities:
*construction manager
4/9
human,material and equipment are available to carry out
the work as planned and without any delay.
*Project engineer
*QC Engineer
*Safety officer
-Ensure that all equipment are propely maintained and in
safe working conditions.
-Follow up all the safety precautions during brick building
works sush as wearing helmet, safety shoes, overalls,
gloves,and vests.
5/9
-Ensure that the working area is barricaded and protected
during the work.
*Site Engineer :
*Foreman :
-Get the instructions to start brick masonry working from
site engineer.
-Distribute the labors productivity and their works.
-Preparea all the required tools for masonry working.
-supervise the labors during work.
9-Methodology :
6/9
*Bricks used for masonry in cement mortar will be soaked
by immersion in water at least one hour prior to start of
actual laying.
7/9
* The locations of the openings for windows or doors, if any,
must be determined before starting work according to the
approved architectural drawings for the project.
10-Safety :
8/9
*All works shall comply with the safety instructions /
procedure as set out in the approved project HSE plan and
all safety recommendations of local authorities shall be
followed.
11-Attachments :
9/9