Chapter 8, Part 1
Chapter 8, Part 1
Prepared by
John Nicholas, Ph.D.
Loyola University Chicago
&
Herman Steyn
University of Pretoria
Advanced Network Analyses & Scheduling
Construction team:
150 people!
Completed house
New Zealand
In 3 hours and 45 minutes
Time – Cost Tradeoff (cont’d)
How do we reduce project duration?
Focus on the Critical Path
◼ Reduce amount of work (scope, requirements)
◼ Use appropriate technology
◼ Pay attention to motivation of project team
◼ Get support from executives and other
stakeholders
◼ Use more sophisticated / expensive resource(s)
◼ Use more resources to complete work in less time
Time – Cost Tradeoff (cont’d)
◼ In certain cases, activity duration is fixed and
more resources won’t help reduce duration
◼ In other cases, activity duration can be
reduced by using more or better resources
x
Cc
Tn = Normal time
normal
Cn x
Tc Time Tn
Time – Cost Tradeoff (cont’d)
Where in-between possibilities exist, assume a
straight line (not stepwise, concave or convex)
cost = ΔC =
Cc - Cn
crash slope Tc - Tn
ΔT
Direct Cost
x
Cc
normal
Cn x
Tc Time Tn
Time – Cost Tradeoff (cont’d)
C, 2
A, 1 E, 2 G, 6
16 days
Start D, 7
End
B, 3 F, 3 H, 1
Time – Cost Tradeoff (cont’d)
C, 2
A, 1 E, 2 G, 6
16 days
Start D, 7
End
B, 3 F, 3 H, 1
C, 2
A, 1 7→6 E, 2 G, 6
16 →15
Start D, 6
End
B, 3 F, 3 H, 1
Time – Cost Tradeoff: Example
Activity Cost
Slope
◼ Reducing D by 1 day adds $10 to A --
cost of project B 5
C 15
A, 1 E, 2 G, 6
11 days
Start D, 2
End
B, 3 F, 3 H, 1
0
Time – Cost Tradeoff: Example
Start
D, 2 11
4 3 End
B, 3 H, 1 10
F, 3
C, 2
6 3
A, 1 E, 1 G, 3
10
D, 2
Start
3 0 End
7
B, 3 F, 3 H, 1
C, 2
A, 1 E, 1 G, 3
7
D, 2
Start
End
B, 3 F, 3 H, 1
Time – Cost Tradeoff: Example
Normal Crash Cost
Activity Tn Cn Tc Cc Slope
A 1 50 1 50 -- Cannot be crashed
B 3 100 2 105 5 Reducing without
crashing A and/or D will
not help
C 2 80 1 95 15 Reducing without
crashing D will not help
D 7 150 2 200 10 Fully crashed
E 2 90 1 100 10 Fully crashed
F 3 110 2 120 10
G 6 180 1 255 15
H 1 60 1 60 -- Cannot crash
Time – Cost Tradeoff: Example
Reduce F and G by 1 day each
C, 2
3 2
A, 1 E, 1 G, 2
7
D, 2
Start
3 2 End
B, 3 H, 1 6
F, 2
DC = 925 + 10 + 15 = $950
Project cannot be shortened further
Time – Cost Tradeoff: Principles
Summary of principles: Determine least expensive
way to finish project by earlier date
❑ Focus on the critical path
❑ Choose least costly (lowest cost slope) alternative to
shorten project duration first
❑ If project duration has not been reduced sufficiently,
choose second-cheapest alternative, and so on
❑ Keep an eye on all non-critical paths
❑ If a non-critical path becomes critical, reduce activity
duration on this path as well in next round.
Time – Cost Tradeoff: Principles
◼ In its simplest form (as illustrated in the
example) the technique does not take account
for variability– other than variability related to
cost (it is a deterministic approach)
◼ What would the implications be if we accepted
that activity duration is actually variable? This
is taken into account in PERT and Critical
Chain methods
Time – Cost Tradeoff: Principles
◼ After crashing activities, other activities become
critical
◼ Should any activity take longer than estimated,
the whole project will be late
◼ Managers can stop the process of crashing
activities at any step to prevent further activities
from becoming critical (reduce the risk of delaying
the project)