EHC Write Up BHEL Document
EHC Write Up BHEL Document
Introduction :-
Electro � hydraulic controller is an integral part of EAST (Electronic Automatic for steam turbine) supplied
with KWU designed turbines. As the name suggest the controller combines the advantages available in
electrical as well as in hydraulic system and provides following additional additional advantages over
conventional governor.
- Increases the life of turbo set by conservative operation with the aid of TSE.
- Reliable operation of isolated power grid by automatic switch over of the load controller to frequency
control.
- Precise maintenance of the rated frequency of the power grid by means of an exact frequency load
curve.
- Low speed deviation under all operational conditions.
- Support of the pressure control system.
Function wise electro � hydraulic controller (EHC) can be divided into following sub section.
1) Speed measurement
2) Speed controller
3) Load controller
4) Pressure controller
5) Control Transfer
6) Position controller
1) Speed measurement :-
Speed measurement system should be commissioned before barring gear as it involves work front
bearing pedestal. For speed measurement four numbers of hall probes are mounted around a disc containing
120 magnets (60 N � Pole and 60 S � Pole placed alternatively). Advantage of the same is that one rotation
of disc will generate 60 puses. So by counting the pulses for one second we can directly detect the turbo set
speed in rpm.
All the four Hall probes are will upto pedestal junction Box. Out of these four Hall probes, three
probes are used for measurement purpose and one is kept as spare. The gap between hall probe and disc
should be maintained around 0.8mm. The three Hall probes which are used, are wired upto three pulse
converter Junction Boxer. (In the previous set all the three pulse converter were mounted in one Junction
Box but as these are mounted in an our tight enclosure in the field due to excessive heat, cards used to fail
Due to this reason in new sets three separate Junction Boxes are provided).
The Hall probes contains 4 wires. A constant current (30 � 80 mA) is fed to the two wires and across output
wires a voltage is generated. The output voltage polarity and magnitude depends upon the magnetic field.
The internal resistance of the Hall probe is around 33 r. When the magnetic disc rotates around the Hall
probes, Hall probe output is a sine wave with a peak voltage of � 700 mv to � 900 mv. In the pulse
converter card these � sine wave are converted into a square wave with a pulse voltage of � 10.0 v. Each
pulse converter card generates three isolated output out of which two outputs are used and one is kept as
spare. In EHC cabinet the speed measurement is done in two independent but identical channels. One
channel is used for controller and another for indication and limit value monitors.
Both measurement channels receive signal form all the three pulse converters. The three signal
processed and one, out of the three signals, is selected for further processing with the left of a specially
designed card ADA 11. Along with the selecting the healthy signal for further processing this card also
generates selective fault alarm if any of the input signal is faulty without affecting the system. This fault can
be acknowledged by switch 511 if signal becomes healthy and turbine speed is more than 13 rpm. If speed
fall below 13 rpm the fault is memorised and it can not be acknowledged. Advantage of the above system
being that at stand still when all the channel are giving no pulses the card will indicate the defective hall
probe and the same can be attended.
After processing the frequency signal is converted into voltage signal for internal use and then into a
current signal for external use
Speed Controller :-
Speed controller is used to increase the turbine speed form barring gear speed to rated speed in a
controlled manner and to assist Auto � synchroniser in synchronising the M/c. After synchronisation speed
controller can be used for taking up the load upto 100% but as a normal practice approx. 10% of load
should be taken with speed controller and then load controller should be taken into services. It is done
because during speed controller mode a small frequency change will cause corresponding change in valve
opening (hence in load) as the valve opening is directly proportional to the difference between grid
frequency and speed set point. Speed controller can be divided into following sub-section.
a) Speed setpoint
b) Speed setpoint control
e) Dn/Dr monitoring
d) Speed controller loop
e) No load correction
The output of the integrator is known as NRTD or NRLIM. The NRTD indicator is available at desk. The
range of the indicator is 0 � 3300 rpm. The integrator has got following extra provisions.
i) Fast calibration is provided during both the follow mode to enable fast matching of input (NR) and
output (NRTD)
ii) Stop mode to block the integrator during disturbance in TSE or steam parameters.
iii) Simulation of 0�K TSE margin (hence blocking the integrator output where it was) of output of
integrator (NRTD) increases more than the actual speed by 45 rpm (originally 17 rpm) before generate
breaker is closed. This ensures that before synchronisation speed controller will not give output more than
30%.
(iv) Generates signal NR> NRTD and nR<nRTD for use during Auto synchronisation.
(v) Generates blocking command for TSE test when nR and nRTD are not matched. This is done to
avoid feeding of incorrect (simulated) values of TSE margins.
Dn/Dt monitoring :-
Responsibility of this loop is to detect low acceleration rate (100 rpm/min) during start ups. The KWU
turbine has two critical speed between 700 rpm and 2850 rpm hence it is not advisable to run the turbine for
prolonged time in this speed zone. To fulfill this requirement this loop detects the low acceleration rate and
bring back the turbine to safe speed (600 rpm). For actuating the dn/dt monitoring following condition have
to be fulfilled.
i) Speed controller output (hence) should be more than 0.0v (with a on time delay of 10 sec.)
ii) ESV�s open
iii) Circuit Breaker open
iv) Actual speed (nact) less than 2850 rpm
v) Speed setpoint (nR) more than 700 rpm (originally 600 rpm)
d) Speed controller loop :-
Speed controller loop is PD (P) loop with a droop of 5%. As the rated speed of the turbine is 3000
rpm hence 5% is 150 rpm. A deviation of 150 rpm will correspond to full opening of the control valve (with
the assumption that full opening of control valve will give full load at rated parameters.
For speed 0 � 3600 rpm = 0 � 10.8 v
i.e. 1 rpm = 3.0 nv
150 rpm = 450.0 nv
For valve 0 � 100 % = 0 � 10.0 v
Hence an input deviation of 450 nv should give a output of 10.0v. So the at 150 rpm difference values
are fully open. Hence the gain of loop is.
10.00
------- = 22.22
0.450
This gain should be adjusted by AE131 R26. The system response. Can be adjusted by Potentiometer
R12 & R13 of AE 131 by using a high speed recorder (Oscillomink). The output of controller is known as
hrnc.
e) No load correction :-
As the speed controller loop is PD (P) so an error in the input is a must to keep the valves open for
running the m/c at the rated speed. To avoid this error between setpoint and actual value a pressure
depended correction signal is giver. As the valve opening required for running the m/c at rated speed is
directly depended on steam pressure. Hence for correction purpose practical reading should be taken when
the m/c is running at rated speed different pressure.
For example :-
Turbine running at 3000 rpm
Output of speed controller at (50kg/cu) = 1.5 v
Output of speed controller at (150kg/cu) = 0.8v
The pressure transmitter range is
0 � 250 = 0 � 10v
The correction input is given with a gain of 0.05 and the overall gain of speed controller loop is 22.22
so net gain for correction signal = 0.05 x 22.22
= 1.11
1.5
hence correction input required at 50 kg/cu = ---- = 1.35 V
1.11
0.8
and correction input required at 150 kg/cm2 = ---- = 0.72 V
1.11
Now two equation can be made with
Y = m x +c y correction signal
X pressure signal
1.35 = m x 2 +c (1)
0.72 = m x 6 +c (2)
By solving above two equation
m= - 0.16
c = 1.67
https://www.bhelpswr.co.in/Technical/C&I/Commissioning/EAST Write Up/Iskamatic Writeup.htm 3/7
1/24/22, 12:36 PM Technical Feedback
Gain (m) should be adjusted by Potentiometer ABO99/RSS � ive polarity of (m) is taken case by
feeding positive signal to negative point of comparator.
Biasing (c) can be adjusted by potentiometer AB115/R13
(3) Load Controllers :-
Load controller is used to maintain the load set by the operator or Automatic load dispatch center
(optional). Load controller is also responsible for taking care of frequency changes and correcting the load.
The controller comes into operation only after synchronise before synchronisation if remains in the follow
mode. The total loop can be divided in following sub section.
a) Load setpoint (PR)
b) Load gradient and TSE margin influence
c) Load setpoint control (PRTD)
d) Frequency influence
e) Load Limiter
f) Actual load Acquisition
g) Final control loop
a) Load setpoint :-
Load setpoint can be changed from cabinet, desk, or for Auto dispatch center (optional). The setpoint
changes at a gradient of 100 MW/min. The gradient remains same through out the range. The load setpoint
indicator is available at desk. The range of the indicator is 0 � 250 MW.
Load gradient and TSE influence :-
Load gradient is an additional feature available in load controller. The load gradient acts in parallel
with TSE margin with a minimum selector. Load gradient range is 0 � 25 MW/min. While for TSE margin 0 �
30�K corresponds to 0 � 25 MW/min Both load gradient and TSE margin have got an On/Off Switch so if
any one is desired to be off taken out of service can be switched off. The one which remains on, controls the
output. If both are off the PRTD changes at fixed ratio of 25 MW/min. Load gradient setting can be changed
from desk or cabinet. Load gradient setting is common for increasing as well as decreasing. In case of TSE
upper margin controller the increasing rate and lower margin controller the decreasing rate. The limiters for
the margins are provided in such a way that � ive upper margin is allowed to control PRTD (hence it can
unload the m/c) while � ive lower margin is not allowed to control the m/c (hence it can not load the m/c).
If TSE influence is on and TSE develops any fault immediately a block command is initiated so that wrong
TSE margins are not allowed to control PRTD. To restore it the TSE influence should be switched off. Before
again switching on the influence the TSE fault should be rectified and acknowledge.
c) Load setpoint control (PRTD) :-
The function of this sub section is similar to the one already described in speed controller. The
maximum rate by change here is 25 mw/m in both directions. The follow mode and fast calibrate signal are
used for different purpose as explain below.
i) If load gradient is off and any change in Pr is made, PRTD changes by 5% (of full range) immediately
and remaining change takes place at the rate given by TSB.
ii) The setpoint controller remains in follow mode when generator breaker is off or load controller off or
load is less than station load. During this mode PRTD follows actual load. This follow mode is a must so that
the PRTD is brought back to zero after breaker opens. After synchronisation PRTD tracks the actual load
(which is taken with speed controller) so that more time is not wasted in bringing the PRTD from zero value
to working value.
iii) During above follow mode fast calibration signal is given so that PRTD follow Pact without any delay.
iv) STOP command is generated if TSE fault appears or any disturbance takes place in steam parameter.
v) Generator blocking command for TSE test when PRTD & PR are not matching
vi) Indicator for PRTD is available in desk with a range of 0 � 250 MW.
d) Frequnecy Influence :-
Frequency influence is used to correct the load setpoint. Depending upon the frequency deviation a
load correction signal is generated. The frequency influence has got a droop of 5% (It can be changed from
2.5% to 8.0% in steps of 0.5% on line) hence a deviation of � 0.5 hc will cause load change of � 40 MW.
The correction signal is limited at �40MW. The circuit has got a filter so that normal hunting in frequency will
not cause hunting in load. But if frequency drifts by even a small amount will cause load change. The
frequency influence can be switched ON/OFF depending upon the requirement. Frequency influence remains
ineffective below a frequency of 45 Hz. Indicator for the correction signal is available at desk. The range of
the same is � 100 MW. The correction signal is known as (prof).
e) Load Limiter :-
Final setpoint (addition of PRTD of Prof) is fed to a minimum to selection with the load limiter. As the
name suggests if the final setpoint becomes more the load limiter setpoint the limiter will control the load.
The limiter also can be used for fast reduction of load in emergency cases. While doing to PR (interior PRTD)
also should be reduced, so that during loading load incr as per PRTD and not as per load limiter.
f) Actual Load Acquisition :-
The actual load is mea in cabinet CJJ08. Three load transducers are prov for this purpose. All the
three load transducers get signal from PT and CT and give the output in mA. The output range for these
transducer is 4 � 20 m1 which corresponds to 0 � 250 mw. These three signal are passed on to EHC cabinet
https://www.bhelpswr.co.in/Technical/C&I/Commissioning/EAST Write Up/Iskamatic Writeup.htm 4/7
1/24/22, 12:36 PM Technical Feedback
for selection and fault indication. The middle value of the three is selected for further processing. If any
value drifts from the other value by more then a certain fixed amount (5%) then a selective alarm is
generated and indicated. The fault does not disturbs the working of the controller as the selection circuit
discards the defective channel. The fault generated can be acknowledged by switch 511 available outside an
selection card once. The fault is rectified.
g) Final controller loop :-
The final loop is a PI controller. The loop can be divided into two major parts consisting of two cards
ARL12 and ARL13 specially designed for this purpose.
Responsibility of ARL12 card is to receive the final setpoint and the actual load. From these two
signals an error signal is generated. The gain of the loop is set in this card. This card has got an inbuilt
frequency influence. Whose responsibility is to prevent the over speeding of the turbine. Hence this
frequency influence acts only in one direction i.e. if frequency is going up it gives a correction signal to close
the valve. If frequency is going down it will not take any action. Unlike the frequency influence described
earlier this influence can not be switched off. ARL12 card also detects the large error between setpoint and
actual value (if it exceeds 10% and frequency is increased beyond 51 Hz) it changes the controller to
isolated grid mode. In this mode the gain of the loop is increased to take fast correction action.
The output of ARL12 card is fed to ARL13 cards. ARL13 card provides the integrator part of the loop.
Apart from the integrator, ARL13 has also got a filter so that it does not takes any action if output of ARL12
is hunting at higher rate than the one set for filter. For this purpose the hunting time prior should be
recorded and the same should be set by potentiometer R11/R12 of ARL13. The setting of R11/R12 should be
same to avoid beat formation hence if the setting is to be changed it one line than if should by done in very
small steps alternatively.
ARL13 card also has provision for follow mode. Two type of follow modes are available.
Following above (hvo) :-
This mode is in operation during following conditions.
(i) Load controller off or
(ii) Generator breaker off or
(iii) Pact < STL and DP>5%
During the above condition the load controller output tracks the speed controller output tracks the speed
controller output all the time with a constant error of � 150mv. This follow mode ensures that during above
conditions the load controller should not come into action.
Following Low (hvu) :-
This follow mode is present once the breaker is closed (synchronised) and speed controller is still in
action. During this mode also the load controller output tracks the speed controller output with error of �
150.0 mv. The only difference in this mode is that the load controller output difference in this mode is that
the load controller output can go more than speed controller output (hence load controller can take over) but
it can not go 150 mv below the speed controller output. The advantage being that due to this follow mode
the load controller can be taken into service any time without any delay after synchronisation if desired.
The output of load controller is limited to + 10V thru first minimum selection circuit (explained in
control transfer). The load controller output is known as hRDC.
4) Pressure Controller :-
Responsibility of pressure control loop is to maintain the pressure within the working range at all
loads pressure controller has got two makes of operation.
a) Initial Pressure mode :-
A pressure deviation signal (difference of required pressure as per load and actual pressure) is fed to
the controller. As long as the deviation is more than + 150mv (Actual > required) the pressure controller
output remains at saturation. If the deviation fall between 0 - + 150mv the output of the pressure controller
jumps from saturation to the output of final minimum selection output (hence it is made reading to take
over). As soon as the deviation becomes � ive the output of pressure controller starts decreasing and it
takes over the control and it will reducer the said as. This mode should per sets be used during start up and
initial loading of load the turbo set.
b) Limit Pressure mode :-
The function of this mode is similar to the initial pressure mode. The only difference being that a
biasing of 10 kg/ur is given in this loop. Hence all the action start after the pressure drops by more than 10
kg/cm2. This mode should be used once the load on turbo set is stablised.
Output of pressure controller is known as hrPRC
5) Control Transfer :-
This loop receives the signal from speed controller (hrnc), load controller (hrPC) and pressure
controller (hrPRC). These signal passes.
Thru a set of MAX/MIN selection and then the final value selected is passed on to position controller. The
functioning of the system is as follows hrnc and hrpc pass thru a MAX value selector and the value selected
is passed on to first MIN value selection. 10.5V is added in hrnc and this value is also fed to first M1 value
selector (This is done to prevent the overspes of the turboset. As soon as the turbine speed increase above
the speed setpoint then speed controller will give output. This output can not pass thru MAX value selector,
hence it limits the output thru first MIN value selector. The value selected in first MIN value selected is
passed on to the second MIN value selector along with the output of pressure controller output (hrPRC). The
value selected here is passed on to positive controller.
All the three selector (one MAX and two MIN have the provision to indicate that which value is
selected from this information respective controller (which is in service) is indicated. The final output of
control transfer loop is known as hr.
6) Position controller :-
Position controller is the final control element in EHC. It receives the signal from control transfer. It
receives the feed back signal from Collins transmitters. For this purpose two Collins transmitters are
provided in the plungers coil. The output of the two Collins passes thru a MIN value selector (logic MAX
selector) as the range is �ve and the value selected is passed on to the controller. The controller compares
the setpoint and the feed back and depending upon the error signal it bring the piston in the desired
position. Some important points in this loop are as follows.
(i) Plunger coil supplied in EHC is an integrator type. The balance point of the coil is � 1.0 V (should be
set any where between � 0.8V to � 1.2V). Similar to an integrator if this voltage (-1.0V) is applied across
the coil, the piston remains where it was. For moving the piston in open direction the voltage has to be
increased so if the voltage is made � 0.9V (-0.9V is more than � 1.0V) piston will keep on moving towards
opening direction till the voltage is again made � 1.0V. As soon as the voltage is made � 1.0V piston will
remain where it was. Similarly if voltage is made � 1.1V ( - 1.1V is less than �1.0V) the piston will keep on
moving towards closing direction till the voltage is again brought back to � 1.0V.
(ii) The Collins transmitters used for a very accurate feed back of the piston position. The output of the
Collins varies from � 8.0v to + 8.0v which is converted into 0 � 10.0v � 0.0v corresponds to positive at
which control valve just starts opening and � 10.0v C to the position at which last control valve is just open.
A constant biasing of + 200.0mv is given for Collins transmitters so as to avoid frequent change from one
Collins to another. In case of wire to in any Collins transmitters, the respective card generates a fault alarm.
If at any time the between the two Collins transmitters exceeds If a fault alarm is generated.
iii) There is a provision to switch ON/OFF the voltage to plunger coil But switching ON or OFF can be only
if the output of position controller is more + 5.0v. This ensures that at the time of OFF the piston is full open
and there will not jump after switching OFF. Similarly it ensures that switching ON, the command for full
open is the hence piston will not go down (hence valves close) once the coil is switched ON.
(to facility working on the controller after of the coil supply).
Problems Faced and modifications done :-
1) The hall probes fails frequently. This is due to mainly due to following reasons
a) Fragile design of Hall probes
b) Failure of MOP bearing (due to this magnetic disk touches the hall probes and damages it)
2) Speed load setpoint does not changes its position after giving the command. This happen mainly due
to dust. This can be rectified by increasing the setting Potentiometer R22 and R23.
3) Dn/Dt monitoring operates when speed is increased for from 600 rpm to 3000 rpm. For this the limit
value monitor ABO59/x25/R14 should be increased to 700 rpm (2.10v) as the original value is two close to
normal soaking speed.
4) Speed controller interferes in the operation if frequency changes even by a very small amount. As
explained in speed controller, to over come this problem a follow mode has been included so that speed
setpoint follows actual speed between 49Hz to 51Hz.
5) Speed controller gets a trip command in the initial rolling even though the turbine has not tripped.
This happens due to momentary different in the trip oil pressure. To avoid this a timer of 2 sec. Is introduced
in the follows command.
6) The pressure controller output is taken via a MAX value selector with a fixed value of 0.8 (10% load).
This is done to ensure that pressure controller does not reduces the load below 10%.
7) Blocking command for load controller output during change over from load controller to speed
controller is removed. This is done so that load controller is allowed to take action of any disturbance takes
place during change over time.
8) Collins transmitter card (AKK-11) generates spurious fault alarm. For this card AKC-11 has to be
modified
9) In some projects wiring mistake in the feedback of Collins transmitters was noticed. For rectifying it,
measure voltage at X14 with respect to X24 in the respective AKC-11 Card. Voltage should be +4.0v to +
when values are fully close. In full open condition it should be between � 4.0v to � 8.0v. If it is reverse
wiring should be changed in Junction box.
10) In some cases mistakes in plunger coil wiring was also found. To detect this feed + 1.5V at pin CB53L
: Z2 with respect to CB53L : Z6, the piston should open fully. If not change the wiring in junction box.
11) Setpoint block command persist and load/speed setpoint cannot be changed. It is not due to any
problem/mistakes. This command can be generated due to disturbance in steam parameters or TSE, If it is
from steam parameter it can be acknowledged by master setpoint release. If it is from TSE, influence should
be switched OFF and master set points release should be acknowledged. Before taking TSE in services again,
TSE fault should be rectified.
The line for 0.0 or 4.0 mA selection was not in correct position. The CT ratio selection was also found
to be an 10 Amp while it should have been at 5.0 Amp. After above two rectifications load controller started
giving correct output.