Community B - B Outgoing

Uploaded by

infowireteks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

Community B - B Outgoing

Uploaded by

infowireteks
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROTECTION RELAY TEST RESULTS

CUSTOMER: LOCATION: NAOC OB_OB


SWITCHGEAR TYPE: INDOOR END USER: NAOC
FEEDER: COMMUNITY FEEDER B_B RELAY MANUFACTURER: ICE

RELAY DETAILS CURRENT TRANSFORMER RATIO


MODEL/TYPE:NP-F915-PL0BAAA-AAA OVERCURRENT = 500/1A
SERIAL NO. 2022013754 EARTHFAULT = 50/1A
DATE: 8TH - 15TH JULY, 2024

THREE PHASE OVERCURRENT - FIRST STAGE (I>)


Settings Measurement
Test 1
Pick up Current Injected Expected Trip Actual Trip
Start Value 0.62In Phase
(A) Current (A) Time (Sec) Time (Sec)
Time Dial 0.15 L1 0.62In 0.60In No trip No trip
Operating Extremely L2 0.62In 0.60In No trip No trip
Characteristics Inverse L3 0.62In 0.60In No trip No trip
Test 2
Start Value 0.62In L1 0.62In 0.80In 18.05 17.9
Time Dial 0.15 L2 0.62In 0.80In 18.05 17.9
Operating Extremely L3 0.62In 0.80In 18.05 17.9
Characteristics Inverse
Test 3
Start Value 0.62In L1 0.62In 1.0In 7.49 7.469
Time Dial 0.15 L2 0.62In 1.0In 7.49 7.469
Operating Extremely L3 0.62In 1.0In 7.49 7.469
Characteristics Inverse
Test 4
Start Value 0.62In L1 0.62In 1.2In 4.37 4.361
Time Dial 0.15 L2 0.62In 1.2In 4.37 4.361
Operating Extremely L3 0.62In 1.2In 4.37 4.361
Characteristics Inverse

THREE PHASE OVERCURRENT - SECOND STAGE (SHORT CIRCUIT) (I>>)


Settings Measurement
Pick up Current Injected Expected Trip Tripping
Start Value 5.0In Phase
(A) Current (A) Time (Sec) Time (Sec)
Time 80msec L1 5.0In 5.02In 80.0m 76.2m
Operating L2 5.0In 5.02In 80.0m 76.2m
Definite Time
Characteristics L3 5.0In 5.02In 80.0m 76.2m

EARTHFAULT - FIRST STAGE (I0>)


Settings Measurement
Pick up Current Expected Trip Actual Trip
Start Value 0.10In Phase Injected Current (A)
(A) Time (Sec) Time (Sec)
Time 80msec L1 0.10In 0.101In 80.0m 66.0m
Operating L2 0.10In 0.101In 80.0m 66.0m
Definite Time
Characteristics L3 0.10In 0.101In 80.0m 66.0m
EARTHFAULT - SECOND STAGE (I0>>)
Start Value 0.20In L1 0.20In 0.200In 80.0m 73.0m
Time 80msec L2 0.20In 0.200In 80.0m 73.0m
Operating L3 0.20In 0.200In 80.0m 73.0m
Definite Time
Characteristics

COMMENT:
Trip test was also conducted for the circuit breaker from the protection relay.
Earthfault first stage;
0.101In was injected and the CB tripped with the correct indication.
Earthfault second stage;
0.200In injected and the CB tripped with the correct indication.

Overcurrent first stage


0.80In was injected and the CB tripped with the correct indication.
Overcurrent short circuit
5.02In was injected and the CB tripped with the correct indication.

Test Carried out by: Witnessed by: