Project Completion Report - ADB-37143-033-pcr-en
Project Completion Report - ADB-37143-033-pcr-en
PUBLIC
This document is being disclosed to the public in accordance with ADB's Access to Information
Policy.
CURRENCY EQUIVALENTS
ABBREVIATIONS
NOTES
(i) The fiscal year (FY) of the Government of India ends on 31 March.
“FY” before a calendar year denotes the year in which the fiscal year
ends, e.g., FY2023 ends on 31 March 2023.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
CONTENTS
Page
BASIC DATA i
I. PROJECT DESIGN AND IMPLEMENTATION 1
A. Rationale 1
B. Project Impact, Outcome, and Output 2
C. Project Costs and Financing 4
D. Disbursement 4
E. Project Schedule 5
F. Implementation Arrangements 5
G. Technical Assistance 6
H. Procurement 7
I. Poverty, Social, and Gender Equality 8
J. Safeguards 8
K. Monitoring and Reporting 11
II. EVALUATION OF PERFORMANCE 11
A. Relevance 11
B. Effectiveness 12
C. Efficiency 13
D. Sustainability 14
E. Development Impact 15
F. Performance of the Borrower and the Executing Agency 16
G. Performance of the Asian Development Bank 16
H. Overall Assessment 17
III. ISSUES, LESSONS, AND RECOMMENDATIONS 17
A. Issues and Lessons 17
B. Recommendations 18
APPENDIXES
1. Design and Monitoring Frameworks 19
2. Costs at Approval and Actual 23
3. Project 2 Cost by Financier 25
4. Disbursement of ADB Loan Proceeds 27
5. Appraisal and Actual Implementation Schedules 28
6. Chronology of Main Events 30
7. Organization Chart of Project Implementation 31
8. Technical Assistance Completion Report 32
9. Contract Awards of ADB Loan Proceeds 39
10. Summary of Contracts 40
11. Safeguards Assessment 41
12. Status of Compliance with Loan Covenants 47
13. Economic and Financial Analyses 78
14. Summary of the Socioeconomic Impacts 90
15. Contribution to Strategy 2030 Operational Priorities 93
BASIC DATA
A. Facility Identification
1. Facility number and facility title 0058: North Eastern State Roads
Investment Program
2. Mode of financial assistance Multitranche financing facility
3. Country India
4. Borrower Government of India
5. Executing agencies (i) Ministry of Development of North
Eastern Region at the national level;
(ii) State of Assam, acting through its
Public Works Department (PWD);
(iii) State of Meghalaya, acting
through its PWD; (iv) State of
Manipur, acting through its PWD;
(v) State of Mizoram, acting through
its PWD; (vi) State of Sikkim, acting
through its Roads and Bridges
Department; and (vii) State of
Tripura, acting through its PWD.
Financing
Approval Amount Financing Product Modality
Item Number ($ million) Source and Nature of Activities
Loan MF0058 200.00 Ordinary Multitranche financing
capital facility
resources
Government 66.70
Project Total 266.70
Source: Asian Development Bank.
Item Loan
Investment program closing date
– In loan agreement at approval 31 March 2020
– Latest revised 30 June 2021
– Number of extensions 1
Financial closing date (Tranche 1) 2 March 2022a
a Tranche 2 financial closing date was 8 November 2021.
Source: Asian Development Bank.
4. Disbursements
a. Disbursement dates by product
First Disbursement,
First Disbursement excluding Capitalization Final Disbursement
Loan 2770 2 April 2013 – 2 March 2022
Loan 3073 9 September 2015 – 8 November 2021
Source: Asian Development Bank.
iii
b. Amount ($ million)
Original Canceled during Last Revised Amount Undisbursed
Allocation Implementation Allocation Disbursed Balance
Category (1) (2) (3 = 1-2) (4) (5 = 3-4)
Loan 2770 74.80 0.00 74.80 74.48 0.32
Loan 3073 125.20 0.00 125.20 125.20 0.00
Total 200.00 0.00 200.00 199.68 0.32
Note: The undisbursed amount was canceled at financial account closure.
Source: Asian Development Bank.
iv
II. PROJECT 2
A. Project Identification
1. Project number and project title 37143-033: North Eastern State
Roads Investment Program – Project
2
2. Mode of financial assistance Ordinary capital resources
3. Country India
4. Borrower Government of India
5. Executing agencies (i) Ministry of Development of North
Eastern Region at the national level;
(ii) State of Assam, acting through its
PWD;
(iii) State of Manipur, acting through
its PWD;
(iv) State of Mizoram, acting through
its PWD; and
(v) State of Tripura, acting through
its PWD.
6. Products
4. Disbursements
a. Disbursement dates by product
First Disbursement,
First Excluding Final
Disbursement Capitalization Disbursement
Loan 3073 9 September 2015 – 8 November 2021
E. Project Implementation
1. Project Schedule
Item Estimate at Actual
Approval
A. PMC
Recruitment Q2 2011–Q4 2012 Q4 2011–Q3 2012
Consulting services execution Q4 2012–Q2 2017 Q3 2012–Q3 2017a
B. Civil Works (Project 2)
Procurement Q2 2012–Q1 2014 Q2 2012–Q2 2015 b
Construction Q1 2014–Q3 2019 Q4 2013–Q3 2021 b
Maintenance Q4 2019–Q4 2020 Q1 2020–Q1 2024
C. CSC (Project 2)
Recruitment Q4 2011–Q4 2013 Q4 2011–Q2 2014
Consulting services execution Q1 2014–Q3 2019 Q4 2013–Q1 2022c
CSC = construction supervision consultant, MDONER = Ministry of Development of North Eastern Region, PMC =
project management consultant, PMU = project management unit, Q = quarter.
a
The PMC was terminated in 2017 upon completion of the original contract and due to poor performance, it was not
extended. Subsequently, the PMU in the MDONER monitored the project.
b The Tripura state terminated the civil works contract and re-awarded it to a new contractor on 18 March 2021. The
civil works was completed on 13 January 2023, beyond the loan completion date of 30 June 2021.
c The states of Mizoram and Assam extended the CSC’s services beyond the loan closing date of 30 June 2021.
Contract Disburse-
Awards ment Financial Technical/
Year Overall Safeguards
Management Output
(%) (%)
Q1 On track 100.000 94.498 Yes Yes Satisfactory
Q2 On track 100.000 80.938 Yes Yes Satisfactory
2017
Q3 On track 100.000 82.958 Yes Yes Satisfactory
Q4 On track 100.000 83.319 Yes Yes Satisfactory
Q1 On track 100.000 83.319 Yes Yes Satisfactory
Q2 On track 98.329 86.340 Yes Yes Satisfactory
2018
Q3 On track 94.766 93.156 Yes Yes Satisfactory
Q4 For attention 100.000 100.000 Yes Yes On track
Q1 On track 97.271 88.817 Yes Yes Satisfactory
Q2 On track 97.544 94.964 Yes Yes Satisfactory
2019 Potential
Q3 96.293 93.425 No Yes Satisfactory
problem
Q4 On track 98.094 100.000 For attention Yes On track
Q1 On track 98.094 100.000 For attention Yes On track
Q2 On track 100.000 95.825 For attention On track On track
2020
Q3 On track 100.000 97.575 For attention On track On track
Q4 On track 99.987 94.734 On track On track On track
Q1 On track 99.987 94.734 On track On track On track
Q2 On track 99.114 94.050 On track On track On track
2021
Q3 On track 100.000 98.907 On track On track On track
Q4 For attention 100.000 100.000 At risk On track On track
Q = quarter.
Virtual
Name of No. of No. of Specialization
Date Mission
Mission Persons Person-Days of Members
(Yes/No)
10–14 October 2017
1–3 November 2017
SPAM 5–9 February 2018 2 10 n, r No
SPAM 16–20 April 2018 2 10 n, r
SPAM 20–24 August 2018 3 15 n, r, t No
SPAM 20–22 December 2018 1 3 n
Review 26 Nov–1 Dec 2018 2 12 n, r No
Review 18–20 February 2019 3 9 a, n, r No
Midterm
6–10 May 2019 4 20 a, n, r, t No
Review
SPAM 23–28 September 2019 2 12 n, r No
Review 10–15 September 2020 4 24 a, k, r, t Yes
Review 16–19 November 2020 5 20 c, k, n, r, t Yes
Review 7–13 January 2021 5 35 a, c, n, r, t Yes
Review 5–8 April 2021 5 20 a, c, n, r, t Yes
a = associate environmental officer, b = associate project analyst, c = associate social safeguards officer, d = country
director, e = economic analysis consultant, f = economist, g = director, h = environmental consultant, i = environmental
officer, j = environmental specialist, k = project analyst, l = principal counsel, m = procurement consultant/specialist, n =
project management specialist/project implementation officer, o = principal portfolio management specialist, p = resettlement
consultant, q = senior project assistant, r = senior project officer/mission leader, s = senior operation assistant, t = social
development specialist/safeguards officer, u = senior social safeguards officer, v = transport/project specialist/mission
leader, w = staff consultant.
SPAM = special project administrative mission.
a The project implementation officer joined on 18 December 2009.
b The environmental officer joined on 18–22 September 2017; the safeguards officer joined on 18–22 September and 10–14
October 2017.
Source: Asian Development Bank.
I. PROJECT DESIGN AND IMPLEMENTATION
A. Rationale
1. The North Eastern Region (NER) of India is connected to the rest of the country only by
a narrow land corridor. It forms a distinct geographical unit and is ethnically, culturally, and
linguistically diverse from the rest of the country. The region represents 8% of India's total
geographic area. As of the 2011 census, the population was about 45 million. It is estimated to
have grown to 52 million by 2022, which is about 4% of India’s population. Of its population,
27% are scheduled tribes. Except for the state of Assam, the NER’s terrain is predominantly
hilly or mountainous, and the region experiences some of the highest rainfall levels in the world,
frequently causing landslides and floods. Road connectivity continues to be poor and prone to
disruption because of inclement weather and landslides.
2. Although the NER is served by road, rail, air, and water transport, road transport
dominates the movement of goods and passengers. The road network in the NER in 2011 was
145,000 kilometers (km), consisting of 35,000 km of surfaced roads—mostly national highways,
state highways, and district roads—and 110,000 km of unpaved roads. Except for the highest-
class roads (mostly national highways maintained by central government agencies), the road
network in the NER required substantial improvement through the expansion and rehabilitation
of individual road sections. The state-level public works departments (PWDs) also required
substantial capacity strengthening.
3. Recognizing that roads and bridges were inadequate to support road transport as the
NER’s dominant transport mode, the Government of India started a national investment
program to improve road connectivity to remote areas in the region. The Special Accelerated
Road Development Program in the North Eastern Region (SARDP-NE), approved by the
Ministry of Road Transport and Highways in September 2005, was designed to (i) improve
higher-class roads, including national highways and state roads, in the region; and (ii) provide
connectivity to state capitals and district headquarters in the NER by developing two-lane
national highways and improving state roads.1 The Ministry of Development of North Eastern
Region (MDONER) developed the North Eastern State Roads Investment Program (NESRIP) in
parallel, complementary to SARDP-NE.2 While the SARDP-NE focused on improving higher-
class roads, NESRIP was designed to improve intrastate connectivity, mainly to district
headquarters and other places of administrative and economic importance in individual states,
and to enhance the capacity of state PWDs to manage their road assets.
4. The Asian Development Bank (ADB) approved a $200 million multitranche financing
facility (MFF) in 2011 to (i) improve 430 km of priority road sections in six states of the NER,
namely Assam, Manipur, Meghalaya, Mizoram, Sikkim, and Tripura; and (ii) provide capacity-
building support to the executing and the implementing agencies in each of the six states.
1 Phase A of SARDP-NE was approved by the Government of India to improve 4,099 km of roads comprising 3,014
km of national highways and 1,085 km of state roads. Of the total, 3,213 km of roads was approved for
implementation and the balance of 886 km was approved “in principle.” A total of 3,333 km of roads was awarded
and 2,101 km was completed by March 2019. It is expected that phase A will be completed during 2023–2024.
2 Government of India, Ministry of Development of North Eastern Region (MDONER). 2011. North Eastern State
Roads Investment Program (NESRIP). New Delhi. This program was approved by the Cabinet Committee on
Economic Affairs (CCEA) on 19 May 2011 at an estimated cost of ₹1,3538.3 million. Subsequently, the project cost
was revised to ₹2,1445.6 million and the CCEA approved the same on 28 February 2019 for implementation in two
tranches. The project entails the construction and upgrading of 432.91 km of roads in India’s six northeastern
states: Assam, Manipur, Meghalaya, Mizoram, Sikkim, and Tripura.
2
5. The MFF modality was appropriate for financing this investment program, as it allowed a
phased implementation of individual subprojects in the six project states with different levels of
project management capacity and exposure to large-scale infrastructure development. The MFF
envisaged two tranches: (i) Tranche 1 (Project 1)—to improve 197.20 km of priority road
sections in Assam, Meghalaya, and Sikkim; and (ii) Tranche 2 (Project 2) to improve 235.71 km
of road sections in Assam, Manipur, Mizoram, and Tripura.3 2 CDTAs aptly supported the MFF
(paras. 23 and para. 24).
6. At appraisal, the MFF was consistent with ADB’s strategic objectives as set out in the
country partnership strategy (CPS) for India, 2009–2012 and in the Eleventh Five Year Plan
(para. 41).4 The MFF was also included in ADB’s country operations business plan for India,
2007–2009. Adequate consultations were held with all stakeholders while formulating the
project. During implementation, no changes were made to the rationale nor to the design and
monitoring framework (DMF) (Appendix 1).
7. At completion, the MFF remained aligned with ADB’s Strategy 2030, especially
operational priority (OP) 1.3.1 (infrastructure assets established or improved), and OP 3.2.5
(new and existing infrastructure assets were made climate- and disaster-resilient).5 The capacity
development and training interventions were aligned with OP 6.1 (entities with improved
management functions and financial stability); and with OP 6.1.1 (government officials with
increased capacity to design, implement, monitor, and evaluate relevant measures.) The
program remains relevant as it supports the Government of India’s goal of “faster, inclusive, and
sustainable growth,” and ADB’s Strategy 2030.6
1. Investment program
8. The MFF’s impact was improved surface transport connectivity in the NER by
connecting the district headquarters with the two-lane national highways and improved state
roads. With the implementation of SARDP-NE (Phase A), the number of district headquarters
connected by two-lane national highways and improved state roads increased from 51 to 85 by
2021 (footnote 1).
9. The envisaged outcome of the program to improve mobility and accessibility in the
project areas was exceeded by 2021: (i) the actual growth rate of traffic on the project and
connector roads was 9.81%, which surpassed the appraisal assumed growth rate of 9%; (ii) the
vehicle operating cost (VOC) on the project roads was reduced by 52.5% for three-axle trucks
against the appraisal target of 50%, and for passenger buses, it was reduced by 42% at
completion against the target of 20%; and (iii) travel time on the project roads was reduced by
more than 50% against the appraisal target of 20%–40%.
3 ADB. 2013. Updated Facility Administration Manual. Manila (Table 1: List of roads to be improved under the
investment program).
4 ADB. 2009. Country Partnership Strategy: India, 2009–2012. Manila; Government of India, Planning Commission.
2008. Eleventh Five Year Plan, 2007–2012. New Delhi.
5 ADB. 2018. Strategy 2030: Achieving a Prosperous, Inclusive, Resilient, and Sustainable Asia and the
Pacific. Manila.
6 Government of India, Planning Commission. 2013. Twelfth Five Year Plan, 2012–2017: Economic Sectors. Vol. II.
New Delhi.
3
10. Output 1: Reconstructed and rehabilitated state roads. This target was achieved. A
total of 432.57 km had been reconstructed by 2021 against the appraisal target of 432.91 km of
state roads (state highways and district roads). 7 The marginal difference of 340 meters at
completion against the appraisal target was because of actual site-specific requirements; the
originally intended origin and destination points were not altered. Rehabilitation works involved
widening the existing roadways, strengthening the road pavement, improving road geometry,
raising embankments, and providing permanent structures at river crossings. Works on state
road sections were completed by 13 January 2023 (para. 14).
11. Output 2: Improved business process and staff skills of the public works
departments. The four output targets were achieved by 2021 and the business process and
staff skills of the state PWDs have improved progressively since 2014 through (i) the
establishment of information technology (IT) based procedures within the PWDs for planning
and project management; (ii) staff training and adequate capacity building in all essential road
management functions; (iii) a road safety program with coordinated engineering, enforcement,
and education components; and (iv) sustained funding for the operation and maintenance
(O&M) of the roads—wherein funding is ensured through the state budget and maintenance is
carried out by each state PWD (Appendix 1).8
2. Project 2
12. The envisaged impact of Project 2 was improved mobility and accessibility in the project
areas. The actual growth rate of traffic on the project roads was 9.89% by 2021, which
exceeded the 9.0% expected growth rate at appraisal.9 The ratio of paved roads to total roads in
project states in the NER increased from 15% to 23% in Assam, 42% to 56% in Manipur, and
42% to 61% in Tripura. However, the growth rate in Mizoram was slightly reduced, from 70% in
2011 to 67% in 2019.10 All of Project 2’s expected outputs were achieved. No changes were
made to the DMF.
13. The expected outcome of Project 2 was to improve the efficiency of road transport in the
project areas in the states of Assam, Manipur, Mizoram, and Tripura. All three outcome targets
were exceeded by 2021: (i) the VOC on the project roads decreased by 53% for the three-axle
trucks, against the appraisal target of 50%; for passenger buses, it decreased by 41% at
completion, against the target of 20%; (ii) travel time on the project roads decreased by 60%
over 2013–2021, against the appraisal target of 20%–40%, from 17 km/hour (h) to 38 km/h in
Assam, from 18 km/h to 41 km/h in Manipur, from 8 km/h to 35 km/h in Mizoram, and from 20
km/h to 42 km/h in Tripura; and (iii) the average daily vehicle-kilometers in the first full year of
operation increased from 456,600 in 2013 to 637,733 in 2021.
7
Based on the updated Facility Administration Manual (October 2013), under Project 1, a total of 197.20 km was
proposed to be improved and 196.78 km has been improved. The marginal difference of 420 meters is because of
the actual requirement at the site, and the difference did not alter the original intended objective. Under Project 2, a
total of 235.71 km was proposed to be improved and 235.79 km has been improved. The completed road lengths
are provided by the project implementation units (PIUs) of Assam, Manipur, Mizoram, and Tripura.
8 Data was collected from the PIUs of Assam, Manipur, Mizoram, and Tripura.
9 The traffic growth rate was calculated using the time series data (DPR in 2011–2021 and actual in 2021).
10 Although the ratio of surface to total road length marginally decreased in Mizoram state from 2011 to 2019, the
surfaced road length nevertheless increased from 8,099 km in 2011 to 10,866 km in 2019.
4
15. At appraisal, the estimated total cost of the investment program was $266.7 million
($109.5 million for Tranche 1 and $157.2 million for Tranche 2). At completion, the actual cost
was $288.21 million ($104.29 million for Tranche 1 and $183.92 million for Tranche 2). At
appraisal, the ADB loan component was $200 million (75%) ($74.8 million for Tranche 1 and
$125.2 million for Tranche 2), and the remaining $66.7 million (25%) ($34.7 million for Tranche
1 and $32.0 million for Tranche 2) was to be financed by the central government and the
respective state governments. At completion, ADB financing was $199.68 million ($74.48 million
for Tranche 1 and $125.20 million for Tranche 2), and the government’s financing was $88.53
million ($29.81 million for Tranche 1 and $58.72 million for Tranche 2). For Tranche 1, the
$74.48 million included the utilization of surplus loan proceeds of $10.21 million to cover part of
a deficit under Tranche 2.13 A detailed comparison of the project financing at appraisal and
completion is presented in Appendix 3.
16. At appraisal, the total cost of Project 2, including base cost, contingencies, and financing
charges, was estimated at $157.2 million. At completion, the overall project cost was $183.92
million, or 17.0% higher than the original estimate. This was because of (i) the higher bid cost
received, and (ii) the unexpected contract variations in civil works quantities due to deficient
detailed project reports (DPRs). At appraisal, the estimated cost of the civil works was $130.19
million, inclusive of contingencies. At completion, the cost of civil works was $157.85 million
inclusive of contingencies.14 The government’s financing at completion—for land acquisition and
resettlement, utility shifting, financing charges, and other implementation costs—increased to
$58.72 million, which was 83.5% higher than the estimate of $32.0 million at appraisal. A
comparison of the project’s costs at appraisal and completion is presented in Appendix 2.
D. Disbursement
17. Loan proceeds were disbursed in accordance with ADB’s Loan Disbursement Handbook
(February 2012, as amended from time to time). Reimbursement procedures were used for civil
works and local currency payments for consulting services. After the first disbursement on 9
September 2015, succeeding disbursements gradually accelerated, peaking in 2019 (27.34%)
and in 2020 (17.56%). Actual yearly disbursements were almost as planned. Under the
11 The remaining balance of works (about 3.5 kms out of 20 km road section) in Tripura state were completed by 13
January 2023 by the state government’s newly appointed contractor, funded by MDONER’s own resources. ADB
project team had regular virtual meetings with PIU officials for expeditious completion of balance works. The
project team also participated in project review meetings conducted by MDONER.
12 The completed road lengths were obtained from the PIUs of Assam, Manipur, Mizoram, and Tripura.
13 The reallocation was approved through a memorandum dated 8 February 2020.
14 The actual total civil works cost of Project 2 at completion was $168.10 million. However, the $10.21 million surplus
E. Project Schedule
18. At appraisal, it was envisaged that the MFF’s availability was up to 30 June 2017.
However, this was extended to 30 June 2021 on 25 November 2013. Project 2 was expected to
be completed in September 2019. The Project 2 loan was approved on 2 December 2013. The
loan and project agreements were signed on 17 February 2014, and Project 2 became effective
on 20 May 2014. The loan was closed on 30 June 2021 against the original loan closing date of
31 March 2020.15 All six subprojects under five civil works contracts of Project 2 were delayed.
However, one subproject of Assam was completed on time, while four subprojects were
completed within the extended loan closing date. The sixth subproject was completed by 13
January 2023. The loan was financially closed on 8 November 2021.
19. The MFF and Project 2 faced the following major implementation difficulties: (i) higher
revised cost estimates because of variations in the quantities of the road works to meet site-
specific requirements, which were significantly higher than the costs approved by the Cabinet
Committee of Economic Affairs (CCEA); 16 (ii) delays in land acquisition because of the lengthy
and time-consuming processes, along with the enactment of the new Land Acquisition Act 2013
effective January 2014;17 (iii) delays in utility shifting and in obtaining forest clearances for tree-
cutting alongside the existing road for widening purposes, other than forest locations, which
involved multiple state government departments and complex processes; (iv) contractual issues,
as delayed payments to contractors’ invoices adversely impacted work progress, apart from
financial burden on the states in the form of contractual claims; (v) additional works and
variation in quantities beyond the contractual provisions; (vi) slow performance of contractors
and consultants; (vii) climatic uncertainties, including prolonged rains leading to landslides and
reducing the working season to just 4–6 months in a year; and (viii) the coronavirus disease
(COVID-19) pandemic, which delayed project implementation in 2020 and 2021. The majority of
the PWDs also extended the periods of consultancy services to suitably match the modified
implementation schedules (para. 26). The CCEA approved the revised cost estimates and the
completion schedule of both tranches under the program until August 2022 (inclusive of the 1-
year defect liability period). The estimated and actual implementation schedules are compared
in Appendix 5, and a chronology of the main events is presented in Appendix 6.
F. Implementation Arrangements
15 Project 2 was extended once from its original closing date of 31 March 2020. The extension was anticipated at the
time of appraisal (para. 20 of Periodic Financing Request of December 2013).
16
The CCEA is headed by the Prime Minister and directs and coordinates all policies and activities in the economic
field, including foreign investment that requires policy decisions at the highest level.
17 The land acquisition process had to be carried out in accordance with the amendments in the new Land Acquisition
Act 2013, enacted in 2014. For this change, revised cost estimates for land acquisition were prepared by the
PWDs of each state, which required approval again from their respective state governments, causing further delay.
6
and/or by an additional chief engineer; and supported by technical, administrative, social focal,
and finance staff. The PMU at MDONER and PIUs were adequately staffed.
21. To support the PMU, a project management consultant (PMC) was recruited to provide
project management, coordination, monitoring, and other related services.18 Each PIU recruited
a consultant to supervise the civil works (para. 26). The construction supervision consultants
(CSCs) carried out all the tasks specified in their terms of reference, including managing
contracts, supervising construction, ensuring quality control, ensuring road safety, overseeing
compliance with safeguards requirements, assisting with financial accounting, and conducting
on-site training. Each PIU also engaged a nongovernment organization (NGO) to implement the
resettlement plans. The NGO contracts were not extended beyond their original contractual
period because of performance issues, and the PIUs subsequently implemented the remaining
actions required under the resettlement plans. To ensure compliance with statutory
requirements in implementing the social and environmental safeguards, each state PIU
nominated an officer with the rank of an executive engineer, who was supported by an assistant
engineer or junior engineers and by the social and environmental specialists of the CSC. The
organization chart for project implementation is presented in Appendix 7.
22. Overall, the MFF and Project 2’s implementation arrangements were adequate.
Implementation issues were resolved through regular review meetings among the Department
of Economic Affairs, MDONER, state governments, contractors, and consultants. The regular
review missions fielded by ADB supported the successful implementation of the program.
G. Technical Assistance
23. Recognizing the importance of strengthening the PWDs’ institutional development and
capacity building in the NER states, a capacity-building technical assistance (TA 7838-IND) of
$1.2 million was provided, financed by the Japan Fund for Prosperous and Resilient Asia and
the Pacific (formerly Japan Fund for Poverty Reduction [JFPR]). The TA was approved on 21
July 2011 and signed on 25 May 2012. A technical assistance cluster subproject (TA 8063-IND)
under the Advanced Project Preparedness for Poverty Reduction Subproject 24 (TA 0003-IND)
was approved on 23 March 2012 for $700,000 to cofinance TA 7838-IND. An international
consulting firm was engaged on 17 December 2012, following ADB’s Guidelines on the Use of
Consultants (2010, as amended from time to time). The consultancy service contract was
extended once, from the original date of 30 June 2014 to 31 December 2014.
24. The consultants began their work on 7 January 2013. They conducted various capacity
building and training through facilitation workshops and prepared various reports, including a
final report containing (i) actions required for streamlined business processes for the road
management by PWDs of the project states, (ii) the creation and operationalization of the Road
Asset Management System (RAMS) database, (iii) the development of a road safety program,
and (iv) options for financing arrangements for road O&M in the project states. Consultants also
developed (i) guidelines and procedures for improved road maintenance operations for each of
the six states, including the use of alternative methods and materials; and (ii) manuals for
inspections, testing, and measurement with detailed procedures, for preparing the reports on
quality and progress of the works by PWD engineers and supervision consultants on all road
and bridge constructions, and for repairs and maintenance activities.
18
The PMC was recruited under Project 1 and continued its services in Project 2.
7
25. All the TA services were completed. The training programs, workshops, and documents
delivered by the consultants were highly valued by the PWDs. Overall, the TA was rated
successful. The TA completion report is in Appendix 8.
H. Procurement
26. ADB approved the advance procurement and retroactive financing under the project.
CSCs were selected through quality- and cost-based selection methods in accordance with
ADB’s Guidelines on the Use of Consultants (2012, as amended from time to time). The
selected CSCs were engaged in December 2012 by the state government of Assam, in
November 2013 by the state government of Tripura, in October 2013 by the state government of
Manipur, and in May 2014 by the state government of Mizoram. The CSC contracts for the
Manipur and Tripura components were effective until June 2021, and the CSC contract for the
Mizoram component was effective until October 2021. However, for the Assam component, the
state government extended the CSC services for their assistance with their own funds and was
effective until March 2022. As envisioned at appraisal during Project 1, MDONER recruited a
PMC in August 2012 to support the ministry in project management and performance
monitoring. The same consultant was engaged for Project 2 to conduct project management
and performance monitoring. The PMC contract was not extended and was closed in August
2017 because the consultant failed to deliver the intended objectives. The PMU staff completed
the required tasks, subsequent to the termination of the PMC.
27. The procurement of civil works followed ADB’s Procurement Guidelines (April 2013, as
amended from time to time). At appraisal, six subprojects comprising five civil works contracts—
one each in Assam, Mizoram, and Tripura states, and two in Manipur state—were procured
through international competitive bidding. All bids were invited as planned at appraisal during
the fourth quarter of 2011. However, Assam and Mizoram states had to undergo a rebidding of
the civil works because of the non-extension of the bidders’ bid validity, citing the change in
materials’ rates. ADB approved the rebidding on 8 October 2013. The civil works contracts were
awarded in February 2015 by Assam, in December 2013 by Manipur, in November 2014 by
Mizoram, and in February 2014 by Tripura against the appraisal target of the fourth quarter of
2013. In Tripura state, the civil works contract was terminated in April 2020 because of the poor
performance of the contractor. A new contractor was procured to complete the balance of the
works in March 2021. The funds allocated under the equipment category were not utilized
because the PWDs did not submit any procurement proposals, as none were required. The
surplus funds under this category were reallocated for completing civil works, as requested by
MDONER.
28. The amounts of the awarded civil works contracts were higher than the estimates at
appraisal. The original administrative approval by MDONER at appraisal required a revision
because of the (i) higher costs of the civil works contracts at the award stage, and (ii) variation
in road works quantities owing to site conditions. Thus, the CCEA approved the revised cost
estimates for the project in February 2019. 19 Along with the approval of the revised cost
estimates, the extension of the projects’ completion schedule until August 2022 (inclusive of the
1-year defect liability period) was also approved by the CCEA. After the CCEA approval of the
revised cost estimates and the issuance of a revised administrative approval by MDONER in
March 2019, the states assessed their subprojects’ revised completion costs and issued
variation orders for civil works and consultancy contracts during April–July 2019.
19
Including those financed by the North Eastern State Roads Investment Program—Project 2 (Loan 3073).
8
29. The civil works were generally completed with delay against the scheduled completion
date. The 43-kilometer Tamulpur–Paneri road section in Assam state was completed by 15
March 2020, which was within the original loan closing. The remaining section, including two
major bridges, was completed by 7 October 2020. The civil works of two contracts in Manipur
state were completed on 31 May 2021 and 29 June 2021, while in Mizoram state, the civil works
was completed on 30 April 2021. In Tripura state, the balance of the civil works was completed
progressively by January 2023 by the reappointed contractor, using MDONER and/or state
resources, as this was already beyond the loan closing date. Overall, the performance of the
contractors regarding ,standards, meeting specifications, and quality was considered adequate.
Details of the contract awards are presented in Appendix 9, and the summary of contracts is
shown in Appendix 10.
30. Gender. Project 2 was categorized as having some gender elements. The project
directly benefited the community, including women, through improved connectivity with the
reconstruction and rehabilitation of state roads. Focus group discussions held during
implementation indicated that most women and girls felt that the road improvements had
benefited them significantly, as better transport services provided them with improved access to
social services, district headquarters, markets, workplaces, higher education, better health
facilities, and better employment opportunities (para. 58). The project performance monitoring
system (PPMS) revealed a decline in travel time by 52% to health centers, by 67% to district
hospitals, and by 59% to major hospitals. The PPMS also reported a decline in poverty by 26%
and an increase in household incomes by 62%. During implementation, the contractors were
encouraged—through consultations and advisories by ADB, CSC, and PIUs—to employ women
in different skilled and unskilled works, thus resulting in female employment being generated.
Women and/or women’s groups were supported in taking up bioengineering works for road
rehabilitation and maintenance. These were ensured by the CSC and PIUs by verifying the
contractor’s records of those employed. Training programs were conducted to improve the PWD
staff's skills, including for women staff.
31. HIV/AIDS. Assam (0.09%) and Tripura states (0.12%) have a low HIV/AIDS prevalence
rate, whereas Manipur (1.05%) and Mizoram states (2.70%) have a higher prevalence
compared with the national adult prevalence rate of 0.21%. According to India’s National AIDS
Control Organization, HIV infection is typically concentrated among the poor and marginalized
groups (including high-risk groups, such as sex workers, drug users, migrant laborers, and truck
drivers). During implementation, the contractors, with the help of NGOs and the CSC’s social
expert, promoted HIV/AIDS awareness among their laborers and disseminated information at
worksites and other specified locations along the project roads on the risks of sexually
transmitted diseases. The CSCs monitored this work. Given the awareness-raising campaign
and based on the data from the States AIDS Control Society, the risk that the project will
increase HIV/AIDS incidence is considered insignificant.
J. Safeguards
as possible, the roads were widened within the existing right-of-way (ROW). For a few stretches
of the project roads, land was acquired to improve road geometry and to optimize efficiency and
safety while minimizing the social risks. Regarding the impact on private land, the project
avoided acquisition in Assam and Tripura and acquired 12.84 hectares (ha) in Mizoram,20 while
the village chiefs consented to strengthen the existing road in Manipur. 21 In total, 756
households were affected by the project—158 households in Assam, 321 in Manipur, 263 in
Mizoram, and 14 in Tripura. Of those affected, 133 were titled households, and 623 were non-
titled households. The project also affected 34 community property resources (CPR). Overall,
the project minimized the impacts at completion compared with the estimated number at
appraisal. The project-affected households were compensated for the loss of assets and were
given resettlement allowances in accordance with the approved RIPPs. The project paid
₹138.51 million as compensation and another ₹11.37 million as allowances to the affected
households. For the CPRs, the project paid ₹10.46 million. The project's social safeguards
categorization was maintained until its completion.
33. For safeguards implementation arrangements, the PWDs of each state established their
respective PIUs, acting as implementing agencies. Each PIU was headed by a project director,
who was supported by a designated staff of the PIU in managing safeguards implementation.
Each PIU recruited a supervision consultant with social safeguard expertise to support the PIUs
during implementation. Manipur and Mizoram PIUs engaged NGOs to support the RIPP
implementation, whereas Assam and Tripura PIUs implemented RIPPs with the CSC expert's
support. The land acquisition, resettlement and rehabilitation were carried out efficaciously with
the aid of awareness-raising and one-on-one meetings with the affected persons, which were
conducted by NGOs and executing agency representatives whenever required. The PMC expert
functioned as an external monitor for the project. Each PIU established a grievance redress
mechanism under the project and made it functional. Minor grievances were received
concerning the compensation amount, which was explained and was amicably resolved. No
grievances were pending at the time of project completion report (PCR) preparation.
34. At appraisal, social impact assessments indicated that the socioeconomic impacts and
benefits from the subprojects for Indigenous peoples would not differ from those for the rest of
the population. The level of literacy and awareness among the Indigenous households and their
participation in project preparation was high; hence, combined RIPPs were prepared. Project 2
had affected 364 Indigenous households, which is 49% of the total affected. Regarding impacts
on Indigenous peoples, out of the total affected in the project states, a maximum of 99% were in
Mizoram,22 followed by Manipur (25.72%) and Assam (20.88%). No Indigenous peoples were
affected in Tripura. The Indigenous peoples were considered vulnerable for the project. In
addition to the compensation at replacement cost for the affected assets, the project provided
additional assistance such as one-time lump sum financial assistance, preference in project
construction activity, and skills training following the RIPPs. The project disclosed information,
20
The state government of Mizoram has various land settlement arrangements for the following: (i) land settlement
certificate holder, (ii) periodic Patta holder, and (iii) village pass or permit holder. Settlement certificate holders are
titleholders who have heritable and transferable rights over the land; the periodic Patta authorizes a person to use
a parcel of land for a definite period under the Mizoram District (Agricultural Land) Act, 1963; and the pass or
permit holder authorizes a person to use a piece of land but does not give them the right of an owner.
21 In Manipur, land is owned by the village chiefs in the hills and no revenue record nor maps are available. There are
legalities with respect to land administration in the hills: (i) the Manipur Land Revenue & Land Reform Act 1960
extends to the whole of Manipur except the hill areas; and (ii) according to the Memorandum of Public Works
Department, Government of Manipur, 1994, the department will not acquire any land to construct roads. The land
for road construction will be donated by the concerned villages. However, compensation for the assets on the land
is to be paid.
22
Mizoram is a Sixth Schedule state under the Constitution of India.
10
and consultations were held with the Indigenous peoples communities throughout the project
cycle. The grievances of Indigenous peoples were found to be no different from those of others.
35. After initial delays, all four states regularly submitted their semiannual social monitoring
reports (SMRs), which were disclosed on ADB's website. At completion, 42 SMRs documenting
the implementation of social safeguards were submitted by the respective PIUs. At completion,
Project 2 remained in Category A for involuntary resettlement, and B for Indigenous peoples.
The PMC worked as an external monitor. Details of social safeguards are presented in
Appendix 11. Project 2 was found to be in compliance with the requirements of ADB’s
Safeguard Policy Statement (2009) for involuntary resettlement and Indigenous peoples.
Overall, the involuntary resettlement and Indigenous peoples' safeguards compliances for
Project 2 were assessed to be satisfactory.
37. The requisite environmental clearances for the road sections in Assam and Manipur
were obtained from the Ministry of Environment, Forest and Climate Change. Other road
sections did not require such clearances. Forest clearances and tree-cutting permissions were
also obtained by the PWDs in all four states under the project. A total of 10.55 ha of forest land
and 8,285 trees were affected. The contractors obtained the statutory permissions under
environmental safeguards and maintained them until the end of the contract by renewing them
regularly. The civil works contracts included environmental management plans to guide the
contractors in complying with environmental safeguard requirements. Testing of the parameters
for ambient air, water quality, and ambient noise levels by the civil works contractors were
initially infrequent; however, it became more frequent with regular follow-ups by the PWD and
CSC. With the help of CSC, the PIUs also closely monitored the ambient air quality,
groundwater quality, noise level, and soil quality results delivered by the contractor. Levels were
reported to be within the permissible limits during project implementation. Compliance with
labor, health and safety, and other statutory regulations was ensured by adhering to the
requirements of environmental management plans and of the national and state governments.
No occupational or community fatalities were reported during the construction stage under the
project. A total of 39 semiannual environmental monitoring reports (EMRs), which documented
the implementation of environmental safeguards from commencement to closure, were
submitted by the respective PWDs, cleared by ADB, and disclosed on ADB’s website. Public
and stakeholder consultations were conducted (details were documented in the EMRs) on a
continuous basis during the implementation under the project. The respective PWDs and PIUs
established grievance redressal committees that remained functional until project closure. The
loan covenants on environmental safeguards were complied with, and the overall environmental
performance of the project was generally satisfactory. Further details on the implementation of
the environmental safeguards are presented in Appendix 11.
11
38. An investment program performance monitoring system (IPPMS) and PPMS were
established by the PMC at MDONER. The IPPMS and PPMS were effectively used to track the
overall MFF and Project 2’s implementation activities, corresponding target dates, expected
outcomes, and assigned responsibilities using a monitoring mechanism. The PMC, through
IPPMS and PPMS, detected some gaps between the plan and the execution of the project and
reported these for the MDONER to take corrective actions. With the help of the CSC, the states
also established baseline performance indicators within 3 months of the loan effective date to
monitor each subproject’s implementation and, thereafter, conducted annual evaluation surveys
under each investment subproject. The evaluation surveys, which were based on review
meetings and included in the annual review of project progress by top management of
MDONER and participating states, identified the major gaps and/or slippages, including the
reasons thereof. Based on these surveys, suitable actions were taken to address the issues.
39. For Project 2, 124 of the 138 covenants in the loan documents were complied with, and
the remaining 14 were partially complied with. During implementation, MDONER and the state
governments provided adequate oversight, coordination, and financial support. The PIUs were
fully operational with adequate staff and resources. The PIUs, in close coordination with the
CSCs, supervised all aspects of the project, including the implementation status of the legal
requirements of the national and state governments. Regular site visits by PIU staff members
and frequent review meetings with the CSC and contractors ensured compliance with these
requirements. Environmental and social safeguard requirements were incorporated in the
contracts and were implemented accordingly. Safeguards monitoring reports were submitted on
time, except for a few that were delayed. The last reports were submitted in 2023 upon
completion of the civil works post-financial closure. Except for covenants related to the
submission of an audited project financial statement (APFS) and a delay in providing fund
facilities, the borrower and the executing agency complied with all loan covenants and project
agreements. The status of compliance with the loan covenants is summarized in Appendix 12.
40. ADB received 30 APFSs from the participating states during fiscal year (FY) 2022. ADB
received and accepted from Assam state APFSs covering FY2016–FY2022, from Manipur state
for FY2016–FY2022, from Mizoram state for FY2015–FY2022, and from Tripura state for
FY2015–FY2022. The APFSs submitted for FY2022 by the states were not fully reconciled with
ADB’s disbursement data, so the reports were unacceptable as a final APFS. The state
governments of Assam, Tripura, Mizoram, and Manipur agreed on a time-bound action plan to
submit the final and fully reconciled APFSs progressively by March 2024. The auditor issued an
unqualified audit opinion for all APFSs, except for Assam state’s FY2019 and FY2021, Manipur
state’s FY2021 and FY2022, and Tripura state’s FY2019. All four states addressed the
observations from ADB’s review of the APFSs. With the exception of APFSs for FY2020 of
Manipur, Mizoram, and Tripura and FY2016 of Manipur, all other APFSs were delayed. The
longest delay was 30 months for Tripura state for FY2015, 17 months for Assam state for
FY2016, 8 months for Mizoram state for FY2015, and 4.7 months for Manipur state for FY2022.
A. Relevance
41. The MFF and Project 2 are both rated relevant at appraisal and at completion. The MFF
and Project 2 are aligned with ADB’s CPS for India, 2009–2012, which framed infrastructure
development as a continuing strategic focus of ADB’s assistance for India. The MFF and Project
12
2 also support ADB Strategy 2030’s OP (para. 7). No conflicts nor overlaps with the initiatives of
other development partners were reported. Both responded to India’s Eleventh Five Year Plan
(2007–2012), which states that "while development efforts over the years have made some
impact (as reflected in some of the Human Development Indicators, which are comparable with
the rest of the country), the region is deficit in physical infrastructure, which has a multiplier
effect on economic development.” At completion, the MFF and Project 2 remained aligned with
ADB’s priority agenda as set out in the CPS, 2018–2022, which stresses the importance of
supporting the Government of India’s goals.
42. The MFF modality was considered appropriate for financing this project, as it allowed a
phased implementation of the individual projects by six project states with different levels of
project management capacity and exposure to large-scale infrastructure development (para. 5).
The NER is the least developed region in India, and many factors have hampered its economic
development. Recognizing the need for accelerated development, the Government of India has
focused on developing the NER in its 5-year plans—mainly through central funding of regional
development activities. In 2001, the national government created a dedicated ministry, the
MDONER, to coordinate and give impetus to the various central development efforts. MDONER
has been responsible for planning, executing, and monitoring development schemes and
projects in the NER. Its vision is to accelerate the pace of socioeconomic development of NER
so that it can enjoy growth parity with the rest of the country.
43. With renewed recognition that poor roads and bridges are a significant constraint to
developing the region's dominant road transport subsector, the central government launched a
national investment program to improve road connectivity in remote areas. The investment
program complemented, and was developed in parallel with the SARDP-NE. The objectives of
the SARDP-NE were to (i) improve higher-class roads, including national highways and state
roads in the region; and (ii) provide connectivity to state capitals and district headquarters in the
NER by developing two-lane national highways. While the SARDP-NE focused on improving
higher-class roads, the investment program focused on (i) improving intrastate connectivity,
mainly to district headquarters and to other places of administrative and economic importance in
the individual states; and (ii) enhancing the capacity of state PWDs to manage their road assets.
As owners of the projects, the state governments and the stakeholders assumed the
responsibility to resolve any implementation issues. The investment program and Project 2 were
implemented as planned, with no change in their overall scope.
44. The links between the DMF’s impact, outcome, and outputs were logical and clear for
the MFF and Project 2. The indicators were appropriate and measurable (paras. 8–14). The
project’s outputs were sufficient to deliver the expected outcome. The northeastern states are
underdeveloped, but the program states under the MFF and Project 2 were well-prepared
during appraisal, and PWDs were actively involved in preparing the DPRs and safeguards
reports. Implementation arrangements were adequate, as issues were resolved through
effective coordination, contributing to the project’s smooth implementation (paras. 20–22). As
envisaged at appraisal, women benefited substantially from the project (para. 30).
B. Effectiveness
45. The MFF and Project 2 are rated effective as the intended outcome and outputs were
achieved. For Project 2, two outcome targets were exceeded, and one was achieved. The VOC
and travel time on completed roads declined by more than the anticipated rate at appraisal
(paras. 9 and 13 and Appendix 1). The MFF outcomes were also achieved. In all six states, the
traffic growth rate surpassed the appraisal target, and the VOCs and travel times on project
13
roads declined. The average traffic growth of all projects in the investment program is 9.81%,
and the VOC and travel time on all project roads decreased as anticipated at appraisal
(Appendix 1).
46. All intended outcomes and outputs of the MFF and Project 2 were either achieved or
exceeded and supported the improvements in the states’ road network. The target outcomes of
Project 1, Project 2, and MFF were exceeded. The target outputs of Project 2 were achieved
through the reconstruction and rehabilitation of 235.79 km of roads in the four states. The
investment program also constructed 432.57 km of roads—including 196.78 km under Project
1—in all six states, achieving the two-lane or intermediate lane standard with earthen shoulders.
The road construction includes (i) elevating and widening flood-prone road sections, protection
works, culverts, and bridges above the predicted flood levels, considering climate change
impacts; and (ii) improving and/or realigning hazardous road sections and bridges for traffic
safety. By improving the roads, vehicle travel time was reduced, which in turn reduced carbon
emissions and contributed to climate resilience. In addition to including road safety provisions in
the detailed engineering design, road safety awareness-raising campaigns were also carried out
systematically in the communities, particularly those along the roads. Environmental and social
safeguard features included in project road construction led to contractors creating an additional
position to implement the safeguards.
47. In all six program states, business processes and staff skills of the PWDs have improved
under a technical assistance project. Under the TA, (i) information technology-based procedures
were developed for planning and project management purposes within the PWDs; (ii) adequate
staff training and capacity building for all essential road management functions was provided;
(iii) a road safety program with coordinated engineering, enforcement, and education
components was put in place; and (iv) sustained funding for O&M of roads was provided (para.
54).
48. Better roads have improved access to all services. The MFF and Project 2 provided
direct employment to women during implementation. Social and environmental safeguards were
generally satisfactorily implemented in all four states as the requirements of ADB’s Safeguard
Policy Statement 2009 were complied with (paras. 32–37). There were no negative impacts on
the land acquisition, resettlement, and rehabilitation nor on Indigenous peoples. Temporary
environmental impacts that occurred during the construction stage were mitigated through
effective environmental management plan (EMP) implementation, supervision, and monitoring.
The PIUs closely monitored the ambient air quality, groundwater quality, noise levels, and soil
quality with the help of the CSC, and levels were reported to be within the permissible limits
during project implementation.
C. Efficiency
49. The MFF and Project 2 are rated efficient. The MFF and Project 2 efficiently utilized the
resources available and advice from top-level government officers and ADB to complete the
project under critical circumstances. The economic internal rate of return (EIRR) of Project 2
was reevaluated using a methodology similar to that adopted at appraisal. The economic
benefits of Project 2 were calculated by comparing the “with-project” and “without-project”
scenarios. In the analysis, the primary economic benefits considered were the VOC savings and
savings in passenger travel time costs. The EIRR computation included the impact of delays
(paras.18–19). Project 2 is economically viable at completion, with a recalculated EIRR of
15.3%, which exceeds ADB’s threshold value of 12.0%. The EIRR of project roads at
completion varies from 14.5% to 19.0% against 15.3% to 22.9% at appraisal.
14
50. The EIRR of Project 2 was subjected to a sensitivity analysis to test the different
maintenance cost and benefit scenarios. Results indicated that even under the most adverse
scenario of a 20% maintenance cost increase, combined with a simultaneous 20% reduction in
benefits, the EIRR is still 12.9%. This indicates that Project 2 is economically robust for all
possible scenarios except for the case of reduced benefits (traffic growth) by 50%, which is only
8.5%. The sensitivity analysis also showed that the EIRR was most sensitive to changes in
economic benefits. Details of the economic reevaluation are presented in Appendix 13.
51. The EIRR of the MFF in all participating states was not calculated at appraisal. However,
the economic analyses for Project 1 and Project 2 were reevaluated, and based on these, the
MFF’s EIRR at completion was derived. There were delays in completing Projects 1 and 2, but
the outcomes and the outputs were achieved. Construction of one of the Project 2 roads was
delayed and could be completed beyond the loan closing date, but the outcomes and outputs
were achieved using state funds after the project’s closure. For Project 1, the EIRR at
completion was calculated at 16.9%, and Project 2 was at 15.3%. The combined EIRR for the
investment program states at completion is calculated at 15.8%, which is above the discount
rate of 12%. Implementation delays were also considered in the computation of the EIRR at
completion. Overall, the MFF is rated efficient.
52. In terms of process efficiency, Project 2 was completed without altering its original
intended objectives, despite challenges and implementation difficulties. MDONER resolved all
implementation issues through high-level meetings with the state governments and regular
review meetings with the PIUs, contractors, and the CSC. Corrective measures were taken
within the contractual framework. Although implementation was delayed, Project 2 delivered all
the required outputs and exceeded the expected outcome.
D. Sustainability
53. The MFF and Project 2 are both rated likely sustainable, considering the institutional and
financial arrangements that are in place for road maintenance.
54. Institutional capacity. According to the financing agreements, each state was
mandated to ensure adequate and timely funding through approved annual budget provision for
the O&M of the project roads for at least 5 years post-construction. An amount to be borne by
the states was provisioned for road maintenance under the administrative and financial sanction
of the project. The amount provisioned is now used for maintenance purposes, based on actual
requirements on the ground. As of December 2022, $600,000 had been spent on road
maintenance by the states, against the estimate of $3.3 million at appraisal, which was
envisioned for 5 years after the completion of civil works and based on the ground
requirements. The roads are in good condition. The overall maintenance of all PWD roads is
also challenging for the states. Recently, some state roads have been upgraded to national
highways. The Government of India is implementing road development projects (on the
upgraded national highways) in the NER using the engineering, procurement, and construction
(EPC) and the build–operate–transfer (BOT) modalities, wherein the maintenance obligations
are built into the civil works contracts. These projects have partially reduced the maintenance
burden on PWDs. The savings allowed the states to maintain other roads. The participating
states are also considering a policy to maintain overall road networks through performance-
based maintenance contracting (PBMC) to improve their quality-maintenance practices and the
15
overall condition of their road assets. 23 Upon the completion of the built-in provision of a 5-year
PBMC in civil works contracts, the project roads will be included in the PBMC policy by the state
PWDs.
55. Financing and maintenance. Project 2 will not generate revenue. The budget
provisions considered at the appraisal stage to maintain the project roads post-construction are
used for the upkeep of these roads. Although it was observed that the road maintenance
expenditure in Assam has been decreasing, the state has significantly increased its capital
expenditure for the reconstruction of roads—from ₹19,433 million in FY2017 to ₹72,252 million
in FY2021. Assam has rapidly increased its capital investment in road improvement and
reconstruction since 2017. The aim is to rehabilitate distressed road assets so they can be used
longer rather than spending huge amounts on maintenance. The PWD of Assam has developed
a road asset management system for decision-making and planning. The state government also
included the provision of a 5-year PBMC in civil works contracts that were awarded under the
new ADB-financed transport sector project in Assam.24
56. Road projects in Manipur, Mizoram, and Tripura were also implemented using the EPC
mode of contracts, embedding PBMC for road maintenance. Road maintenance expenditure
increased by 27% in Manipur during FY2017–FY2022, 86% in Mizoram during FY2017–
FY2023, and 12% in Tripura during FY2017–FY2023. The state governments appear committed
to more sustainable road maintenance (Appendix 13), as evidenced by their practice of adopting
private sector participation through the hybrid annuity, build–operate–transfer, and EPC contract
models and utilizing PBMC even for contracts awarded using the bill of quantities and
measurement contract mode. The PWDs assess the required yearly maintenance budget and
expenditure on a need basis by considering on-the-ground requirements, which cover routine,
recurrent, specific, periodic, and emergency situations.25
57. Both the MFF and Project 2 are assessed as environmentally and socially sustainable.
Innovative and cost-effective technologies and locally available materials were used to protect
the environment. Using local materials and other innovative technologies substantially reduced
the projects’ carbon footprint. Using a standard DPR template ensured that the adopted designs
complied with the technical, environmental, social, and road safety norms.26
E. Development Impact
58. The development impact of both the MFF and Project 2 is rated satisfactory.
Interconnectivity among the improved state roads has increased (paras. 8,10,12, and 14). The
project roads complement the development activities being undertaken under the SARDP-NE
(footnote 1). The projects have helped establish long-term and far-reaching improvements in the
state road network by enabling shorter transit times, lower VOCs, and smoother road surfaces.
Improved transport services enabled local people to reach larger markets where they can sell
products at higher prices. Bus services also increased on project roads because of better riding
from the subdivision level, (ii) aggregating the estimates at the district and division levels, and (iii) consolidating
them at the state level. This process is adopted across the majority of states in India. The budget is approved
based on the requisition made. Apart from the yearly budget allocation, supplementary budget allocation may also
be considered by the state government on a need basis and when required.
26 Improved, all-weather connectivity has minimized flooding and inundation of habitations, resulting in a better quality
quality and less vehicular wear and tear. People living near the project roads, including women
and girls, gained access to improved and affordable public transport, and safer access to public
services such as health and educational facilities. Girls can reach schools quicker and more
safely via public transport or bicycle. Travel times to reach the nearest health center have
decreased considerably on project roads (para. 30). Medical and emergency facilities within the
project roads’ influence area are more easily accessible because of improved connectivity.
59. Project 2 reduced the average VOC per km for cars, buses, and trucks. Improved roads
led to greater investment in roadside businesses, resulting in increased land prices by 27% to
80% within the areas of project roads. Surveys carried out after project completion showed that
rural households’ incomes rose by an average of 62% because of increased economic activity
along the project roads. Hotels, cafes, shops, garages, and workshops along the project roads
have increased commercial activities by more than 100%, creating employment opportunities.
State governments reported that the project provided some 7.8 million person-days of
employment during implementation. The projects’ positive impact on the state economy is
significant given its direct and indirect benefits. The MFF and Project 2 also contributed to OP 1,
OP 3, and OP 6 of ADB’s Strategy 2030 (paras. 7, 41). Appendix 14 presents the projects’
socioeconomic impacts, and Appendix 15 presents the projects’ contribution to Strategy 2030’s
operational priorities.
60. Improved road safety measures have reduced accidents and traffic congestion on
project roads, especially during the rainy season (Appendix 14). However, the improved road
conditions have also encouraged some vehicles to exceed the speed limit, leading to accidents
in mixed traffic conditions. To control this, the PWDs, with the help of local police, are
conducting road safety awareness-raising programs, providing additional road safety signs
(particularly speed limit signs), adding speed-calming measures (such as raised pedestrian
crossings and rumble strips), and stepping up enforcement of traffic laws.
61. The overall performance of the borrower, the executing agency, and implementing
agencies is rated satisfactory. The borrower facilitated timely loan signing. The borrower,
MDONER, and state PWDs actively participated during Project 2 preparation and
implementation through tripartite portfolio review meetings. The implementing agencies (the
PWDs) provided counterpart funds and implemented all aspects of the project, including project
design and preparation, procurement, land acquisition, other preconstruction activities, and
contract management. Compliance with the loan covenants was adequate, except for the
delayed submission of the APFS, reconciliation issues in the final APFS, and the fund flow
facilities that led to intermittent delays in the release of contractor payments. In their report
preparation, all four states are reconciling the final APFSs for FY2022 with those of ADB’s
disbursement records and are adhering to the suggested follow-up actions from the India
Resident Mission’s APFS review. The reconciled APFSs are expected to be submitted by March
2024 for ADB’s review. The PIUs, through the state governments, have also taken possible
measures to overcome the challenges and difficulties encountered during implementation
(paras. 20–22).
H. Overall Assessment
63. Overall, the MFF and Project 2 are rated successful. They were rated relevant at
appraisal and remain so at completion, given that they continue to align with the development
objectives and strategies of the central government and of ADB. The MFF and Project 2 are
rated effective in achieving their outputs and outcome, given their support for upgraded road
standards and enhanced road safety. The MFF and Project 2 are rated efficient in achieving
their outcomes and outputs. The EIRR of Project 2 was recalculated at 15.3%, which is above
ADB’s threshold value of 12.0%. The MFF and Project 2 are rated likely sustainable, given that
the institutional capacity of state government agencies in the construction of major road works
has improved. The technical and financial management capacities for road sector management
were enhanced, and their capacity to provide adequate financial support for road maintenance
was improved. The MFF and Project 2 also significantly contributed to accelerating the states’
economic growth by establishing a more efficient transport system.
Overall Ratings
Rating
Criteria Project 1 Project 2 MFF
Relevance Relevant Relevant Relevant
Effectiveness Effective Effective Effective
Efficiency Efficient Efficient Efficient
Sustainability Likely sustainable Likely sustainable Likely sustainable
Overall Assessment Successful Successful Successful
Development impact Satisfactory Satisfactory Satisfactory
Borrower and executing agency Satisfactory Satisfactory Satisfactory
Performance of ADB Satisfactory Satisfactory Satisfactory
ADB = Asian Development Bank.
Source: Asian Development Bank.
64. Timelines for the completion of civil construction works. The climatic constraints,
limited working seasons in NER, difficult terrain, and availability of experienced local labor and
construction materials were not factored in when setting the construction period. Accordingly,
the PWDs needed to extend the contracts’ duration to complete the civil works contracts.
65. Deficiency in the detailed project reports. There was a huge difference between
actual quantity requirement based on site-specific conditions and those indicated in the DPRs.
This occurred because of the deficiency in preparation of the DPRs. Because of the insufficient
provision of quantities in the bill of quantities, contractors had to put a huge claim in the form of
revision of rates and the actual quantity. Given this, careful attention should be taken while
preparing the DPR and estimating the quantities. Proof-checking of the bid documents is
18
essential before inviting the bids. The design consultants with sufficient experience in preparing
the DPR of hill roads should be carefully selected to avoid or minimize errors.
66. Accurate and well-researched estimate. There were significant time gaps of 4–5 years
between the finalization of the DPRs, including cost estimates and the completion of the bidding
process. This has led to higher contract costs in comparison to the engineering estimates. As
such, wide time gaps should be avoided between the finalization of the estimate, initiation of the
bidding process, and awarding of contracts to avoid incurring time and cost overruns.
B. Recommendations
67. Slow fund flow mechanism. In most states, local currency payments of the contractors’
invoices, particularly those under central-sponsored schemes, were delayed because of state
governments’ inadequate budgets and failure to allocate funds to the PIUs in a timely manner.
Consequently, the states carried the financial burden arising from the contractors’ claims,
causing implementation delays resulting in additional unwanted implications. Thus, it is
recommended that PWDs consider the direct payment method in place of the reimbursement
procedure, with the approval of the Department of Economic Affairs in accordance with the ADB
Loan Disbursement Handbook (2022, as amended from time to time), to pay contractors,
suppliers, and consultants on a selective basis with all necessary precautions.
68. Sustainable road maintenance. As a long-term measure, it is suggested that the state
PWDs use EPC and hybrid annuity modes of contracts from the conventional bill of quantities
(BOQ) modality. The use of a systematic and innovative approach by the PWDs should reduce
maintenance costs, in addition to significantly improving the delivery and quality of future
projects and ultimately supporting the sustainability of state road infrastructure.
69. Capacity development of executing agencies. Although adequate due diligence was
exercised by the executing and implementing agencies during project design and preparation,
the northeastern states are unfamiliar with the latest construction technology. They are
inexperienced in dealing with contractual matters. Extensive training programs by specific field
experts are recommended for the PWD staff in new projects.
70. Green highways. The government should consider the realities of climate change and
the scarcity of natural construction materials like aggregates in planning, designing, and
constructing green roads and highways that are ecologically sustainable.
71. Hill road maintenance. The hill roads, particularly in northeastern states, are
susceptible to landslides. Hence, during maintenance periods, sufficient provisions for slope
protection work should be included for future road projects.
72. Further action or follow-up. A larger portion of the NER road network has now been
rehabilitated with the assistance of ADB, the World Bank, and the Government of India. The
states are aware of the need to gradually shift from the traditional road-by-road maintenance
system to a more systematic area-wide road asset maintenance system (RAMS) to cover the
developed road network in a more efficient manner. Recognizing this challenge, ADB may
provide a TA to further strengthen the asset management capacity of the NER states.
73. Timing of the project performance evaluation report. ADB’s Independent Evaluation
Department can prepare the project performance evaluation report after March 2024 once the
respective state PWDs have submitted the reconciled final APFS.
Appendix 1 19
Travel time on the project roads c. Exceeded. The travel time on the
reduce by 20%–40%. project roads was reduced by more than
50%.
Outputs By 2017: By 2021:
2b. Staff training and capacity 2b. Achieved. Staff training and
building adequately capturing all capacity building that were undertaken
essential road management adequately captured all essential road
functions. management functions.
2c. Road safety program with 2c. Achieved. Road safety program with
coordinated engineering, coordinated engineering, enforcement,
enforcement, and education and education components are in place.
components in place.
2d. Sustained funding for road 2d. Achieved. Sustained funding from
operation and maintenance the state budget (each state) for road
established and in place. operation and maintenance have been
established and are in place. c
20 Appendix 1
ADB = Asian Development Bank, EA = executing agency, km = kilometers, NER = North Eastern Region, PWD =
Public Works Department.
a Phase A of SARDP-NE was approved by the Government of India for improving 4,099 km of roads (3,014 km of
national highways and 1,085 km of state roads). Of these, 3,213 kms were approved for implementation and the
balance of 886 km was approved “in principle.” A total of 3,333 kms of roads was awarded and 2,101 kms have
been completed by March 2019. Phase A is expected to be completed during 2023–2024.
b ADB. 2013. Updated Facility Administration Manual. Manila. Table 1: List of Roads to be Improved under the
Investment Program. In Table 1, the length of roads to be improved under the investment program was reduced to
432.91 km against the 433.70 km envisaged at appraisal, as indicated in Facility Administration Manual of June
2011. However, at completion, there is a marginal difference of 340 meters, which is due to the actual requirement
at site, but without altering the original intended objective.
c
The activities to achieve outputs 2a–2d were completed progressively by 2014, under the technical assistance
program of the project, and is reported as being currently in use, although further strengthening and improvement
are required. A human resource and training cell was formulated in each of the participating states. Detailed report
on the training needs assessment, training plans, guideline documents, manuals, and software (including for
planning, management, other road management functions, human resources management system, and Road
Asset Management System (RAMS), etc.) was prepared and disseminated to all the participating states. A series
of facilitation workshops and capacity-building workshops were conducted on topics such as organizational issues,
transport planning, RAMS, financing for road maintenance, and the need for a dedicated Road Fund. Road safety
programs were also initiated including (i) a review of the existing arrangements for managing and monitoring road
safety, (ii) training of the relevant personnel for the effective implementation of road safety, and (iii) proposing
modifications for effective institutional arrangements. The participating states also recognized the importance of
road safety, including the prevention of accidents and the establishment of a road safety council. An overseas
training program on “Maintenance and Rehabilitation of Roads and Bridges using Road Asset Management
System” was organized in Malaysia in June 2014 to showcase the use of RAMS. Ten participants from six PWDS
of the North Eastern states participated. The participating states allocated sufficient budget to meet the yearly
maintenance of the road assets, as evident from their historical budgets, except for Assam, which has been
prioritizing the reconstruction of roads over the maintenance of distressed road assets.
Sources: TA consultants’ final report, surveys conducted by the project implementation units (PIUs), and discussions
with the PIUs of Assam, Manipur, Mizoram, and Tripura.
Appendix 1 21
mentioned for VOC of 3-axle truck and bus are not correct. Moreover, there is no reason for higher amount in the
case of Assam (Rs. 250) compared with Tripura (Rs. 130). Tripura is having hilly terrain compared with Assam;
hence the VOC should be more than Assam which is mostly flat terrain.
c As per the surveys conducted by the project implementing units (PIUs) and discussions with the PIUs of Assam,
investment program. In Table 1, the length of roads to be improved under tranche 2 was increased to 235.71 km
22 Appendix 1
(Assam = 62.56 km, Manipur = 97.85 km, Mizoram = 55.00 km, and Tripura = 20.30 km) against the project roads’
length of 231.40 km as envisaged at appraisal (as indicated in the Facility Administration Manual of June 2011).
Sources: Asian Development Bank and the state executing agencies.
Appendix 2 23
Sources: Asian Development Bank and the PIUs of Assam, Manipur, Mizoram, and Tripura.
.
24 Appendix 3
Sources: Asian Development Bank and the PIUs of Assam, Manipur, Mizoram, and Tripura.
26 Appendix 3
Item Actual
Total ADB Borrower ADB
share(%)
Base Costs
I. Investment Component
1. Right-of-Way and Social and 8.19 0.00 8.19 0.00
Environmental Measures
2.1 Civil Works (roads and bridges) 157.85 116.39 41.46 73.70
2.2 Road Maintenance 0.59 0.00 0.59 0.00
3. Construction Supervision Consultants 8.81 8.81 0.00 100.00
4. Equipment 0.00 0.00 0.00 0.00
5. PIU Cost 0.07 0.00 0.07 0.00
Subtotal 175.51 125.20 50.31 71.30
II. Project Management and Capacity
Development Component
1. Project Management Consultant 0.00 0.00 0.00 0.00
2. PMU Cost) 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00 0.00
Base Cost Total 175.51 125.20 50.31 71.30
Physical Contingency 0.00 0.00 0.00 0.00
Price Contingency 0.00 0.00 0.00 0.00
Financing Charges during 8.41 0.00 8.41 0.00
Implementation
Total 183.92 125.20 58.72 68.10
ADB = Asian Development Bank, PIU = project implementation unit, PMU = project management unit.
a Civil works contracts include cost toward contingencies.
Sources: Asian Development Bank and the PIUs of Assam, Manipur, Mizoram, and Tripura.
Appendix 4 27
Figure A4: Projected and Actual Cumulative Disbursement of ADB Loan Proceeds
($ million)
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022-24
Activity Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Y1 Y2 Y3
A PMC
Recruitment
Consulting services
Execution
B CW (Project 2)
Procurement
Construction
Maintenance
C CSC (Project 2)
Recruitment
Consulting services
Execution
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022-26
Activity Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Y1 Y2 Y3 Y4 Y5
A PMC
Recruitment
Consulting services
Execution
B CW (Project 1)
Procurement
Construction
Maintenance
C CSC (Project 1)
Recruitment
Consulting services
Execution
D CW (Project 2)
Procurement
Construction
Maintenance
E CSC (Project 2)
Recruitment
Consulting services
Execution
ADB = Asian Development Bank, DEA = Department of Economic Affairs, EA = executing agency, MDONER = Ministry of Development of North Eastern Region,
MORTH = Ministry of Road and Highway Transport, NEC = North Eastern Counsel, PIU = project implementation unit, PWD = Public Works Department.
Sources: Asian Development Bank and the project implementation units of Assam, Manipur, Mizoram, and Tripura.
32 Appendix 8
Description
The North Eastern Region (NER) of India is connected only by a narrow land corridor to the rest of the country.
Except for the state of Assam, the NER’s terrain is predominantly hilly to mountainous, and the region experiences
some of the highest rainfall levels in the world, frequently causing landslides and floods. Road connectivity continues
to be poor and prone to disruption due to inclement weather and landslides. Although the NER is serviced by road,
rail, air, and water transport, road transport dominates the movement of goods and passengers. The road network in
the NER in 2011 comprised 145,000 kilometers (km), consisting of 35,000 km of surfaced roads—mostly national
highways, state highways, and district roads—and 110,000 km of unpaved roads. Except for the highest-class roads
(mostly national highways maintained by central government agencies), the road network in the NER required
substantial improvement through the expansion and rehabilitation of individual road sections. The state-level public
works departments (PWDs) also required substantial capacity strengthening.
Recognizing that roads and bridges were inadequate to support road transport as the NER’s dominant transport
mode, the Ministry of Development of North Eastern Region (MDONER) developed the North Eastern State Roads
Investment Program, which was designed to improve intrastate connectivity, mainly to district headquarters and other
places of administrative and economic importance in individual states, and to enhance the capacity of state PWDs to
manage their road assets. Subsequently on 21 July 2011, the Asian Development Bank (ADB) approved a $200-
million multitranche financing facility (MFF) North Eastern State Roads Investment Program (NESRIP) to (i) improve
430 km of priority road sections in six states of the NER, namely Assam, Manipur, Meghalaya, Mizoram, Sikkim, and
Tripura; and (ii) provide capacity-building support to the executing agency (MDONER) and the implementing
agencies—the PWD or its equivalent in each of the six states.
To facilitate institutional development and capacity building of the PWDs, a capacity development technical
assistance (CDTA), the Capacity Building for North Eastern State Roads Sector TA was attached to the MFF. The TA
was financed on a grant basis by the Japan Fund for Prosperous and Resilient Asia and the Pacific (JFPR) for
$1,200,000. The TA was to (i) strengthen state PWD road management by introducing modern road management
practices; and (ii) facilitate the road management role of state PWDs by introducing more effective and efficient road
management processes and systems, and establishing road maintenance funds. A parallel cluster CDTA, Advanced
Project Preparedness for Poverty Reduction TA, also supported the capacity development component of the MFF.1
This TA focused on (i) identifying actions for streamlining the business processes for road management by PWDs of
1
The capacity building support for the MFF was split into two separate, yet related TA projects. Prior to the MFF
approval (as agreed during the Joint Advisory Committee of the TA Cluster on 18 March 2010), a CDTA of $1.9
million was envisaged to be approved as a piggybacked TA to the MFF, of which $1.2 million will be financed on
grant basis by JFPR, and $0.7 million by the Government of United Kingdom under the ongoing Cluster TA 0003-
IND Advanced Project Preparedness for Poverty Reduction. However, only the JFPR-financing (TA 7838) was
approved with the MFF in 2011. This was due to the difference in the TA processing procedure between JFPR and
the Cluster TA (with pending extension of implementation period at that time). The said financing from UKNI–
ATF—a Cooperation Fund with the United Kingdom and Ireland was approved under the TA Cluster in 2012 under
subproject TA 8063 (consequently the cluster TA was extended from 31 July 2012 to 31 December 2014).
Appendix 8 33
the project states, (ii) making the Road Asset Management System (RAMS) database operational, (iii) having road
safety program developed, and (iv) identifying options for financing arrangements for road operation and
maintenance in the project states. Therefore, the capacity building support was split into two separate, yet related TA
components.
Implementation Arrangements
MDONER was the executing agency while ADB-administered the TA. Six North Eastern states (Assam, Manipur,
Meghalaya, Mizoram, Sikkim, and Tripura) public works department or its equivalent were the implementing
agencies. The TA project was implemented for 31 months, including an extension of 6 months up to 31 December
2014. The TA became effective on 25 May 2012, 10 months after TA approval due to the delay in the approval
process of the MFF. ADB engaged a consulting firm, Lea International Ltd, following quality- and cost-based
selection method, using a quality–cost ratio of 80:20 and simplified technical proposals in accordance with ADB’s
Guidelines on the Use of Consultants (2010, as amended from time to time).4 The same consulting firm was engaged
for both CDTAs (different contracts and common team leader) due to the related nature of the two CDTAs. Team
members of the consulting firm for each TA worked closely to complement activities. The contract completion date for
both contracts was 6 December 2014. TA 7838-IND engaged a total of 76.5 person-months inputs against the
planned 60 person-months. The consultants were to assist in the following areas: (i) institutional aspects, (ii) road
maintenance financing, (iii) improved quality management of construction and maintenance, (iv) human resource
development program, (v) potential tolls to generate road maintenance fund, and (vi) training and human resource
development. TA 8063 utilized a total of 44 person-months inputs against the planned 34 person-months. The
consultants were to (i) assist in equipment procurement required for effective road management, (ii) implement the
road asset management system, and (iii) develop and implement the road safety initiative.
The performance of the consultants was rated satisfactory. The consultants were quick to adjust in the methodology
at the commencement of their services when they noticed that it is better that the consultants visit each and every
state of the North Eastern states rather than officers from the states travelling to one specific state to attend central-
based workshops. The consultants conducted periodic reviews with ADB, the executing agency, and state
implementing agencies to deliver the tasks and responsibilities assigned to them under the contract. The
performance of the executing agency and the state implementing agencies were also satisfactory as they gave full
support to the consultants in all activities under the TA project. Also, the executing agency and the state
implementing agencies endorsed the change in methodology proposed by the consultants. The counterpart staff of
the executing agencies were very cooperative in providing support to the consultants whenever required.
Conduct of Activities
Output 1. Institutional capacity strengthened. The consultants (i) reviewed actions proposed under the institutional
development and capacity building (IDCB) plans for the institutional aspects; (ii) prepared guidelines and procedures
for improved road maintenance operations, including the use of alternate methods and materials, among others; and
(iii) conducted seminars and case studies (involving state governments and state departments, stakeholders, and the
community) on the main principles of transport planning, project programming, and methodologies for project costing
2 ADB. 2011. Report and Recommendation of the President to the Board of Directors on a Proposed Multitranche
Financing Facility and Technical Assistance Grant India: North Eastern State Roads Investment Program. Manila.
(paras. 20-21)
3 The outputs were derived from the terms of reference of the consultants.
4 For TA 7838, Lea International Ltd. was the consulting firm and the contract was awarded on 17 December 2012
The firm commenced its services on 7 January 2013, physically closed on 6 December 2014, and financially closed
on 31 May 2015. For TA 8063, Lea International Ltd. was also the consulting firm and the contract was awarded on
12 December 2012. The firm commenced its services on 7 February 2013, physically closed on 6 December 2014,
and financially closed on 31 May 2015.
34 Appendix 8
and financing. During the TA implementation, around 14 meetings took place between the consultants, ADB,
executing agency, and the state implementing agencies. About 20 reports, manuals, and guidelines were submitted.
A series of workshops were held, such as Inception workshop, state-level capacity development workshops, seminar
on transport planning for North Eastern states, workshops on road asset management, workshop on human resource
management and training needs, and workshop on financing for road maintenance. A dedicated road fund seminar
was also conducted on (i) transport planning and project programming, (ii) institutional issues, (iii) financing for road
construction and maintenance, (iv) human resource management and training, (v) an overseas study tour. An
overseas training program on “Maintenance and Rehabilitation of Roads and Bridges using Road Asset Management
System (RAMS)” was organized in Malaysia in June 2014 to showcase the use of RAMS. Ten participants from six
PWDS of the North Eastern states participated.
Output 2. Road maintenance financing developed. The consultants (i) conducted assessment on the possible
modalities of securing additional funds for road maintenance in each of the project states; (ii) assisted PWDs in
establishing a Road Maintenance Fund; (iii) assisted PWDs in developing road maintenance funding principles,
strategies, and guidelines for managing the road maintenance funds; and (iv) Assisted in the development of road
maintenance treatment selection process. A seminar on financing for road construction and maintenance and a
seminar on road asset management were also held.
Output 3. Quality management of construction and maintenance improved. The consultants (i) assisted the
PWDs in developing a quality management system for the construction and maintenance works, including a quality
management manual, procedures, and reporting system; (ii) prepared the manual with detailed procedures for
carrying out inspections, testing and measurement, and preparing reports on the quality and progress of the works
for use by the PWD engineers and supervision consultants in all road and bridge construction, repairs, and
maintenance activities; (iii) trained PWD staff in the use of the manual; and (iv) assisted the PWDs to identify,
prepare specifications, and procure testing equipment and facilities required for implementing the quality
management system.
Output 4. A Human Resource Development Program implemented. The consultants (i) assisted the PWDs in
developing a staffing plan and staff recruitment strategy and procedures, (ii) assisted the PWDs in assessing training
needs for the PWDs, (iii) prepared a 3-year training plan for each state, (iv) finalized the training need assessment
(TNA) forms for each North Eastern state, and (v) formulated five guideline documents on human resource
development and training, namely (a) Guidelines for conduct of TNA in NE states; (b) Guidelines for preparing the
training plan based on TNA; (c) Guidelines for design of training programmes; (d) Guidelines for development of
training & learning material; and (e) Guidelines for evaluation of training. There was an establishment of an HR and
Training cell in each of the PWDs by appointment of counterpart staff. These staff continued to perform functional
tasks even after completion of the TA project. The completed TNA forms received post survey from six NE States
totaling 228. Six state-specific reports on TNA and training plan were issued to each of the six NE states.
Output 5. Examine potential tolls to generate road maintenance funds. The consultants examined the possibility
of alternate funding sources, including fuel taxes and tolls, through road user charges and private sector participation.
Output 6. Training and human resource development provided. Detailed report on the training needs
assessment, training plans, guideline documents, manuals, and software (including for planning, management, other
road management functions, human resources management system, Road Asset Management System (RAMS),
etc.) was prepared and disseminated to all the participating states. A series of facilitation workshops and capacity-
building workshops were conducted that included topics on organizational issues, transport planning, RAMS,
financing for road maintenance, and the need for a dedicated Road Fund.
The key reports produced by the consultant team were as follows: (i) inception report, (ii) quarterly progress reports,
(iii) draft final report, and (iv) final report. The final report contained actions required for (i) a streamlined business
processes for road management by PWDs of the project states, (ii) the creation and operationalization of the Road
Asset Management System (RAMS) database, (iii) the development of a road safety program, and (iv) options for
financing arrangements for road operation and maintenance in the project states. In addition to the above, the
consultants also produced the Guidelines and procedures for improved road maintenance operations prepared for
each of the six states, including the use of alternate methods and materials, etc. The guidelines were simple and self-
explanatory for the use of each state PWDs. Manuals were also produced for (a) inspections, testing, and
measurement with detailed procedures; and (b) for preparing the reports on quality and progress of the works by
PWD engineers and supervision consultants on all road and bridge construction, repairs, and maintenance activities.
The manuals were finalized based on the pilot test conducted on samples of different types of works. Based on
consultations among ADB, executing agencies, state implementing agencies, and consultants, the TA also
established a human resource and training cell, procured IT equipment, and installed a road asset management
system (RAMS) in each of the participating states.
Appendix 8 35
Road safety programs were also initiated including (i) a review of the existing arrangements for managing and
monitoring road safety, (ii) training of the relevant personnel for the effective implementation of road safety, and (iii)
proposing modifications for effective institutional arrangements. The participating states also recognized the
importance of road safety, including the prevention of accidents and the establishment of a road safety council. The
participating states allocated sufficient budget to meet the yearly maintenance requirements, as evident from their
historical budgets, except for Assam, which has been prioritizing the reconstruction of roads over the maintenance of
distressed road assets.
The design and rationale for using a TA were appropriate. During the
project processing of the NESRIP, the Department of Economic Affairs,
Ministry of Finance, the Ministry of Development of North Eastern Region
and the Governments of the project states requested for the CDTA as the
state PWDs in the NER had limited exposure to modern road
management practices, and their capacity needed substantial
enhancement, both for implementation of the NESRIP and for overall
management of the road network under their responsibility. The CDTA
covered a broad scope to improve state PWDs’ overall performance
through improvement in their business processes and institutional
structure. The CDTA aimed at institutionalizing the good practices being
adopted and experiences gained so that the changes being initiated
under the NESRIP could be sustained and replicated in other areas of
PWDs’ operation.
Effectiveness The TA is rated effective as the outcome and all outputs were achieved. Effective
The consultant achieved all deliverables and carried out the activities as
mentioned in their TORs, namely (i) institutional aspects, (ii) road
maintenance financing, (iii) improved quality management of construction
and maintenance, (iv) human resource development program, (v)
potential tolls to generate road maintenance fund, and (vi) training and
human resource development. Overall, the reports, guidelines, and
manuals prepared were of good quality and the training programs and
facilitation workshops targeted the needs of the stakeholders of the NER
states. The TA facilitated the PWDs of the NE States in (i) improved
capacity in planning, programming, policy formulation and asset
management; and (ii) prepared them for taking larger responsibility as
‘managers’ of the roads being developed under various road
development schemes. Further, these PWDs were ready to replicate the
good project management practices introduced under the NESRIP in
other areas of their operation. One of the most significant outputs of the
TA project was the state PWDs’ exposure to the concept of
establishment of a dedicated RAMs cell along with a robust RAMs in all
state PWDs. It helped the PWD staff to gain a first-hand working
knowledge of the system’s workings and its importance in convincing the
financial planners for an adequate allotment of funds toward road
maintenance. The states were encouraged to establish dedicated cells in
the PWDs for the following four functions: (i) human resource
36 Appendix 8
Cofinancing for the JFPR component is highly appreciated and ADB is grateful
to the Government of Japan for timely granting the funds when requested for
the successful completion of the TA project.
Follow-Up Actions
ADB should closely monitor the implementation of the consultants’ recommendations on institutional changes, road
asset management, and creation of road maintenance funds in the NER states’ PWDs.
38 Appendix 8
Table A9: Annual and Cumulative Contract Awards of ADB Loan Proceeds
($ million)
Annual Contract Awards Cumulative Contract Awards
Year Amount Amount
% of Total % of Total
($ million) ($ million)
2014 94.10 56.25 94.10 56.25
2015 33.80 20.20 127.90 76.45
2016 0.00 0.00 127.90 76.45
2017 1.90 1.14 129.80 77.59
2018 0.00 0.00 129.80 77.59
2019 0.00 0.00 129.80 77.59
2020 37.50 22.41 167.30 100.00
2021 0.00 56.25 167.30 100.00
Total 167.30
ADB = Asian Development Bank.
Source: Asian Development Bank’s Loan Financial Information System.
Figure A9: Projected and Actual Cumulative Contract Awards of ADB Loan Proceeds
($ million)
SUMMARY OF CONTRACTS
Table A10.1: Summary of Civil Contracts
Original /Revised
Length Contract Date/ Actual Amount ADB Financing
Package No. Contractor Name of Road Procurement Contract Amount
(km) Commencement (₹) ($)
(₹)
AS-02 DRA-SGCCL- Tamulpur to Paneri 10-Feb-15 /
ICB 62.56 2,891,600,000 3,882,500,000 34,787,828.45
AS-03 ANPL (JV) Paneri to Udalguri 10-Feb-15
28-Dec-13 /
MN06-CW-1 DRAIPL-ABCI(JV) Tupul-Bishnupur ICB 50.80 1,872,764,790 1,904,933,522 28,847,117.69
24-Jan-14
28-Dec-13 /
MN06-CW-2 DRAIPL-ABCI(JV) Thoubal-Kasom khullen ICB 47.13 1,733,671,249 2,298,135,466 16,352,857.44
24-Jan-14/
Tantia 11-Nov-14/
MZ-01 Serchhip to Buarpui ICB 55.00 2,045,145,316 2,698,300,000 30,399,414.17
Construction ltd 03-Dec-14
ECI-Nayak(JV) /
Vasishta 25-Feb-14/
TR-01 Udaipur to Melaghar ICB 20.30 802,600,000 765,700,000 6,006,084.73
Construction Pvt. 06-Apr-15
Ltd
ADB = Asian Development Bank, ICB = international competitive bidding, km = kilometer, ₹ = Indian rupee, $ = United States dollar.
Sources: ADB’s Integrated Disbursement System and the project implementation units of Assam, Manipur, Mizoram, and Tripura states.
SAFEGUARDS ASSESSMENT
A. Involuntary Resettlement
1. Project 2 was category A for involuntary resettlement impact in accordance with ADB's
Safeguard Policy Statement (2009). At appraisal, a Resettlement Framework was formulated to
guide the preparation of safeguards documents, and six combined resettlement and indigenous
peoples plans (RIPPs) were prepared under the project and disclosed on the ADB website. A
due diligence report was prepared and disclosed during the implementation of the Manipur CW2
package. 1 The project was implemented with minimum land acquisition and involuntary
resettlement by adopting the most feasible technical designs. As far as possible, the roads were
widened within the existing right-of-way. At a few stretches of the project, roads required land
acquisition to improve geometry, road safety, and widening. The project's social safeguards
categorization continued until its completion.
2. Out of the six roads, land acquisition was required in Mizoram2 state, which was also
minimized at completion. Roads of Assam, Manipur,3 and Tripura states did not involve any land
acquisition as right-of-way was available or the roads were constructed within available land.
There were impacts on titleholders (THs), non-titleholders (NTHs), and community property
resources (CPRs). Of the project affected 756 households, 133 were THs, and 623 were NTHs.
In addition, the project also affected 34 CPRs. Table A11.1 shows the actual impacts at
completion.
1 Due diligence was prepared for widening a section of road from an intermediate lane to a standard two-lane road
from Km. 81+450 (Thoubal) to Km 88+700 (Yairipok), excluding the stretch from Km 82+350 to 83+150 (800 rm).
2 Mizoram state has various land settlement arrangements: (i) land settlement certificate holder, (ii) periodic patta
holder, and (iii) village pass/permit holder. Settlement certificate holder are titleholders who have heritable and
transferable rights over the land; the periodic patta authorizes a person to use a parcel of land for a definite period
under the Mizoram District (Agricultural Land) Act, 1963; and the pass/permit authorizes a person to use a piece of
land but does not give them the rights of an owner.
3 In Manipur, land is owned by the village chiefs in the hills and no revenue record or maps were available. There are
legalities with respect to land administration in the hills: (i) The Manipur Land Revenue & Land Reform Act 1960
extends to the whole of Manipur except the hill areas; and (ii) Memorandum of Public Works Department,
Government of Manipur, 1994—according to this order, the department will not acquire any land to construct roads.
The land for road construction will be donated/consented by concerned villages. However, the compensation for
the assets on the land is to be paid.
42 Appendix 11
Sources: The project implementation units of Assam, Manipur, Mizoram, and Tripura states.
In Rupees (₹)
Description
Assam Manipur Mizoram Tripura Total
Compensation for 138,513,234.35
2,144,268.35 63,210,304.00 72,083,441.00
assets 1,075,221
R&R allowances 1,539,000.00 925,750.00 6,494,500.00 11,373,646.00
Compensation for 10,164,774.24
748,147.24 3,340,146.00 6,002,961.00 73,520*
CPRs
Total 4,431,415.59 67,476,200.00 84,580,902.00 1,148,741.00 160,051,654.60
CPR = common property resources, R&R = resettlement and rehabilitation.
*One thatched room could not be paid for as the owner remained absent after multiple efforts to locate them,
including the PIU's notice in the local newspaper.
Sources: The project implementation units of Assam, Manipur, Mizoram, and Tripura states.
Indigenous Peoples’
Total of Affected Households
Affected Households
State Non- Total Affected
Titleholders Total No.
Titleholders Households/State (%)
Mizoram 110 153 253 251 98.91
Tripura 0 14 14 0 0
Total 133 613 736 364 49.45
5. IPs were considered vulnerable under the project, and additional assistance provisions
were made under the RIPPs. In addition to the compensation at replacement cost for the
affected assets, the project provided additional assistance such as one-time lump sum financial
assistance, preference in project construction activity, and skills training following the RIPPs.
The project disclosed information, and consultations were held with the IP communities
throughout the project life.
7. Consultations and grievance redress. The project held consultations during its lifetime
and disclosed the safeguards documents to the stakeholders. Adequate care was taken to
include the women and other vulnerable groups in the consultation process. Each project
established a grievance redressal committee (GRC) to address the concerns of the local
communities and displaced persons, considering the local requirements. The GRC was made
functional and facilitated the resolution of the grievances referred. The GRC mechanism
adopted in the project was effective and conducted meetings whenever required and resolved
the grievances. Efforts were made to resolve issues at the PIU level and were generally
redressed within the time frame recommended in RIPPs. The projects received a few
grievances related to compensation amount, which were resolved amicably. The grievances of
IPs were no different from the others. The PIU bore all the costs incurred in resolving the
complaints. The recommendation of GRC for the payment of compensation was complied with,
and no outstanding issues are pending in the project.
8. Monitoring. Each state regularly submitted social monitoring reports (SMR) with initial
delays. The project states submitted a total of 41 SMRs. Out of 41 SMRs, 10 each by Assam,
Manipur, Tripura, and 11 by Mizoram were submitted and disclosed on ADB website. A due
diligence report was also prepared for a project road in Manipur and was disclosed. The SMRs
confirmed that RIPPs were implemented adequately and satisfactorily. The PMC functioned as
an external monitor for the project, and after the PMC, the PMU reviewed the reports prepared
by the PIUs. At completion, the project categorization remained unchanged for IR and IP.
44 Appendix 11
9. Challenges and lessons. The project was completed successfully, and the suggestions
and guidance provided by the missions from time to time to the project authorities were followed
and implemented. The social safeguards implementation was satisfactory. However, a few
challenges and lessons learned during the implementation are (i) the roads were spread over
four states of northeast India, and covering all four states in one visit by ADB staff was not
possible due to logistical challenges; (ii) the northeast EAs were exposed to ADB safeguards
requirements for the first time, and the capacity was low and different for each PIU; (iii)
availability of local experts in social safeguards was virtually none existent, and experts from
other parts of India were not very committed and proactive in supporting the PIUs. In the future,
multi-state road projects should be avoided as far as possible, enhancing local capacity in
safeguards management through training and preference in engagement in the project and
provision of the junior social expert in the CSC team with long-term inputs rather than
intermittent inputs of a highly experienced expert are a few suggestions to improve safeguards
management.
10. The project was classified as category B for environment in conformance with ADB’s
Safeguard Policy Statement (SPS) (2009) and remained the same until the completion of the
project. During processing of the investment program, an environmental assessment and review
framework was prepared and disclosed on ADB’s website in 2010 to guide and assessment of
the environmental aspects of activities undertaken within the project including the preparation of
initial environmental examinations (IEE) reports during processing of subsequent tranches
under the MFF. At appraisal of project 2, four initial environmental examination reports (one
each for Assam, Manipur, Mizoram, and Tripura) covering all six subprojects under project 2
were prepared and disclosed on ADB’s website in February 2013. The standard operating
procedure (SOP) pertaining to health and safety plan in response to COVID-19 pandemic, as an
addendum to IEE reports were also prepared, cleared, and disclosed on ADB website in June
2020.
11. The IEE reports indicate that the environmental impact would mostly occur during
construction because of carriageway widening, compaction works, quarrying and borrow-area
activities, but no permanent environmental impacts were envisaged. The necessary budget for
implementation of mitigation measures was included in the approved costs of subprojects. The
various aspects associated with implementation of environmental safeguards have been
detailed below:
12. Statutory environmental compliance. The requisite environmental clearances from the
Ministry of Environment, Forest and Climate Change of Assam and Manipur were received by
respective PWDs of above two states for three subprojects4 under the project. The proposed
works were not located (i) inside or near any designated core, or eco-sensitive areas of national
parks, sanctuaries, and biosphere reserves; or any other ecologically/environmentally sensitive
areas; and (ii) there were no rare, threatened, and endangered species (flora and fauna) within
the project areas. A total of 10.55 ha of forest land and 8,285 trees (for 210 trees in Assam,
7,461 trees in Manipur, 184 trees in Mizoram, and 430 trees in Tripura) were affected. The
requisite forest clearance,5 tree-cutting permissions, no objection certificates were also obtained
4
The ECs were obtained for (i) Tamulpur to Udalgiri (AS02 &03) road section in the state of Assam; and (ii) MN
CW1&2: Tupul to Bishnupur and Thoubal to Kasom Khullen in the state of Manipur. ECs were not required for road
section in Mizoram and the road section in Tripura.
5 Forest clearance for the diversion of 9.55 ha land was obtained for the road section in Manipur state, and 0.99 ha
land was obtained for a road section in Mizoram state.
Appendix 11 45
from the regulatory agencies by the respective PWDs of Assam, Manipur, Mizoram, and Tripura
under the project. The work in forest areas commenced only after obtaining the requisite
permissions. The implementation of the project got delayed in some of the states, due to delay
in obtaining the requisite forest clearances. Further, to accomplish the compensatory
afforestation (in 1:2 ratio), the respective PIUs executed an agreement with the State’s Forest
departments for tree plantation over next 5 years under the project. The compensatory
plantation of 18,8866 trees were planted under the project. The respective contractors from all
four states responsible for different subprojects obtained all requisite permissions/consents
/license (for construction plants, materials, labor license, etc., used) in compliance with
environmental regulations of the country. Further, the renewal of the permissions/consents/
license was also ensured by the respective PWDs until the closure of the project.
13. Institutional arrangements. The environment and social safeguards cell (ESSC) were
established by the respective PWDs (Assam, Manipur, Mizoram, and Tripura) to look after the
implementation, supervision, and monitoring of environmental safeguards measures associated
with the subprojects. The ESSC consists of key officials and support staff of respective PWDs.
An executive engineer rank officer was made as nodal officer by the Manipur and Tripura state
PWDs. A junior engineer was assigned to look after the implementation of the environmental
issues by the Assam and Mizoram states PWD within the PIU. The ESSC were tasked to
coordinate environmental management including implementation of the environment
management plan. An environment specialist of the CSCs, on an intermittent basis, supported
the respective PIUs in the implementation of the ADB-cleared environmental management plans
under the project. In all states throughout the project period, the CSC supported environment
safeguards implementation. All civil works contractors were made to designate one
environment, health and safety officer for implementation and coordination purposes.
6 Compensatory plantation of 18,886 trees, such as (i) 840 trees in the state of Assam; (ii) 14,916 trees in the state of
Manipur; (iii) 1,840 trees in the state of Mizoram; and (iv)1,290 trees in Tripura were carried out (which is higher
than the required number as provided) under the project.
46 Appendix 11
states) were submitted by the respective executing agencies and cleared and disclosed on ADB
website.7
17. Status of compliance with environmental loan covenants. The loan covenants
pertaining to environmental safeguards were complied with. The status of loan covenants is
presented in Appendix 12.
7
https://www.adb.org/projects/37143-033/main
Appendix 12 47
1. The Asian Development Bank (ADB) project completion report (PCR) team
conducted an economic reevaluation of the project 2 using a methodology similar to the one
used at appraisal with updated data. The “without” project scenario assumed that the
original state of the roads would be retained. The “with” project scenario considered the
improvement of the roads carried out under the project enabling vehicles to move faster
with lower operating costs and reduced travel time. Economic benefits of project 2 were
calculated by comparing the “with” and “without” project scenarios. The project 2 economic
internal rate of return (EIRR) was calculated and subjected to a sensitivity test.
B. Economic Rationale
2. Improvements from the project will generate job opportunities and lead to the
development of economic activities in the project region (Appendix 14). Road improvement
and its contribution to economic development activities is a natural consequence. With the
slow growth performance of the state governments under the past five-year plans, the
Government of India renewed its recognition that inadequate road networks were the major
constraints to the development efforts and, thus started a national investment program to
improve road connectivity to remote regions, including the northeastern region (NER). The
multitranche financing facility (MFF) investments complement the Special Accelerated Road
Development Program in the Northeastern Region (SARDP-NE), with roads under tranches
1 and 2, linking the state capitals and districts. The investments also enhanced the capacity
of the executing agencies, including the Public Works Department (PWD) staff, in project
preparation and road asset management best practices.
(i) The economic evaluation of the proposed project was undertaken using the Highway
Development Model 4 (HDM-4). The costs to the road agency and road users in the
“without” and “with” project cases were estimated and used for deriving the net costs
and benefits with the project and to calculate the economic viability of the project road
sections.
(ii) The life of roads was taken as the improvement period followed by 20 years of
operation.
(iii) All costs and benefits are expressed in Indian rupees (₹) at 2021 constant prices.
4. The project consists of six secondary roads spread in three North Eastern states. All
roads are single to intermediate-lane carriageways having a carriageway varies between
3.0 meters (m) and 5.5 m. The majority of the project road sections were in poor condition.
Most of the project road sections failed due to poor pavement structure, lack of adequate
maintenance, and heavy traffic loading. The project roads serve many villages where
agriculture is the main economic activity. All roads were upgraded to the standard width, as
per India Road Congress (IRC) norms, with geometric improvements as stipulated in the
detailed project report (DPR). The project roads are improved and/or upgraded to 5.5–7.0 m
carriageway with earthen shoulder of 2.5 m on either side (considered as “with project”
scenario). The details are presented in Table A13.1.
1
Guidelines for the Economic Analysis of Projects (2017); Guidelines for the Economic Analysis of Projects
(1997)
Appendix 13 79
Table A13.1: List of Project Road Sections and Base Year (2011) Characteristics
6. Review of historical data. Earlier traffic surveys were carried out in 2011 at the
DPR stage, which was subsequently used, as secondary data at project appraisal stage.
The current traffic data in 2021, after the construction of roads, were collected from five
roads at the project completion report (PCR) stage. The traffic counts for five vehicle types
were collected, including passenger car and/or van, bus, two-wheelers, and two categories
of freight trucks, including light commercial vehicle (LCV), two-axle and three-axle trucks.
7. Comparison of overall traffic growth. For comparison purpose, the baseline data
of 2011 and the 2021 post-construction data of each of the project road were compiled and
summarized in Table A13.2.
8. By comparing the traffic count of motorized vehicles (annual average daily traffic
[AADT] in numbers), it is observed that the annual traffic growth rates vary from 8.7% to
10.3% per annum. By studying the traffic’s composition, it is observed that cars account for
31% and two-wheelers account for 42%, thus, comprising 73% of the total traffic on the
80 Appendix 13
project roads. All other types of vehicles (buses, trucks, three-wheelers and tractors, etc.)
are comprises to 26% . The traffic growth by vehicle category is discussed below.
9. Past trend of vehicle registration. The compound annual growth rate (CAGR) by
type of the registered vehicles in each of the investment program states is presented in
Table A13.3.
10. At appraisal stage, the traffic growth rates for passenger and goods traffic were
calculated based on time-series data on traffic volume on the project roads and on the
state’s gross domestic product (GDP) growth forecast. Hence, the aggregate/uniform
growth rate for each category of vehicle was applied for all road sections located in three
states. The adopted growth rate at appraisal stage is presented below:
Traffic growth rates of 8% for passenger traffic; and 10% for freight traffic.
Higher growth rate of 15% was assumed for the opening year, being a diverted
traffic.
Generated traffic after road opening is assumed to be 10% of normal traffic.
11. At PCR stage, the growth rates were calculated based on time-series data, the
CAGR derived from the survey data (secondary traffic data, based on classified traffic
volume count along the project roads during the DPR [2011] and at the PCR stage post-
construction, 2021). The adopted growth rates for each road, under the vehicle category, is
summarized in Table A13.4.
12. At appraisal, while carrying out economic analysis, the provision of generated traffic
of 10% of normal traffic in 2012 was considered (after completion of road improvement
works). However, at PCR, no generated traffic has been considered, presuming the traffic
of 2021, based on post-construction traffic volume data, has already taken the
enhancement of traffic due to generated traffic. It is pertinent to mention that project roads
significantly completed the upgrading works in the first 4 years (2016–2020) and better
Appendix 13 81
facility was made available to the commuter. Further, the traffic growth rates are reduced by
0.5% every 5 years in the analysis for each vehicle category in the analysis period.
13. As per the detailed design report, all roads were proposed for reconstruction,
rehabilitation and/or upgrading to have adequate pavement composition for the horizon
period and a standard intermediate and/or double-lane width as proposed in the contract
documents. Construction cost was taken from the actual expenditure incurred for each
respective contract. Comparing with the total cost estimation (₹9,345.8 million) at appraisal,
the actual project cost (₹11,549.6 million) was 32.6% higher. The summary is given in Table
A13.5a.
14. The analysis used the domestic price numeraire. Economic cost was assessed by
applying the estimated conversion factor (0.89) using updated shadow wage rate factor
(SWRF) of 0.782 and shadow exchange rate factor (SERF) of 1.043 applicable to respective
components of financial cost. At appraisal, financial costs were converted to economic
costs using the conversion factor of 0.85 and presented in Table A13.5b.
2 SERF applied for traded component was 1.04; estimated based on imports, exports, and custom duties data for the period
2016–2020 (https://wits.worldbank.org); calculated based on ERD Technical Note Series No. 11 (http://www.adb.org/
Economics).
3
SWRF applied for unskilled labor was 0.78; estimated based on wage rate provided by notification issued by the Labor
Welfare Department, Government of Assam.
82 Appendix 13
15. The duration of construction was as per the actual construction period for each
contract. By project completion, the construction duration was varying from 50–60 months
between 2015 and 2020. The actual cost for each year was used in the reevaluation.
Maintenance Costs
16. The cost of routine maintenance was taken as per prevailing market rates in the
state of Assam, Manipur, Mizoram, and Tripura. The cost of periodic maintenance was
derived from the quoted rate of the bidder. The routine and periodic maintenance, used in
the HDM-4 model, are summarized in Table A13.6.
F. Maintenance Strategy
17. The “without-project” scenario was also proposed with routine maintenance due to
the deteriorated condition of the roadway and to carry out necessary activities like cleaning
of earth drains and longitudinal drains more frequently and rigorously. The project roads
significantly completed the upgrading works in the first 3 years (2017–2019) and better
facility was made available to the commuter. However, work on other activities, like road
marking, signages, protection works, and others, continued up to 2020.
G. Project Benefits
18. The motorized (MT) and nonmotorized (NMT) savings in vehicle operating costs and
passenger travel time costs were considered as direct benefits due to the project and are
considered in the current analysis.
19. The value of travel time for passenger vehicles was estimated based on the wage
rates and income distribution in each state. Value of time for a bus passenger was
calculated from agricultural labor wage and skilled labor wage presented in Table A13.7.
The income share distribution in India indicates that the top 20% of the population has a
44.4% share of income, the next 20% of the population has 20.5% share of the income and
the lowest 60% of the population has an income share of 35.1%. Assuming that these
groups represent the car, two-wheeler and bus users, the per capita income index of car,
two-wheeler, and bus users is 2.22 (44.4/20), 1.025 (20.5/20) and 0.585 (35.1/60) or two-
wheeler and car passenger time may be valued at 1.7 and 3.5 times the bus passenger
value of time.
Appendix 13 83
Source: Consultant’s estimate based on the wage rate data from the Ministry of Labor and Employment,
Government of India and “Manual on Economic Evaluation of Highway Projects in India (IRC: SP30-
2019).”
20. The value of time of two-wheeler and car passengers, thus estimated, is given in
Table A13.8. The value of nonworking time is taken as 25% of the working time.
21. Passenger travel time cost savings were recalculated for different types of
passenger vehicles (car, jeep, taxi, two-wheeler, and bus). To estimate time cost savings,
the unit value of time for passengers and cargo, and other factors were included, as follows:
(i) average vehicle loads; (ii) percentage of work-related trips; (iii) time costs by different
road users; and (iv) travel speeds for different types of passenger vehicles, which were
taken from the IRC: SP30-2019: Manual on Economic Evaluation of Highway Projects in
India. Since most of the roads are intermediate lanes and/or narrow two-lanes, the
considerable increase in traffic movement is expected as a result of improved road
conditions and the resulting development activities. As the volume of nonmotorized traffic is
negligible, accordingly, thus any savings/benefits for such traffic have not been
considered. The improvement of rural roads to connect with urban centers is necessary so
that income generation and wider commodity and service circulation take place in
rural areas. The additional benefits provided by upgraded roads to these habitations
include health, education, agriculture, poverty reduction, safer movement of traffic, and
others, which have not been considered in the analysis.
22. Due to improved road condition, vehicles can now be driven faster than before the
project, leading to substantial economic benefits in the project areas. The value of work
time and leisure time were given separately an hourly wage, as a required input of HDM
84 Appendix 13
(per hour rate for passenger working time and passenger nonworking time). For each
contract package, the vehicle operating cost (VOC) per vehicle-km was computed for each
class of vehicle, using input values for the economic costs of a new vehicle, tire, fuel,
lubricants, and maintenance labor. The value of the respective inputs was taken from the
IRC: SP:30-2019. The VOC savings per vehicle-km were estimated for project roads—from
narrow width to standard configuration with standard geometry and rehabilitation. The
summary of savings in VOC is presented in Table A13.9.
23. Based on the assumptions and parameters above, the EIRRs were calculated for all
project roads, with their respective traffic growth rate and cost for a horizon period starting
from the construction period with 20 years of operation period. As a whole (aggregate as a
northeastern states network), the reevaluated EIRR for the six roads is 15.3%. The
reevaluated EIRRs for the four packages are given in Table A13.10.
24. At the disaggregated level, economic analysis was carried out for six roads. All
roads yielded an EIRR that is more than 12%. The reevaluated EIRR for six roads ranges
from 14.5 to 19.0. The project is considered economically viable. The costs and benefit
streams for the aggregate total of the six project roads over the full evaluation period are
shown in Table A13.13.
25. The EIRR was subjected to a sensitivity analysis to test different scenarios of
maintenance costs and benefits, as carried out at appraisal. The results indicated that the
project will continue to be economically viable for all scenarios except for one option. If a
20% maintenance cost increase would be combined with a 20% benefit reduction, the EIRR
would be still 12.9% for the whole project. The sensitivity analysis confirmed that the project
has a robust economic viability. It also showed that the EIRR was more sensitive to
changes in economic benefits. The results of the sensitivity analysis are shown in Table
A13.11.
Appendix 13 85
26. Overall, the EIRR of the investment program of all the states was not calculated at
appraisal. The reevaluation of project 1 has already been completed and presented in the
PCR in September 2023. The reevaluation of project 2 is presented above. The results of
the economic analysis for the two projects of the MFF are presented in Table A13.12.
27. The overall EIRR for the investment program at completion was estimated at 15.8%
which is above the discount rate of 12%. The detailed cash flows of the EIRR calculations
for the project as well as each state is presented in Table A13.14.
86 Appendix 13
Table A13.13: Cost and Benefit Streams for Consolidated Project 2 Roads
(₹ million)
Year Capital Recurrent VOC Time Net Benefits
Table A13.14: Cost and Benefit Streams for the Multitranche Financing Facility
(₹ million)
Year Capital Recurrent VOC Time Net Benefits
2012 0.00 -8.65 0.00 0.00 8.65
2013 98.11 -8.65 0.00 0.00 -89.46
2014 226.08 -8.65 0.00 0.00 -217.43
2015 127.97 -8.65 0.00 0.00 -119.32
2016 2,056.18 -20.99 0.00 0.00 -2,035.19
2017 2,367.63 -20.99 9.65 -0.02 -2,337.02
2018 2,973.42 -27.75 55.39 1.29 -2,888.99
2019 3,950.38 -22.12 151.23 11.16 -3,765.88
2020 4,091.09 -20.99 280.60 51.10 -3,738.41
2021 183.43 -5.13 1,138.22 803.67 1,763.59
2022 136.50 -5.13 1,232.83 875.91 1,977.36
2023 0.00 -5.13 1,332.32 956.48 2,293.93
2024 0.00 -5.13 1,438.47 1,045.68 2,489.28
2025 0.00 1,095.97 1,553.00 1,144.83 1,601.86
2026 0.00 -5.13 1,785.70 1,253.76 3,044.60
2027 0.00 -5.13 1,941.71 1,374.24 3,321.07
2028 0.00 -5.13 2,113.39 1,515.59 3,634.11
2029 0.00 -5.13 2,312.00 1,682.89 4,000.01
2030 0.00 1,095.97 2,546.87 1,884.53 3,335.42
2031 0.00 -5.13 2,987.46 2,122.77 5,115.36
2032 0.00 -5.13 3,308.12 2,385.45 5,698.70
2033 0.00 -5.13 3,666.00 2,691.85 6,362.98
2034 0.00 -5.13 3,989.71 2,980.92 6,975.76
2035 0.00 1,096.03 4,343.44 3,313.66 6,561.06
2036 0.00 -5.13 5,044.30 3,720.43 8,769.86
2037 0.00 -5.13 5,466.46 4,081.59 9,553.18
2038 0.00 -5.13 5,962.90 4,515.53 10,483.56
2039 0.00 -5.13 6,243.50 4,691.17 10,939.80
2040 -753.38 -4.87 6,466.97 4,895.61 12,120.83
EIRR 15.8%
NPV 3,300.05
EIRR = economic internal rate of return, NPV = net present value, VOC = vehicle operating cost.
Source: The highway design manual (HDM)-generated reports of the project completion report team.
J. Sustainability Analysis
28. The project will not generate revenue. In accordance with ADB guidelines, 4 the
financial sustainability of the project was assessed by considering the recurrent costs to be
assumed by the Assam, Manipur, Mizoram, and Tripura states (Table A13.6).
29. The sustainability of the project was evaluated by assessing the historical
expenditure allocated to all activities of the PWD by the Assam, Manipur, Mizoram, and
4 Financial Analysis and Evaluation, Technical Guidance Note (2019); Financial Due Diligence, A Methodology
Note (2009); and Financial Management and Analysis of Projects (the Guidelines, 2005).
88 Appendix 13
Tripura states, which includes repair and maintenance. Table A13.15 summarizes the four
states PWD’s total expenditure since FY2018.
Appendix 13 89
Source: The Public Works Departments of the four states; and their historical maintenance expenditures.
30. From Table A13.15, the four states’ PWDs expenditure for road maintenance has been relatively constant from FY2018 to
FY2022. To maintain the roads in good condition, PWDs found the expenditure incurred in the last 5 years consistent and sufficient.
The state governments are also committed to a sustainable road maintenance by adopting efficient contracting modes, such as the
engineering procurement and construction (EPC), and the build–operate–transfer (BOT) where performance-based maintenance is
built in the contract. The four states’ PWD’s assessment of the yearly maintenance budget requirement and expenditure is on a
need basis or according to the actual ground requirements. Ground requirements cover the estimation for routine, recurrent,
specific, periodic, and emergency maintenance.
90 Appendix 14
1. According to the 2011 census, the total population of North Eastern states was 45
million, the population density was 174 per square kilometer. The per capita income of the
Assam, Manipur, and Tripura is lower than India, whereas Mizoram is on the higher side.1 The
economy of the region is largely agrarian in nature with over 70% of the population engaged in
agriculture for livelihood, service sector comes next, and the manufacturing sector is still at a
nascent stage. However, the region is an emerging market of 400 million people, including the
neighboring nations of Bangladesh, Myanmar, Bhutan, and Nepal. The region has hydropower
potential estimated at nearly 50,000 MW, natural gas reserves of 190 billion cubic meters, coal
reserves of over 900 million tons, and oil reserves of over 500 million tons. Large mineral
resources, including limestone reserves of around 5000 million tons and a forest cover that is
25% of the country’s forest area. Apart from above, and due to its strategic location, there were
numerous development activities initiated by the Government of India. The Prime Minister’s
Development Initiative for NorthEast (PM-DevINE) will be implemented through the North-
Eastern Council, which will boost the economy of the region.
2. Roads comprise the predominant mode of transport services in the state because of its
topography. Major initiatives for road development in recent years is going to substantially
benefit all sectors, including agriculture, mining, tourism, education, and heath care. As of
2017–2018, the total length of the roads in the NER was 573,983 kilometers (km), including
13,640 km of national highways, 20,138 km of state highways, 39,425 km of major district
roads, 9,406 km of urban roads, and remaining rural roads. Under the SARDP-NE, about 8,000
km of national highways and state roads are proposed for development.
3. At project 2 completion, 235.79 km of roads of six road sections were rehabilitated and
improved by widening and/or strengthening in three project states. The three outcome indicators
were achieved, as follows: (i) actual growth rates of traffic on the project and connector roads
was 9.89 %, which surpassed the assumed growth rate of 9%; (ii) vehicle operating cost on the
project roads reduced by 53% for three-axle trucks, and by 41% for passenger buses at
completion; and (iii) travel time on the project roads reduced by more than 50%.
4. Agricultural and land development. Land prices along the project roads have
escalated by an average of 43% (Table A14) due to improved roads, and this trend is
continuing. Prior to the road improvements, the region was not considered very attractive for
economic activities. Improved roads are giving farmers access to better and larger markets and
higher profit margins. Improved access is also helping local youth remain in rural areas, thus,
contributing to the rise in agricultural land prices. These factors have contributed to the
appreciation of land prices.
5. Access to market and social services. With the improved road conditions, agricultural
traffic increased. After the project, farmers could travel easily to larger and distant markets. This
2
Government of India, Niti Ayog. 2021. National Multidimensional Poverty Index. New Delhi.
Appendix 14 91
stimulated the development of local transport services. Adequate passenger transport services,
primarily minibuses and large jeeps, are operating. The bus service frequency has increased
on most of the project roads. Time taken to the nearest health center was reduced to less than
30 minutes on the project roads. The connectivity to various social and other service centers
has improved substantially, such as for education, banking services, and grain markets.
Noteworthy impacts include the following:
(i) Students, including girls, are able to travel to larger towns for higher education.
(ii) Villagers can access better health facilities in larger centers and doctors are now more
willing to visit and treat patients in the rural areas.
(iii) Access to banks and rural financial institutions have improved.
(iv) Farmers can travel to larger markets at greater distance to obtain better prices for their
produce.
(v) The rural community is better informed about market conditions and other matters.
6. Household income and poverty reduction. Surveys carried out after project
completion indicate that incomes of rural households increased by an average of 62%. The
higher incomes were mainly the result of commercial activities along the project roads with
increase in roadside businesses of hotels and/or dhabas, shops, and garages and/or workshops
due to increased traffic number. Many local laborers were hired by the project during its
implementation. The use of local construction materials and services helped to increase the
incomes of residents. These opportunities particularly helped those living below the poverty line.
These positive impacts on the socioeconomic development of the project area are expected to
be sustained.
8. Road safety. Mandatory cautionary and information road signs were installed along the
project roads. Blind spots on road sections were given special attention during design and
implementation of the project. Shoulder improvements, culvert and bridge construction,
structural repairs, and other improvements contributed to safer road travel. Improved road
safety measures helped to reduce traffic congestion, especially during the rainy season.
However, some of the vehicles tend to exceed the speed limit due to the improved road
condition. Many pedestrians and mixed traffic of motorcycles, nonmotorized vehicles, and
animal-driven carts are on the project roads, especially in residential areas. The PIUs, in
coordination with the local police provided additional safety measures like speed limit,
pedestrian crossing signs and markings, and fines for speed limit violators to address increased
traffic speed, which made it difficult for women and children to cross the roads.
92 Appendix 14
Commercia
Househo Acci-
Land Value l Land Time to Time to Time to Hotel/ Garage/
Con-tract IRI mm/km Poverty ld In- Shop dents
Name of Road (₹ lac/ ha) Value (₹ Health Major District Dhaba Workshop
Pac-kage (Before/ After) Reduced come (In- (Increase) Redu-
(Increase) million/ ha) Center Hospital Hospital (Increase) (Increase)
crease) ced
(Increase)
AS-02 Tamulpur to Paneri 43% 68% 7,900/ 2,500 54% 54% 69% -21% 58% 114% 73% 143% -78%
AS-03 Paneri to Udalguri 53% 63% 8,200/ 2,800 56% 52% 70% -24% 58% 118% 63% 167% -56%
MN06-CW1 Tupul to Bishnupur 46% 80% 9,800/ 2,710 48% 60% 69% -22% 59% 80% 125% 150% -74%
Thoubal to Kasom
MN06-CW2 43% 73% 9,300/ 2,760 54% 64% 70% -21% 59% 103% 79% 80% -74%
khullen
Serchhip to Buarpui
MZ 46% 75% 6,200/ 2,750 33% 61% 58% -37% 78% 60% 44% 50% -65%
Road, Mizoram
TP Udaipur to Melaghar 27% 80% 9,750/ 2,700 69% 60% 69% -29% 62% 80% 125% 150% -74%
Average 43% 73% 8,525/ 2,703 52% 59% 67% -26% 62% 93% 85% 123% -70%
₹ = Indian rupee, ha = hectare.
Sources: The project implementation units of Assam, Manipur, Mizoram, and Tripura states.
Appendix 15 93
6.1.1 Government officials with Improved PWDs staff were Achieved. Under the
increased capacity to capacity of trained for one or more project, various training
design, implement, PWDs staff areas of road design programs were conducted
monitor, and evaluate and construction to improve the capacity of
number in
relevant measures. management, road the PWDs’ staff in the
(number) relevant safety, and essential areas of road design and
areas. knowledge of climate- construction management,
resilient design of road safety, and on
roads. essential knowledge on
climate-resilient road
designs.