PDM-MS Project-Setup V4 en
PDM-MS Project-Setup V4 en
Station V4 – Quick
Setup
Siemens
SIMATIC PDM Maintenance Station V4 Industry
Online
https://support.industry.siemens.com/cs/ww/en/view/109810636 Support
Legal information
Legal information
Use of application examples
Application examples illustrate the solution of automation tasks through an interaction of several components in
the form of text, graphics and/or software modules. The application examples are a free service by Siemens AG
and/or a subsidiary of Siemens AG ("Siemens"). They are non-binding and make no claim to completeness or
functionality regarding configuration and equipment. The application examples merely offer help with typical
tasks; they do not constitute customer-specific solutions. You yourself are responsible for the proper and safe
operation of the products in accordance with applicable regulations and must also check the function of the
respective application example and customize it for your system.
Siemens grants you the non-exclusive, non-sublicensable and non-transferable right to have the application
examples used by technically trained personnel. Any change to the application examples is your responsibility.
Sharing the application examples with third parties or copying the application examples or excerpts thereof is
permitted only in combination with your own products. The application examples are not required to undergo the
customary tests and quality inspections of a chargeable product; they may have functional and performance
defects as well as errors. It is your responsibility to use them in such a manner that any malfunctions that may
occur do not result in property damage or injury to persons.
Disclaimer of liability
Siemens shall not assume any liability, for any legal reason whatsoever, including, without limitation, liability for
the usability, availability, completeness and freedom from defects of the application examples as well as for
related information, configuration and performance data and any damage caused thereby. This shall not apply in
cases of mandatory liability, for example under the German Product Liability Act, or in cases of intent, gross
negligence, or culpable loss of life, bodily injury or damage to health, non-compliance with a guarantee,
fraudulent non-disclosure of a defect, or culpable breach of material contractual obligations. Claims for damages
arising from a breach of material contractual obligations shall however be limited to the foreseeable damage
typical of the type of agreement, unless liability arises from intent or gross negligence or is based on loss of life,
bodily injury or damage to health. The foregoing provisions do not imply any change in the burden of proof to
your detriment. You shall indemnify Siemens against existing or future claims of third parties in this connection
© Siemens AG 2022 All rights reserved
Other information
Siemens reserves the right to make changes to the application examples at any time without notice. In case of
discrepancies between the suggestions in the application examples and other Siemens publications such as
catalogs, the content of the other documentation shall have precedence.
The Siemens terms of use (https://support.industry.siemens.com) shall also apply.
Security information
Siemens provides products and solutions with Industrial Security functions that support the secure operation of
plants, systems, machines and networks.
In order to protect plants, systems, machines and networks against cyber threats, it is necessary to implement –
and continuously maintain – a holistic, state-of-the-art industrial security concept. Siemens’ products and
solutions constitute one element of such a concept.
Customers are responsible for preventing unauthorized access to their plants, systems, machines and networks.
Such systems, machines and components should only be connected to an enterprise network or the Internet if
and to the extent such a connection is necessary and only when appropriate security measures (e.g. firewalls
and/or network segmentation) are in place.
For additional information on industrial security measures that may be implemented, please visit
https://www.siemens.com/industrialsecurity.
Siemens’ products and solutions undergo continuous development to make them more secure. Siemens strongly
recommends that product updates are applied as soon as they are available and that the latest product versions
are used. Use of product versions that are no longer supported, and failure to apply the latest updates may
increase customer’s exposure to cyber threats.
To stay informed about product updates, subscribe to the Siemens Industrial Security RSS Feed at:
https://www.siemens.com/industrialsecurity.
Table of contents
Legal information .............................................................................................................................. 2
1 Overview .................................................................................................................................. 4
1.1 Introduction ................................................................................................................ 4
1.2 Components Used ..................................................................................................... 4
2 Installation of PDM MS V4 ...................................................................................................... 5
3 General Settings...................................................................................................................... 6
3.1 Ethernet Settings in Windows:................................................................................... 6
3.2 PDM Settings ............................................................................................................. 8
4 Project Setup ........................................................................................................................... 9
4.1 Project Setup with Example Project .......................................................................... 9
4.2 New Project Setup ...................................................................................................10
4.3 Hardware Configuration (HW-Config) of the PC Station .........................................10
4.4 Hardware Configuration of the PLC.........................................................................13
5 Creating the PDM Network Structure ..................................................................................14
5.1 Basic Network Settings ............................................................................................14
© Siemens AG 2022 All rights reserved
5.2 Import or Manual Creation of the PDM Data for the Devices ..................................16
6 Engineering Steps for the Maintenance Station ................................................................17
7 Overview of Steps for Changing the Project ......................................................................22
8 Appendix ................................................................................................................................24
8.1 Service and support .................................................................................................24
8.2 Industry Mall ............................................................................................................25
8.3 Links and literature ..................................................................................................25
8.4 Change documentation ...........................................................................................25
1 Overview
1.1 Introduction
This document describes the changes for the successor versions, the PDM Maintenance
Station V4.0 or V4.0.1.
The setup for the PDM Maintenance Station V3.0 is described in the application example “PDM
Maintenance Station - Setting up a Project”. Also, the configurations are described in section 3
in this document and many configuration steps are the same. The application example can be
found under the following link:
https://support.industry.siemens.com/cs/us/en/view/109776936
The PDM MS V4.x can be used in the same way as the V3.
With the PDM MS V4, up to 1000 field devices can be monitored; with the PDM MS V3, it is only
a maximum of 500 field devices.
Major changes in the software are the easier handling of changes in the monitored plant project
through many improvements and enhancements in the "Import from HWC station" function.
There is a third option for exporting parameter data with selectable parameters that can be read
online (faster than reading all parameters online).
The PDM MS V4 is based on Windows 10 Enterprise 2019 LTSC (instead of Windows 7
Ultimate 32-bit).
There is no extra installation setup like for the PDM MS V3. The PDM MS V4 software is
installed directly from the PCS 7 Media Package.
© Siemens AG 2022 All rights reserved
The PDM MS V2 contained an IPC 427E with 4GB and the PDM MS V3 contained 8GB main
memory.
PDM MS V4 can in principle be used with the same hardware, but for an update to PDM MS
V4.x, 16GB main memory is recommended, especially for large projects.
Instead of the internal Soft-PLC WinAC RTX 2010 controller, the SIMIT Virtual Controller,
including a dongle for it, is used.
Table 1-1
Product Product ID/ Download link
PDM MAINTENANCE 6ES7650-0RJ04-0YX0
STATION BASIC V4.0
SIMATIC PDM, HART 6ES7658-3EX78-2YB5
SERVER V9.2
(optional)
SIMATIC PDM Device Download
Library 1#2021 https://support.industry.siemens.com/cs/ww/en/view/109805356
PDM 1 CLIENT 6ES7658-3UA00-2YB5
(optional)
PDM 10/100/1000 6ES7658-3XC00-2YB5
TAGs (optional) 6ES7658-3XD00-2YB5
6ES7658-3XE00-2YH5
2 Installation of PDM MS V4
To install the operating system, proceed as follows:
1. Install the new operating system Windows 10 Enterprise 2019 LTSC from the restore stick.
Select either “Restore System-Partition (Windows only)” or “Reset to delivery condition” in
the installation process.
2. Install the PDM MS software from the delivered stick or the PCS 7 Media Package:
Figure 2-1
© Siemens AG 2022 All rights reserved
3. Install the SIMIT Virtual Controller. You will find it below “Additional Products” in the folder
“SIMIT VC”:
Figure 2-2
In case of an update from PDM MS V4.0 to PDM MS V4.0 SP1, install the “old” SIMIT VC
NOTE from the PCS 7 V9.1 Media Package. Then you can use the existing license and dongle.
(There are no new functions with the newer SIMIT VC.)
3 General Settings
This section describes the general settings to be made in Windows and in the SIMATIC
Manager (after opening/creating the project).
1. Configure a suitable IP address and network mask in the Windows network properties.
Figure 3-1
© Siemens AG 2022 All rights reserved
Use LAN #02 or LAN #03 for the plant bus (can also be a direct connection to a PROFINET
network).
NOTE
LAN #01 can be used for an optional connection to a terminal bus.
Figure 3-2
© Siemens AG 2022 All rights reserved
Figure 3-3
© Siemens AG 2022 All rights reserved
Settings for the PDM MS in the plant hierarchy below “Advanced Diagnostic Settings…”
NOTE (export paths, web links, …) or the configuration of the PDM server (secure / unsecure
connection etc.) are the same as for the PCS 7 Maintenance Station.
4 Project Setup
Either use the example project or create a new project.
Figure 4-2
Figure 4-3
2. Change the name of the PC station according to your PDM MS computer name.
© Siemens AG 2022 All rights reserved
Figure 4-4
3. Configure the first IP address on the “IE General” tab of the PC station:
Figure 4-5
© Siemens AG 2022 All rights reserved
4. Only if SNMP devices (such as PCs, switches and other network objects) are to be
monitored in the PDM MS is it necessary for an OPC server to be inserted here and the
SNMP devices to be added and configured in the SNMP configuration of the OPC server.
5. Save and compile the HW-Config.
Figure 4-6
© Siemens AG 2022 All rights reserved
Figure 4-7
© Siemens AG 2022 All rights reserved
Figure 4-8
NOTE The first time a PC station is networked, the local computer name is added automatically.
Figure 5-1
4. Navigate to the Ethernet settings (for the PC station), select “Use network adapter” and any
© Siemens AG 2022 All rights reserved
Figure 5-2
Figure 5-3
Figure 5-4
5.2 Import or Manual Creation of the PDM Data for the Devices
1. Follow the steps in section 8.3 for manual creation or section 8.4 for “Import from HWC
station” in the application example “PDM Maintenance Station – Setting up a project” under
the following link: https://support.industry.siemens.com/cs/us/en/view/109776936
2. The PDM network structure with all field devices has been created:
Figure 5-5
© Siemens AG 2022 All rights reserved
If all settings incl. subnet IDs are OK, the user can now communicate with the field devices
using the PDM MS, e.g. update the diagnostic status manually from the process device network
view.
To use the Maintenance Station Runtime, the SIMIT Virtual Controller must be started and the
Maintenance Station must be activated and configured.
Figure 6-1
3. To start the SIMIT VC, select "Options > Plant Hierarchy > Start Simit VC".
Figure 6-2
© Siemens AG 2022 All rights reserved
Figure 6-3
Figure 6-4
© Siemens AG 2022 All rights reserved
7. Activate the option “Maintenance Station PDM (no AS diagnostics)” in the menu of the plant
hierarchy settings.
Figure 6-5
© Siemens AG 2022 All rights reserved
Figure 6-6
Figure 6-7
Here, an "S7 connection" is used as with real controllers (not the "K-bus" as with PDM MS
© Siemens AG 2022 All rights reserved
NOTE V3).
Figure 6-8
© Siemens AG 2022 All rights reserved
Figure 6-9
Export PDM data to the ES project and import this export file
This is possible for single PLC controllers and from a node not higher than a bus system
(PROFIBUS or PROFINET) in the network view. At least the bus system must already be
inserted in the target project (with the correct subnet IDs).
Export either via process device network view or via Hardware Configurator. Import only via
process device network.
Export and import of an S7 / PCS 7 archive with PDM data (“Import from HWC station”)
A project with a PC and Ethernet bus (plant bus) must already be inserted in the target project in
the network view (with the correct subnet IDs).
Figure 7-1
© Siemens AG 2022 All rights reserved
Figure 7-2
© Siemens AG 2022 All rights reserved
The project network structure including all substructures and all field devices is always
configured in the process device network view (in the SIMATIC Manager of the PDM MS)!
Please note that a CFC editor or a HW configurator for any process periphery cannot be used
on a PDM MS. Compiling and downloading the chart folder is also necessary here, although
no CFC editor can be used!
NOTICE
Do not forget to restart SIMIT VC after restarting the PDM MS.
The CPU cannot be used as an AS with a program (CFCs etc.) on a PDM MS. The PDM MS
must always be connected to a plant with existing PROFIBUS DP masters, PROFINET IO
controllers or HART multiplexers!
8 Appendix
8.1 Service and support
Industry Online Support
Do you have any questions or need assistance?
Siemens Industry Online Support offers round the clock access to our entire service and support
know-how and portfolio.
The Industry Online Support is the central address for information about our products, solutions
and services.
Product information, manuals, downloads, FAQs, application examples and videos – all
information is accessible with just a few mouse clicks:
support.industry.siemens.com
Technical Support
The Technical Support of Siemens Industry provides you fast and competent support regarding
all technical queries with numerous tailor-made offers
– ranging from basic support to individual support contracts. Please send queries to Technical
Support via Web form:
siemens.com/SupportRequest
© Siemens AG 2022 All rights reserved
Service offer
Our range of services includes the following:
• Plant data services
• Spare parts services
• Repair services
• On-site and maintenance services
• Retrofitting and modernization services
• Service programs and contracts
You can find detailed information on our range of services in the service catalog web page:
support.industry.siemens.com/cs/sc
The Siemens Industry Mall is the platform on which the entire siemens Industry product portfolio
is accessible. From the selection of products to the order and the delivery tracking, the Industry
Mall enables the complete purchasing processing – directly and independently of time and
location:
mall.industry.siemens.com