In Service Welding - Velocity or Flow Rate of Process Fluid
In Service Welding - Velocity or Flow Rate of Process Fluid
2 Sh t
P= (i.e. Method 1 equation F=E=T=1)
D
Where:
Sh = Maximum allowable hoop stress, in N/mm2, calculated from the relevant
toughness formula in Appendix 14.
D = Outside diameter of run-pipe, in mm.
t = Nominal thickness, in mm.
P = Maximum allowable operating pressure during welding, in N/mm2.
8.3.3.4 Velocity of Process Fluid
Minimum Velocity
Welding on a line under no-flow conditions (i.e. 0 m/s) or intermittent-flow conditions,
i.e. a flare line, shall not be attempted unless it has been confirmed that no explosive
or flammable mixture will occur during the welding operation. In this respect, it shall
be confirmed that no ingress of oxygen in the line is possible.
In cases where this requirement cannot be met, purging shall be used. A minimum
purge velocity of 0.4 m/s should be maintained.
Maximum Velocity
High liquid flow will usually cause rapid cooling of the weld area during the hot-tap
welding. Under these circumstances the minimum interpass temperatures may not
be attainable, resulting in undesired material properties. A suggested maximum
velocity for liquid flow during welding is 1.75 m/s. If the actual velocity is greater than
this figure, it is recommended to carry out heat loss tests at the actual hot-tap
location. In the event of rapid cooling (i.e. where the cooling rate is such that the
minimum specified interpass temperature is not achieved), special interpass heating
techniques may be needed or the welding procedure amended.
There is no restriction on maximum velocity for gas lines, subject to the attainment of
acceptable interpass temperatures.
8.3.4 Hot-Tap Location
Hot-taps shall not be executed upstream of rotating equipment unless strainers,
capable of removing machining swarf, are fitted.
The chosen location on the run-pipe should be checked and verified as suitable for
the hot-tap connection, taking into account the following factors, as a minimum:
Layout of branch to be tied-in
Diameter and ovality
Copyright © 2019 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
Rev
Page
21 / 65
ABU DHABI GAS INDUSTRIES LTD. (GASCO)
PIPING TIE-INS
300 0.75
200 0.85
120 0.91
Minimum Velocity :
In cases where this requirement cannot be met, purging shall be used. A minimum
purge velocity of 0.4 m/s should be maintained.
Maximum Velocity :
High liquid flow will usually cause rapid cooling of the weld area during the hot-tap
welding. Under these circumstances the minimum interpass temperatures may not
be attainable, resulting in undesired material properties. A suggested maximum
velocity for liquid flow during welding is 1.75 m/s. If the actual velocity is greater than
this figure, it is recommended to carry out heat loss tests at the actual hot-tap
______________________________________________________________________________________________________D
GS-1300-100/FH
Rev
Page
22 / 65
ABU DHABI GAS INDUSTRIES LTD. (GASCO)
PIPING TIE-INS
location. In the event of rapid cooling (i.e. where the cooling rate is such that the
minimum specified interpass temperature is not achieved), special interpass heating
techniques may be needed or the welding procedure amended.
There is no restriction on maximum velocity for gas lines, subject to the attainment of
acceptable interpass temperatures.
8.3.4 Hot-Tap Location
The chosen location on the run-pipe should be checked and verified as suitable for
the hot-tap connection, taking into account the following factors, as a minimum:
• Layout of branch to be tied-in
• Diameter and ovality
• Pipe wall thickness
• Internal and/or external corrosion
• Defects in the pipe wall (e.g. laminations)
• Soundness of adjacent welds
• Internal deposits
Heat loss tests should be performed for large lines due to the excessive heat loss at
the weld area during the hot-tap welding operation.
8.4 DESIGN
8.4.1 Base Materials
Base materials of the run-pipe and the branch connection shall be compatible in
terms of weldability. Materials having the same P number, as defined in ASME IX,
may be used as the basis of compatibility. However, where grades with special
numbers (SP-1 etc.) are to be used, a materials/welding specialist should review the
proposed materials.
8.4.2 Design Calculations
______________________________________________________________________________________________________D
GS-1300-100/FH