Jaw Ejv 0360 H P - Isat - Rev.0 - STR - 01 Mar 21 - Rev.0 (2) 1
Jaw Ejv 0360 H P - Isat - Rev.0 - STR - 01 Mar 21 - Rev.0 (2) 1
&
DESIGN DRAWING
Prepared By
GF SST 70 M
01 MAR 2021
Note :
CONTENT
1. ANALYSIS RESULT
2. CALCULATION ANALYSIS
CRITERIA
3. SUPPORTING DATA
5. STRENGTHEN TOWER
ANALYSIS
6. FOUNDATION ANALYSIS
7. DRAWING
SITE NAME : Diponegoro-
Sumberejo
SITE ID : JAW-EJV-0360-H-P
Tower Data
Antenna Loading
Antenna Type Quantity Dimension (mm) Elevation Direction
(magl)
Existing
RF HCPT 3 1980x320x80 + 59.00 065⁰ 160⁰ 255⁰
RRU HCPT 3 560x447x133 + 59.00 0⁰
MW HCPT 1 Ø 600 + 60.20 304.48⁰
MW HCPT 1 Ø 1200 + 58.50 254.57⁰
MW HCPT 1 Ø 1800 + 52.50 040⁰
MW HCPT 1 Ø 1800 + 47.00 280⁰
MW HCPT 1 Ø 1800 + 43.50 280.62⁰
MW HCPT 1 Ø 1800 + 42.30 270⁰
MW HCPT 1 Ø 300 + 41.00 065.7⁰
MW HCPT 1 Ø 600 + 40.00 063.19⁰
MW HCPT 1 Ø 600 + 36.50 070⁰
MW HCPT 1 Ø 600 + 35.00 257.89⁰
MW HCPT 1 Ø 900 + 35.00 129⁰
Proposed
RF ISAT 3 2750x399x199 + 68.50 000⁰ 120⁰ 240⁰
MW ISAT 9 400x300x100 + 68.50 000⁰
RRU ISAT 1 Ø 1200 + 68.50
Tension Compression
Fx (kN) Fy (kN) Fz (kN) Fx (kN) Fy (kN) Fz (kN)
Maximum Reaction
-62.823 0.413 653.365 76.419 -0.377 821.641
Conclusion
Tension Compression
Fx (kN) Fy (kN) Fz (kN) Fx (kN) Fy (kN) Fz (kN)
Maximum Reaction
-71.745 0.329 713.611 89.404 -0.287 927.661
Conclusion
Reza A.Y.
Project Manager / 27 Jan 2021
2. CALCULATION ANALYSIS CRITERIA
Diponegoro- Sumberejo 1 of 7
DESIGN CRITERIA
A. Design Standard
1. The design basis of the tower applied is EIA Standard EIA-222-F “Structural
Standards for Steel Antenna Tower and Antenna Supporting Structure. “ The
fabrication and materials of the tower will be according to the relevant
Indonesian Standard and/or Japanese Industrial Standard.
2. The self-supporting tower has triangle cross sections.
3. All the legs and bracings are made of equal angles steel.
4. All the connections in the field are made with steel bolts, each fitted with one
spring washer and nut.
B. Loading
1. Dead Load
Dead load is the dead weight of tower structure and all appurtenances such as
ladder, feeder, antenna, etc.
2. Wind Load
Wind load includes wind load acting on tower structure, appurtenances, antenna,
etc. Wind load is based on the 100-km/hour basic wind velocity. Wind load shall be
calculated in accordance with EIA-222-F.
Mt = fa x X + Fs x Y + M
Where :
Fa : Axial Load (lb)
Fs : Side Force (lb)
M : Twisting Moment (ft-lb)
Ca : Wind Load Coefficient
Cs : Wind Load Coefficient
Cm : Wind Load Coefficient
Ha : Wind Load Antenna (lb)
Mt : Total twisting Moment (ft-lb)
V : Wind Velocity (mph)
A : Normal projected area of antenna (ft2)
D : Antenna Diameter (ft)
X : The Offset of the Mounting pipe (ft)
Y : The distance on the reflector axis from the reflector vertex to
the center of the mounting pipe (ft)
Load combination
CL = DL + WL < 1.330
Where :
CL : Load Combination
DL : Dead weight of the structure and appurtenances.
WL : Design wind load on the structure, appurtenances, etc.
3. Antenna
Antenna attached in the tower is :
Antenna Loading
Antenna Type Quantity Dimension Elevation Direction
(mm) (magl)
Existing
RF HCPT 3 1980x320x80 + 59.00 065⁰ 160⁰ 255⁰
RRU HCPT 3 560x447x133 + 59.00 0⁰
MW HCPT 1 Ø 600 + 60.20 304.48⁰
MW HCPT 1 Ø 1200 + 58.50 254.57⁰
MW HCPT 1 Ø 1800 + 52.50 040⁰
MW HCPT 1 Ø 1800 + 47.00 280⁰
Diponegoro- Sumberejo 3 of 7
Proposed
RF ISAT 3 2750x399x199 + 68.50 000⁰ 120⁰ 240⁰
MW ISAT 9 400x300x100 + 68.50 000⁰
RRU ISAT 1 Ø 1200 + 68.50
4. Seismic Load
For the stress due to seismic load is smaller than stress due to wind load the
combination of dead load and seismic load shall not be taken into account.
C. Strength Assessment
value calculated for Fcr in ASCE Manual 52 divided by the yield stress of the
member.
Compression
• On the gross section of axially loaded compression members when KL/r is less
than C c
( KL / r ) 2
1 − 2 Fy
2C c
Fa =
5 3( KL / r ) ( KL / r ) 3
+ − 3
3 8C c 8C c
2π 2 E
Where Cc =
Fy
exceeds Cc
12π 2 E
Fa =
23( KL / r ) 2
For single angle member
The reduction factor Q shall be
76
b/t ≤ Ψ Q=1
Fy
76 155 b
Ψ <b /t < Ψ Q = 1.340 – 0.00447 Fy / Ψ
Fy Fy t
155 15500
b/t ≥ Ψ Q= 2
Ψ2
Fy b
Fy
t
Diponegoro- Sumberejo 5 of 7
Shear on Bolt
Fv = 0.60 Fu / 2.35
Fv = Allowable shear stress
(ref: AISC ASD, Commentary on Spec for Structural Joint Using ASTM A325 &
ASTM A490)
Bearing on Bolt
F p = 1.2 Fu
panel
Remarks :
- A single bolt connection shall be considered as unrestrained against rotation
- A multiple bolt connection properly detailed to minimize eccentricities shall be
considered to offer partial restraint if the connection is to a member having
adequate flexural strength to resist of the joint
D. Materials
Steel materials to be used for the towers and appurtenances conform to the
relevant Indonesia standards and/or Japanese Industrial Standard.
1. Structural steel
2. Bolts
Tensile
Yield point Bearing stress
strength
Classification (Fy) (Fp)
(Fu)
(MPa) (MPa)
(MPa)
ASTM A325 585 825 1200
JIS B1051 grade 560 800 1200
3. Welding
4. Galvanized
G. Structural Analysis
Three-dimension structure analysis should be applied to determine tower member
stresses. The analysis is carried out by computer program on the basis of a valid
stress analysis program.
Computer program used in this analysis is MicroStran/MSTower. This program is
based on direct stiffness/finite element method. MSTower is a specific program for
tower analysis.
3. SUPPORTING DATA
Design Order JAW-EJV-0360-H-P Diponegoro- Sumberejo INDOSAT Rev 0.0 PT. WHIDIA BHARAYA 25/01/2021 GF-2
Subject: Design Order JAW-EJV-0360-H-P Diponegoro- Sumberejo INDOSAT Rev 0.0 PT. WHIDIA BHARAYA 25/01/2021 GF-2
From: Arip Rahman <[email protected]>
Date: 23/01/2021 21:12
To: Deny <[email protected]>, Amalia Fathiningrum <[email protected]>, Lulu Diyanah <[email protected]>
CC: Engineering STR <[email protected]>, Dewantara Zahirshah <[email protected]>, Reza Arienurdin Yusuf <[email protected]>, "[email protected]" <Sunaryo@whidia-
bharaya.co.id>, 'Ateng Zaelani' <[email protected]>, 'Adi Baong' <[email protected]>, "[email protected]" <[email protected]>, Yusep Hendra <[email protected]>
Proposed Antenna :
Proposed RF&MW
Protelindo Site ID Type Site RF QTY MW Dimension RRU QTY Transmissi Type
Antenna Isat
Regards,
Arip Rahman
PT Profesional Telekomunikasi Indonesia | Subsidiary of PT Sarana Menara Nusantara, Tbk
Phone: +62 21 23585500 | ext: 590 | Fax: +62 21 23586446
www.ptsmn.co.id
DISCLAIMER:
This e-mail and its attachments may contain confidential information from PT PROFESIONAL TELEKOMUNIKASI INDONESIA or its affiliates to the intended recipient(s). If you are not the intended recipient(s), or the employee or agent responsible for delivery
of this message to the intended recipient(s), you are hereby notified that any dissemination, distribution or copying of this e-mail message is strictly prohibited. If you receive this e-mail in error, please notify the sender by phone or email immediately and delete
this e-mail and its attachments. No representation is made that this e-mail and its attachments is free of viruses or other defects. Virus scanning is recommended and is the responsibility of the recipient.
Attachments:
1 of 1 26/01/2021 8:31
10cm - SCALE WITH CAUTION AS DISTORTION CAN OCCUR
°
90
0°
Y
N
L
E
N
Leg-3
O
GENSET
FUEL TANK
Leg-2
F T Leg-1
D
(Proposed ISAT BTS PAD 2.4 x1.5 )
PROTEL/CME/C
1 R0 1
4. EXISTING TOWER ANALYSIS
Civil Engineering
Job: Proposed 27 Jan 2021
DIPONEGORO 05:05
GF SST 70 M
Y
X
theta: 195 phi: 15
Y X
theta: 180 phi: 0
X Y
theta: 270 phi: 0
Z X
theta: 0 phi: 90
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.td
Civil Engineering Page 2 of 2
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.td
Civil Engineering Page 1 of 3
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.twr
Civil Engineering Page 2 of 3
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.twr
Civil Engineering Page 3 of 3
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.twr
Civil Engineering Page 1 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 2 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 3 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 4 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 5 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 6 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 7 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 8 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 9 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 10 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 11 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 12 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 13 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 14 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 15 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 16 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 17 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 18 of 18
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.rpt
Civil Engineering Page 1 of 2
Job: Proposed 27 Jan 2021
DIPONEGORO 5:06
GF SST 70 M
I N P U T / A N A L Y S I S R E P O R T
C O N D I T I O N N U M B E R
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.p1
Civil Engineering Page 2 of 2
Job: Proposed 27 Jan 2021
DIPONEGORO 5:06
GF SST 70 M
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\Proposed.p1
5. STRENGTHEN TOWER ANALYSIS
Civil Engineering
Job: STR 27 Jan 2021
DIPONEGORO 05:06
GF SST 70 M
Y
X
theta: 195 phi: 15
Y X
theta: 180 phi: 0
X Y
theta: 270 phi: 0
Z X
theta: 0 phi: 90
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.td
Civil Engineering Page 2 of 2
27 Jan 2021
5:06
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.td
Civil Engineering Page 1 of 3
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.twr
Civil Engineering Page 2 of 3
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.twr
Civil Engineering Page 3 of 3
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.twr
Civil Engineering Page 1 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 2 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 3 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 4 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 5 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 6 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 7 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 8 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 9 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 10 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 11 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 12 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 13 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 14 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 15 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 16 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 17 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 18 of 18
27 Jan 2021
5:07
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.rpt
Civil Engineering Page 1 of 2
Job: STR 27 Jan 2021
DIPONEGORO 5:07
GF SST 70 M
I N P U T / A N A L Y S I S R E P O R T
C O N D I T I O N N U M B E R
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.p1
Civil Engineering Page 2 of 2
Job: STR 27 Jan 2021
DIPONEGORO 5:07
GF SST 70 M
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
N O D E D I S P L A C E M E N T S
MStower [V6.00.010]
D:\Project\Protelindo\2021\Diponegoro- Sumberejo\25 Jan'21 (Isat rev.0)\Tower Analysis\STR.p1
PT. WHIDIA BHARAYA
A. MATERIAL
Material :
F yA 36ksi
F V 0.3 F yA F V 74.463MPa
2. Concrete
f'c 18.675MPa
3. Baseplate
Fy 250MPa
B. SUPPORT REACTION
Compression Force:
F compress 927661N
F compress 94595.096kgf
Tension Force:
F tension 713611 N
F tension 72768.071kgf
Horizontal Force :
F hor 89404N
Anchor Diameter :
anchor 32mm
2
Aanchor 804.248 mm
At nanchor Aanchor
2
At 64.34cm
Anchor Strength :
F hor
fva
At
fva 13.896MPa
Resume if fva F V "OK" "NOT OK" Resume "OK"
Fv F V 1.33 Fv 99.036MPa
F tension
fta fta 110.913 MPa
At
fva fta
0.7
Fv Ft
fva fta 1 "OK" "NOT OK"
Resume3 if
Fv Ft Resume3 "OK"
D. BASE PLATE
Steel SS-400
FyB 250MPa
Concrete
F compress
2
Ab Ab 0.142 m
Fp
B Ab B 0.377 m
60
59
130
502
120 500
79
130
60
Buse 500mm
b 79mm
mn 60mm
sn 500mm
2 2
Abuse Buse Abuse 0.25 m
F compress
tp1 2mn tp1 1.268cm
Abuse FyB 1.33
F tension
Tn Tn 89.201kN
nanchor
Mn Tn b Mn 7.047kN m
6 Mn
tp2 tp2 1.841cm
sn 0.75 FyB 1.33
tprequired 1.841cm
tpexisting 5.0cm
Resume4 if tprequired tpexisting "OK" "NOT OK" Resume4 "OK"
EXISTING
Code date
29 Januari 2021
V9.11.27 F
EXISTING FOUNDATION SUMMARY
SITE NAME : Diponegoro- Sumberejo
SITE ID : JAW-EJV-0360-H-P
TOWER DATA
Project PROTELINDO
Tower Type SST 70M
Flood Elv -
SUPPORT REACTION
FOUNDATION DESCRIPTION
Foundation Type Raft
Depth of Foundation 1200 mm
Pedestal Dimension 700 x 700 mm
Pad Dimension 9000 x 9000 mm
REMARK
Catatan :
Pondasi tidak mampu menahan beban, sehingga di perlukan perkuatan pondasi.
EXISTING
FOUNDATION ANALYSIS
DESCRIPTION
Base Width (BW) = 7 m Slab
Concrete Cover = 50 mm Dimension (m) = 2.4 x 2.4 x 0.25
Number of Pedestal = 3
Pedestal Tie Beam Number of Beam = 0
Pedestal Dimension = 0.7 x 0.7 m Dimension = 0 x 0 m
Above Ground Level = 0.5 m Bottom Elv (-) = 0 m
H Pedestal Under Ground Level = 0.6 m
Pad Pile
Pad Dimension (B) = 9 x 9 x 0.35 m Total Number of Pile = 0
Depth of Foundation = 1.2 m Dimension = 0 m (Diameter)
Number of Pad = 1 Elevation (-) = 0 m
MATERIAL SPECIFICATION
Soil
qc = 15 kgf/cm2
qall = qc / 15 = 1.00 kgf/cm2 = 98.07 KN/m2
Concrete
Specified Compressive strength
K = 22.5 N/mm²
fc = 18.68 N/mm²
Unit weight of Concrete (submerge)
γcsm = 1400 kgf/m³
Concrete strength of factor
β1 = 0.85
Unit weight of Concrete (dry)
γcd = 2400 kgf/m³
Rebar
Unit weight of Steel (γs) = 7850 kgf/m³
Specified Yield strength
fy1 = 240 N/mm² for diameter ≤ Ø 12 mm (plain rebar)
fy2 = 390 N/mm² for diameter ≥ Ø 13 mm (derformed rebar)
V9.11.27 1 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
EXISTING
SUPPORT REACTION
Tension Force
Node FX FY FZ MX MY MZ
2005 -29.294 31.788 452.74 0.365 -1.054 0.197
2015 -28.779 -32.796 463.787 -0.88 -0.712 -0.195
2035 -71.745 0.329 -713.611 -0.001 -0.001 0
Resultant -129.817 -0.679 202.916 38.146 -4737.84 -5.169
Compress Force
Node FX FY FZ MX MY MZ
2005 28.103 -27.245 -353.917 -0.291 1.36 -0.243
2015 27.767 28.473 -370.828 0.823 0.859 0.234
2035 89.404 -0.287 927.661 0.043 -0.13 -0.002
Resultant 145.274 0.942 202.916 -58.613 5215.7 4.805
Pedestal Slab
Volume = 1.62 m3 Volume = 4.32 m3
H Dry = 1.10 m H Dry = 0.25 m
H Submerge = 0.00 m H Submerge = 0.00 m
Dry Weight = 3880.80 kgf Dry Weight = 10368.00 kgf
Surmerge Weight = 0.00 kgf Surmerge Weight = 0.00 kgf
Total Weight = 3880.80 kgf Total Weight = 10368.00 kgf
= 38.06 kN
Tie Beam
Pad Volume = 0.00 m3
3
Volume = 28.35 m H Dry = 0.00 m
H Dry = 0.35 m H Submerge = 0.00 m
H Submerge = 0.00 m Dry Weight = 0.00 kgf
Dry Weight = 68040.00 kgf Surmerge Weight = 0.00 kgf
Surmerge Weight = 0.00 kgf Total Weight = 0.00 kgf
Total Weight = 68040.00 kgf
= 667.27 kN Existing Foundation
Weight of Concrete = 0 kgf
TOTAL WEIGHT OF CONCRETE Weight of Backfill = 0 kgf
3
Total Volume = 34.29 m
Total Weight = 82288.80 kgf Concrete Hole Area = 0 m2
= 807.01 kN Volume = 0.00 m3
H Dry = 0.35 m
H Submerge = 0.00 m
Dry Weight = 0.00 kgf
Surmerge Weight = 0.00 kgf
Weight = 0.00 kgf
V9.11.27 2 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
EXISTING
VOLUME CALCULATION
V9.11.27 3 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
EXISTING
STABILITY CALCULATION
Sliding Capacity
Friction Coefficient (∂fr) = 0.45
Horizontal Force
Fa = 145.27 kN
SFsliding = Fresisting
Fa
SF Overturning = M resisting
M overturning
= 1.76 > 1.5 (OK)
Bearing Capacity
PCAmats Output = 124.36 KN/m2
SF bearing = 116.90
124.36
= 0.94 < 1 (NOT OK)
Punching Shear
Shear stress (Vu) = 0.53 kN Shear resistance factor = 0.75
Shear resistance (Φ Vc) = 1.08 kN
SF Punch Shear = Φ Vc / Vu
= 2.04 > 1 (OK)
V9.11.27 4 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
EXISTING
PEDESTAL REINFORCEMENT
Load Factor (µf) = 1
Stirrup Bar
Quantity of section (ns) = 2 strength reduction factor for shear
Horizontal force (Vn) = 89.40 kN Φsh = 0.75
Effective depth (Ef.d) = 632 mm
Nominal shear strength of the concrete
Vcon = Φsh*(bb/6)*Ef.d*√fc Stirrup Spacing
= 238.977 kN s = Av*fy*Ef.d/Vs
Minimum Stirrup Spacing = 267 mm
Flexure Bar
minimum reinforcement area minimum Number of bar
As.minp = 0.01*b.t*b.b Nbar = As.minp/((π/4)*Pdrd2)
= 4900 mm² = 25 or 28
Trial 28
Pcacol Input
Pedestal Dimension = 700 x 700 mm Specified Yield Strength of Steel
Factored Tension = -713.611 kN fy = 390 N/mm²
Factored Compress = 927.661 kN
Factored Moment = 98.344 kN.m Specified Yield Strength of Conrete
fc = 18.675 N/mm²
RESULT : (OK)
V9.11.27 5 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
EXISTING
PAD REINFORCEMENT
Spacing Spacing
s = ( 1000 mm ) / ( n ) s = ( 1000 mm ) / ( n )
s = 287.35 mm s = 167.62 mm
s = 280 mm s = 160 mm
Spacing Spacing
s = ( 1000 mm ) / ( n ) s = ( 1000 mm ) / ( n )
s = 287.35 mm s = 148.90 mm
s = 280 mm s = 140 mm
RESULT : (OK)
V9.11.27 6 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
EXISTING
Pcacol Output
Reinforcement
Ped Bar 28 D 16
Stirrup ø 10 - 150
3D View
Lampiran-1 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
EXISTING
Pad Reinforcement Contours
2
Asx (Top) 699.999 mm
2
Asx (Top) 1200.003 mm (Around of Pedestal)
2
Asx (Down) 699.999 mm
2
Asx (Down) 1209.705 mm (Around of Pedestal)
Lampiran-2 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
EXISTING
Pad Reinforcement Contours
2
Asy (Top) 699.999 mm
2
Asy (Top) 1200.003 mm (Around of Pedestal)
2
Asy (Down) 699.999 mm
2
Asy (Down) 1350.9 mm (Around of Pedestal)
Lampiran-3 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
EXISTING
Pressure Down
2
Pressure 1 124.357 KN/m = 124.357 KN/m2
Lampiran-4 1/29/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
EXISTING
Punch Shear
Max Vu = 0.53 kN
Max Vc = 1.08 kN
Lampiran-5 1/29/2021
FOUNDATION ANALYSIS AND DESIGN DRAWING
STRENGTHENING
Code date
24 Februari 2021
V9.11.27 F
STRENGTHENING FOUNDATION SUMMARY
SITE NAME : Diponegoro- Sumberejo
SITE ID : JAW-EJV-0360-H-P
TOWER DATA
Project PROTELINDO
Tower Type SST 70M
Flood Elv -
SUPPORT REACTION
FOUNDATION DESCRIPTION
Foundation Type Raft
Depth of Foundation 1200 mm
Pedestal Dimension 700 x 700 mm
Pad Dimension 9450 x 10000 mm
REMARK
Catatan :
Pondasi tidak mampu menahan beban, sehingga di perlukan perkuatan pondasi.
Rekomendasi yang kami berikan adalah pelebaran pad.
STRENGTHENING
FOUNDATION ANALYSIS
DESCRIPTION
Base Width (BW) = 7 m Slab
Concrete Cover = 50 mm Dimension (m) = 2.4 x 2.4 x 0.25
Number of Pedestal = 3
Pedestal Tie Beam Number of Beam = 0
Pedestal Dimension = 0.7 x 0.7 m Dimension = 0 x 0 m
Above Ground Level = 0.5 m Bottom Elv (-) = 0 m
H Pedestal Under Ground Level = 0.6 m
Pad Pile
Pad Dimension (B) = 9.45 x 10 x 0.35 m Total Number of Pile = 0
Depth of Foundation = 1.2 m Dimension = 0 m (Diameter)
Number of Pad = 1 Elevation (-) = 0 m
MATERIAL SPECIFICATION
Soil
qc = 15 kgf/cm2
qall = qc / 15 = 1.00 kgf/cm2 = 98.07 KN/m2
Concrete
Specified Compressive strength
K = 22.5 N/mm²
fc = 18.68 N/mm²
Unit weight of Concrete (submerge)
γcsm = 1400 kgf/m³
Concrete strength of factor
β1 = 0.85
Unit weight of Concrete (dry)
γcd = 2400 kgf/m³
Rebar
Unit weight of Steel (γs) = 7850 kgf/m³
Specified Yield strength
fy1 = 240 N/mm² for diameter ≤ Ø 12 mm (plain rebar)
fy2 = 390 N/mm² for diameter ≥ Ø 13 mm (derformed rebar)
V9.11.27 1 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
STRENGTHENING
SUPPORT REACTION
Tension Force
Node FX FY FZ MX MY MZ
2005 -29.294 31.788 452.74 0.365 -1.054 0.197
2015 -28.779 -32.796 463.787 -0.88 -0.712 -0.195
2035 -71.745 0.329 -713.611 -0.001 -0.001 0
Resultant -129.817 -0.679 202.916 38.146 -4737.84 -5.169
Compress Force
Node FX FY FZ MX MY MZ
2005 28.103 -27.245 -353.917 -0.291 1.36 -0.243
2015 27.767 28.473 -370.828 0.823 0.859 0.234
2035 89.404 -0.287 927.661 0.043 -0.13 -0.002
Resultant 145.274 0.942 202.916 -58.613 5215.7 4.805
Pedestal Slab
Volume = 1.62 m3 Volume = 4.32 m3
H Dry = 1.10 m H Dry = 0.25 m
H Submerge = 0.00 m H Submerge = 0.00 m
Dry Weight = 3880.80 kgf Dry Weight = 10368.00 kgf
Surmerge Weight = 0.00 kgf Surmerge Weight = 0.00 kgf
Total Weight = 3880.80 kgf Total Weight = 10368.00 kgf
= 38.06 kN
Tie Beam
Pad Volume = 0.00 m3
3
Volume = 33.08 m H Dry = 0.00 m
H Dry = 0.35 m H Submerge = 0.00 m
H Submerge = 0.00 m Dry Weight = 0.00 kgf
Dry Weight = 79380.00 kgf Surmerge Weight = 0.00 kgf
Surmerge Weight = 0.00 kgf Total Weight = 0.00 kgf
Total Weight = 79380.00 kgf
= 778.48 kN Existing Foundation
Weight of Concrete = 0 kgf
TOTAL WEIGHT OF CONCRETE Weight of Backfill = 0 kgf
Total Volume = 33.10 m3
Total Weight = 79432.80 kgf Concrete Hole Area = 16.9 m2
= 779.00 kN Volume = 5.92 m3
H Dry = 0.35 m
H Submerge = 0.00 m
Dry Weight = 14196.00 kgf
Surmerge Weight = 0.00 kgf
Weight = 14196.00 kgf
V9.11.27 2 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
STRENGTHENING
VOLUME CALCULATION
V9.11.27 3 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
STRENGTHENING
STABILITY CALCULATION
Sliding Capacity
Friction Coefficient (∂fr) = 0.45
Horizontal Force
Fa = 145.27 kN
SFsliding = Fresisting
Fa
SF Overturning = M resisting
M overturning
= 2.28 > 1.5 (OK)
Bearing Capacity
PCAmats Output = 111.81 KN/m2
SF bearing = 116.90
111.81
= 1.05 > 1 (OK)
Punching Shear
Shear stress (Vu) = 0.53 kN Shear resistance factor = 0.75
Shear resistance (Φ Vc) = 1.08 kN
SF Punch Shear = Φ Vc / Vu
= 2.04 > 1 (OK)
V9.11.27 4 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
STRENGTHENING
PEDESTAL REINFORCEMENT
Load Factor (µf) = 1
Stirrup Bar
Quantity of section (ns) = 2 strength reduction factor for shear
Horizontal force (Vn) = 89.40 kN Φsh = 0.75
Effective depth (Ef.d) = 632 mm
Nominal shear strength of the concrete
Vcon = Φsh*(bb/6)*Ef.d*√fc Stirrup Spacing
= 238.977 kN s = Av*fy*Ef.d/Vs
Minimum Stirrup Spacing = 267 mm
Flexure Bar
minimum reinforcement area minimum Number of bar
As.minp = 0.01*b.t*b.b Nbar = As.minp/((π/4)*Pdrd2)
= 4900 mm² = 25 or 28
Trial 28
Pcacol Input
Pedestal Dimension = 700 x 700 mm Specified Yield Strength of Steel
Factored Tension = -713.611 kN fy = 390 N/mm²
Factored Compress = 927.661 kN
Factored Moment = 98.344 kN.m Specified Yield Strength of Conrete
fc = 18.675 N/mm²
RESULT : (OK)
V9.11.27 5 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
STRENGTHENING
PAD REINFORCEMENT
Spacing Spacing
s = ( 1000 mm ) / ( n ) s = ( 1000 mm ) / ( n )
s = 287.35 mm s = 162.62 mm
s = 280 mm s = 160 mm
Spacing Spacing
s = ( 1000 mm ) / ( n ) s = ( 1000 mm ) / ( n )
s = 287.35 mm s = 146.94 mm
s = 280 mm s = 140 mm
Recommendation Recommendation
D16 - 250 mm D16 - 125 mm
RESULT : (OK)
V9.11.27 6 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
STRENGTHENING
Pcacol Output
Reinforcement
Ped Bar 28 D 16
Stirrup ø 10 - 150
3D View
Lampiran-1 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
STRENGTHENING
Pad Reinforcement Contours
2
Asx (Top) 699.999 mm
2
Asx (Top) 1218.235 mm (Around of Pedestal)
2
Asx (Down) 699.999 mm
2
Asx (Down) 1238 mm (Around of Pedestal)
Lampiran-2 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
STRENGTHENING
Pad Reinforcement Contours
2
Asy (Top) 699.999 mm
2
Asy (Top) 1236.879 mm (Around of Pedestal)
2
Asy (Down) 699.999 mm
2
Asy (Down) 1368.862 mm (Around of Pedestal)
Lampiran-3 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
STRENGTHENING
Pressure Down
2
Pressure 1 111.81 KN/m = 111.81 KN/m2
Lampiran-4 2/24/2021
SITE NAME : Diponegoro- Sumberejo PROJECT : PROTELINDO
SITE ID : JAW-EJV-0360-H-P TOWER TYPE : SST 70M
STRENGTHENING
Punch Shear
Max Vu = 0.53 kN
Max Vc = 1.08 kN
Lampiran-5 2/24/2021
7. DRAWING
Site Name : DIPENOGORO - SUMBEREJO
Tower Type : Tower SST 70 M